By designing an information-based multi-clad arch frame installation trolley, and using the main arm and auxiliary arm systems to quickly install the pre-assembled arch frame outside the hole, solving the problems of low construction efficiency and high safety risks in the existing technology. Efficient and safe tunnel support construction has been achieved.
Patent Information
- Application Number
- CN202420734144.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-10
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-10
AI Technical Summary
It is difficult for existing arch frame installation equipment to complete multi-clad arch frame installation, resulting in low construction efficiency and safety risks and high-intensity labor problems when constructing in the tunnel.
An informative multi-clad arch frame installation trolley was designed, using the construction machinery chassis, main arm system and auxiliary arm system to realize the pre-complete arch frame splicing, tensioning and mesh welding work outside the hole, and through the main arm and The auxiliary arm system quickly installs multi-cage arch frames in the hole to reduce construction time and personnel risks in the hole.
By pre-assemblying the arch frame outside the hole, multiple arch frames can be quickly installed in the hole, significantly improving the initial support efficiency, reducing construction costs and safety risks, and improving construction efficiency.
Smart Images

Figure CN222066795U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel construction machinery, in particular to an information-based multi-arch installation trolley. Background Art
[0002] In the current tunnel construction, the composite lining support method is basically adopted. In the initial support stage, the construction process of arch frame, mesh, concrete and anchor rod forms temporary support on the excavation surface to achieve the early self-stabilization function of the tunnel and avoid the problem of tunnel instability and collapse. Under the existing construction process conditions, the characteristics of mechanized construction are also very obvious, that is, the efficiency of top finding, mesh hanging and reinforcement welding before arch erection is not high, and the overall construction efficiency of the initial support stage is not significantly improved.
[0003] Traditionally, arch erection is done manually, which involves a large number of workers and a working environment close to the tunnel face. This poses a high safety risk and can cause mass casualties in the event of an accident. In addition, manual labor is labor-intensive and arch erection is time-consuming. Due to the requirements for each cycle of advance, work such as erecting frames, hanging nets, and welding reinforcement bars must be performed in the tunnel, and hanging nets and welding reinforcement bars are relatively time-consuming.
[0004] To this end, the use of mechanized arch frame installation trolleys can reduce the labor intensity of workers and improve construction efficiency. The existing arch frame installation trolleys have the functions of tunnel steel frame installation, auxiliary anchor rod and anchor net installation, auxiliary arch frame reinforcement welding, etc., which can reduce construction costs and operation risks.
[0005] For example, the patent publication number CN114575898A applied by the applicant, an arch-anchor integrated operation trolley and its construction method, the vehicle body is equipped with an intermediate arm and a side arm, and the coordinated operation between the arms can realize the installation of mesh in the tunnel first, then the arch, and finally the mesh and the arch for reinforcement welding. The above equipment performs operations such as splicing of the arch, welding of mesh and arch reinforcement in the tunnel, which takes a long time, and can only install a single arch at a time in the tunnel, and the construction efficiency needs to be improved.
[0006] If the arch frame can be processed in advance in the steel structure workshop outside the tunnel, the arch frame splicing, tensioning, meshing, welding and other work can be completed outside the tunnel in advance, and the installation of 2 to 3 arch frames can be completed at one time in the tunnel, it will inevitably greatly reduce the arch erection time near the tunnel face and improve the initial support efficiency. Summary of the invention
[0007] In order to solve the problem that conventional arch frame installation equipment is difficult to complete the installation of multiple arch frames, resulting in low construction efficiency, the utility model provides an information-based multiple arch frame installation trolley, which completes the arch frame splicing, reinforcement, mesh welding and other works outside the tunnel in advance to achieve the assembly of multiple arch frames, and then uses the installation trolley to directly install multiple arch frames in the tunnel, thereby improving the support efficiency.
[0008] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0009] An information-based multi-arch installation trolley, comprising an engineering machinery chassis, a cab, a hydraulic station system for providing power to the entire vehicle, a main arm system and an auxiliary arm system;
[0010] The cab is rotatably arranged in the middle of the engineering machinery chassis, which is convenient for adjusting the driving direction and facilitating the movement of the driving trolley in the tunnel. The hydraulic station system is arranged at the rear of the engineering machinery chassis, and the main arm system and the auxiliary arm system are arranged at the front. The auxiliary arm systems are spaced apart on both sides of the main arm.
[0011] The main arm system includes a main arm device with multiple degrees of freedom and an arch frame grabbing device. The rear end of the main arm device is connected to the chassis of the engineering machinery, and the front end is connected to the arch frame grabbing device, so as to facilitate the movement of the arch frame grabbing device. The arch frame grabbing device includes a leveling mechanism and a telescopic clamp for clamping multiple arch frames. The telescopic clamp is rotatably arranged above the leveling mechanism.
[0012] The auxiliary arm system includes an auxiliary arm frame device with multiple degrees of freedom and an auxiliary arm platform. The auxiliary arm frame device has the same structure as the main arm frame device. The rear end of the auxiliary arm frame device is connected to the chassis of the engineering machinery, and the front end is connected to the auxiliary arm platform, so as to drive the auxiliary arm platform to move. The auxiliary arm platform includes a second leveling mechanism, a hanging basket, a winch mechanism and a lifting mechanism. The hanging basket is rotatably arranged above the second leveling mechanism, and the winch mechanism and the lifting mechanism are arranged on one side of the hanging basket.
[0013] Furthermore, the engineering machinery chassis is equipped with an engine and wheels controlled by the engine, which facilitates the moving function of the installation trolley. Front and rear hydraulic legs are respectively provided at the front and rear of the engineering machinery chassis, which improves the stability of the installation trolley when it stops. The engineering machinery chassis is also provided with an electrical cabinet, a storage cabinet, a battery cabinet, a ladder and a prism.
[0014] Furthermore, the cab includes a cab, a driving console, a host computer and a scanner. The cab is connected to the chassis of the engineering machinery through a shock-absorbing seat, which facilitates the shock absorption of the cab. The driving console is rotatably arranged in the cab, and the host computer and the scanner are respectively arranged inside and outside the top of the cab. The scanner is a three-dimensional laser scanner, which is convenient for sensing and scanning the environment in the tunnel.
[0015] Furthermore, the main boom device and the auxiliary boom device both include a fixed seat, a swing seat and a telescopic arm. The fixed seat is arranged on the chassis of the engineering machinery, and the swing seat is horizontally hinged on one side of the fixed seat to facilitate the horizontal swing of the swing seat. The fixed seat and the swing seat are arranged side by side on the left and right, and a side thrust cylinder is arranged between the swing seat and the fixed seat to provide power for the swing of the swing seat. The telescopic arm is vertically hinged above the swing seat to facilitate the vertical swing of the telescopic arm. A pitch cylinder is arranged between the rear end of the telescopic arm and the swing seat to provide power for the swing of the telescopic arm.
[0016] Furthermore, the fixed seat is provided with a swing encoder for monitoring the deflection of the swing seat, the swing seat is provided with a pitch encoder for monitoring the deflection of the telescopic arm, and the telescopic arm is provided with a telescopic pull-rope displacement sensor, so as to facilitate the monitoring of the movements of various components;
[0017] The arch grabbing device is arranged at the front end of the telescopic arm of the main boom device, and the auxiliary arm platform is arranged at the front end of the telescopic arm of the auxiliary boom device.
[0018] Furthermore, the leveling mechanism 1 includes a lifting arm and a leveling cylinder 1, the front end of the main boom device is hinged to the lifting arm and the leveling cylinder 1 respectively, and one end of the leveling cylinder 1 is also hinged to the lifting arm, so as to drive the lifting arm to perform pitching and swinging;
[0019] The telescopic clamp is connected to the top of the lifting arm through a rotary drive 1, which facilitates the telescopic clamp to rotate. The telescopic clamp includes a rectangular main frame, a telescopic rod group and an adjusting cylinder. The main frame is hinged on the top of the rotary drive 1. The adjusting cylinder is arranged between the main frame and the rotary drive 1 to realize the swing of the main frame. The telescopic rod group is arranged on both sides of the main frame. The telescopic rod group includes two telescopic rods with clamping claws on the top that are arranged in opposite directions.
[0020] Furthermore, the second leveling mechanism comprises an L-shaped arm and a second leveling cylinder, the front end of the auxiliary arm device is hinged to the L-shaped arm and the second leveling cylinder respectively, and one end of the second leveling cylinder is also hinged to the L-shaped arm, so as to facilitate the pitching and rotation of the L-shaped arm;
[0021] The upper part of the L-shaped arm is connected with a mounting platform through a rotary drive 2, so as to drive the mounting platform to move. The hanging basket is arranged on one side of the mounting platform, and the hoisting mechanism and the lifting mechanism are arranged on the other side of the mounting platform.
[0022] Furthermore, the hoisting mechanism includes a vertical beam, a hydraulic winch, a pulley and a grab head. The hydraulic winch and the pulley are arranged on one side of the vertical beam. One end of the wire rope on the hydraulic winch extends out, passes around the pulley and is connected to the grab head outward, so as to facilitate the grab head to be retracted and released.
[0023] The lifting mechanism includes a lifting arm and a lifting oil cylinder for driving the lifting arm. The lifting arm is arranged above the other side of the vertical beam. The lifting arm is a four-bar linkage mechanism, and an extension arm is arranged on the lifting arm. The movement of the lifting arm can drive the extension arm to turn over. The cross-section of the extension arm is in the shape of "丄", and both sides of the lower end of the extension arm are bent inward to form a shape of "]". The lifting oil cylinder is hinged between the lifting arm and the lower part of the other side of the vertical beam.
[0024] By the above technical solution, the beneficial effects of the utility model are as follows:
[0025] The utility model has a reasonable structural design. The construction machinery chassis can drive a main boom system and two auxiliary boom systems to move simultaneously. The main boom system is used to grab and install multiple arch frames at the vault part, and the auxiliary boom system is used to grab and install multiple arch frames at both sides of the arch bottom. The assembly operation of multiple arch frames, mesh sheets and tie bars is pre-completed outside the tunnel, so as to transfer the construction of the dangerous working surface in the tunnel to the safe area outside the tunnel. Inside the tunnel, through the cooperation of the main boom system and the auxiliary boom system, the docking and installation operation of multiple arch frames in a whole ring can be directly carried out in the tunnel, which can reduce the arch erection time in the tunnel, reduce the number of operators, reduce the construction cost and improve the primary support efficiency.
[0026] The main boom device and the auxiliary boom device of the utility model have the same structure and both have the characteristics of multiple degrees of freedom. Their own postures are adjustable and the angles are variable, and they have functions of telescoping, pitching and swinging, horizontal swinging and leveling, which can meet the needs of flexible movement in the tunnel and can better drive multiple arch frames to move and install.
[0027] The main boom device of the utility model drives the arch frame grabbing device to move. The arch frame grabbing device can firmly grab multiple arch frames at the vault part through the telescopic clamp, and at the same time, the pitching angle and the horizontal rotation angle of the multiple arch frames can be adjusted. The auxiliary boom device drives the auxiliary boom platform to move. People can be carried in the hanging basket on the auxiliary boom platform, and the hoisting mechanism is used for the lifting and lowering of the arch frame. The lifting mechanism is used for arch frame grabbing and adjusting the assembling action of the arch frame. The hoisting mechanism cooperates with the lifting mechanism to conveniently grab and fix multiple arch frames at both sides of the arch bottom, and can also adjust the pitching angle and the horizontal rotation angle of the multiple arch frames, which facilitates the docking and installation of multiple arch frames.
[0028] The utility model proposes a positioning method using a total station in conjunction with a prism for the parking position of the installation trolley in the tunnel, so as to facilitate the determination of the relative position of the equipment. At the same time, a scanner is installed on the cab, which can scan the environment in the tunnel and identify obstacles, facilitating the movement of the installation trolley. Encoders are installed on the multiple parts of the installation trolley to monitor the rotation angle of the parts. A pull-rope displacement sensor is also installed to monitor the operation of the telescopic arm to prevent interference and collision during the movement of the parts, making the operation process safer. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a front view of an information-based multi-arch installation trolley of the utility model.
[0030] Figure 2 The utility model is a top view of an information-based multi-arch installation trolley.
[0031] Figure 3 The utility model is a schematic diagram of a cab of an information-based multi-arch mounting trolley.
[0032] Figure 4 The utility model is a schematic diagram of a main boom device of an information-based multi-arch mounting trolley.
[0033] Figure 5 It is a front view of an arch frame grabbing device of an information-based multi-arch frame installation trolley of the utility model.
[0034] Figure 6 The utility model is a top view of an arch frame grabbing device of an information-based multi-arch frame installation trolley.
[0035] Figure 7 The utility model is a schematic diagram of an auxiliary arm support device of an information-based multi-arch frame installation trolley.
[0036] Figure 8 The utility model is a schematic diagram of an auxiliary arm platform of an information-based multi-arch frame installation trolley.
[0037] The numbers in the attached drawings are: 1 engineering machinery chassis, 2 cab, 201 cab room, 202 driving console, 203 host computer, 204 scanner, 3 hydraulic station system, 4 main arm system, 5 auxiliary arm system, 61 front hydraulic outrigger, 62 rear hydraulic outrigger, 7 electrical cabinet, 8 storage cabinet, 9 battery cabinet, 10 ladder, 11 prism, 12 shock absorber seat, 131 main arm frame device, 132 arch frame grabbing device, 14 fixed seat, 15 swing seat, 16 telescopic arm, 17 side thrust cylinder, 18 pitch cylinder, 19 leveling mechanism 1, 191 lifting Brace, 192 leveling cylinder one, 20 telescopic clamp, 21 main frame, 22 telescopic rod group, 23 clamp, 24 telescopic rod, 25 adjusting cylinder, 26 slewing drive one, 271 auxiliary arm frame device, 272 auxiliary arm platform, 28 leveling mechanism two, 281 L-type arm, 282 leveling cylinder two, 29 hanging basket, 30 winch mechanism, 301 vertical beam, 302 hydraulic winch, 303 pulley, 304 grab head, 31 lifting mechanism, 311 lifting arm, 312 lifting cylinder, 313 extension arm, 32 mounting table, 33 slewing drive two. DETAILED DESCRIPTION
[0038] The specific implementation of the utility model is described in detail below with reference to the accompanying drawings:
[0039] like Figure 1 to Figure 8 As shown, an information-based multi-arch installation trolley includes an engineering machinery chassis 1, a cab 2, a hydraulic station system 3 for providing power to the entire vehicle, a main arm system 4 and an auxiliary arm system 5.
[0040] The engineering machinery chassis 1 is equipped with an engine and wheels controlled by the engine, realizing the walking function of the engineering machinery chassis 1. The transmission structure is engine-torque converter-drive shaft-axle-wheel, and thus the transmission form of the mounting platform 32 is simple and easy to maintain. In order to ensure the stability of the mounting platform 32 after stopping, the engineering machinery chassis 1 is respectively provided with front hydraulic legs 61 and rear hydraulic legs 62 at the front and rear. The hydraulic legs are extended and rest against the ground, which can improve the stability of the mounting platform 32 during operation.
[0041] At the same time, the engineering machinery chassis 1 is also provided with an electrical cabinet 7, a storage cabinet 8, a battery cabinet 9, a ladder 10 for entering and exiting the cab 2, and a prism 11. The function of the prism 11 is to cooperate with the total station and can be used to locate the position of the mounting platform 32 in the tunnel.
[0042] The cab 2 is rotatably arranged in the middle of the engineering machinery chassis 1, so that the mounting platform 32 vehicle has a two-way driving function, can provide driving vision in different directions in front and behind, improve the convenience of the mounting platform 32 vehicle entering and exiting the tunnel, and facilitate rapid transition in the tunnel. The cab 2 includes a driving cabin 201, a driving console 202, a host computer 203 and a scanner 204. The driving cabin 201 is connected to the engineering machinery chassis 1 through a shock-absorbing seat 12 to slow down the vibration generated when the mounting platform 32 vehicle is running and transmitted to the cab 2. A driving console 202 is rotatably arranged in the driving cabin 201. The rotation means of the driving console 202 is the existing technology. On the basis of the fixing of the driving cabin 201, the driving console 202 can rotate 180° in the driving cabin 201, thereby changing the driving direction.
[0043] A host computer 203 and a scanner 204 are respectively arranged inside and outside the top of the cockpit 201. The host computer 203 can realize real-time monitoring and control, data collection and processing, remote control and management of the installation platform 32 vehicle. The scanner 204 is a three-dimensional laser scanner 204, which can scan the environment inside the tunnel and provide a judgment basis for the movement of the installation platform 32 vehicle.
[0044] A hydraulic station system 3 is arranged at the rear of the engineering machinery chassis 1, and the hydraulic station system 3 can provide hydraulic driving force for the operation of the entire installation platform 32. The hydraulic station system 3 is a prior art and will not be described in detail here. A main arm system 4 and an auxiliary arm system 5 are arranged in front of the engineering machinery chassis 1. The auxiliary arm systems 5 are distributed at intervals on both sides of the main arm, that is, there is one main arm system 4 and two auxiliary arm systems 5. The main arm system 4 cooperates with the auxiliary arm system 5 to realize the installation and construction of multiple arch frames in the tunnel.
[0045] The main arm system 4 is used to realize the grabbing and installation of multiple arch frames at the top of the tunnel arch. The main arm system 4 has the functions of telescoping, pitching, swinging left and right, and leveling. The main arm system 4 includes a multi-degree-of-freedom main arm device 131 and an arch frame grabbing device 132. The rear end of the main arm device 131 is connected to the engineering machinery chassis 1 to realize the installation of the main arm device 131. The front end of the main arm device 131 is connected to the arch frame grabbing device 132, which can drive the arch frame grabbing device 132 to move.
[0046] The main boom device 131 includes a fixed seat 14, a swing seat 15 and a telescopic arm 16. The fixed seat 14 is arranged on the engineering machinery chassis 1, and the swing seat 15 is horizontally hinged on one side of the fixed seat 14. The fixed seat 14 and the swing seat 15 are arranged side by side.
[0047] In order to realize the horizontal left and right swing of the swing seat 15, a side thrust cylinder 17 is arranged between the swing seat 15 and the fixed seat 14, and the side thrust cylinder 17 can drive the swing seat 15 to swing. In order to realize the monitoring of the swing angle of the swing seat 15, a swing encoder for monitoring the deflection of the swing seat 15 is arranged on the fixed seat 14. When the swing seat 15 swings, the swing encoder can record the rotation angle of the swing seat 15.
[0048] A telescopic arm 16 is vertically hinged above the swing seat 15. The length of the telescopic arm 16 is adjustable. The telescopic arm 16 is a prior art and can adopt a telescopic arm structure commonly used in engineering machinery. Here, the main body of the telescopic arm 16 is composed of a basic arm, a primary arm and a secondary arm. In order to monitor the running length of the telescopic arm 16, a telescopic pull rope displacement sensor is provided on the telescopic arm 16.
[0049] In order to achieve the vertical pitch and yaw of the telescopic arm 16, a pitch cylinder 18 is provided between the rear end of the telescopic arm 16 and the swing seat 15. There are two pitch cylinders 18, and the sizes of the two pitch cylinders 18 are different. In order to detect the yaw angle of the telescopic arm 16, a pitch encoder for monitoring the deflection of the telescopic arm 16 is provided on the swing seat 15. When the telescopic arm 16 pitches, the pitch encoder can record the rotation angle of the telescopic arm 16.
[0050] An arch frame grasping device 132 is arranged at the front end of the telescopic arm 16 of the main boom device 131. The arch frame grasping device 132 includes a leveling mechanism 19 and a telescopic clamp 20 for clamping multiple arch frames. The telescopic clamp 20 is rotatably arranged above the leveling mechanism 19, which can drive the telescopic clamp 20 to rotate horizontally. The telescopic clamp 20 is used to clamp and fix multiple arch frames.
[0051] The leveling mechanism 19 includes a lifting arm 191 and a leveling cylinder 192. The front end of the main arm support device 131 is hinged to the lifting arm 191 and the leveling cylinder 192 respectively. One end of the leveling cylinder 192 is also hinged to the lifting arm 191. The leveling cylinder 192 can be used to drive the lifting arm 191 to perform pitch rotation.
[0052] The lifting arm 191 is connected to the telescopic clamp 20 via a rotary drive 26, thereby driving the telescopic clamp 20 to rotate horizontally. Since the arch grabbing device 132 has both pitch rotation and horizontal rotation functions, two encoders can be used here to monitor the rotation angles of the lifting arm 191 and the telescopic clamp 20 respectively.
[0053] The telescopic clamp 20 includes a rectangular main frame 21, a telescopic rod group 22 and an adjusting cylinder 25. The main frame 21 is hinged above the rotary drive 26, and an adjusting cylinder 25 is arranged between the main frame 21 and the rotary drive 26, which can drive the main frame 21 to swing in the vertical direction. Telescopic rod groups 22 are arranged on both sides of the main frame 21. The telescopic rod group 22 includes two telescopic rods 24 with clamps 23 on the top arranged in opposite directions. The operation of the telescopic rod 24 is realized by a telescopic cylinder, that is, a telescopic cylinder is arranged on the main frame 21, which is not shown in the figure. Each telescopic cylinder is connected to a telescopic rod 24. The two telescopic cylinders in each telescopic rod group 22 run simultaneously to drive the two telescopic rods 24 to approach each other, and then the clamps 23 can be used to clamp the tops of multiple arch frames.
[0054] The installation platform 32 uses the auxiliary arm system 5 to coordinate with the main arm system 4 to better fix the multiple arch frames on the basis of the main arm system 4 grabbing multiple arch frames, thereby improving the reliability of grabbing. The auxiliary arm system 5 is used to realize the grabbing and installation of multiple arch frames on both sides of the tunnel arch bottom. The auxiliary arm system 5 also has the functions of telescopic, pitching, left and right swinging and leveling.
[0055] The auxiliary arm system 5 includes a multi-degree-of-freedom auxiliary arm frame device 271 and an auxiliary arm platform 272. The auxiliary arm frame device 271 has the same structure and operating principle as the main arm frame device 131, and can perform multi-posture transformation. The rear end of the auxiliary arm frame device 271 is connected to the engineering machinery chassis 1 to achieve the installation of the auxiliary arm frame, and the front end of the auxiliary arm frame device 271 is connected to the auxiliary arm platform 272, which can drive the auxiliary arm platform 272 to move.
[0056] An auxiliary arm platform 272 is arranged at the front end of the telescopic arm 16 of the auxiliary arm frame device 271, and the auxiliary arm platform 272 includes a second leveling mechanism 28, a hanging basket 29, a hoisting mechanism 30 and a lifting mechanism 31. The hanging basket 29 is rotatably arranged above the second leveling mechanism 28, and a hoisting mechanism 30 and a lifting mechanism 31 are arranged on one side of the hanging basket 29. The hanging basket 29, the hoisting mechanism 30 and the lifting mechanism 31 rotate together on the same platform.
[0057] The leveling mechanism 28 includes an L-shaped arm 281 and a leveling cylinder 282. The front end of the auxiliary arm frame device 271 is respectively hinged to the L-shaped arm 281 and the leveling cylinder 282. One end of the leveling cylinder 282 is also hinged to the L-shaped arm 281. The L-shaped arm 281 can be driven to perform pitch rotation by the leveling cylinder 282. The mounting platform 32 is connected to the top of the L-shaped arm 281 through the rotary drive 233, which can drive the mounting platform 32 to rotate horizontally. Since the auxiliary arm platform 272 has both pitch rotation and horizontal rotation functions, two encoders can be used here to monitor the rotation angles of the L-shaped arm 281 and the mounting platform 32 respectively.
[0058] A hanging basket 29 is arranged on one side of the installation platform 32. The hanging basket 29 is a folding hanging basket 29, which increases the working space for personnel and provides a safety protection platform for the construction operation of workers. A hoisting mechanism 30 and a lifting mechanism 31 are arranged on the other side of the installation platform 32.
[0059] The hoisting mechanism 30 is used to hook the side parts of multiple arch frames, which is convenient for the lifting and lowering of the arch frames. The hoisting mechanism 30 includes a vertical beam 301, a hydraulic winch 302, a pulley 303 and a grabbing head 304. The vertical beam 301 is arranged on the installation platform 32. The hydraulic winch 302 and the pulley 303 are arranged on one side of the vertical beam 301. One end of the steel wire rope on the hydraulic winch 302 extends out, bypasses the pulley 303 and is connected with the grabbing head 304 outward. The grabbing head 304 is used to hook the side parts of multiple arch frames. At the same time, the hydraulic winch 302 drives the grabbing head 304 to move upward, so as to lift and support the side parts of multiple arch frames.
[0060] The lifting mechanism 31 is used to lift the side parts of multiple arch frames. The lifting mechanism 31 includes a lifting arm 311 and a lifting oil cylinder 312 for driving the lifting arm 311. The lifting arm 311 is arranged above the other side of the vertical beam 301. The lifting arm 311 is used for arch frame grabbing and adjusting the assembling action of the arch frame. The lifting arm 311 is a four-bar linkage mechanism, which includes an arm one, an arm two, an arm three and an arm four. The arm one is fixed on the vertical beam 301. The arm two and the arm three are respectively hinged on both sides below the arm one. The arm two is far away from the vertical beam 301 and the arm three is close to the vertical beam 301. The arm four is hinged between the arm two and the arm three.
[0061] An extension arm 313 is arranged on the lifting arm 311. Specifically, the arm two extends downward to form the extension arm 313. The cross section of the extension arm 313 is in the shape of "丄", and both sides of the lower end of the extension arm 313 are bent inward to form the shape of "]". A lifting oil cylinder 312 is hinged between the lifting arm 311 and the lower part of the other side of the vertical beam 301. The lifting oil cylinder 312 can be used to drive the extension arm 313 to swing. The lower end of the extension arm 313 can be far away from or close to the installation platform 32. The shape of the lower end of the extension arm 313 can stably lift the side parts of multiple arch frames and prevent the side parts of multiple arch frames from shifting.
[0062] The principle of the utility model is: the installation of multiple arch frames, meshes and tie bars at the top of the tunnel arch is completed in advance outside the tunnel, and the installation of multiple arch frames, meshes and tie bars at both sides of the tunnel arch bottom is completed, and they are moved into the tunnel together. Before erecting the arch, the front hydraulic legs 61 and the rear hydraulic legs 62 of the mounting platform 32 are extended to allow the mounting platform 32 to be stably supported on the ground. Multiple arch frames are placed at the front end of the mounting platform 32, and the telescopic arm 16 of the main arm system 4 is extended until the arch frame grasping device 132 at the front end is driven close to the ground, and the main arm frame device 131 is adjusted to make the telescopic arm 16 deflect at an angle, and cooperate with the telescopic clamp 20 to complete the clamping of multiple arch frames at the top of the arch, and then the telescopic arm 16 is lifted to drive the multiple arch frames to move to a high position. At this time, the leveling cylinder 192 is controlled to lift the multiple arch frames to the vicinity of the predetermined position of the arch, and then the multiple arch frames are adjusted to the predetermined installation position of the arch through the arch grabbing device 132.
[0063] The telescopic arm 16 of the auxiliary arm system 5 is extended to the end close to the face, and the swing angle of the auxiliary arm frame device 271 is adjusted to make the front end of the hanging basket 29 close to the ground. The grab head 304 of the hoisting mechanism 30 is used to pull up the side of the multiple arch frames on the ground, and then the lifting cylinder 312 is used to drive the extension arm 313 to turn outward, and the arches on both sides of the arch frame are lifted to the predetermined position. The position of the multiple arch frames is finely adjusted through the rotary drive of the hanging basket 29 and the lifting cylinder 312. The docking of the whole ring of multiple arch frames is finally achieved through the coordinated action of the main arm system 4 and the auxiliary arm system 5. After the docking is completed, the staff will perform bolt connection operations in the hanging basket 29.
[0064] The embodiments described above are only preferred embodiments of the present invention and are not intended to limit the scope of implementation of the present invention. Therefore, any equivalent changes or modifications made based on the structures, features and principles described in the patent scope of the present invention should be included in the patent application scope of the present invention.
Claims
1. An information-based multi-arch installation trolley, characterized in that: It comprises an engineering machinery chassis (1), a cab (2), a hydraulic station system (3) for providing power to the entire vehicle, a main arm system (4) and an auxiliary arm system (5); The cab (2) is rotatably arranged in the middle of the engineering machinery chassis (1), the hydraulic station system (3) is arranged at the rear of the engineering machinery chassis (1), the main arm system (4) and the auxiliary arm system (5) are arranged at the front, and the auxiliary arm systems (5) are spaced apart on both sides of the main arm; The main arm system (4) comprises a main arm device (131) with multiple degrees of freedom and an arch frame grabbing device (132); the rear end of the main arm device (131) is connected to the engineering machinery chassis (1), and the front end is connected to the arch frame grabbing device (132); the arch frame grabbing device (132) comprises a leveling mechanism (19) and a telescopic clamp (20) for clamping multiple arch frames; the telescopic clamp (20) is rotatably arranged above the leveling mechanism (19); The auxiliary arm system (5) comprises an auxiliary arm frame device (271) with multiple degrees of freedom and an auxiliary arm platform (272). The auxiliary arm frame device (271) and the main arm frame device (131) have the same structure. The rear end of the auxiliary arm frame device (271) is connected to the engineering machinery chassis (1), and the front end is connected to the auxiliary arm platform (272). The auxiliary arm platform (272) comprises a second leveling mechanism (28), a hanging basket (29), a hoisting mechanism (30) and a lifting mechanism (31). The hanging basket (29) is rotatably arranged above the second leveling mechanism (28), and the hoisting mechanism (30) and the lifting mechanism (31) are arranged on one side of the hanging basket (29).
2. The information-based multi-arch installation trolley according to claim 1 is characterized in that: The engineering machinery chassis (1) is provided with an engine and wheels controlled by the engine. The front and rear of the engineering machinery chassis (1) are respectively provided with front hydraulic outriggers (61) and rear hydraulic outriggers (62). The engineering machinery chassis (1) is also provided with an electrical cabinet (7), a storage cabinet (8), a battery cabinet (9), a ladder (10), and a prism (11).
3. The information-based multi-arch installation trolley according to claim 1 is characterized in that: The cab (2) comprises a cab (201), a driving console (202), a host computer (203) and a scanner (204); the cab (201) is connected to the engineering machinery chassis (1) via a shock-absorbing seat (12); the driving console (202) is rotatably arranged in the cab (201); the host computer (203) and the scanner (204) are respectively arranged inside and outside the top of the cab (201); and the scanner (204) is a three-dimensional laser scanner (204).
4. The information-based multi-arch installation trolley according to claim 1 is characterized in that: The main boom device (131) and the auxiliary boom device (271) both comprise a fixed seat (14), a swing seat (15) and a telescopic arm (16); the fixed seat (14) is arranged on the engineering machinery chassis (1); the swing seat (15) is horizontally hinged to one side of the fixed seat (14); the fixed seat (14) and the swing seat (15) are arranged side by side; a side thrust cylinder (17) is arranged between the swing seat (15) and the fixed seat (14); the telescopic arm (16) is vertically hinged above the swing seat (15); and a pitch cylinder (18) is arranged between the rear end of the telescopic arm (16) and the swing seat (15).
5. The information-based multi-arch installation trolley according to claim 4 is characterized in that: The fixed seat (14) is provided with a swing encoder for monitoring the deflection of the swing seat (15), the swing seat (15) is provided with a pitch encoder for monitoring the deflection of the telescopic arm (16), and the telescopic arm (16) is provided with a telescopic pull rope displacement sensor; The arch frame grabbing device (132) is arranged at the front end of the telescopic arm (16) of the main boom device (131), and the auxiliary arm platform (272) is arranged at the front end of the telescopic arm (16) of the auxiliary boom device (271).
6. The information-based multi-arch installation trolley according to claim 1 is characterized in that: The leveling mechanism (19) comprises a lifting arm (191) and a leveling cylinder (192); the front end of the main arm support device (131) is hinged to the lifting arm (191) and the leveling cylinder (192) at the upper and lower ends thereof, respectively; one end of the leveling cylinder (192) is also hinged to the lifting arm (191); The lifting arm (191) is connected to the telescopic clamp (20) via a rotary drive (26) above. The telescopic clamp (20) includes a rectangular main frame (21), a telescopic rod group (22) and an adjusting cylinder (25). The main frame (21) is hinged above the rotary drive (26). The adjusting cylinder (25) is arranged between the main frame (21) and the rotary drive (26). The telescopic rod group (22) is arranged on both sides of the main frame (21). The telescopic rod group (22) includes two telescopic rods (24) with clamping claws (23) on the top that are arranged in opposite directions.
7. The information-based multi-arch installation trolley according to claim 1 is characterized in that: The second leveling mechanism (28) comprises an L-shaped arm (281) and a second leveling cylinder (282); the front end of the auxiliary arm support device (271) is hinged to the L-shaped arm (281) and the second leveling cylinder (282) at upper and lower ends thereof, respectively; one end of the second leveling cylinder (282) is also hinged to the L-shaped arm (281); The L-shaped arm (281) is connected to a mounting platform (32) via a second rotary drive (33), the hanging basket (29) is arranged on one side of the mounting platform (32), and the hoisting mechanism (30) and the lifting mechanism (31) are arranged on the other side of the mounting platform (32).
8. The information-based multi-arch installation trolley according to claim 7 is characterized in that: The hoisting mechanism (30) comprises a vertical beam (301), a hydraulic winch (302), a pulley (303) and a grab head (304); the hydraulic winch (302) and the pulley (303) are arranged on one side of the vertical beam (301); one end of a steel wire rope on the hydraulic winch (302) extends out, passes around the pulley (303), and is externally connected to the grab head (304); The lifting mechanism (31) includes a lifting arm (311) and a lifting oil cylinder (312) for driving the lifting arm (311). The lifting arm (311) is arranged above the other side of the vertical beam (301). The lifting arm (311) is a four-bar linkage mechanism. An extension arm (313) is arranged on the lifting arm (311). The cross-section of the extension arm (313) is in the shape of "丄", and both sides of the lower end of the extension arm (313) are bent inwards to form a "]" shape. The lifting oil cylinder (312) is hinged between the lifting arm (311) and the lower part of the other side of the vertical beam (301).