Asymmetric hoisting construction structure for suspension bridge in mountainous area under limited site

By adopting an asymmetric lifting structure in mountain suspension bridges, adjusting the lifting sequence and using cable lifting systems, the problem of insufficient assembly site of the main beam of the suspension bridge under terrain limitations is solved, and construction efficiency and construction period are improved.

CN222043942UActive Publication Date: 2024-11-22SICHUAN ROAD & BRIDGE CONSTRUCTION GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420697238.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-07
Publication Date
2024-11-22
Estimated Expiration
2034-04-07

AI Technical Summary

Technical Problem

In the construction of mountain suspension bridges, due to terrain restrictions, it is impossible to build the main beam assembly site on both sides of the strait, resulting in a reduction in the local cable lifting area above the assembly site, affecting the construction period.

Method used

Asymmetric lifting construction structure is adopted to adjust the lifting order of the main beam of the suspension bridge, adjust the symmetrical installation between the two sides of the strait to asymmetrical installation, and install the first strait beam section for limited installation, and reserve the hoisting area above the assembly site, and perform through the cable lifting system and rotating spreader. Lifting, the main beam assembly construction is carried out using the cable system and the steel truss assembly site.

Benefits of technology

Effectively utilize the limited assembly site, improve the assembly efficiency of the main beam and ensure the construction cycle of the entire bridge.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222043942U_ABST
    Figure CN222043942U_ABST
Patent Text Reader

Abstract

The utility model provides an asymmetric hoisting construction structure for a suspension bridge in a mountainous area under a limited site. The method is characterized by mainly comprising the following steps: (1) symmetrically mounting; (2) side beam sections of a non-assembly field are installed; (3) side beam sections of the assembly field are installed; (4) closing the side beam sections of the non-assembly field; and (5) full-bridge closure. According to the method, 1, an asymmetric hoisting mode is adopted, the hoisting sequence of the main beams is adjusted, a limited main beam assembling site is fully utilized, the main beam assembling efficiency in the assembling site is guaranteed, and the construction period of a full bridge is guaranteed;
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of bridge engineering, in particular to an asymmetric hoisting construction structure of a suspension bridge in a mountainous area with limited space. Background Art

[0002] As the expressway network extends to the western mountainous areas, large bridges across mountainous areas, river valleys, gullies, etc. emerge in an endless stream, and bridges with strong spanning capacity such as suspension bridges, cable-stayed bridges, and arch bridges are constantly being used. However, due to the influence of mountainous sites and roads, mountainous bridge construction also faces many difficulties.

[0003] In the construction of suspension bridges in mountainous areas, due to terrain restrictions, it is impossible to build main beam assembly sites on both sides. In the case of a single-side assembly site, as the main beam is installed from the middle span to the side span, the area of ​​local cable hoisting above the assembly site will be reduced, resulting in less space available for the steel truss assembly site, which will affect the construction period of the suspension bridge main beam installation. This patent example mainly solves how to more effectively use the limited assembly site to ensure the construction progress. Utility Model Content

[0004] The purpose of the present application is to provide an asymmetric hoisting construction structure for a suspension bridge in a mountainous area with limited site, to adjust the hoisting sequence of the main beam of the suspension bridge, to change the symmetrical installation on both sides to an asymmetric installation, to install a limited beam section on one side, to reserve a hoisting area above the assembly site, and to effectively utilize the assembly site for main beam assembly construction.

[0005] The utility model is implemented by providing an asymmetric hoisting construction structure for a suspension bridge in a mountainous area with limited space, which is characterized by comprising a cable hoisting system, a cable hoist and a steel truss assembly site;

[0006] The cable hoisting system is composed of a cable system and a rotating hoist, and the steel truss girder assembly yard is a steel truss girder bridge deck and truss assembly structure constructed of steel and concrete;

[0007] Below the cable crane is a steel truss girder segment, and at both ends of the steel truss girder segment are the non-assembly yard side beam segment and the assembly yard shore side beam segment.

[0008] Furthermore, the cable system includes load-bearing ropes, saddles, traction ropes and lifting ropes, and all ropes are anchored to corresponding anchor structures.

[0009] Furthermore, the rotating hanger adopts a gear rotating shaft, and the rotating mechanism is rotated by a remote control motor.

[0010] Furthermore, the steel truss assembly site is located at the bottom and front of the cable tower, with only one bank erected, divided into a bridge deck and a steel truss assembly area, and is erected through a steel tube Bailey beam support.

[0011] The corresponding implementation process of this application is:

[0012] Step 1: Symmetrical installation

[0013] The steel truss segments are installed symmetrically from the mid-span to the side span until they are installed in the area above the steel truss assembly site.

[0014] Step 2: Installation of side beam sections at non-assembly sites

[0015] Install the non-assembly site shore side beam sections from the mid-span to the tower area in sequence until the remaining end beams and the secondary end (joined) beam sections are installed. First, install the end beam segments using the swinging method, and then transport the secondary end beam as the jointed beam section to the front of the tower below the installation position for temporary storage.

[0016] Step 3: Installation of the side beam section at the assembly yard

[0017] The shore side beam sections of the assembly yard are installed sequentially from the mid-span to the tower area. Each time a beam end is installed, an assembly area in the assembly yard will become unusable. Therefore, during assembly, the main beams should be assembled in the assembly yard in sequence according to the hoisting order to make full use of the assembly area until the remaining joint beam sections are hoisted.

[0018] Step 4: Joining of non-assembly site side beam sections

[0019] First, the side beam sections that are not on the assembly site are connected and joined, and the beam sections stored in front of the tower are directly lifted vertically to the installation position for installation to complete the connection of the single-side beam sections.

[0020] Step 5: Full bridge closure

[0021] Lift the jointed beam section stored in the assembly yard and lift it vertically directly to complete the jointing of the entire bridge section.

[0022] The advantages of this application are: this application adopts an asymmetric lifting method, adjusts the main beam lifting sequence, fully utilizes the limited main beam assembly site, ensures the main beam assembly efficiency in the assembly site, and ensures the construction period of the entire bridge. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 This is the construction drawing for hoisting of symmetrical beam sections;

[0024] Figure 2 This is the construction drawing for the hoisting of asymmetric beam sections;

[0025] Figure 3 This is the construction drawing for hoisting the joint beam section.

[0026] Among them: 1-main tower; 2-cable crane; 3-mid-span symmetrical lifting area; 4-steel truss assembly yard; 5-non-assembly yard shore beam section; 6-assembly yard shore beam section; 7-non-assembly yard shore end beam; 8-non-assembly yard shore joint beam section; 9-assembly yard shore joint beam section DETAILED DESCRIPTION

[0027] The following will be combined with the attached Figure 1-Figure 3 The method is described in detail, and the technical solution in the embodiment of the method is described clearly and completely. Obviously, the described embodiment is only a part of the embodiment of this patent, not all of the embodiments. Based on the embodiments in this patent, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this patent.

[0028] The present application provides an asymmetric hoisting construction structure for a suspension bridge in a mountainous area with limited site. By adjusting the hoisting sequence of the main beam of the suspension bridge, the symmetrical installation on both sides is adjusted to an asymmetric installation, and the beam section on one side is installed limitedly, and a hoisting area above the assembly site is reserved, so that the assembly site is effectively used for the main beam assembly construction.

[0029] like Figure 1-Figure 3 As shown, the utility model discloses an asymmetric hoisting construction structure for a suspension bridge in a mountainous area with limited space; it includes a cable hoisting system, a cable hoist 2 and a steel truss assembly site 4;

[0030] The cable hoisting system is composed of a cable system and a rotating hoist, and the steel truss girder assembly yard 4 is a steel truss girder bridge deck and truss assembly structure constructed of steel and concrete;

[0031] Below the cable crane 2 is a steel truss beam segment 3, and at both ends of the steel truss beam segment 3 are a non-assembly yard side beam segment 5 and an assembly yard shore side beam segment 6.

[0032] In the present application, the cable system includes a load-bearing rope, a saddle, a traction rope and a lifting rope, and all ropes are anchored to corresponding anchor structures.

[0033] In the present application, the rotating sling adopts a gear rotating shaft, and the rotating mechanism is rotated by a remote control motor.

[0034] In the present application, the steel truss assembly yard 4 is located at the bottom of the cable tower 1 and in front of the cable tower. It is only constructed on one side and is divided into a bridge deck and a steel truss assembly area. It is constructed through a steel tube Bailey beam support.

[0035] The following is combined with Figure 1 , 2 3. Further describe the specific implementation methods of this patent:

[0036] Step 1: Symmetrical installation: The steel truss segments 3 are symmetrically installed from the mid-span to the side span sides of the bridge until they are installed to the segments in the area above the steel truss assembly site 4.

[0037] Step 2: Installation of non-assembly-yard side beam segments: Install the non-assembly-yard shore side beam segments 5 from the mid-span to the tower area in sequence until the remaining end beams 7 and the secondary end (joined) beam segments 8 are installed. First, the end beam segment 7 is installed by swinging, and the secondary end beam is transported as the joint beam segment 8 to the front of the tower below the installation position for temporary storage.

[0038] Step 3: Installation of the side beam sections at the assembly yard: Install the side beam sections 6 at the assembly yard in sequence from the mid-span to the tower area. Every time a main beam is installed, an assembly area in the assembly yard 4 will be unusable. Therefore, during assembly, the main beams should be assembled in the assembly yard 4 in sequence according to the lifting order, and the assembly area should be fully utilized until the remaining joint beam sections 9 are lifted.

[0039] Step 4: Jointing of the non-assembly-yard side beam segments: First, joint and connect the non-assembly-yard side beam segments 5, and directly lift the beam segments 8 stored in front of the tower vertically to the installation position for installation, thus completing the jointing of the single-side beam segments.

[0040] Step 5: Closing the entire bridge: Lift the closure beam section 9 stored in the assembly yard, lift it vertically directly, and complete the closure of the entire bridge section.

[0041] The advantages of the utility model are: the application adopts an asymmetric lifting method, adjusts the main beam lifting sequence, fully utilizes the limited main beam assembly site, ensures the main beam assembly efficiency in the assembly site, and ensures the construction period of the entire bridge.

Claims

1. An asymmetric hoisting construction structure for a suspension bridge in a mountainous area with limited space, characterized by: include Cable hoisting system, cable hoist (2) and steel truss assembly site (4); The cable hoisting system is composed of a cable system and a rotating hoist, and the steel truss girder assembly yard (4) is a steel truss girder bridge deck and truss assembly structure constructed of steel and concrete; Below the cable crane (2) is a steel truss beam segment (3), and at both ends of the steel truss beam segment (3) are a non-assembly yard side beam segment (5) and an assembly yard shore side beam segment (6).

2. According to claim 1, the asymmetric hoisting construction structure of a suspension bridge in a mountainous area with limited space is characterized by: The cable system includes a load-bearing rope, a saddle, a traction rope and a lifting rope, and all the ropes are anchored on corresponding anchor structures.

3. According to claim 1, the asymmetric hoisting construction structure of a suspension bridge in a mountainous area with limited space is characterized by: The rotating hanger adopts a gear rotating shaft, and the rotating mechanism is rotated by a remote control motor.

4. According to claim 1, the asymmetric hoisting construction structure of a suspension bridge in a mountainous area with limited space is characterized by: The steel truss assembly site (4) is located at the bottom of the cable tower (1) and in front of the cable tower. It is only constructed on one side and is divided into a bridge deck and a steel truss assembly area. The steel truss assembly area is constructed using a steel tube Bailey beam support.