Bearing trolley for disassembling and assembling large nut at end part of electrolytic cell

By designing a support cart for disassembly and assembly of the large nut at the end of the electrolytic cell, the lifting and spacing adjustment mechanism is used to solve the problem of gravity affecting the guide sleeve and butterfly spring during the electrolytic cell disassembly and assembly, and a single-person operation of the large nut is achieved. It is convenient to disassemble and assembly, reduces human resource waste and safety risks, and improves disassembly and assembly efficiency and safety.

CN222038381UActive Publication Date: 2024-11-22ZHANGJIAGANG FURUI HYDROGEN ENERGY EQUIP CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323495724.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-21
Publication Date
2024-11-22
Estimated Expiration
2033-12-21

AI Technical Summary

Technical Problem

During the disassembly and assembly of the electrolytic cell, the guide sleeve and the butterfly spring are affected by gravity, resulting in safety risks when disassembling the large nut, and it requires two people to cooperate, which wastes human resources and is inconvenient.

Method used

A support trolley for disassembly and assembly of large nuts at the end of the electrolytic cell is designed, including a frame, universal wheel, push handle, lifting platform and lifting drive mechanism, as well as a spacing adjustment mechanism and support arm, through the hydraulic cylinder The lead screw realizes lifting and spacing adjustment, allowing single-person operation to facilitate disassembly and assemble large nuts.

Benefits of technology

It realizes the convenient disassembly and assembly of large nuts of single-person electrolytic cell, reduces human resource waste and safety risks, and improves disassembly and assembly efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222038381U_ABST
    Figure CN222038381U_ABST
Patent Text Reader

Abstract

The utility model discloses a bearing trolley for disassembling and assembling a large nut at the end part of an electrolytic bath, which comprises a frame, universal wheels arranged at the bottom of the frame, a pushing handle arranged at the rear part of the frame, a lifting platform and a lifting driving mechanism arranged on the frame, two bearing arms and a distance adjusting mechanism arranged at the front end of the lifting platform, the front lower ends of the two shear fork arms are hinged to the front portion of the frame, the front upper ends of the two shear fork arms are hinged to the front portion of the lifting platform, the rear lower ends of the two shear fork arms are installed on the frame in a front-back sliding mode, and the rear upper ends of the two shear fork arms are installed on the lifting platform in a front-back sliding mode. The front lower portions of the two shear fork arms are fixed through a cross rod, a pedal type hydraulic cylinder is arranged on the frame, a cylinder body of the pedal type hydraulic cylinder is hinged to the frame, and the top of a piston rod of the pedal type hydraulic cylinder is hinged to the cross rod. The bearing trolley can be used for bearing the guide sleeve on the electrolytic bath, so that a large nut can be conveniently disassembled and assembled by only one person.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of electrolytic cell production equipment, in particular to a supporting trolley for disassembling and assembling a large nut at the end of an electrolytic cell. Background Art

[0002] The alkaline electrolytic cell is composed of two end pressure plates, two end plates, and a number of electrolytic chambers stacked together. Multiple tension bolts are used to penetrate the overall structure, and the overall structure is fastened at both ends of the tension bolts with insulating washers, guide rings, butterfly springs, guide sleeves, and large nuts.

[0003] When workers disassemble and assemble the electrolytic cell, when installing and removing the large nut at the bottom, the guide sleeve, disc spring and other parts will fall down due to the influence of gravity, and when removing the large nut, the disc spring is in a compressed state, which has a reverse force on the guide sleeve, making it very inconvenient for workers to install and remove the large nut. Current solution: The work of disassembling and assembling the large nut is carried out by two workers, one holding the bottom of the guide sleeve with his hand, and the other worker disassembling and installing the large nut. Disadvantages of the current solution: Simple nut removal requires two people, which wastes human resources; workers holding the guide sleeve by hand to disassemble the large nut has certain safety risks. Utility Model Content

[0004] The technical problem to be solved by the utility model is to provide a supporting trolley for disassembling and assembling the large nuts at the end of an electrolytic cell, which can be conveniently disassembled and assembled by only one person.

[0005] In order to solve the above problems, the technical solution adopted by the utility model is: a supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell, characterized in that it includes: a frame, a universal wheel is arranged at the bottom of the frame, a push handle is arranged at the rear of the frame, a lifting platform and a lifting drive mechanism that can drive the lifting platform to lift are arranged on the frame, two supporting arms arranged side by side on the left and right and a spacing adjustment mechanism that can drive the two supporting arms to move closer or move away from each other are arranged on the front end of the lifting platform, and the structure of the lifting drive mechanism includes: two scissor arms arranged side by side on the left and right and located between the lifting platform and the frame, each scissor arm is formed by two scissor rods cross-hinged, the hinge shafts at the intersection of the two scissor arms are arranged to the left and right, and the two hinge shafts are relative The two scissor arms are connected to form an axis, the front lower ends of the two scissor arms are respectively hinged to the front part of the frame, the front upper ends of the two scissor arms are respectively hinged to the front part of the lifting platform, the rear lower ends of the two scissor arms can be slidably installed on the frame forwards and backwards, the rear upper ends of the two scissor arms can be slidably installed on the lifting platform forwards and backwards, the front lower parts of the two scissor arms are fixed by a cross bar, and a foot-operated hydraulic cylinder is arranged on the frame below the two scissor arms, the cylinder body of the foot-operated hydraulic cylinder is hinged to the frame, the top of the piston rod of the foot-operated hydraulic cylinder is hinged to the cross bar, the foot pedal of the foot-operated hydraulic cylinder is located at the rear of the frame, and the piston rod of the foot-operated hydraulic cylinder can drive the two scissor arms to stand up synchronously after being extended, so that the lifting platform can rise under the drive of the two scissor arms.

[0006] Furthermore, the aforementioned supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell, wherein: the structure of the spacing adjustment mechanism includes: a left-right running screw, the screw is rotatably mounted on the front end of the lifting platform through two bearings, a handle for driving the screw to rotate is provided on one end of the screw, the left and right parts of the screw have opposite thread rotation directions, the two supporting arms are respectively threadedly connected to the left and right parts of the screw, and a guiding mechanism capable of guiding the two supporting arms left and right is provided between the two supporting arms and the lifting platform, after the screw is driven to rotate by the handle, the two supporting arms can approach toward each other or move away from each other under the drive of the screw.

[0007] Furthermore, the aforementioned supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell, wherein: an arc-shaped notch for avoiding the large nut is respectively arranged on the opposite sides of the front of the two supporting arms.

[0008] Furthermore, the aforementioned supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell, wherein: the supporting arm is welded by angle steel and square steel, the angle steel is located in front of the square steel, the rear end of the angle steel is welded to the front end of the square steel, and the arc-shaped notch is arranged on the horizontal side of the angle steel.

[0009] Furthermore, the aforementioned supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell, wherein: each universal wheel on the frame is equipped with a brake.

[0010] Furthermore, the aforementioned supporting trolley for disassembling and assembling the large nuts at the end of the electrolytic cell, wherein: a tray for placing the large nuts is provided on the lifting platform.

[0011] The advantages of the utility model are as follows: the supporting trolley drives the lifting platform to rise through the lifting drive mechanism, and at the same time, after adjusting the distance between the two supporting arms through the spacing adjustment mechanism, the two supporting arms can support the guide sleeve on the electrolytic cell, so that only one person is needed to conveniently disassemble and assemble the large nut. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 The utility model is a schematic structural diagram of a supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell. DETAILED DESCRIPTION

[0013] The present invention will be described in further detail below in conjunction with specific embodiments and accompanying drawings.

[0014] like Figure 1 As shown, a supporting trolley for disassembling and assembling a large nut at the end of an electrolytic cell comprises: a frame 1, a universal wheel 2 is arranged at the bottom of the frame 1, a pushing handle 3 is arranged at the rear of the frame 1, a lifting platform 4 and a lifting drive mechanism capable of driving the lifting platform 4 to lift are arranged on the frame 1, two supporting arms 5 arranged side by side on the left and right and a spacing adjustment mechanism capable of driving the two supporting arms 5 to move towards each other or move away from each other are arranged on the front end of the lifting platform 4, and the structure of the lifting drive mechanism comprises: two scissor arms 6 arranged side by side on the left and right and located between the lifting platform 4 and the frame 1, each scissor arm 6 is formed by cross-hinging two scissor rods 7, a hinge shaft 8 at the intersection of the two scissor arms 6 is arranged to face left and right, and the two hinge shafts 8 are connected to form an axis, the front lower ends of the two scissor arms 6 are respectively hinged to the front of the frame 1, and the two scissor arms 6 are respectively hinged to the front of the frame 1. The front upper ends are respectively hinged to the front parts of the lifting platform 4, and the rear lower ends of the two scissor arms 6 can be slidably installed on the frame 1 forwards and backwards, and the rear upper ends of the two scissor arms 6 can be slidably installed on the lifting platform 4 forwards and backwards. In this embodiment, the rear lower ends and rear upper ends of the two scissor arms 6 are respectively installed by linear guide rails, and the front lower parts of the two scissor arms 6 are fixed by a cross bar 9. A foot-operated hydraulic cylinder 10 is provided on the frame 1 below the two scissor arms 6, and the cylinder body of the foot-operated hydraulic cylinder 10 is hinged to the frame 1, and the top of the piston rod of the foot-operated hydraulic cylinder 10 is hinged to the cross bar 9, and the foot pedal of the foot-operated hydraulic cylinder 10 is located at the rear of the frame 1. After the piston rod of the foot-operated hydraulic cylinder 10 is extended, it can drive the two scissor arms 6 to stand up synchronously, so that the lifting platform 4 can rise under the drive of the two scissor arms 6. The pedal-operated hydraulic cylinder 10 is a commonly used hydraulic cylinder that can be purchased now. The hydraulic cylinder can be extended after repeated pedaling, and can be retracted after the pressure is released by the pressure release operating rod.

[0015] In this embodiment, the structure of the spacing adjustment mechanism includes: a left-right running lead screw 11, which is rotatably mounted on the front end of the lifting platform 4 through two bearings, and a handle 12 for driving the lead screw 11 to rotate is provided on one end of the lead screw 11. The left and right parts of the lead screw 11 have opposite thread rotation directions, and the two supporting arms 5 are respectively threadedly connected to the left and right parts of the lead screw 11. A guide mechanism that can guide the two supporting arms 5 left and right is provided between the two supporting arms 5 and the lifting platform 4. The guide mechanism is usually a linear guide rail. After the lead screw 11 is driven to rotate by the handle 12, the two supporting arms 5 can move closer to each other or away from each other under the drive of the lead screw 11, so as to adapt to large nuts and guide sleeves of different sizes.

[0016] The two supporting arms 5 are respectively provided with an arc-shaped notch 13 for avoiding the large nut on the opposite sides of the front part. The designed arc-shaped notch 13 can make the two supporting arms 5 contact with the guide sleeve to a large extent without affecting the tightening and loosening of the large nut, thereby increasing the stability of the support. The supporting arm 5 is welded by an angle steel 14 and a square steel 15. The angle steel 14 is located in front of the square steel 15, and the rear end of the angle steel 14 is welded to the front end of the square steel 15. The arc-shaped notch 13 is arranged on the horizontal side of the angle steel 14, and the square steel 15 is threadedly connected with the lead screw 11. Each universal wheel 2 on the frame 1 is provided with a brake, so that the trolley can be stopped without moving when supporting. A tray 16 for placing large nuts is provided on the lifting platform 4, and the large nuts and other parts to be installed or the disassembled parts can be placed in the tray 16, without having to use other carts to place the parts.

[0017] During operation, the supporting trolley is pushed to the bottom of the large nut, and then the lifting platform 4 is driven to rise by the lifting drive mechanism, and the distance between the two supporting arms 5 is adjusted by the spacing adjustment mechanism. Finally, the two supporting arms 5 can support the guide sleeve on the electrolytic cell, so that only one person is needed to conveniently disassemble and assemble the large nut. When the vertical edges on the two angle steels 14 support the guide sleeve on the horizontal edges thereon, the guide sleeve and the butterfly spring can be limited to the left and right to prevent the guide sleeve and the butterfly spring from shaking left and right.

Claims

1. A supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell, characterized in that: include: The frame is provided with a universal wheel at the bottom of the frame, a push handle is provided at the rear of the frame, a lifting platform and a lifting drive mechanism capable of driving the lifting platform to lift are provided on the frame, two supporting arms arranged side by side on the left and right and a spacing adjustment mechanism capable of driving the two supporting arms to move toward each other or move away from each other are provided on the front end of the lifting platform, and the structure of the lifting drive mechanism comprises: two scissor arms arranged side by side on the left and right and located between the lifting platform and the frame, each scissor arm is formed by cross-hinging two scissor rods, a hinge shaft at the intersection of the two scissor arms is arranged toward the left and right, and the two hinge shafts are connected to form an axis, and the front lower ends of the two scissor arms are respectively opposite to the front of the frame The two scissor arms are hinged to the front of the lifting platform, and the rear lower ends of the two scissor arms can be slidably mounted on the frame. The rear upper ends of the two scissor arms can be slidably mounted on the lifting platform, and the front lower parts of the two scissor arms are fixed by a cross bar. A foot-operated hydraulic cylinder is arranged on the frame below the two scissor arms. The cylinder body of the foot-operated hydraulic cylinder is hinged to the frame, and the top of the piston rod of the foot-operated hydraulic cylinder is hinged to the cross bar. The foot pedal of the foot-operated hydraulic cylinder is located at the rear of the frame. After the piston rod of the foot-operated hydraulic cylinder is extended, it can drive the two scissor arms to stand up synchronously, so that the lifting platform can rise under the drive of the two scissor arms.

2. The supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell according to claim 1, characterized in that: The structure of the spacing adjustment mechanism includes: a left-right running screw, which is rotatably mounted on the front end of the lifting platform through two bearings, a handle for driving the screw to rotate is provided on one end of the screw, the left and right parts of the screw have threads that rotate in opposite directions, the two supporting arms are threadedly connected to the left and right parts of the screw respectively, and a guide mechanism that can guide the two supporting arms left and right is provided between the two supporting arms and the lifting platform, after the screw is driven to rotate by the handle, the two supporting arms can approach each other or move away from each other under the drive of the screw.

3. The supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell according to claim 1 or 2, characterized in that: An arc-shaped notch for avoiding the large nut is respectively arranged on the opposite sides of the front parts of the two supporting arms.

4. The supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell according to claim 3, characterized in that: The supporting arm is welded by angle steel and square steel. The angle steel is located in front of the square steel. The rear end of the angle steel is welded to the front end of the square steel. The arc notch is arranged on the horizontal side of the angle steel.

5. The supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell according to claim 1 or 2, characterized in that: Each universal wheel on the frame is equipped with brakes.

6. The supporting trolley for disassembling and assembling the large nut at the end of the electrolytic cell according to claim 1 or 2, characterized in that: A tray for placing large nuts is arranged on the lifting platform.

Citation Information

Cited By

  • Train center pin nut taking-out device and method

    CN120206209A