Multi-channel multi-instrument automatic gas sample injector

Through the design of a multi-channel multi-instrument automatic gas sampler, the multi-gas switching device and vacuum pump combined with a three-way valve are used to solve the problem that only samples and residual gas can be provided for one analytical instrument in the prior art, and the impact measurement of samples and residual gases can be achieved. Multiple instrument combination and rapid detection reduce sample consumption and detection time.

CN222050231UActive Publication Date: 2024-11-22AIBONENG (GUANGZHOU) SCI & TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420441328.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-07
Publication Date
2024-11-22
Estimated Expiration
2034-03-07

AI Technical Summary

Technical Problem

The existing multi-channel switching valve can only provide samples for one analytical instrument, and the mixing of residual gas with new gas during switching affects the measurement value, resulting in increased sample consumption and extended measurement time, especially when the sample volume is small.

Method used

A multi-channel multi-instrument automatic gas sampler is designed, and a multi-gas switching device and a vacuum pump are used to combine multiple instruments and fast gas switching, automatically extracting residual gas, reducing sample consumption and measurement time.

Benefits of technology

It realizes rapid and automated inspection of multiple instruments, reduces sample consumption and detection time, improves gas analysis efficiency, and saves time for experimental personnel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222050231U_ABST
    Figure CN222050231U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of automatic sampling equipment for gas analysis, and discloses a multi-channel multi-instrument automatic gas sampler which comprises a multi-gas-path switching device, at least two sample bottles, at least two sample switching valves connected with the sample bottles respectively, at least two sample analyzers, a gas inlet pipeline and a gas outlet pipeline, the multi-way switching valve device can be connected with a plurality of gas samples at the same time, and the function of rapidly switching different gas samples is achieved; the gas tee joint can quickly switch gas channels, and a plurality of tee joints are matched with one another to realize gas channel vacuumizing or transportation, and also have the function of multi-instrument connection; the gas pipeline is connected with all the devices to realize gas transportation; the vacuum pump is matched with the switching valve and the tee joint to pump away residual gas influencing the test in the gas path, and the vacuum pump can also provide gas transportation for the analyzer. The device can be used for automatically conveying various samples to one or more analyzers, so that the personnel demand is reduced, the sample consumption is reduced, and the detection time is effectively shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of automatic sampling equipment for gas analysis, and more specifically to a multi-channel multi-instrument automatic gas sampler. Background Art

[0002] The multi-channel gas path switching valve can quickly open or close the required injection channel to switch the target sample for subsequent analytical instruments.

[0003] At present, multi-channel switching valves are widely used in various fields, but there are still areas that can be improved. For example, due to the shared outlet pipe, samples can only be provided to one analytical instrument. In addition, when switching to other samples, the residual gas in the shared outlet pipe will mix with the newly switched gas, causing the gas concentration to change and affecting the measured value. This requires continuous sampling to completely clean the residual gas from the previous time from the gas line and analyzer, and a certain amount of sample needs to be consumed during this period. When the sample amount is small, it will bring difficulties to subsequent analysis. Utility Model Content

[0004] The technical problem to be solved by the utility model is to overcome the above problems existing in the prior art and provide a multi-channel multi-instrument automatic gas sampler.

[0005] In order to solve the problem of only being able to provide samples for one analytical instrument, the utility model uses a plurality of tee designs to achieve rapid switching of gas circuits while meeting the working conditions of the analytical instrument (such as maintaining a certain pressure and flow, maintaining gas flow, etc.), thereby achieving the purpose of using multiple instruments in conjunction. In addition, the device is equipped with a vacuum pump, which can be used with the tee to extract the residual gas in the gas circuit and the switching valve, effectively reducing the residual gas, thereby achieving the purpose of reducing sample consumption and reducing instrument measurement time. In addition, the above accessories are all controlled by an automatic control system, and there is no need for the experimenter to wait and operate the instrument for a long time. The device effectively improves the efficiency of gas analysis, reduces the sample volume requirement, and saves the experimenter's time.

[0006] The purpose of the utility model is achieved through the following technical solutions:

[0007] A multi-channel multi-instrument automatic gas sampler, comprising a multi-gas path switching device, at least two sample bottles, at least two sample switch valves respectively connected to the sample bottles, at least two sample analyzers, an air inlet pipeline and an air outlet pipeline;

[0008] Each of the sample switch valves leads to a multi-gas path switching device for switching different sample measurement channels;

[0009] The multi-gas-path switching device leads to the first three-way valve, the first outlet of the first three-way valve is connected to the first vacuum pump, the second outlet of the first three-way valve is connected to the inlet of the multi-gas-path switching valve, the multi-gas-path switching valve is provided with N+1 outlets, wherein the Nth outlet of the multi-gas-path switching valve is connected to the first inlet of the third three-way valve, and the second inlet of the third three-way valve can be connected to air; the outlet of the third three-way valve is connected to the first sample analyzer and the second vacuum pump in sequence;

[0010] The N+1th outlet of the multi-gas path switching valve is also connected to the first inlet of the N+3th three-way valve, and the second inlet of the N+3th three-way valve can be connected to air; the outlet of the N+3th three-way valve is connected to the N+1th sample analyzer and the N+2th vacuum pump in sequence;

[0011] Wherein, N is a natural number and N≥1.

[0012] Preferably, when N is equal to 1; the multi-gas-circuit switching device leads to the first three-way valve, the first outlet of the first three-way valve is connected to the first vacuum pump, the second outlet of the first three-way valve is connected to the inlet of the multi-gas-circuit switching valve, the first outlet of the multi-gas-circuit switching valve is connected to the first inlet of the third three-way valve, and the second outlet of the multi-gas-circuit switching valve is connected to the first inlet of the fourth three-way valve; the second inlet of the third three-way valve can be connected to the air, and the outlet of the third three-way valve is connected to the first sample analyzer and the second vacuum pump in sequence; the second inlet of the fourth three-way valve can be connected to the air, and the outlet of the fourth three-way valve is connected to the second sample analyzer and the third vacuum pump in sequence.

[0013] Preferably, when N is equal to 1; the multi-gas circuit switching device leads to the first three-way valve, the second outlet of the first three-way valve is connected to the first inlet of the multi-gas circuit switching valve, the second outlet of the multi-gas circuit switching valve is connected to the first inlet of the third three-way valve, and the second outlet of the multi-gas circuit switching valve is connected to the first inlet of the fourth three-way valve; the second inlet of the third three-way valve can be connected to the air, and the outlet of the third three-way valve is connected to the first sample analyzer and the second vacuum pump in sequence; the first outlet of the first three-way valve is directly connected to the vacuum pump, so that the vacuum pump simultaneously evacuates the analyzer and the pipeline.

[0014] Preferably, when N is equal to 2; the multi-gas-path switching device leads to the first three-way valve, the first outlet of the first three-way valve is connected to the first vacuum pump, the second outlet of the first three-way valve is connected to the first inlet of the multi-gas-path switching valve, the first outlet of the multi-gas-path switching valve is connected to the first inlet of the third three-way valve, the second inlet of the third three-way valve can be connected to air, and the outlet of the third three-way valve is connected to the first sample analyzer and the second vacuum pump in sequence; the second outlet of the multi-gas-path switching valve is connected to the first inlet of the fourth three-way valve, the second inlet of the fourth three-way valve can be connected to air, and the outlet of the fourth three-way valve is connected to the second sample analyzer and the third vacuum pump in sequence;

[0015] The third outlet of the multi-gas path switching valve is connected to the first inlet of the fifth three-way valve, the second inlet of the fifth three-way valve can be connected to air, and the outlet of the fifth three-way valve is connected to the third sample analyzer and the fourth vacuum pump in sequence.

[0016] Compared with the prior art, the utility model has the following beneficial effects:

[0017] The utility model discloses a multi-channel multi-instrument combined automatic gas sampler, which realizes the rapid and automatic detection of multiple gas samples by multiple instruments. It includes a multi-way gas switching valve device, multiple switch valves, multiple gas tees, gas pipelines, and multiple vacuum pumps. The multi-way switching valve device can connect multiple gas samples at the same time and realize the function of quickly switching different gas samples; the gas tee can quickly switch the gas channel, and multiple tees cooperate with each other to realize the vacuum or transportation of the gas circuit, and also has the function of connecting multiple instruments; the gas pipeline connects various devices to realize gas transportation; the vacuum pump cooperates with the switching valve and the tee to extract the residual gas in the gas circuit that affects the test, and the vacuum pump can also provide gas transportation for the analyzer. The device can automatically transport multiple samples to one or more analyzers, reduce the need for personnel, reduce sample consumption, and effectively reduce the detection time. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 An implementation method of a multi-channel multi-instrument automatic gas sampler (connected to two gas analyzers);

[0019] Figure 2 Another embodiment of a multi-channel multi-instrument automatic gas sampler (connected to two gas analyzers);

[0020] Figure 3 Another implementation of a multi-channel multi-instrument automatic gas injector (connected to three gas analyzers). DETAILED DESCRIPTION

[0021] The specific implementation methods of the present invention are further described below. It should be noted that the description of these implementation methods is used to help understand the present invention, but does not constitute a limitation of the present invention. In addition, the technical features involved in the various implementation methods of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0022] Example 1

[0023] Multi-channel multi-instrument automatic gas injector, such as Figure 1 As shown, it includes multiple sample bottle switch valves, multiple gas path switching devices, a tee, a vacuum pump, and a gas pipeline.

[0024] Three-way valve (Explanation: A is the inlet of the three-way valve, B is the outlet 1 of the three-way valve, and C is the outlet 2 of the three-way valve. The number after the letter is the number of the three-way valve, such as the inlet of the three-way valve 1 is A1, and the outlet 1 of the three-way valve 2 is B2. Three-way valve 3 and three-way valve 4 have two inlets, distinguished by "A31" and "A32", and "A41" and "A42").

[0025] This embodiment provides a multi-channel multi-instrument automatic gas sampler, including a multi-gas path switching device, at least two sample bottles, at least two sample switch valves respectively connected to the sample bottles, two sample analyzers, an air inlet pipeline and an air outlet pipeline;

[0026] Each of the sample switch valves leads to a multi-gas path switching device for switching different sample measurement channels; the multi-gas path switching device leads to a first three-way valve (in this embodiment, Figure 1 The first outlet of the first three-way valve (in this embodiment, Figure 1 B1) and the first vacuum pump (in this embodiment Figure 1 The second outlet of the first three-way valve (in this embodiment Figure 1 C1) and the second three-way valve (in this embodiment Figure 1 The inlet of the three-way valve 2) (in this embodiment Figure 1 A2) is connected to the first outlet of the second three-way valve (in this embodiment Figure 1 B2) and the third three-way valve (in this embodiment Figure 1 The first inlet of the three-way valve 3) (in this embodiment Figure 1 A31 of the second three-way valve is connected, and the second outlet of the second three-way valve (in this embodiment Figure 1 C2) and the fourth three-way valve (in this embodiment Figure 1 The first inlet of the three-way valve 4) (in this embodiment Figure 1 A41 of the third three-way valve is connected; the second inlet of the third three-way valve (in this embodiment is Figure 1A32 of the third three-way valve) can be connected to air, and the outlet of the third three-way valve (in this embodiment is Figure 1 C3) is sequentially connected to the first sample analyzer (in this embodiment Figure 1 Analyzer 1), the second vacuum pump (in this embodiment Figure 1 The second inlet of the third three-way valve (in this embodiment Figure 1 A32 of the fourth three-way valve) can be connected to air, and the second inlet of the fourth three-way valve (in this embodiment Figure 1 A42 of the fourth three-way valve) can also be connected to air, and the outlet of the fourth three-way valve (in this embodiment Figure 1 C4) is sequentially connected to the second sample analyzer (in this embodiment Figure 1 Analyzer 2), the third vacuum pump (in this embodiment Figure 1 The vacuum pump 3) is connected.

[0027] Specifically, in this embodiment, three sample bottles, namely, sample bottle 1, sample bottle 2 and sample bottle 3, are shown, corresponding to three sample switch valves, namely, switch valve 1, switch valve 2 and switch valve 3. Switch valve 1, switch valve 2 and switch valve 3 are all connected to a multi-gas path switching device, and the other side of the multi-gas path switching device is connected to a three-way valve 1, so that the gas of the multi-gas path switching device enters the inlet A1 of the three-way valve 1, and the first outlet B1 of the three-way valve 1 is connected to the vacuum pump 1; the second outlet C1 of the three-way valve 1 is connected to the inlet A2 of the three-way valve 2, and the first outlet B2 of the three-way valve 2 is connected to the first inlet A31 of the three-way valve 3; the second outlet C2 of the three-way valve 2 is connected to the first inlet A41 of the three-way valve 4; the second inlet A32 of the three-way valve 3 can be directly connected to the air, and the outlet C3 of the three-way valve 3 is connected to the analyzer 1, and the analyzer 1 is connected to the vacuum pump 2; the second inlet A42 of the three-way valve 4 can be directly connected to the air, and the outlet C4 of the three-way valve 4 is connected to the analyzer 2 and the vacuum pump 3 in sequence.

[0028] The outlet of the multi-gas circuit switching device is connected to a three-way valve 1 (A1), which can switch the device from the sample transport state to the vacuum state. One end of the three-way valve outlet B1 is connected to the vacuum pump 1, and the other end C1 leads to the inlet (A2) of the three-way valve 2. The three-way valve 2 can select which analytical instrument the sample is directed to by switching the outlets (B2, C2), wherein the outlet B2 is connected to the inlet A31 of the three-way valve 3, and the outlet C2 is connected to the inlet A41 of the three-way valve 4. The three-way valve 3 and the three-way valve 4 have two inlets, inlet 1 (A31, A41) is the sample gas inlet, and inlet 2 (A32, A42) is the air inlet. When the sample gas is not connected, inlet 2 will be opened. This is to keep the working pressure of the gas analyzer at a normal level, so as to avoid the vacuum pump being constantly pumping gas due to the lack of gas in the gas circuit, resulting in too low pressure and damage to the analyzer. The only outlets (C3, C4) of the three-way valve 3 and the three-way valve 4 are connected to the analyzer. Among them, the sample bottle is connected to the multi-channel gas switching device through a switch valve. All switch valves are closed by default. The switch valves of the corresponding sample bottles are opened only when the samples are tested. When the sample test is completed and the next sample bottle needs to be switched, the switch valves are closed to evacuate the gas line to quickly clean up the residual gas in the gas line.

[0029] The above valves can be switched manually or electrically. The vacuum pump can extract the sample gas remaining at the front end of the analyzer pipeline, and different functions can be realized by switching the above three-way valve 1. The number of vacuum pumps can be increased or decreased according to the number of analyzers and the working principle.

[0030] Example 2

[0031] In this embodiment, the analyzer and the vacuum pump can be used to simultaneously evacuate the analyzer and evacuate the pipeline. Figure 2 As shown, the rest of the structure is the same as that of Example 1.

[0032] The multi-gas path switching device leads to the first three-way valve (in this embodiment Figure 2 The second outlet of the first three-way valve (in this embodiment Figure 2 C1) and the second three-way valve (in this embodiment Figure 2 The inlet of the three-way valve 2) (in this embodiment Figure 2 A2) is connected to the first outlet of the second three-way valve (in this embodiment Figure 2 B2) and the third three-way valve (in this embodiment Figure 2 The first inlet of the three-way valve 3) (in this embodiment Figure 2 A31 of the second three-way valve is connected, and the second outlet of the second three-way valve (in this embodiment Figure 2 C2) and the fourth three-way valve (in this embodiment Figure 2 The first inlet of the three-way valve 4) (in this embodiment Figure 2A41 of the third three-way valve is connected; the second inlet of the third three-way valve (in this embodiment is Figure 2 A32 of the third three-way valve) can be connected to air, and the outlet of the third three-way valve (in this embodiment is Figure 2 C3) is sequentially connected to the first sample analyzer (in this embodiment Figure 2 Analyzer 1), the first vacuum pump (in this embodiment Figure 2 The first outlet of the first three-way valve (in this embodiment Figure 2 B1) is also directly connected to the first vacuum pump (in this embodiment Figure 2 The vacuum pump 1) enables the first vacuum pump to simultaneously evacuate the first sample analyzer and evacuate the pipeline; the second inlet of the fourth three-way valve (in this embodiment Figure 2 A42 of the fourth three-way valve) can be connected to the air, and the outlet of the fourth three-way valve (in this embodiment Figure 2 C4) is sequentially connected to the second sample analyzer (in this embodiment Figure 2 Analyzer 2), the second vacuum pump (in this embodiment Figure 2 The vacuum pump 2) is connected.

[0033] This embodiment shows three sample bottles, namely sample bottle 1, sample bottle 2 and sample bottle 3, corresponding to three sample switch valves, namely switch valve 1, switch valve 2 and switch valve 3. The switch valve 1, the switch valve 2 and the switch valve 3 are all connected to the multi-gas path switching device, and the other side of the multi-gas path switching device is connected to the three-way valve 1, so that the gas of the multi-gas path switching device enters the inlet A1 of the three-way valve 1, and the second outlet C2 of the three-way valve 1 is connected to the inlet A2 of the three-way valve 2, and the first outlet B2 of the three-way valve 2 is connected to the first inlet A31 of the three-way valve 3; the second outlet C2 of the three-way valve 2 is connected to the first inlet A41 of the three-way valve 4; the second inlet A32 of the three-way valve 3 can be directly connected to the air, and the outlet C3 of the three-way valve 3 is connected to the analyzer 1, and the analyzer 1 is connected to the vacuum pump 1; the first outlet B1 of the three-way valve 1 is also connected to the vacuum pump 1; so that the vacuum pump 1 can simultaneously evacuate the analyzer 1 and the pipeline; the second inlet A42 of the three-way valve 4 can be directly connected to the air, and the outlet C4 of the three-way valve 4 is connected to the analyzer 2 and the vacuum pump 2 in sequence.

[0034] Example 3

[0035] like Figure 3 As shown, the rest of the structure is the same as that of Example 1.

[0036] The multi-gas path switching device leads to the first three-way valve (in this embodiment Figure 3 The first outlet of the first three-way valve (in this embodiment, Figure 3 B1) and the first vacuum pump (in this embodiment Figure 3The second outlet of the first three-way valve (in this embodiment Figure 1 C1) and the inlet of the multi-way valve (in this embodiment Figure 3 A2) is connected.

[0037] The first outlet of the multi-way valve (in this embodiment Figure 3 B2) and the third three-way valve (in this embodiment Figure 3 The first inlet of the three-way valve 3) (in this embodiment Figure 3 A31 of the third three-way valve is connected to the second inlet of the third three-way valve (in this embodiment Figure 3 A32 of the third three-way valve) can be connected to air, and the outlet of the third three-way valve (in this embodiment is Figure 3 C3) is sequentially connected to the first sample analyzer (in this embodiment Figure 3 Analyzer 1), the second vacuum pump (in this embodiment Figure 3 The second outlet of the multi-way valve (in this embodiment Figure 3 C2) and the first inlet of the fourth three-way valve (in this embodiment Figure 3 A41 of the fourth three-way valve is connected, and the second inlet of the fourth three-way valve (in this embodiment Figure 3 A42 of the fourth three-way valve) can be connected to air, and the outlet of the fourth three-way valve (in this embodiment is Figure 3 C4) is sequentially connected to the second sample analyzer (in this embodiment Figure 3 Analyzer 2), the fourth vacuum pump (in this embodiment Figure 3 The third outlet of the multi-way valve (in this embodiment Figure 3 D2) and the first inlet of the fifth three-way valve (in this embodiment Figure 3 A51 of the fifth three-way valve is connected to the second inlet of the fifth three-way valve (in this embodiment Figure 3 A52 of the fifth three-way valve) can be connected to air, and the outlet of the fifth three-way valve (in this embodiment is Figure 3 C5) is sequentially connected to the third sample analyzer (in this embodiment Figure 3 Analyzer 3), the third vacuum pump (in this embodiment Figure 3 The vacuum pump 3) is connected.

[0038] In this embodiment, three sample bottles are shown, namely, sample bottle 1, sample bottle 2 and sample bottle 3, corresponding to three sample switch valves, namely, switch valve 1, switch valve 2 and switch valve 3. Switch valve 1, switch valve 2 and switch valve 3 are all connected to a multi-gas switching device, and the other side of the multi-gas switching device is connected to a three-way valve 1, so that the gas of the multi-gas switching device enters the inlet A1 of the three-way valve 1, and one end of the outlet B1 of the three-way valve 1 is connected to the vacuum pump 1, and the other end C1 leads to the inlet (A2) of the multi-way valve. The first outlet B2 of the multi-way valve is connected to the inlet A31 of the three-way valve 3, the second inlet A32 of the three-way valve 3 can be directly connected to the air, and the outlet C3 of the three-way valve 3 is connected to the analyzer 1, and the analyzer 1 is connected to the vacuum pump 2; the second outlet C2 of the multi-way valve is connected to the first inlet A41 of the three-way valve 4; the second inlet A42 of the three-way valve 4 can be directly connected to the air, and the outlet C4 of the three-way valve 4 is connected to the analyzer 2 and the vacuum pump 4 in sequence; the third outlet D2 of the multi-way valve is connected to the first inlet A51 of the three-way valve 5; the second inlet A52 of the three-way valve 5 can be directly connected to the air, and the outlet C5 of the three-way valve 5 is connected to the analyzer 3 and the vacuum pump 3 in sequence.

[0039] The embodiments of the present invention are described in detail above, but the present invention is not limited to the described embodiments. For those skilled in the art, various changes, modifications, substitutions and variations of these embodiments are made without departing from the principles and spirit of the present invention, and still fall within the scope of protection of the present invention.

Claims

1. A multi-channel multi-instrument automatic gas sampler, characterized in that: It includes a multi-gas path switching device, at least two sample bottles, at least two sample switch valves respectively connected to the sample bottles, at least two sample analyzers, an air inlet pipeline and an air outlet pipeline; Each of the sample switch valves leads to a multi-gas path switching device for switching different sample measurement channels; The multi-gas-path switching device leads to the first three-way valve, the first outlet of the first three-way valve is connected to the first vacuum pump, the second outlet of the first three-way valve is connected to the inlet of the multi-gas-path switching valve, the multi-gas-path switching valve is provided with N+1 outlets, wherein the Nth outlet of the multi-gas-path switching valve is connected to the first inlet of the third three-way valve, and the second inlet of the third three-way valve can be connected to air; the outlet of the third three-way valve is connected to the first sample analyzer and the second vacuum pump in sequence; The N+1th outlet of the multi-gas path switching valve is also connected to the first inlet of the N+3th three-way valve, and the second inlet of the N+3th three-way valve can be connected to air; the outlet of the N+3th three-way valve is connected to the N+1th sample analyzer and the N+2th vacuum pump in sequence; Wherein, N is a natural number and N≥1.

2. The multi-channel multi-instrument automatic gas sampler according to claim 1, characterized in that: When N is equal to 1; The multi-gas-circuit switching device leads to the first three-way valve, the first outlet of the first three-way valve is connected to the first vacuum pump, the second outlet of the first three-way valve is connected to the inlet of the multi-gas-circuit switching valve, the first outlet of the multi-gas-circuit switching valve is connected to the first inlet of the third three-way valve, and the second outlet of the multi-gas-circuit switching valve is connected to the first inlet of the fourth three-way valve; the second inlet of the third three-way valve can be connected to the air, and the outlet of the third three-way valve is connected to the first sample analyzer and the second vacuum pump in sequence; the second inlet of the fourth three-way valve can be connected to the air, and the outlet of the fourth three-way valve is connected to the second sample analyzer and the third vacuum pump in sequence.

3. The multi-channel multi-instrument automatic gas sampler according to claim 1, characterized in that: When N is equal to 1; The multi-gas-circuit switching device leads to the first three-way valve, the second outlet of the first three-way valve is connected to the first inlet of the multi-gas-circuit switching valve, the second outlet of the multi-gas-circuit switching valve is connected to the first inlet of the third three-way valve, and the second outlet of the multi-gas-circuit switching valve is connected to the first inlet of the fourth three-way valve; the second inlet of the third three-way valve can be connected to the air, and the outlet of the third three-way valve is connected to the first sample analyzer and the second vacuum pump in sequence; the first outlet of the first three-way valve is directly connected to the vacuum pump, so that the vacuum pump can simultaneously evacuate the analyzer and the pipeline.

4. The multi-channel multi-instrument automatic gas sampler according to claim 1, characterized in that: When N is equal to 2; The multi-gas-path switching device leads to the first three-way valve, the first outlet of the first three-way valve is connected to the first vacuum pump, the second outlet of the first three-way valve is connected to the first inlet of the multi-gas-path switching valve, the first outlet of the multi-gas-path switching valve is connected to the first inlet of the third three-way valve, the second inlet of the third three-way valve can be connected to air, and the outlet of the third three-way valve is connected to the first sample analyzer and the second vacuum pump in sequence; the second outlet of the multi-gas-path switching valve is connected to the first inlet of the fourth three-way valve, the second inlet of the fourth three-way valve can be connected to air, and the outlet of the fourth three-way valve is connected to the second sample analyzer and the third vacuum pump in sequence; The third outlet of the multi-gas path switching valve is connected to the first inlet of the fifth three-way valve, the second inlet of the fifth three-way valve can be connected to air, and the outlet of the fifth three-way valve is connected to the third sample analyzer and the fourth vacuum pump in sequence.