Pipeline system for preventing vacuum leakage of steam turbine
By installing U-shaped sealed ring steam leakage pipelines and valves in the pipeline between the turbine and condenser, the vacuum leakage problem is solved, the economy and reliability of the unit are improved, and the dependence on vacuum pumps is reduced.
Patent Information
- Application Number
- CN202420958890.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-07
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-05-07
AI Technical Summary
The pipes connected to the steam turbine and the condenser are prone to vacuum leakage after use for a period of time, resulting in unqualified vacuum tightness of the condenser and affecting the economy and reliability of the unit.
A vacuum leakage pipeline system for steam turbines is designed. By installing a U-shaped sealed ring steam leakage pipeline between the high-pressure cylinder and the condenser, and equipped with valves and shaft seal valves, the leakage steam is recovered by pressure differential and the leakage pipeline is switched. To the shaft seal overflow pipe, avoid vacuum leakage, and extract water from the valve during shutdown.
It effectively reduces the leakage of the steam turbine and condenser connection pipelines, avoids the vacuum leakage problem of condenser, improves the economy and reliability of the unit, and reduces dependence on vacuum pumps.
Smart Images

Figure CN222045879U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of thermal power generation equipment, in particular to a pipeline system for preventing vacuum leakage of a steam turbine. Background Art
[0002] A steam turbine, also known as a steam turbine engine, is a rotary steam power device. High-temperature and high-pressure steam passes through a fixed nozzle to become an accelerated steam flow and is then sprayed onto the blades, causing the rotor with the blade rows to rotate and perform work externally.
[0003] The connection between the high-pressure combined steam valve of the steam turbine and the high-pressure cylinder is a direct threaded connection, the seal is a metal U-shaped sealing ring, and a steam leakage pipeline is designed to connect to the condenser.
[0004] After the pipeline connecting the turbine and condenser has been used for a period of time, there will be vacuum leakage in the pipeline, causing the vacuum tightness of the condenser to be unqualified for a long time, requiring multiple devices to operate at the same time, affecting the economy of the unit.
[0005] Therefore, it is necessary to provide a steam turbine vacuum leakage prevention pipeline system to solve the above technical problems. Utility Model Content
[0006] The utility model provides a steam turbine vacuum leakage prevention pipeline system, which solves the problem that after a period of use, the pipeline connecting the steam turbine and the condenser will leak vacuum, resulting in the condenser vacuum tightness being unqualified during the production period, requiring multiple devices to operate simultaneously, affecting the economy of the unit.
[0007] In order to solve the above technical problems, the utility model provides a steam turbine vacuum leakage prevention pipeline system comprising: a high-pressure cylinder;
[0008] Two high-pressure combined steam valves, the two high-pressure combined steam valves are respectively installed at the two steam ports of the high-pressure combined steam valves, the outlets of the two high-pressure combined steam valves are both installed with U-shaped sealing ring leakage pipes, the other end of one of the U-shaped sealing ring leakage pipes is installed with a second valve, the other end of the other U-shaped sealing ring leakage pipe is installed with a first valve, the other ends of the first valve and the second valve are connected to the inlet of the condenser through the U-shaped sealing ring leakage pipe, and the outer surfaces of the two U-shaped sealing ring leakage pipes are respectively installed with a first shaft sealing valve and a second shaft sealing valve through a mounting pipe;
[0009] The outlet of the condenser is also provided with a U-shaped sealing ring leakage pipe. The other ends of the first shaft sealing valve and the second shaft sealing valve are connected to the shaft sealing pipe through a mounting pipe. The mounting pipe and the U-shaped sealing ring leakage pipe are made of the same material. The connection between the first shaft sealing valve and the second shaft sealing valve and the first valve and the second valve can refer to Figure 1The high-pressure cylinder is the main component of the steam turbine. It converts steam energy into mechanical energy to drive the generator to generate electricity. The high-pressure combined steam valve adjusts the steam flow and controls the speed of the steam turbine. The U-shaped sealing ring leakage pipe creates a pressure difference inside and outside the U-shaped sealing ring and recovers the U-shaped sealing ring leakage steam. The condenser cools the steam after the turbine has done work and recycles it. The shaft seal pipe provides sealing steam to the turbine shaft seal.
[0010] Preferably, the outlet of the condenser is equipped with a shaft seal overflow control station through a U-shaped sealing ring steam leakage pipeline, and one end of the shaft seal overflow control station is equipped with a shaft seal pipeline;
[0011] The shaft seal pipe and U-shaped seal ring steam leakage pipe are also made of the same material.
[0012] Preferably, the inlet of the condenser is fixedly connected with a connecting pipe, the other end of the connecting pipe is fixedly connected with a filter box, and a display is installed on the front of the filter box;
[0013] The display can be a tablet computer that can operate the equipment. The connecting pipe and the U-shaped sealing ring steam leakage pipe are made of the same material.
[0014] Preferably, a filter bucket is installed inside the filter box, a sewage pipe is fixedly connected to the bottom of the filter bucket, and a sewage valve is installed at the other end of the sewage pipe;
[0015] The sewage pipe is sealed at the connection where it passes through the filter box.
[0016] Preferably, a sealing cover is installed on the top of the filter box, a mounting shell is installed on the top of the sealing cover, and heat dissipation holes are opened on the front and back of the mounting shell;
[0017] A U-shaped sealing ring steam leakage pipeline is installed on the sealing cover and is connected with the first valve and the second valve.
[0018] Preferably, a driving motor is installed inside the mounting shell, a rotating rod is installed at the output end of the driving motor, and a cleaning brush is installed on the outer surface of the rotating rod through a mounting frame;
[0019] The position of the mounting bracket can be referred to in the figure. The cleaning brush is in contact with the inner surface of the filter bucket, and a seal is provided between the rotating rod and the sealing cover.
[0020] Compared with the related art, the steam turbine vacuum leakage prevention pipeline system provided by the utility model has the following beneficial effects:
[0021] The utility model provides a steam turbine vacuum leakage prevention pipeline system. In order to reduce leakage of the pipeline connecting the steam turbine and the condenser, when the unit is started, the first shaft seal valve and the second shaft seal valve are closed, and the first valve and the second valve are opened at the same time. After the unit is normally loaded, the first shaft seal valve and the second shaft seal valve are opened first, and then the first valve and the second valve are closed, and the leaking steam pipeline to the condenser is switched to the shaft seal overflow mother pipe to avoid the problem of vacuum leakage of the condenser. When the unit is shut down, the first valve and the second valve are opened, and the first shaft seal valve and the second shaft seal valve are closed, and the water accumulated in the valve is pumped out by vacuum to prevent water accumulation in the valve. The condenser vacuum is improved by the structure, the economy of the unit is improved, and the reliability of the unit is improved. In summer, two vacuum pumps can be used and one can be used as a standby. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 A schematic structural diagram of a first embodiment of a steam turbine vacuum leakage prevention piping system provided by the utility model;
[0023] Figure 2 Provided for the utility model Figure 1 An enlarged view of point A is shown;
[0024] Figure 3 A schematic structural diagram of a second embodiment of a steam turbine vacuum leakage prevention piping system provided by the utility model;
[0025] Figure 4 A structural schematic diagram of a filter bucket is provided for the utility model;
[0026] Figure 5 The utility model provides a structural schematic diagram of a cleaning brush.
[0027] Numbers in the figure: 1. high-pressure cylinder, 2. high-pressure combined steam valve, 3. U-shaped sealing ring leakage pipe, 4. condenser, 5. shaft seal pipe, 6. shaft seal overflow control station, 7. first valve, 8. second valve, 9. first shaft seal valve, 10. second shaft seal valve, 11. rotating rod, 12. mounting frame, 13. connecting pipe, 14. filter box, 15. drain pipe, 16. drain valve, 17. display, 18. mounting shell, 19. sealing cover, 20. filter bucket, 21. driving motor, 22. heat dissipation hole, 23. cleaning brush, 27. mounting pipe. DETAILED DESCRIPTION
[0028] The utility model is further described below in conjunction with the accompanying drawings and implementation modes.
[0029] Please refer to Figure 1 , Figure 2 ,in, Figure 1 A schematic structural diagram of a first embodiment of a steam turbine vacuum leakage prevention piping system provided by the utility model; Figure 2 Provided for the utility model Figure 2 The enlarged view of point A is shown. The steam turbine vacuum leakage prevention piping system includes: high pressure cylinder 1;
[0030] Two high-pressure combined steam valves 2, the two high-pressure combined steam valves 2 are respectively installed at the two steam ports of the high-pressure combined steam valve 2, the outlets of the two high-pressure combined steam valves 2 are both installed with U-shaped sealing ring leakage pipes 3, the other end of one of the U-shaped sealing ring leakage pipes 3 is installed with a second valve 8, the other end of the other U-shaped sealing ring leakage pipe 3 is installed with a first valve 7, the other ends of the first valve 7 and the second valve 8 are connected to the inlet of the condenser 4 through the U-shaped sealing ring leakage pipe 3, and the outer surfaces of the two U-shaped sealing ring leakage pipes 3 are respectively installed with a first shaft sealing valve 9 and a second shaft sealing valve 10 through a mounting pipe 24;
[0031] The outlet of the condenser 4 is also provided with a U-shaped sealing ring steam leakage pipe 3. The other ends of the first shaft sealing valve 9 and the second shaft sealing valve 10 are connected to the shaft sealing pipe 5 through the installation pipe 24. The installation pipe 24 and the U-shaped sealing ring steam leakage pipe 3 are made of the same material. The connection between the first shaft sealing valve 9 and the second shaft sealing valve 10 and the first valve 7 and the second valve 8 can refer to Figure 1 The high-pressure cylinder 1 is the main component of the steam turbine, which converts steam energy into mechanical energy to drive the generator to generate electricity. The high-pressure combined steam valve 2 adjusts the steam flow and controls the turbine speed. The U-shaped sealing ring leakage pipe 3 creates a pressure difference between the inside and outside of the U-shaped sealing ring and recovers the U-shaped sealing ring leakage steam. The condenser 4 cools the steam after the turbine works and recycles it. The shaft seal pipe 5 provides sealing steam to the turbine shaft seal to prevent steam leakage and air leakage. The first valve 7 and the second valve 8 can allow the U-shaped sealing ring to leak steam to the condenser for switching. The first shaft seal valve 9 and the second shaft seal valve 10 can allow the U-shaped sealing ring to leak steam to the shaft seal for switching.
[0032] The outlet of the condenser 4 is provided with a shaft seal overflow control station 6 through a U-shaped sealing ring steam leakage pipe 3, and one end of the shaft seal overflow control station 6 is provided with a shaft seal pipe 5;
[0033] The shaft seal pipe 5 and the U-shaped seal ring steam leakage pipe 3 are also made of the same material, and the shaft seal overflow control station 6 automatically controls the shaft seal pressure to prevent overpressure.
[0034] The working principle of the steam turbine vacuum leakage prevention pipeline system provided by the utility model is as follows:
[0035] When the unit is started, close the first shaft seal valve 9 and the second shaft seal valve 10, and open the first valve 7 and the second valve 8 at the same time. After the unit is under normal load, open the first shaft seal valve 9 and the second shaft seal valve 10 first, and then close the first valve 7 and the second valve 8, and switch the steam leakage pipeline to the condenser to the shaft seal overflow main pipe to avoid vacuum leakage in the condenser. When shutting down, open the first valve 7 and the second valve 8, close the first shaft seal valve 9 and the second shaft seal valve 10, and use vacuum to pump out the water in the valve to prevent water accumulation in the valve.
[0036] Compared with the related art, the steam turbine vacuum leakage prevention pipeline system provided by the utility model has the following beneficial effects:
[0037] In order to reduce leakage in the pipeline connecting the turbine and the condenser 4, when the unit is started, the first shaft seal valve 9 and the second shaft seal valve 10 are closed, and the first valve 7 and the second valve 8 are opened at the same time. After the unit is under normal load, the first shaft seal valve 9 and the second shaft seal valve 10 are opened first, and then the first valve 7 and the second valve 8 are closed, and the leaking steam pipeline to the condenser is switched to the shaft seal overflow main pipe to avoid vacuum leakage in the condenser. When shutting down, the first valve 7 and the second valve 8 are opened, and the first shaft seal valve 9 and the second shaft seal valve 10 are closed. The water accumulated in the valve is pumped out by vacuum to prevent water accumulation in the valve. The vacuum of the condenser 4 is improved through this structure, the economy of the unit is improved, and the reliability of the unit is improved. In summer, two vacuum pumps can be used and one can be used as a backup.
[0038] Second embodiment
[0039] Please refer to Figure 3-Figure 4 - Figure 5 , Figure 3 A schematic structural diagram of a second embodiment of a steam turbine vacuum leakage prevention piping system provided by the utility model; Figure 4 A structural schematic diagram of a filter bucket is provided for the utility model; Figure 5 The utility model provides a schematic diagram of the structure of the cleaning brush. Based on the steam turbine vacuum leakage prevention pipeline system provided by the first embodiment of the present application, the second embodiment of the present application proposes another steam turbine vacuum leakage prevention pipeline system. The second embodiment is only a preferred embodiment of the first embodiment, and the implementation of the second embodiment will not affect the independent implementation of the first embodiment.
[0040] Specifically, the difference of the steam turbine vacuum leakage prevention piping system provided in the second embodiment of the present application is that the inlet of the condenser 4 is fixedly connected with a connecting pipe 13, the other end of the connecting pipe 13 is fixedly connected with a filter box 14, and a display 17 is installed on the front of the filter box 14;
[0041] The display 17 can be a tablet computer that can operate the device. The connecting pipe 13 and the U-shaped sealing ring steam leakage pipe 3 are made of the same material.
[0042] A filter hopper 20 is installed inside the filter box 14, a sewage pipe 15 is fixedly connected to the bottom of the filter hopper 20, and a sewage valve 16 is installed at the other end of the sewage pipe 15;
[0043] The sewage pipe 15 is sealed at the connection point of the filter box 14, and the filter hopper 20 is in the shape of a funnel. Figure 4 .
[0044] A sealing cover 19 is installed on the top of the filter box 14, and a mounting shell 18 is installed on the top of the sealing cover 19. The front and back sides of the mounting shell 18 are provided with heat dissipation holes 22;
[0045] A U-shaped sealing ring steam leakage pipe 3 is installed on the sealing cover 19 and is connected to the first valve 7 and the second valve 8. The heat dissipation hole 22 is used to assist heat dissipation.
[0046] A driving motor 21 is installed inside the mounting shell 18, a rotating rod 11 is installed at the output end of the driving motor 21, and a cleaning brush 23 is installed on the outer surface of the rotating rod 11 through a mounting frame 12;
[0047] The position of the mounting bracket 12 can be referred to Figure 5 The cleaning brush 23 contacts the inner surface of the filter bucket 20, and a sealing process is performed between the rotating rod 11 and the sealing cover 19, but the rotation of the rotating rod 11 is not affected.
[0048] Compared with the related art, the steam turbine vacuum leakage prevention pipeline system provided by the utility model has the following beneficial effects:
[0049] In order to prevent water or steam containing impurities from entering the interior of the condenser 4, a filter box 14 is installed at the inlet of the condenser 4 through a connecting pipe 13, and a filter bucket 20 with a drain pipe 15 is installed inside the filter box 14, and then the filter box 14 will be sealed using a sealing cover 19 with a pipeline, and a cleaning brush 23 that can clean the filter bucket 20 is installed inside the filter box 14 through a driving motor 21. In actual use, water or steam containing impurities enters the interior of the filter box 14 through the U-shaped sealing ring leakage pipe 3, and is filtered through the filter bucket 20. The filtered water or steam enters the interior of the condenser 4 through the connecting pipe 13, and the filtered impurities will flow into the interior of the drain pipe 15. After that, it is only necessary to start the driving motor 21 regularly to drive the cleaning brush 23 to clean the inner surface of the filter bucket 20 to avoid blockage, and the impurities inside the drain pipe 15 can be discharged by only regularly opening the drain valve 16. Through this design, the water or steam entering the interior of the condenser 4 can be filtered, and the impurities entering the interior of the condenser 4 to affect normal use are reduced.
[0050] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A steam turbine vacuum leakage prevention piping system, characterized in that: include: High pressure cylinder; Two high-pressure combined steam valves, the two high-pressure combined steam valves are respectively installed at the two steam ports of the high-pressure combined steam valve, the outlets of the two high-pressure combined steam valves are both installed with U-shaped sealing ring steam leakage pipes, the other end of one of the U-shaped sealing ring steam leakage pipes is installed with a second valve, the other end of the other U-shaped sealing ring steam leakage pipe is installed with a first valve, the other ends of the first valve and the second valve are connected to the inlet of the condenser through the U-shaped sealing ring steam leakage pipe, and the outer surfaces of the two U-shaped sealing ring steam leakage pipes are respectively installed with a first shaft sealing valve and a second shaft sealing valve through a mounting pipe.
2. The steam turbine vacuum leakage prevention piping system according to claim 1, characterized in that: The outlet of the condenser is provided with a shaft seal overflow control station via a U-shaped sealing ring steam leakage pipeline, and one end of the shaft seal overflow control station is provided with a shaft seal pipeline.
3. The steam turbine vacuum leakage prevention piping system according to claim 1, characterized in that: The inlet of the condenser is fixedly connected with a connecting pipe, the other end of the connecting pipe is fixedly connected with a filter box, and a display is installed on the front of the filter box.
4. The steam turbine vacuum leakage prevention piping system according to claim 3, characterized in that: A filter bucket is installed inside the filter box, a sewage pipe is fixedly connected to the bottom of the filter bucket, and a sewage valve is installed at the other end of the sewage pipe.
5. The steam turbine vacuum leakage prevention piping system according to claim 3, characterized in that: A sealing cover is installed on the top of the filter box, a mounting shell is installed on the top of the sealing cover, and heat dissipation holes are opened on the front and back of the mounting shell.
6. The steam turbine vacuum leakage prevention piping system according to claim 5, characterized in that: A driving motor is installed inside the installation shell, a rotating rod is installed at the output end of the driving motor, and a cleaning brush is installed on the outer surface of the rotating rod through a mounting frame.