Concrete detection device for constructional engineering

By designing a concrete detection device including a strength monitor, a motor and a crushing chamber, the problems of environmental impact and resource waste in the prior art are solved, and the efficiency of concrete crushing and the accuracy of monitoring results are improved.

CN222070301UActive Publication Date: 2024-11-26ZHENGZHOU ZHONGZHOU BUILDING MATERIALS INSPECTION & TESTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420502751.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-15
Publication Date
2024-11-26
Estimated Expiration
2034-03-15

AI Technical Summary

Technical Problem

The existing concrete strength monitoring device will affect the surrounding environment when used, and lead to waste of concrete resources, and it is difficult for concrete to enter the inlet for crushing, affecting the detection efficiency.

Method used

A concrete detection device for construction engineering is designed, including a strength monitor, a motor, a crushing chamber, a drive shaft, a spring rod, a shot put, an inlet port and a cover plate. The concrete is crushed by a motor drives the shot put and passes through an inclined slide. The trough structure ensures the concrete smoothly into the inlet, and then collects the broken concrete to reduce waste.

Benefits of technology

It effectively reduces the impact of concrete on the environment, reduces resource waste, and improves the working efficiency of concrete crushing, ensuring the accuracy of monitoring results and the safety of site.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222070301U_ABST
    Figure CN222070301U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of detection, and particularly relates to a concrete detection device for constructional engineering, which comprises a strength monitor, the middle part of the strength monitor is in sliding connection with a pressing sheet; a bottom sheet is fixedly connected to the middle part of the strength monitor; the middle part of the strength monitor is fixedly connected with a motor; a crushing cavity is formed in the middle of the strength monitor; the output end of the motor is fixedly connected with a transmission shaft; a spring rod is fixedly connected to the middle of the transmission shaft; the end part of the spring rod is fixedly connected with a lead ball; a feeding hole is formed in the middle of the strength monitor; the bottom of the strength monitor is rotationally connected with a cover plate; according to the step, after concrete monitoring is completed, the monitored concrete can be crushed and collected, then the situation that the monitored concrete influences the surrounding environment can be reduced, meanwhile, the crushed concrete can be collected, and then the situation that the concrete is wasted can be reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of detection, in particular to a concrete detection device for construction engineering. Background Art

[0002] As people's living standards continue to improve, the requirements for housing are also gradually increasing. Existing houses need to use concrete to reinforce the main frame. Concrete has the characteristics of abundant materials, low price and simple production process, and is widely used.

[0003] The use of concrete can effectively distribute and transfer loads, bear the loads of the building itself and the outside, thereby ensuring the stability and safety of the building. At the same time, the use of concrete can improve the building's earthquake resistance and wind resistance, and increase the strength of the building.

[0004] After using concrete to pour a building, it is necessary to monitor the strength of the concrete and conduct an intelligent assessment of the service condition, reliability, durability and bearing capacity of the building. However, when using the existing strength monitoring device, the concrete is crushed and poured directly on the ground before the next strength monitoring is performed, which will have a certain impact on the surrounding environment and cause a certain waste of concrete resources. Therefore, in view of the above problems, a concrete detection device for construction engineering is proposed. Summary of the invention

[0005] In order to make up for the deficiencies of the prior art and solve at least one technical problem raised in the background technology, the utility model proposes a concrete detection device for construction engineering.

[0006] The technical solution adopted by the utility model to solve its technical problems is: the utility model is a concrete detection device for construction engineering, comprising a strength monitor; a pressure plate is slidably connected to the middle of the strength monitor; a bottom plate is fixedly connected to the middle of the strength monitor; a motor is fixedly connected to the middle of the strength monitor; a crushing chamber is provided at the beginning of the middle of the strength monitor; a transmission shaft is fixedly connected to the output end of the motor; a spring rod is fixedly connected to the middle of the transmission shaft; a lead ball is fixedly connected to the end of the spring rod; a feed port is provided at the beginning of the middle of the strength monitor; and a cover plate is rotatably connected to the bottom of the strength monitor.

[0007] Preferably, a card slot is provided in the middle of the strength monitor; a hinge is fixedly connected to the middle of the strength monitor; a slide is fixedly connected to the middle of the hinge; a baffle is fixedly connected to the middle of the slide; and the baffle is slidably connected to the card slot.

[0008] Preferably, a circular ring is fixedly connected to the middle of the cover plate; an insertion rod is slidably connected to the middle of the circular ring; and a card is fixedly connected to the end of the insertion rod.

[0009] Preferably, a pliers is slidably connected to the middle of the bottom film; a disc is fixedly connected to the end of the pliers; a small spring is fixedly connected to the middle of the disc; and a scraper is fixedly connected to the end of the pliers.

[0010] Preferably, a protective plate is fixedly connected to the middle of the strength monitor; and a rotating plate is rotatably connected to the middle of the protective plate.

[0011] Preferably, a limiting plate is fixedly connected to the middle portion of the blocking plate; and the limiting plate is slidably connected to the card slot.

[0012] Preferably, a collecting fence is fixedly connected to the middle of the scraper.

[0013] The utility model is beneficial in that:

[0014] 1. The utility model discloses a concrete detection device for construction engineering, which can crush and collect the monitored concrete after the concrete monitoring is completed, thereby reducing the impact of the monitored concrete on the surrounding environment, and can collect the crushed concrete at the same time, thereby reducing the waste of concrete.

[0015] 2. The concrete detection device for construction engineering described in the utility model can reduce the difficulty of the detected concrete to enter the feed port when it is necessary to place the concrete inside the crushing chamber through the feed port, and further improve the work efficiency of placing the concrete when it is necessary to crush the concrete. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0017] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;

[0018] Figure 2 It is a three-dimensional cross-sectional structural schematic diagram of the utility model;

[0019] Figure 3 This is a schematic diagram of the pliers structure in the utility model;

[0020] Figure 4 It is a schematic diagram of the structure of the slide plate in the utility model;

[0021] Figure 5 for Figure 2 A magnified image of point A;

[0022] Figure 6 for Figure 3 Enlarged view of point B.

[0023] In the figure: 1. Strength monitor; 11. Motor; 12. Crushing chamber; 13. Drive shaft; 14. Spring rod; 15. Lead ball; 16. Feed inlet; 17. Cover plate; 18. Pressing plate; 19. Bottom plate; 2. Slot; 21. Hinge; 22. Slide plate; 23. Baffle; 3. Ring; 31. Insert rod; 32. Card; 4. Pliers; 41. Disc; 42. Small spring; 43. Scraper; 5. Protective plate; 51. Turntable; 6. Limiting plate; 7. Collecting column. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0025] like Figure 1-3 As shown, a concrete detection device for construction engineering includes a strength monitor 1; a pressing plate 18 is slidably connected to the middle of the strength monitor 1; a bottom plate 19 is fixedly connected to the middle of the strength monitor 1; a motor 11 is fixedly connected to the middle of the strength monitor 1; a crushing chamber 12 is provided at the beginning of the middle of the strength monitor 1; a transmission shaft 13 is fixedly connected to the output end of the motor 11; a spring rod 14 is fixedly connected to the middle of the transmission shaft 13; a lead ball 15 is fixedly connected to the end of the spring rod 14; a feed port 16 is provided at the beginning of the middle of the strength monitor 1; a cover plate 17 is rotatably connected to the bottom of the strength monitor 1; when working, when it is necessary to monitor the concrete, the concrete to be monitored can be placed in the middle of the bottom plate 19, and then the pressing plate can be used to 18 applies pressure to the concrete. After the concrete in the middle of the bottom plate 19 is crushed, the concrete in the middle of the bottom plate 19 can be placed in the crushing chamber 12 through the feed port 16, and then the motor 11 is operated, and then the lead ball 15 can be used to crush the concrete in the crushing chamber 12. After the concrete in the crushing chamber 12 is crushed, the cover plate 17 can be opened from the bottom of the strength monitor 1, and then the crushed concrete can be taken out. After the concrete monitoring is completed, this step can be completed. The monitored concrete can be crushed and collected, thereby reducing the impact of the monitored concrete on the surrounding environment. At the same time, the crushed concrete can be collected, thereby reducing the waste of concrete.

[0026] like Figure 1-4As shown, there is a card slot 2 at the beginning of the middle part of the strength monitor 1; a hinge 21 is fixedly connected to the middle part of the strength monitor 1; a slide plate 22 is fixedly connected to the middle part of the hinge 21; a baffle 23 is fixedly connected to the middle part of the slide plate 22; the baffle 23 is slidably connected to the card slot 2; during operation, when it is necessary to place the concrete inside the crushing chamber 12 through the feed port 16, the baffle 23 can be pulled out from the inside of the card slot 2, and the slide plate 22 can be tilted at the bottom of the feed port 16 through the action of the hinge 21, so that the tested concrete can be placed in the middle of the feed port 16 through the slide plate 22. This step can reduce the difficulty of the tested concrete to enter the inside of the feed port 16 when the concrete needs to be placed inside the crushing chamber 12 through the feed port 16, and can improve the work efficiency when placing the concrete when it is necessary to crush the concrete.

[0027] like Figure 1-5 As shown, a ring 3 is fixedly connected to the middle of the cover plate 17; a plug rod 31 is slidably connected to the middle of the ring 3; a card 32 is fixedly connected to the end of the plug rod 31; during operation, when the lead ball 15 is used to crush concrete, the plug rod 31 can be placed in the middle of the ring 3, and then the cover plate 17 can be used to seal the bottom of the crushing chamber 12 to reduce the leakage of concrete through the cover plate 17. The card 32 can reduce the sliding of the plug rod 31 when using the plug rod 31. This step can seal the unbroken concrete inside the crushing chamber 12 when the concrete needs to be crushed, so as to effectively crush the concrete blocks inside the crushing chamber 12.

[0028] like Figure 1-6 As shown, a pliers 4 is slidably connected to the middle of the bottom film 19; a disc 41 is fixedly connected to the end of the pliers 4; a small spring 42 is fixedly connected to the middle of the disc 41; a scraper 43 is fixedly connected to the end of the pliers 4; during operation, after the concrete is tested, there will be some broken concrete residues in the middle of the bottom film 19. At this time, the pliers 4 can be placed in the middle of the bottom film 19, and then the scraper 43 can be fitted with the bottom film 19 and the middle of the pressing plate 18 through the action of the small spring 42, and then the pliers 4 can be pulled outward to remove the concrete residues in the middle of the bottom film 19. This step can be used to clean the bottom film 19 and the middle of the pressing plate 18 after the concrete is tested, thereby reducing the situation where the concrete residues in the middle of the bottom film 19 cause inaccurate concrete monitoring, thereby improving the accuracy of the concrete monitoring results.

[0029] like Figure 1As shown, a protective plate 5 is fixedly connected to the middle of the strength monitor 1; a rotating plate 51 is rotatably connected to the middle of the protective plate 5; during operation, when monitoring concrete, the protective plate 5 and the rotating plate 51 can be used to protect the monitoring site, and when the concrete to be monitored needs to be placed in the middle of the bottom film 19, the rotating plate 51 can be rotated in the middle of the protective plate 5. This step can reduce the occurrence of debris splashing to the outside during the monitoring process when testing the strength of concrete, thereby protecting the monitoring site.

[0030] like Figure 4 As shown, the middle part of the baffle 23 is fixedly connected to a limiting plate 6; the limiting plate 6 is slidably connected to the slot 2; during operation, when the slide plate 22 is used to guide the concrete, the limiting plate 6 can be used to fix the baffle 23 on the side of the strength monitor 1. This step can reduce the situation where the slide plate 22 flips excessively from the side of the strength monitor 1 when the slide plate 22 is needed to guide the concrete.

[0031] like Figure 3 As shown, the scraper 43 is fixedly connected with a collecting bar 7 in the middle. During operation, when the scraper 43 is used to clean the residue in the middle of the pressing sheet 18, the collecting bar 7 can be used to wrap the residue. This step can reduce the possibility that the residue passes over the scraper 43 and falls again into the middle of the bottom sheet 19 when the scraper 43 is used to clean the residue.

[0032] Working principle: during operation, when it is necessary to monitor the concrete, the concrete to be monitored can be placed in the middle of the bottom plate 19, and then the pressing plate 18 is used to apply pressure to the concrete. After the concrete in the middle of the bottom plate 19 is crushed, the concrete in the middle of the bottom plate 19 can be placed in the crushing chamber 12 through the feed port 16, and then the motor 11 is operated, and then the lead ball 15 can be used to crush the concrete in the crushing chamber 12. After the concrete in the crushing chamber 12 is crushed, the cover plate 17 can be opened from the bottom of the strength monitor 1, and then the crushed concrete can be taken out. After the concrete monitoring is completed, this step can be performed to crush and collect the monitored concrete, thereby reducing the impact of the monitored concrete on the surrounding environment. The situation occurs, and the crushed concrete can be collected at the same time, thereby reducing the waste of concrete. When it is necessary to place the concrete in the crushing chamber 12 through the feed port 16, the baffle 23 can be pulled out from the inside of the card slot 2. Through the action of the hinge 21, the slide plate 22 can be set at an angle at the bottom of the feed port 16, and the monitored concrete can be placed in the middle of the feed port 16 through the slide plate 22. This step can reduce the situation that the monitored concrete is difficult to enter the feed port 16 when it is necessary to place the concrete in the crushing chamber 12 through the feed port 16, and thus when it is necessary to crush the concrete, the work efficiency of placing the concrete can be improved. When the lead ball 15 is used to crush the concrete, the insertion rod 3 can be 1 is placed in the middle of the ring 3, and then the cover plate 17 can be used to block the bottom of the crushing chamber 12 to reduce the leakage of concrete through the cover plate 17. The card 32 can reduce the sliding of the plug rod 31 when using the plug rod 31. This step can seal the unbroken concrete inside the crushing chamber 12 when the concrete needs to be crushed, and then the concrete blocks inside the crushing chamber 12 can be effectively crushed. After monitoring the concrete, there will be some broken concrete residues in the middle of the bottom plate 19. At this time, the pliers 4 can be placed in the middle of the bottom plate 19, and then the scraper 43 can be fitted with the bottom plate 19 and the middle of the pressing plate 18 through the action of the small spring 42, and then the pliers 4 can be pulled outward to perform the crushing. The concrete residue in the middle of the bottom film 19 can be taken out. This step can be used to clean the bottom film 19 and the middle of the pressing plate 18 after the concrete is tested, thereby reducing the situation where the concrete residue in the middle of the bottom film 19 causes inaccurate concrete monitoring, thereby improving the accuracy of the concrete monitoring results. When monitoring the concrete, the protection plate 5 and the rotating plate 51 can be used to protect the monitoring site. When the concrete to be monitored needs to be placed in the middle of the bottom film 19, the rotating plate 51 can be rotated in the middle of the protection plate 5. This step can reduce the situation where debris splashes outward during the monitoring process when testing the strength of the concrete, thereby protecting the monitoring site. When the slide plate 22 is used to divert the concrete,The stopper 6 can be used to fix the baffle 23 on the side of the strength monitor 1. This step can reduce the situation that the slide plate 22 is overturned from the side of the strength monitor 1 when the slide plate 22 is needed to guide the concrete. When the scraper 43 is used to clean the residue in the middle of the pressing plate 18, the collection bar 7 can be used to wrap the residue. This step can reduce the situation that the residue passes over the scraper 43 and falls to the middle of the bottom plate 19 again when the scraper 43 is used to clean the residue.

[0033] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments, and the above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, and these changes and improvements fall within the scope of the utility model to be protected.

Claims

1. A concrete testing device for construction engineering, comprising a strength monitor (1); a pressing plate (18) is slidably connected to the middle of the strength monitor (1); a bottom plate (19) is fixedly connected to the middle of the strength monitor (1); the characteristics are: A motor (11) is fixedly connected to the middle of the strength monitor (1); a crushing chamber (12) is provided at the beginning of the middle of the strength monitor (1); a transmission shaft (13) is fixedly connected to the output end of the motor (11); a spring rod (14) is fixedly connected to the middle of the transmission shaft (13); a lead ball (15) is fixedly connected to the end of the spring rod (14); a feed inlet (16) is provided at the beginning of the middle of the strength monitor (1); and a cover plate (17) is rotatably connected to the bottom of the strength monitor (1).

2. A concrete detection device for construction engineering according to claim 1, characterized in that: A slot (2) is provided at the middle of the strength monitor (1); a hinge (21) is fixedly connected to the middle of the strength monitor (1); a slide plate (22) is fixedly connected to the middle of the hinge (21); a baffle (23) is fixedly connected to the middle of the slide plate (22); and the baffle (23) is slidably connected to the slot (2).

3. A concrete detection device for construction engineering according to claim 1, characterized in that: A circular ring (3) is fixedly connected to the middle of the cover plate (17); an insertion rod (31) is slidably connected to the middle of the circular ring (3); and a card (32) is fixedly connected to the end of the insertion rod (31).

4. A concrete detection device for construction engineering according to claim 1, characterized in that: The middle of the bottom plate (19) is slidably connected to a pliers (4); the ends of the pliers (4) are fixedly connected to a disc (41); the middle of the disc (41) is fixedly connected to a small spring (42); and the ends of the pliers (4) are fixedly connected to a scraper (43).

5. A concrete detection device for construction engineering according to claim 1, characterized in that: A protective plate (5) is fixedly connected to the middle of the strength monitor (1); and a rotating plate (51) is rotatably connected to the middle of the protective plate (5).

6. A concrete detection device for construction engineering according to claim 2, characterized in that: A limiting plate (6) is fixedly connected to the middle portion of the blocking plate (23); the limiting plate (6) is slidably connected to the card slot (2).

7. A concrete detection device for construction engineering according to claim 4, characterized in that: A collecting fence (7) is fixedly connected to the middle of the scraper (43).