Recycled asphalt structure for pavement patching

By adopting a combination of multi-layer structure and drainage conduits in pavement repair, the problem of difficulty in repairing large-scale cracks in the existing technology is solved, the road surface strength and service life after repair are improved, and the practicality of repair is enhanced.

CN222065059UActive Publication Date: 2024-11-26FUJIAN SHUNTIANLI ENG TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420119448.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-17
Publication Date
2024-11-26
Estimated Expiration
2034-01-17

AI Technical Summary

Technical Problem

The existing technology is difficult to effectively repair asphalt pavement with large-scale cracks, resulting in the pavement still being prone to cracks after repair, which increases the probability of traffic accidents and reduces the practicality of repair.

Method used

Using structures including surface connection layer, emulsified asphalt bonding layer, regenerated asphalt concrete layer, reinforcement layer, concrete reinforcement layer, pebbles layer, cement base layer and gravel layer, the structural strength is improved through drainage conduits and steel columns to ensure that after repair road surface stability.

Benefits of technology

It improves the use strength and life of recycled asphalt, reduces the cracking and damage of the road surface after repair, and enhances the practicality of repair.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222065059U_ABST
    Figure CN222065059U_ABST
Patent Text Reader

Abstract

The utility model discloses a recycled asphalt structure for pavement patching, which comprises a surface connecting layer, an emulsified asphalt bonding layer, a recycled asphalt concrete layer, a reinforcing layer, a concrete reinforcing layer, a cobblestone layer, a cement foundation layer, a gravel layer and a soil base layer, the recycled asphalt concrete layer is arranged at the bottom of the emulsified asphalt bonding layer, the reinforcing layer is arranged at the bottom of the recycled asphalt concrete layer, the concrete reinforcing layer is arranged at the bottom of the reinforcing layer, and the cobblestone layer is arranged at the bottom of the concrete reinforcing layer. The recycled asphalt concrete layer, the first steel column, the second steel column, the concrete reinforcing layer, the cobblestone layer, the cement foundation layer and the gravel layer are matched with one another, so that the strength of recycled asphalt in use is improved, the phenomenon that a pavement is cracked and damaged after being repaired is reduced, the service life of the recycled asphalt is prolonged, and the service life of the recycled asphalt is prolonged. And the practicability is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of asphalt, in particular to a regenerated asphalt structure for road surface repair. Background Art

[0002] Asphalt pavement will develop cracks and damage after being used for a period of time, and the asphalt pavement needs to be repaired, which requires the use of recycled asphalt to repair it.

[0003] According to the application number: CN201920347545.8, a recycled asphalt structure for road repair includes a prefabricated layer, a recycled asphalt concrete layer laid on the prefabricated layer, and a recycled asphalt surface layer laid on the recycled asphalt concrete layer; the prefabricated layer and the recycled asphalt concrete layer are both located in the diseased excavation area of ​​the original asphalt pavement, and the recycled asphalt surface layer is flush with the upper surface of the original asphalt pavement; the prefabricated layer is spliced ​​by at least two base prefabricated parts, and the recycled asphalt layer is filled between adjacent base prefabricated parts.

[0004] The asphalt structure in the above case is only suitable for repairing small areas or small cracks on the road surface, and cannot guarantee the strength of the asphalt after repairing a larger area. As a result, the asphalt road surface is prone to cracking for a long time, increasing the probability of traffic accidents and reducing practicality. For this reason, we provide a recycled asphalt structure for road repair. Utility Model Content

[0005] The purpose of the utility model is to provide a regenerated asphalt structure for road repair to solve the problems raised in the above background technology.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a regenerated asphalt structure for road repair, comprising a surface connecting layer, an emulsified asphalt bonding layer, a regenerated asphalt concrete layer, a reinforcing layer, a concrete reinforcement layer, a pebble layer, a cement base layer, a crushed stone layer and a soil base layer.

[0007] Preferably, the emulsified asphalt bonding layer is arranged at the bottom of the surface connecting layer, the regenerated asphalt concrete layer is arranged at the bottom of the emulsified asphalt bonding layer, the reinforcing layer is arranged at the bottom of the regenerated asphalt concrete layer, the concrete reinforcement layer is arranged at the bottom of the reinforcing layer, the pebble layer is arranged at the bottom of the concrete reinforcement layer, the cement base layer is arranged at the bottom of the pebble layer, the gravel layer is arranged at the bottom of the cement base layer, and the soil base layer is arranged at the bottom of the gravel layer.

[0008] Preferably, the reinforcement layer is made of a first steel column and a second steel column, the length of the first steel column is 5-10 cm, and the length of the second steel column is set according to the width of the road surface.

[0009] Preferably, interconnected drainage ducts are provided between the surface connection layer, emulsified asphalt bonding layer, recycled asphalt concrete layer, reinforcement layer, concrete reinforcement layer, pebble layer, cement base layer and gravel layer. The number of the drainage ducts is four and they are respectively arranged on both sides of the top of the surface connection layer.

[0010] Preferably, the surface connection layer is made of titanium dioxide, and the thickness of the surface connection layer is 1-5 cm.

[0011] Preferably, the thickness of the emulsified asphalt bonding layer is 1-10 cm, the thickness of the recycled asphalt concrete layer is 1-10 cm, the thickness of the reinforcement layer is 1-10 cm, the thickness of the concrete reinforcement layer is 1-10 cm, the thickness of the cobblestone layer is 1-10 cm, the thickness of the cement base layer is 1-10 cm, and the thickness of the crushed stone layer is 1-10 cm.

[0012] Compared with the prior art, the beneficial effects of the utility model are as follows:

[0013] The utility model improves the strength of the regenerated asphalt during use through the mutual cooperation of the regenerated asphalt concrete layer, the first steel column, the second steel column, the concrete reinforcement layer, the pebble layer, the cement base layer and the crushed stone layer, thereby reducing the phenomenon of cracking and damage after road surface repair, thereby increasing the service life of the regenerated asphalt and improving practicality. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;

[0015] Figure 2 It is a structural cross-sectional view of the front view of the utility model.

[0016] In the figure: 1 surface connection layer, 2 emulsified asphalt bonding layer, 3 recycled asphalt concrete layer, 4 reinforcement layer, 41 first steel column, 42 second steel column, 5 concrete reinforcement layer, 6 pebble layer, 7 cement base layer, 8 crushed stone layer, 9 soil base layer, 10 drainage duct. DETAILED DESCRIPTION

[0017] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0018] See also Figure 1-2A regenerated asphalt structure for road repair includes a surface connection layer 1, an emulsified asphalt bonding layer 2, a regenerated asphalt concrete layer 3, a reinforcing layer 4, a concrete reinforcement layer 5, a pebble layer 6, a cement base layer 7, a crushed stone layer 8 and a soil base layer 9. The emulsified asphalt bonding layer 2 is arranged at the bottom of the surface connection layer 1. The surface connection layer 1 is made of titanium dioxide. The thickness of the surface connection layer 1 is 1-5 cm. Titanium dioxide can be mixed with asphalt to reduce pollutants in the air. When a car passes by, the asphalt containing titanium dioxide can purify the air and eliminate 25% to 45% of nitrogen oxides in vehicle emissions. By setting the surface connection layer 1, the air can be purified. The regenerated asphalt concrete layer 3 is arranged at the bottom of the emulsified asphalt bonding layer 2. The reinforcing layer 4 is arranged at the bottom of the regenerated asphalt concrete layer 3. The reinforcing layer 4 is made of a first steel column 41 and a second steel column 42. The length of the first steel column 41 is 5-10 cm, and the length of the second steel column 42 is set according to the width of the road surface. The concrete reinforcement layer 5 is arranged at the bottom of the reinforcing layer 4. The pebble layer 6 is arranged At the bottom of the concrete reinforcement layer 5, the cement base layer 7 is arranged at the bottom of the pebble layer 6, the gravel layer 8 is arranged at the bottom of the cement base layer 7, and the soil base layer 9 is arranged at the bottom of the gravel layer 8. The surface connection layer 1, the emulsified asphalt bonding layer 2, the recycled asphalt concrete layer 3, the reinforcement layer 4, the concrete reinforcement layer 5, the pebble layer 6, the cement base layer 7 and the gravel layer 8 are all provided with drainage ducts 10 that are interconnected. The number of drainage ducts 10 is four and they are respectively arranged on both sides of the top of the surface connection layer 1. The drainage ducts 10 It can only be set on both sides of the road, not in the middle of the road, so that rainwater from the outside can be quickly discharged into the soil base layer 9 through the drainage duct 10. The thickness of the emulsified asphalt bonding layer 2 is 1-10cm, the thickness of the recycled asphalt concrete layer 3 is 1-10cm, the thickness of the reinforcement layer 4 is 1-10cm, the thickness of the concrete reinforcement layer 5 is 1-10cm, the thickness of the pebble layer 6 is 1-10cm, the thickness of the cement base layer 7 is 1-10cm, and the thickness of the crushed stone layer 8 is 1-10cm.

[0019] Through the mutual cooperation of the recycled asphalt concrete layer 3, the first steel column 41, the second steel column 42, the concrete reinforcement layer 5, the pebble layer 6, the cement base layer 7 and the crushed stone layer 8, the strength of the recycled asphalt during use is improved, thereby reducing the phenomenon of cracking and damage after road surface repair, thereby increasing the service life of the recycled asphalt and improving its practicality.

[0020] When in use, the road surface that needs to be repaired in a large area is cleaned thoroughly, and the residual roadbed on the road surface is removed so that the soil base layer 9 can be excavated, and then a crushed stone layer 8, a cement base layer 7, a pebble layer 6, a concrete reinforcement layer 5, a reinforcement layer 4, and a recycled asphalt concrete layer 3 are laid on the soil base layer 9 in sequence, and finally an emulsified asphalt bonding layer 2 and a surface connection layer 1 are laid on the asphalt.

[0021] In summary: the recycled asphalt structure of the road repair solves the problems raised in the above-mentioned background technology through the mutual cooperation of the recycled asphalt concrete layer 3, the first steel column 41, the second steel column 42, the concrete reinforcement layer 5, the pebble layer 6, the cement base layer 7 and the crushed stone layer 8.

[0022] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A recycled asphalt structure for road repair, characterized in that: It comprises a surface connection layer (1), an emulsified asphalt bonding layer (2), a recycled asphalt concrete layer (3), a reinforcement layer (4), a concrete reinforcement layer (5), a pebble layer (6), a cement base layer (7), a crushed stone layer (8) and a soil base layer (9); The emulsified asphalt bonding layer (2) is arranged at the bottom of the surface connection layer (1), the regenerated asphalt concrete layer (3) is arranged at the bottom of the emulsified asphalt bonding layer (2), the reinforcing layer (4) is arranged at the bottom of the regenerated asphalt concrete layer (3), the concrete reinforcement layer (5) is arranged at the bottom of the reinforcing layer (4), the pebble layer (6) is arranged at the bottom of the concrete reinforcement layer (5), the cement base layer (7) is arranged at the bottom of the pebble layer (6), the crushed stone layer (8) is arranged at the bottom of the cement base layer (7), and the soil base layer (9) is arranged at the bottom of the crushed stone layer (8); The reinforcement layer (4) is made of a first steel column (41) and a second steel column (42), the length of the first steel column (41) is 5-10 cm, and the length of the second steel column (42) is set according to the width of the road surface.

2. The regenerated asphalt structure for road repair according to claim 1, characterized in that: Interconnected drainage ducts (10) are provided between the surface connection layer (1), the emulsified asphalt bonding layer (2), the recycled asphalt concrete layer (3), the reinforcement layer (4), the concrete reinforcement layer (5), the pebble layer (6), the cement base layer (7) and the crushed stone layer (8), and the number of the drainage ducts (10) is four and they are respectively provided on both sides of the top of the surface connection layer (1).

3. The regenerated asphalt structure for road repair according to claim 2, characterized in that: The surface connection layer (1) is made of titanium dioxide, and the thickness of the surface connection layer (1) is 1-5 cm.

4. The regenerated asphalt structure for road repair according to claim 2, characterized in that: The thickness of the emulsified asphalt bonding layer (2) is 1-10 cm, the thickness of the recycled asphalt concrete layer (3) is 1-10 cm, the thickness of the reinforcement layer (4) is 1-10 cm, the thickness of the concrete reinforcement layer (5) is 1-10 cm, the thickness of the pebble layer (6) is 1-10 cm, the thickness of the cement base layer (7) is 1-10 cm, and the thickness of the crushed stone layer (8) is 1-10 cm.