Working well

By setting up drilling piles outside the working well hole and setting up horizontal support structures in the well, the problem of instability or collapse of geological bodies around the working well hole is solved, and construction safety and well wall stability are improved.

CN222066751UActive Publication Date: 2024-11-26NO 1 ENG LIMITED OF CR20G +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420006436.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-02
Publication Date
2024-11-26
Estimated Expiration
2034-01-02

AI Technical Summary

Technical Problem

The lack of support for the geological bodies around the holes of the working well, resulting in instability or collapse during construction, posing safety hazards.

Method used

The drilling piles are arranged outside the hole of the working well, and a horizontal support structure is set up in the well. The drilling piles are composed of multiple vertically arranged drilling piles. One end of the drilling piles extends into the stable formation, and the support structure Connected between the well walls, enhancing the lateral stress capacity of the well wall.

Benefits of technology

It effectively prevents geological instability or collapse caused by construction, improves the stability and safety of the working well, and enhances the lateral stress strength of the well wall.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222066751U_ABST
    Figure CN222066751U_ABST
Patent Text Reader

Abstract

The utility model discloses a working well which comprises a well bottom, drilling row piles, a supporting structure and a water stopping structure, a well body comprises the well bottom and well walls, the well bottom and the well walls jointly define an inner cavity, structural joints are formed in the well walls, and a hole is formed in one well wall; the drilling row piles are arranged on the outer side of the well wall where the hole is located, the drilling row piles are arranged around the hole, the drilling row piles comprise a plurality of drilling piles, and the drilling piles stretch into a stable stratum below; the supporting structure comprises a supporting beam and supporting plates, the supporting beam is horizontally arranged, the two ends of the supporting beam are connected between the two different well walls, and the horizontally-arranged supporting plates are connected to the included angles formed by every two adjacent well walls. The water stop structure comprises a dewatering well and a water stop curtain, the water stop curtain is arranged at the position of the structural joint on the outer side of the well wall, and the dewatering well is arranged in the geological body on the outer side of the well body. The drilling row piles support geologic bodies on the outer sides of the holes, the supporting structure reinforces the well wall, and the structural stability of the working well is effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of underground engineering, in particular to a working well. Background Art

[0002] Working pits are widely used in the construction of underground projects such as tunnels. The walls and bottom of the working pit support the geological bodies outside the working pit, controlling the displacement of the geological bodies within a certain range to ensure the stability of the foundation pit and the safety of the operations in the pit. However, due to the lack of support for the geological bodies around the opening of the working pit, the geological bodies around the opening are easily disturbed and unstable or collapsed during the subsequent construction through the opening, posing certain safety hazards. Utility Model Content

[0003] The main purpose of the utility model is to provide a working well, aiming to solve the technical problem that the geological body around the hole of the working well in the prior art is prone to instability or collapse, which poses certain safety hazards.

[0004] In order to achieve the above-mentioned purpose, the utility model proposes a working well.

[0005] A working well, comprising a well body, a row of bored piles, a supporting structure and a water-stopping structure, wherein the well body comprises a well bottom and a plurality of well walls arranged around the edge of the well bottom, wherein the well bottom and the plurality of well walls together form an inner cavity of the well body, each of the well walls is provided with a structural seam, and one of the well walls is provided with a hole; the row of bored piles is arranged outside the well wall where the hole is located, and the row of bored piles is arranged around the hole, wherein the row of bored piles comprises a plurality of vertically arranged bored piles, and one end of the bored pile extends into a stable stratum below; A supporting structure is arranged in the inner cavity, and the supporting structure includes a supporting beam and a supporting plate. The supporting beam is horizontally arranged and its two ends are connected between two different well walls. The angle formed by the two adjacent well walls is connected with the horizontally arranged support plate. The water-stopping structure includes a dewatering well and a plurality of water-stopping curtains. A water-stopping curtain is arranged at a position corresponding to each structural seam on the outer side of each well wall. The water-stopping curtain is used to seal the corresponding structural seam. The dewatering well is arranged in the geological body outside the well body.

[0006] Optionally, the well wall where the hole is located is a reinforced well wall; the multiple bored piles in the bored pile row are distributed in sequence along the width direction of the reinforced well wall, and the pile holes of two adjacent bored piles are connected to each other.

[0007] Optionally, the drilled pile row is closely attached to the outer side of the reinforced well wall.

[0008] Optionally, the number of the drilled pile rows is multiple, and the multiple rows of drilled pile rows are arranged side by side in a direction away from the reinforced well wall.

[0009] Optionally, the number of the drilled pile rows is two rows, the drilled pile row close to the reinforced well wall is an inner row of piles, the drilled pile row away from the reinforced well wall is an outer row of piles, and the outer row of piles is close to the inner row of piles.

[0010] Optionally, the length of the inner row of piles is L1, the length of the outer row of piles is L2, and the width of the hole is D, wherein L1≥L2>D.

[0011] Optionally, the well body is divided into a plurality of well sections connected in sequence along its vertical direction, and each well section is provided with the support structure.

[0012] Optionally, a single water-stop curtain includes a plurality of mutually interlocking jet grouting piles, and the lower end of each of the jet grouting piles extends into the stable stratum below.

[0013] Optionally, a single water-stop curtain includes three jet grouting piles, and the three jet grouting piles are arranged in a triangle.

[0014] Optionally, there are multiple precipitation wells, and the multiple precipitation wells are arranged at intervals on the periphery of the well body.

[0015] Optionally, the bored piles are all round piles, the diameter of a single bored pile is a preset diameter, the spacing between two adjacent bored piles in each row of the bored piles is a preset spacing, and the preset diameter is greater than the preset spacing.

[0016] Optionally, the bottom of the well is arranged at an angle, and a water collecting trough is arranged at the lowest end of the bottom of the well.

[0017] The utility model proposes a working well, in which a row of bored piles is arranged outside the well wall where the hole is located. The row of bored piles is composed of a plurality of bored piles arranged side by side along the extending direction of the well wall. The row of bored piles supports the geological body outside the hole, and prevents the geological body outside the hole from being disturbed and causing instability or collapse during the subsequent construction through the hole, thereby reducing the hidden safety hazards in the construction of the working well. At the same time, the working well in the utility model is provided with a horizontal support structure in the well, and the support structure is connected between the well walls of the working well, so as to improve the lateral force strength of the well wall and enhance the stability of the working well. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.

[0019] Figure 1 This is a schematic diagram of the top view of the working well of an embodiment of the utility model;

[0020] Figure 2 It is a side view structural diagram of a working well of an embodiment of the utility model;

[0021] Figure 3 It is a schematic diagram of the local structure of a working well according to an embodiment of the utility model.

[0022] Description of Figure Numbers:

[0023] Label name Label name 10 Well 30 Support structure 11 Well wall 31 Support beam 12 Inner cavity 32 Support plate 13 Well Section 33 Laminate 111 Cave entrance 40 Water stop structure 112 Structural seams 41 Waterproof curtain 20 Drilled pile 411 Jet Grouting 21 Bored piles 42 Precipitation well

[0024] The realization of the purpose, functional features and advantages of the utility model will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0026] It should be noted that all directional indications in the embodiments of the present invention (such as up, down, left, right, front, back...) are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0027] In the present invention, unless otherwise clearly specified and limited, the terms "connection", "fixation", etc. should be understood in a broad sense. For example, "fixation" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0028] In addition, if there are descriptions involving "first", "second", etc. in the embodiments of the utility model, the descriptions of "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the meaning of "and / or" appearing in the full text includes three parallel schemes. Taking "A and / or B" as an example, it includes scheme A, or scheme B, or a scheme that satisfies both A and B. In addition, the technical solutions between the various embodiments can be combined with each other, but it must be based on the ability of ordinary technicians in this field to implement. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the utility model.

[0029] In the present invention, the description of the directions such as "upper" and "lower" is as follows: Figure 2 The directions shown are for reference only and are used to explain the Figure 2 The relative position relationship between the components in the shown posture. If the specific posture changes, the directional indication will also change accordingly.

[0030] The utility model provides a working well, including a well body 10, a bored pile row 20, a support structure 30 and a water stop structure 40, the well body 10 includes a well bottom and a plurality of well walls 11 arranged around the well bottom edge, the well bottom and the plurality of well walls 11 together form an inner cavity 12 of the well body 10, each well wall 11 is provided with a structural seam 112, one of the well walls 11 is provided with a hole 111; the bored pile row 20 is arranged outside the well wall 11 where the hole 111 is located, and the bored pile row 20 is arranged around the hole 111, the bored pile row 20 includes a plurality of vertically arranged bored piles 21, one end of the bored pile 21 extends to the bottom in a stable stratum; a supporting structure 30 is arranged in the inner cavity 12, and the supporting structure 30 includes a supporting beam 31 and a supporting plate 32. The supporting beam 31 is horizontally arranged and its two ends are connected between two different well walls 11. The angle formed by two adjacent well walls 11 is connected with a horizontally arranged supporting plate 32; the water-stopping structure 40 includes a dewatering well 42 and a plurality of water-stopping curtains 41. A water-stopping curtain 41 is arranged at a position corresponding to each structural seam 112 on the outer side of each well wall 11. The water-stopping curtain 41 is used to seal the corresponding structural seam 112. The dewatering well 42 is arranged in the geological body outside the well body 10.

[0031] like Figure 1 As shown, Figure 1It is a schematic diagram of the top structure of a working well of an embodiment of the utility model; a plurality of well walls 11 of the working well are connected in sequence to separate the inner cavity 12 of the working well from the geological body on the outside, and the plurality of well walls 11 support the geological body on the outside of the working well, and a plurality of supporting structures 30 arranged in the inner cavity 12 are connected between the well walls 11 on different sides to help the well walls 11 support the lateral geological body; a structural seam 112 on the well wall 11 extends vertically from the top of the well wall 11 to the bottom of the well, and a plurality of structural seams 112 divide the well wall 11 into multiple sections to prevent uneven settlement of various parts of the well wall 11 and cause continuous collapse; a plurality of water-stop curtains 41 are closely attached to the outside of the well wall 11 to seal each structural seam 112; a plurality of bored piles 21 are arranged in the geological body on the outside of the well wall 11, and each bored pile 21 extends vertically downward from the ground to a stable stratum underground to ensure that each bored pile 21 has sufficient anti-slip and anti-overturning capabilities. The bored piles 21 arranged side by side form a bored pile row 20, which together stabilize and support the geological body outside the well wall 11 where the hole 111 is located. In this embodiment, the bottom of the working well is rectangular, and the working well wall 11 has four.

[0032] The working well proposed by the utility model has at least the following effects:

[0033] (1) The bored piles 20 are arranged outside the well wall 11 on the side where the hole 111 is located, and play a role in stabilizing and supporting the geological body outside the hole 111, thereby preventing the geological body around the hole 111 from becoming unstable or collapsing due to disturbance during subsequent construction through the hole 111, thereby enhancing the stability of the geological body outside the well wall 11, thereby increasing the safety in the working well.

[0034] (2) Multiple horizontal supports are connected between different side well walls 11, which enhances the correlation between the multiple well walls 11, thereby improving the overall stability of the working well.

[0035] Furthermore, the well wall 11 where the hole 111 is located is a reinforced well wall 11; the multiple bored piles 21 in the bored pile row 20 are distributed in sequence along the width direction of the reinforced well wall 11, and the pile holes of two adjacent bored piles 21 are connected to each other.

[0036] In this embodiment, any two adjacent bored piles 21 in the bored pile row 20 are interlocked with each other, and the pile holes of each bored pile 21 are interconnected. After the drilling of all the interlocking piles is completed, concrete can be poured into the holes of multiple interlocking piles together, effectively improving the construction efficiency; after the concrete in the interlocking piles solidifies, the multiple interlocking piles together form a continuous bored pile row 20, effectively improving the support capacity for the geological body outside the reinforced well wall 11. At the same time, the bored pile row 20 itself has good anti-seepage performance, which can prevent external groundwater from infiltrating into the working well, further improving the stability of the working well.

[0037] Specifically, the bored pile row 20 is closely attached to the outer side of the reinforced well wall 11. The bored pile row 20 and the reinforced well wall 11 are closely attached, and there is no gap between the bored pile row 20 and the reinforced well wall 11, which can further improve the anti-seepage performance of the working well.

[0038] Furthermore, the number of the bored piles 20 is multiple rows, and the multiple rows of bored piles 20 are arranged side by side in a direction away from the reinforced well wall 11. In the multiple rows of bored piles 20 support structure, each row of bored piles 21 shares the lateral earth pressure, and the multiple rows of bored piles 20 form a stable spatial structure, which significantly improves the ability of the bored piles 20 to resist the lateral earth pressure in the direction perpendicular to the reinforced well wall 11, improves the support capacity of the bored piles 20, and maintains the stability of the working well.

[0039] In one embodiment, the number of the bored piles 20 is two rows, the bored piles 20 close to the reinforced well wall 11 are inner row piles, and the bored piles 20 away from the reinforced well wall 11 are outer row piles, and the outer row piles are close to the inner row piles.

[0040] like Figure 1 As shown, the two rows of bored piles 20 are closely arranged and fit against the outer side of the reinforced well wall 11, so as to further enhance the anti-seepage capability of the bored piles 20 and improve the stability of the working well.

[0041] In one embodiment, the length of the inner row of piles is L1, the length of the outer row of piles is L2, and the width of the hole 111 is D, wherein L1≥L2>D.

[0042] like Figure 1 As shown, the length L1 of the inner row of piles is greater than the length L2 of the outer row of piles, and the lengths of the two rows of bored piles 21 are both greater than the width D of the hole 111, ensuring that the support range of the bored pile row 20 covers the entire hole 111, and that each bored pile 21 in the outer row of piles can be supported by the inner row of piles, thereby improving the stability of the structure of the two rows of bored piles 21.

[0043] In one embodiment, the well body 10 is vertically divided into a plurality of well sections 13 connected in sequence, and each well section 13 is provided with a support structure 30. Figure 1 and Figure 2 As shown, Figure 2 It is a side view structural diagram of a working well according to an embodiment of the utility model. A horizontal support structure 30 is provided in each well section 13, a partition wall is also provided in each well section 13, and a layer plate 33 is provided between two well sections 13 connected to each other.

[0044] In this embodiment, the working shaft is divided into a plurality of shaft sections 13 along the height, and the partition walls and layer plates 33 divide the working shaft into a plurality of work rooms, thereby improving the space utilization rate in the working shaft and facilitating construction workers to carry out construction at different heights.

[0045] In one embodiment, a single water-stop curtain 41 includes a plurality of mutually interlocking jet grouting piles, and the lower end of each jet grouting pile extends into the stable stratum below.

[0046] like Figure 3 As shown, Figure 3 It is a schematic diagram of the local structure of a working well of an embodiment of the utility model; a plurality of rotary jet piles are interlocked with each other, and a connection is formed between each rotary jet pile, so that the overall stability of the water-stop curtain 41 is better. At the same time, the water-stop curtain 41 is arranged close to the well wall 11, so that the well wall 11 and each rotary jet pile can be force-connected, which can improve the reinforcement effect of the well wall 11 and ensure the water-stopping effect of the water-stop curtain 41.

[0047] In one embodiment, a single water-stop curtain 41 includes three jet grouting piles, and the three jet grouting piles are arranged in a triangle.

[0048] like Figure 3 As shown, three jet grouting piles are arranged in a triangle, two of which are set close to the well wall 11, and the other is located on the side away from the well wall 11. The three jet grouting piles are interlocked and cast as a whole, further improving the overall structural stability and water-stopping performance of the water-stop curtain 41.

[0049] In one embodiment, there are multiple precipitation wells 42 , and the multiple precipitation wells 42 are arranged at intervals on the outer circumference of the well body 10 .

[0050] A single precipitation well 42 extends vertically downward from the ground to below the well bottom elevation. Multiple precipitation wells 42 are arranged at a certain distance around the working well, so that the groundwater around the working well converges into each precipitation well 42, lowering the groundwater level within the working well, thereby reducing the probability of instability or collapse of the geological body due to soil erosion and maintaining the stability of the working well structure.

[0051] In one embodiment, the bored piles 21 are all round piles, the diameter of a single bored pile 21 is a preset diameter, and in each row of bored piles, the spacing between two adjacent bored piles 21 is a preset spacing, and the preset diameter is greater than the preset spacing, so that the bored piles have sufficient lateral support force to meet the requirements of retaining soil.

[0052] It can be explained that the preset diameter is 1000mm, the preset spacing is 800mm, the length of the bite part of two adjacent bored piles 21 is 200mm, and the multiple bored piles 21 are integrally cast by plain concrete without the need to lay steel cages. The sufficient bite length makes the bored pile structure stable and the construction simple.

[0053] In one embodiment, the well bottom is inclined, and a water collecting trough is provided at the lowest end of the well bottom.

[0054] By pouring an inclined cushion layer at the bottom of the well to form a slope, the water collection tank is set at the lowest position of the well bottom to collect the water at the bottom of the well. The specific size of the water collection tank depends on the actual water collection speed and is not limited in the utility model.

[0055] The above description is only an optional embodiment of the present invention, and does not limit the patent scope of the present invention. All equivalent structural changes made by using the contents of the present invention specification and drawings under the concept of the present invention, or directly / indirectly applied in other related technical fields are included in the patent protection scope of the present invention.

Claims

1. A working well, characterized in that: The working well comprises: A well body, comprising a well bottom and a plurality of well walls arranged around the edge of the well bottom, wherein the well bottom and the plurality of well walls together form an inner cavity of the well body, each of the well walls is provided with a structural seam, and one of the well walls is provided with a hole; A bored pile row, wherein the bored pile row is arranged outside the well wall where the hole is located, and the bored pile row is arranged around the hole, and the bored pile row comprises a plurality of vertically arranged bored piles, and one end of the bored pile extends into the stable stratum below; A support structure, the support structure is arranged in the inner cavity, the support structure comprises a support beam and a support plate, the support beam is arranged horizontally and its two ends are connected between two different well walls, and the angle formed by two adjacent well walls is connected to the horizontally arranged support plate; A water-stopping structure, comprising a drainage well and a plurality of water-stopping curtains, wherein a water-stopping curtain is arranged at a position corresponding to each structural seam on the outer side of each well wall, and the water-stopping curtain is used to seal the corresponding structural seam, and the drainage well is arranged in a geological body outside the well body.

2. The working well according to claim 1, characterized in that: The well wall where the hole is located is a reinforced well wall; the plurality of bored piles in the bored pile row are distributed in sequence along the width direction of the reinforced well wall, and the pile holes of two adjacent bored piles are connected to each other.

3. The working well according to claim 2, characterized in that: The drilled pile rows are closely attached to the outer side of the reinforced well wall.

4. The working well according to claim 2, characterized in that: The number of the drilled pile rows is multiple, and the multiple rows of drilled pile rows are arranged side by side in a direction away from the reinforced well wall.

5. The working well according to claim 4, characterized in that: The number of the drilled piles is two rows, the drilled piles close to the reinforced well wall are inner row piles, the drilled piles away from the reinforced well wall are outer row piles, and the outer row piles are close to the inner row piles.

6. The working well according to claim 5, characterized in that: The length of the inner row of piles is L1, the length of the outer row of piles is L2, and the width of the hole is D, wherein L1≥L2>D.

7. A working well according to any one of claims 1 to 6, characterized in that: The well body is divided into a plurality of well sections connected in sequence along its vertical direction, and each well section is provided with the support structure.

8. The working well according to any one of claims 1 to 6, characterized in that: Each of the water-stop curtains comprises a plurality of mutually interlocking jet grouting piles, and the lower end of each of the jet grouting piles extends into the stable stratum below.

9. The working well according to claim 8, characterized in that: Each of the water-stop curtains comprises three jet-jet piles, and the three jet-jet piles are arranged in a triangle.

10. The working well according to any one of claims 1 to 6, characterized in that: There are multiple precipitation wells, and the multiple precipitation wells are arranged at intervals on the outer periphery of the well body.

11. The working well according to any one of claims 1 to 6, characterized in that: The bored piles are all round piles, the diameter of a single bored pile is a preset diameter, and in each row of the bored piles, the spacing between two adjacent bored piles is a preset spacing, and the preset diameter is greater than the preset spacing.

12. The working well according to any one of claims 1 to 6, characterized in that: The bottom of the well is arranged inclined, and a water collecting trough is arranged at the lowest end of the bottom of the well.