Temporary isolation guardrail for constructional engineering

By designing a pieceable isolation pile and accommodating cavity structure, as well as an additional isolation barrel and handle, the problems of insufficient guardrail recycling function and exposure of the scissor mechanism in the prior art are solved, and the multifunctional use and service life of the guardrail are achieved.

CN222045306UActive Publication Date: 2024-11-22中嘉建设集团有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420069762.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-11
Publication Date
2024-11-22
Estimated Expiration
2034-01-11

AI Technical Summary

Technical Problem

The temporary isolation guardrails for existing construction projects lack auxiliary functions in the recycling state, and the scissor mechanism is exposed outside, which affects the service life.

Method used

An isolation pile and a receiving cavity structure are designed that are assembled by the left and right halves. The scissor mechanism can be hidden inside in the closed state, and multi-functional use is achieved by adding an isolation barrel and a pieceable handle.

Benefits of technology

The dual-purpose function of the guardrail is realized, which extends the service life, and improves the functional perfection and practicality through the added isolation barrel and handle.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222045306U_ABST
    Figure CN222045306U_ABST
Patent Text Reader

Abstract

The temporary isolation guardrail for the constructional engineering comprises an isolation pile, the isolation pile is provided with a containing cavity, a shear fork mechanism is arranged in the containing cavity, the shear fork mechanism is provided with a left upper supporting foot, a left lower supporting foot, a right upper supporting foot and a right lower supporting foot, the isolation pile comprises a left half pile body and a right half pile body, and the containing cavity comprises a left half cavity and a right half cavity; a left fixed lug seat and a left movable lug seat are arranged in the left half cavity, a left sliding rail is arranged in the left half cavity, the left movable lug seat is connected to the left sliding rail in a sliding mode, a right fixed lug seat and a right movable lug seat are arranged in the right half cavity, a right sliding rail is arranged in the right half cavity, and the right movable lug seat is connected to the right sliding rail in a sliding mode; the upper left supporting leg is hinged to the left fixed lug, the lower left supporting leg is hinged to the left movable lug, the upper right supporting leg is hinged to the right fixed lug, and the lower right supporting leg is hinged to the right movable lug. The isolation guardrail has the advantages of being easy to recycle, diversified in function, complete in overall function and high in practicability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of engineering facilities, and more specifically, to a temporary isolation guardrail for construction engineering. Background Art

[0002] In the construction of construction projects, temporary isolation guardrails are required. Such isolation guardrails usually need to be easy to install and recycle. However, most isolation guardrails have no other auxiliary functions when they are recycled. Therefore, the utility model proposes a temporary isolation guardrail for construction projects. Utility Model Content

[0003] The purpose of the utility model is to overcome the deficiencies in the prior art and to provide a temporary isolation guardrail for construction engineering, which has the characteristics of being easy to recycle and having various functions.

[0004] In order to solve the above technical problems, the purpose of the utility model is achieved as follows: the utility model involves a temporary isolation guardrail for construction engineering, including an isolation pile, the isolation pile has a receiving cavity, a scissor mechanism extending horizontally left and right is arranged in the receiving cavity, the scissor mechanism has a left upper support leg, a left lower support leg, a right upper support leg and a right lower support leg, the isolation pile is composed of left and right halves, the isolation pile includes a left half pile body and a right half pile body, the receiving cavity is composed of left and right halves, the receiving cavity includes a left half cavity and a right half cavity, the left half cavity is arranged on the left half pile body, and the right half cavity is arranged on the right half pile body;

[0005] The left half cavity is provided with a left fixed ear seat on the top and a left movable ear seat on the bottom, the left half cavity is provided with a left slide rail extending vertically up and down, the left movable ear seat is slidably connected to the left slide rail, the right half cavity is provided with a right fixed ear seat on the top and a right movable ear seat on the bottom, the right half cavity is provided with a right slide rail extending vertically up and down, the right movable ear seat is slidably connected to the right slide rail;

[0006] The upper left support leg is hinged on the left fixed ear seat, the lower left support leg is hinged on the left movable ear seat, the upper right support leg is hinged on the right fixed ear seat, and the lower right support leg is hinged on the right movable ear seat.

[0007] The utility model is further configured as follows: the isolation pile has a pile base having a diameter larger than the top;

[0008] It also includes an isolation cylinder sleeved on the isolation pile, and the bottom end of the isolation cylinder is provided with a flared groove for the pile base to be embedded.

[0009] The utility model is further configured as follows: a handle is provided on the top of the isolation pile, and the handle is also composed of left and right halves. The handle includes a left half handle body and a right half handle body. The left half handle body is arranged on the left half pile body, and the right half handle body is arranged on the right half pile body.

[0010] In summary, the utility model has the following beneficial effects:

[0011] 1. The guardrail can be folded and unfolded. It can be used as a guardrail when unfolded and as an isolation pile when folded. It has dual functions.

[0012] 2. When the guardrail is folded and used as an isolation pile, the scissor mechanism can be hidden inside, avoiding the scissor mechanism of the multi-hinged structure from being exposed to the outside, thus extending the service life.

[0013] 3. The added isolation cylinder can not only be used as an isolation pile alone, but also used to splice and fix the split left and right half pile bodies. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0015] Figure 2 yes Figure 1 A schematic diagram of the structure in another state;

[0016] Figure 3 This is a schematic diagram of the structure of the isolation tube used in the utility model;

[0017] Figure 4 The utility model is used to embody the schematic diagram of the handle structure. DETAILED DESCRIPTION

[0018] In order to enable those skilled in the art to better understand the technical solution of the utility model, the preferred implementation scheme of the utility model is described below in conjunction with specific embodiments, but it should be understood that these descriptions are only for further illustrating the features and advantages of the utility model, rather than limiting the patent requirements of the utility model. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the utility model.

[0019] The utility model is further described below in conjunction with the accompanying drawings and preferred embodiments.

[0020] Example 1

[0021] See also Figure 1 and Figure 2As shown, a temporary isolation guardrail for construction engineering involved in this embodiment includes an isolation pile 100, the isolation pile 100 has a receiving chamber 101, a scissor mechanism 200 extending horizontally left and right is arranged in the receiving chamber 101, the scissor mechanism 200 has an upper left support leg 201, a lower left support leg 202, an upper right support leg 203 and a lower right support leg 204, the isolation pile 100 is composed of left and right halves, the isolation pile 100 includes a left half pile body 102 and a right half pile body 103, the receiving chamber 101 is composed of left and right halves, the receiving chamber includes a left half chamber 104 and a right half chamber 105, the left half chamber 104 is arranged on the left half pile body 102, and the right half chamber 105 is arranged on the right half pile body 103;

[0022] The left half cavity 104 is provided with an upper left fixed ear seat 106 and a lower left movable ear seat 107, the left half cavity 104 is provided with a left slide rail 108 extending vertically up and down, the left movable ear seat 107 is slidably connected to the left slide rail 108, the right half cavity 105 is provided with an upper right fixed ear seat 109 and a lower right movable ear seat 110, the right half cavity 105 is provided with a right slide rail 111 extending vertically up and down, the right movable ear seat 110 is slidably connected to the right slide rail 111;

[0023] The upper left support leg 201 is hinged on the left fixed ear seat 106 , the lower left support leg 202 is hinged on the left movable ear seat 107 , the upper right support leg 203 is hinged on the right fixed ear seat 109 , and the lower right support leg 204 is hinged on the right movable ear seat 110 .

[0024] In this embodiment, the right half pile body 103 is moved rightward relative to the left half pile body 102, or the left half pile body 102 is moved leftward relative to the right half pile body 103, so that the left half pile body 102 and the right half pile body 103, which were originally close together, can be separated. During the separation, the scissor mechanism 200 is opened, and the guardrail is opened for blocking. On the contrary, the scissor mechanism 200 is closed and hidden in the accommodating cavity 101, and the left half pile body 102 and the right half pile body 103, which are joined at the left and right sides, form an isolation pile 100, which is used for local point blocking and warning.

[0025] Example 2

[0026] See also Figures 1 to 4 As shown, the present embodiment involves a temporary isolation guardrail for construction projects, which is further configured on the basis of Embodiment 1, wherein the isolation pile 100 has a pile base 112 with a diameter larger than the top; and also includes an isolation tube 300 sleeved on the isolation pile 100, and the bottom end of the isolation tube 300 has a flared groove 301 for the pile base 112 to be embedded.

[0027] In this embodiment, by providing the isolation cylinder 300 , the isolation cylinder 300 alone has the local point blocking and warning functions of the isolation pile 100 .

[0028] When the isolation tube 300 is sleeved on the isolation pile 100 , the left half pile body 102 and the right half pile body 103 , which are originally separable naturally, can be bound.

[0029] Among them, by cooperating with the pile base 112 having a diameter larger than the top and the expanded groove 301 for the pile base 112 to be embedded, when the isolation cylinder 300 is lifted upward, the isolation pile 100 can be moved upward together to prevent the isolation pile 100 from falling off from the bottom of the isolation cylinder 300.

[0030] Example 3

[0031] See also Figures 1 to 4 As shown, the present embodiment involves a temporary isolation guardrail for construction projects, which is further configured on the basis of Embodiment 2, that the top of the isolation pile 100 has a handle 113, and the handle 113 is also composed of left and right halves. The handle 113 includes a left half handle body 114 and a right half handle body 115, and the left half handle body 114 is arranged on the left half pile body 102, and the right half handle body 115 is arranged on the right half pile body 103.

[0032] In this embodiment, the handle 113 is provided to facilitate holding. When the isolation pile 100 is lifted by the handle, the isolation cylinder 300 on the isolation pile 100 can be moved upward together, which is convenient for transfer.

[0033] The utility model relates to a temporary isolation guardrail for construction projects, which can be folded and unfolded. It can be used as a guardrail in the unfolded state and as an isolation pile in the folded state, and has dual functions. The guardrail used as an isolation pile in the folded state can hide the scissor mechanism inside, so as to avoid the scissor mechanism of the multi-hinged structure being exposed to the outside, thereby extending the service life. The additional isolation cylinder can be used not only as an isolation pile alone, but also as a splicing and fixing of the split left half pile body and the right half pile body. The overall function is complete and the practicability is strong.

[0034] Unless otherwise specified, in the present invention, the terms "length", "width", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicating orientation or positional relationship are based on the orientation or positional relationship actually shown, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, the terms describing the orientation or positional relationship in the present invention are only used for illustrative purposes and cannot be understood as limitations on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood in combination with the embodiments and according to specific circumstances.

[0035] Unless otherwise clearly specified and limited, in the present invention, the terms "disposed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0036] The preferred specific embodiments of the utility model are described in detail above. It should be understood that ordinary technicians in this field can make many modifications and changes based on the concept of the utility model without creative work. Therefore, all technical solutions that can be obtained by technicians in this technical field based on the concept of the utility model through logical analysis, reasoning or limited experiments on the basis of the existing technology should be within the scope of protection determined by the claims.

Claims

1. A temporary isolation guardrail for construction engineering, characterized in that: The invention comprises an isolation pile, the isolation pile has a receiving cavity, a scissor mechanism extending horizontally left and right is arranged in the receiving cavity, the scissor mechanism has a left upper support leg, a left lower support leg, a right upper support leg and a right lower support leg, the isolation pile is composed of left and right halves, the isolation pile comprises a left half pile body and a right half pile body, the receiving cavity is composed of left and right halves, the receiving cavity comprises a left half cavity and a right half cavity, the left half cavity is arranged on the left half pile body, and the right half cavity is arranged on the right half pile body; The left half cavity is provided with a left fixed ear seat on the top and a left movable ear seat on the bottom, the left half cavity is provided with a left slide rail extending vertically up and down, the left movable ear seat is slidably connected to the left slide rail, the right half cavity is provided with a right fixed ear seat on the top and a right movable ear seat on the bottom, the right half cavity is provided with a right slide rail extending vertically up and down, the right movable ear seat is slidably connected to the right slide rail; The upper left leg is hinged on the left fixed ear seat, the lower left leg is hinged on the left movable ear seat, the upper right leg is hinged on the right fixed ear seat, and the lower right leg is hinged on the right movable ear seat; The isolation pile has a pile base with a diameter larger than the top; and also includes an isolation cylinder sleeved on the isolation pile, wherein the bottom end of the isolation cylinder has an expanded groove for the pile base to be embedded.

2. The temporary isolation guardrail for construction engineering according to claim 1 is characterized in that: The top of the isolation pile is provided with a handle, which is also composed of left and right halves. The handle includes a left half handle body and a right half handle body. The left half handle body is arranged on the left half pile body, and the right half handle body is arranged on the right half pile body.