Opening-to-opening adjusting device for transportation of large flue in limited space

By designing a large flue transportation counterpart adjustment device in the confined space in the sintering machine system, the gantry, electric reverse chain, automatic decoupler and jack are used to solve the problem of transportation and counterpart difficulties of flue gas pipelines in the confined space. , realizes accurate counterpart and efficient welding of pipeline modules, reducing installation difficulty.

CN222063969UActive Publication Date: 2024-11-26SHANGHAI ERSHIYE CONSTR CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420758222.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-12
Publication Date
2024-11-26
Estimated Expiration
2034-04-12

AI Technical Summary

Technical Problem

In the sintering machine system, the installation of the flue gas pipeline in a confined space has problems such as transportation difficulties, counterpart difficulties and welding difficulties, which leads to extremely difficult installation.

Method used

A large flue transportation counterpart adjustment device in confined space is designed, including a gantry, electric reverse chain, automatic decoupler and jack. Through these devices, the pipe module can be lifted, moved and aligned, and the pipe module can be realized to achieve the precise counterpart of the pipe module and welding.

Benefits of technology

The device can easily and quickly transport the pipeline module to the installation position of the frame beam, and accurately counterpart and welding of the pipeline module through electric reverse chains and jacks, improving construction efficiency, reducing the use of auxiliary tools, and reducing installation difficulty.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222063969U_ABST
    Figure CN222063969U_ABST
Patent Text Reader

Abstract

The utility model relates to a large flue transportation opening aligning adjusting device in a limited space, which comprises a portal frame, the portal frame comprises two supports, the tops of the two supports are fixedly connected with a cross beam, each support comprises two oblique beams, the tops of the two oblique beams are fixedly connected, the bottoms of the two oblique beams are connected through a walking part, and the two oblique beams and the walking part form a triangular structure. Two hanging lugs are fixed to the cross beam, electric chain blocks are hung on the two hanging lugs, two automatic detachers are fixed to the bottom of each electric chain block, and jacks are fixed to the opposite inner sides of the two supports. In the transportation process, the pipeline module is always in a horizontal state, the pipeline module can be conveniently and rapidly transported to the installation position of the frame beam through the walking part, and when opening alignment is needed in the follow-up pipeline module installation, the upper and lower elevation correction of the pipeline module is conducted through the lifting of the electric chain block; and the left and right elevation correction of the pipeline module is performed through the four jacks, so that the accurate alignment of the pipeline module can be quickly realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of flue installation, in particular to a large flue transport matching adjustment device in a confined space. Background Art

[0002] The sintering process is to sinter various iron ore raw materials into block-shaped finished sintered ore under high temperature and high pressure conditions, which provides qualified raw materials for blast furnace smelting and is one of the important and indispensable processes in steel smelting. A large amount of flue gas rich in nitrogen oxides, sulfur dioxide, carbon dioxide and various dusts will be generated during the sintering process. The flue gas is collected through the main exhaust flue gas duct under the sintering machine, and sent to environmental protection dust removal facilities such as electrostatic precipitator, adsorption and analysis tower, and denitrification device. It is discharged after purification. The sintering machine plant is a concrete frame structure with a sintering machine on the top, the main exhaust flue gas duct in the middle, and a belt conveyor at the bottom.

[0003] In the sintering machine system installation project, the installation of flue gas ducts is one of the key and difficult points. The installation volume is large, the installation route is long, the number of interfaces is large, the welding volume is large, the diameter of the flue gas duct is φ5.4m-φ6.7m, and the unit weight is 15t~20t after the assembly is completed. It is installed on a +7.2m frame beam. The installation space is 155m long * 8.5m wide * 9.3m high, the upper part is a fully enclosed reinforced concrete platform, and the side is a semi-enclosed strip confined space with reinforced concrete columns equidistantly distributed at a spacing of 7.2 meters. The construction process is all high-altitude operations, the working surfaces on both sides are less than 1.0m, the working surface is narrow, the unit weight of the pipeline module is large, and it is difficult to transport in the confined space, difficult to match and difficult to weld. The current commonly used installation solution is lifting with lifting equipment outside the plant + setting a winch inside + pulling it into place with inclined force + workers welding on a narrow working surface. This solution still cannot solve the problems of difficult transportation, matching and welding of pipeline modules, so the installation of the main exhaust flue gas duct is extremely difficult. Utility Model Content

[0004] The main purpose of the utility model is to propose a large flue transport matching adjustment device in a confined space, which can effectively solve the problems in the background technology.

[0005] In order to achieve the above objectives, the present invention is implemented through the following technical solutions:

[0006] A device for adjusting the transportation of large flue gas in a confined space comprises a gantry, the gantry comprises two brackets, the tops of the two brackets are fixedly connected with a cross beam, the brackets comprise two inclined beams, the tops of the two inclined beams are fixedly connected, the bottoms are connected by a running part, the two inclined beams and the running part form a triangular structure, two hanging ears are fixed on the cross beam, two hanging ears are hung with electric fall chains, two automatic unhooks are fixed on the bottom of each electric fall chain, and jacks are fixed on the relative inner sides of the two brackets.

[0007] Optionally, a plurality of ladder steps are fixed to the outer sides of the two inclined beams in the bracket.

[0008] Optionally, a running brake switch control box is provided on the inclined beam, and the running brake switch control box is used to control the running part, and the running brake switch control box is connected to an operating handle via a cable.

[0009] Optionally, there are four jacks in total, which are individually fixed on the inner sides of the four inclined beams, and the four jacks are symmetrically arranged at the same elevation.

[0010] Optionally, a U-shaped groove is fixed on the inner side of the four inclined beams, and the bottoms of the four jacks are embedded in and fixed in the U-shaped groove.

[0011] The utility model provides a large flue transport matching adjustment device in a confined space, which has the following beneficial effects:

[0012] The four automatic unhookers are securely fixed to the lifting ears on the pipeline module, and the pipeline module is lifted to an appropriate height by an electric fall chain. The running gear is then operated to move the device on the full-length guide rail to transport the pipeline module to the installation position of the frame beam. Both sides of the pipeline module are connected to two automatic unhookers. During the transportation process, the pipeline module is always in a horizontal state. The running gear can conveniently and quickly transport the pipeline module to the installation position of the frame beam. After installation in place, the pull rope of the automatic unhooker is pulled to achieve automatic unhooking. When alignment is required during the subsequent installation of the pipeline module, the upper and lower elevations of the pipeline module are corrected by lifting and lowering the electric fall chain, and the left and right elevations of the pipeline module are corrected by four jacks, which can quickly achieve accurate alignment of the pipeline module. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a front view of the transport docking adjustment device of the utility model;

[0014] Figure 2 It is a side view of the transport docking adjustment device of the utility model;

[0015] Figure 3 This is a schematic diagram of the installation structure of the pipeline module of the utility model.

[0016] In the figure: 1. gantry; 11. bracket; 12. crossbeam; 111. inclined beam; 112. running gear; 2. hanging ears; 3. electric fall chain; 4. automatic unhooking device; 5. jack; 6. ladder steps; 7. running brake switch control box; 8. cable; 9. operating handle; 10. U-shaped slot; 100. pipeline module. DETAILED DESCRIPTION

[0017] In order to make the purpose, technical solution and advantages of the utility model clearer, the technical solution of the utility model will be clearly and completely described below in conjunction with the accompanying drawings of the utility model.

[0018] The technical solution of the utility model will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0019] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.

[0020] In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, "multiple" means two or more, unless otherwise clearly and specifically defined. In addition, the terms "installed", "connected", and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal connection of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present utility model can be understood according to specific circumstances.

[0021] Examples, such as Figure 1-3As shown, a large flue transport matching adjustment device in a confined space includes a gantry 1, the gantry 1 includes two brackets 11, the tops of the two brackets 11 are fixedly connected with a crossbeam 12, the bracket 11 includes two inclined beams 111, the tops of the two inclined beams 111 are fixedly connected, and the bottoms are connected by a running part 112, the two inclined beams 111 and the running part 112 form a triangular structure, two hanging ears 2 are fixed on the crossbeam 12, two hanging ears 2 are hung with electric fall chains 3, two automatic unhooking devices 4 are fixed to the bottom of each electric fall chain 3, and jacks 5 are fixed to the relative inner sides of the two brackets 11.

[0022] The cross beam 12 and the inclined beam 111 are both H-shaped steels. The bottom of the inclined beam 111 is welded to the running gear 112. The running gear 112 includes a steel wheel power device and a braking device. In the bracket 11, the two inclined beams 111 and the running gear 112 form a stable triangular structure that can withstand greater pressure. The cross beam 12 is perpendicular to the running gear 112 on both sides. The hanging ears 2 are cut from steel plates and symmetrically welded at appropriate positions on the cross beam 12.

[0023] During operation, two full-length rails are laid on the ground, and the device is installed on the two full-length rails. The two running parts 112 are adapted to the two full-length rails, and an external power supply is connected. The running part 112 and the electric fall chain 3 are powered on for test operation to test whether they are operating normally. After normal operation, the four automatic unhooking devices 4 are reliably fixed to the lifting ears on the pipeline module 100, and the pipeline module 100 is lifted to an appropriate height through the electric fall chain 3. Then the running part 112 is operated to move the device on the full-length rails, and the pipeline module 100 is transported to the installation position of the frame beam. Both sides of 100 are connected to two automatic unhooking devices 4. During the transportation process, the pipeline module 100 is always in a horizontal state. The pipeline module 100 can be easily and quickly transported to the installation position of the frame beam through the running part 112. After installation in place, the pull rope of the automatic unhooking device 4 is pulled to realize automatic unhooking. When alignment is required in the subsequent installation of the pipeline module 100, the upper and lower elevations of the pipeline module 100 are corrected by lifting and lowering the electric fall chain 3, and the left and right elevations of the pipeline module 100 are corrected by four jacks 5, so that the pipeline module 100 can be quickly and accurately aligned.

[0024] In a specific embodiment, a plurality of ladder steps 6 are fixed to the outer sides of the two inclined beams 111 in the bracket 11. The welders can use the ladder steps 6 on the inclined beams 111 to wear safety belts and move up and down, and cooperate with the hanging basket to gradually complete the welding construction of the annular welds at the mating parts. There is no need to set up scaffolding and other auxiliary tools for welding, which saves space and improves construction efficiency.

[0025] In a specific embodiment, a running brake switch control box 7 is provided on the inclined beam 111. The running brake switch control box 7 is used to control the running unit 112. The running brake switch control box 7 is connected to an operating handle 9 via a cable 8. The installer can control the running and braking of the running unit 112 within a safe range through the operating handle 9.

[0026] In a specific embodiment, there are four jacks 5, which are individually fixed on the inner sides of the four inclined beams 111. The four jacks 5 are symmetrically arranged at the same elevation. The four jacks 5 correct the left and right elevations of the pipeline module 100 by squeezing the side of the pipeline module 100.

[0027] In a specific embodiment, a U-shaped slot 10 is fixed on the inner side of the four inclined beams 111 , and the bottoms of the four jacks 5 are embedded in and fixed in the U-shaped slot 10 , thereby ensuring that the jacks 5 are firmly installed on the inclined beams 111 .

[0028] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.

Claims

1. A large flue transport matching adjustment device in a confined space, characterized by: It includes a gantry, which includes two brackets, the tops of the two brackets are fixedly connected with a crossbeam, the bracket includes two inclined beams, the tops of the two inclined beams are fixedly connected, the bottoms are connected through a running part, the two inclined beams and the running part form a triangular structure, two hanging ears are fixed on the crossbeam, two hanging ears are hung with electric fall chains, two automatic unhooks are fixed on the bottom of each electric fall chain, and jacks are fixed on the relative inner sides of the two brackets.

2. According to claim 1, a large flue transport matching adjustment device in a confined space is characterized in that: A plurality of ladder steps are fixed on the outer sides of the two inclined beams in the bracket.

3. According to claim 1, a large flue transport matching adjustment device in a confined space is characterized in that: A running brake switch control box is arranged on the inclined beam, and the running brake switch control box is used to control the running part. The running brake switch control box is connected to an operating handle through a cable.

4. The device for adjusting the large flue transport port in a confined space according to claim 1 is characterized in that: There are four jacks in total, which are fixed separately on the inner sides of the four inclined beams, and the four jacks are symmetrically arranged at the same elevation.

5. The device for adjusting the large flue transport port in a confined space according to claim 4 is characterized in that: The inner sides of the four inclined beams are all fixed with U-shaped slots, and the bottoms of the four jacks are embedded in and fixed in the U-shaped slots.