Double-row tool apron and numerical control lathe

By designing a double row of tool holders, using sliders to drive multiple fixed components to move, providing multiple tool selection, solving the problem of limited number of CNC lathe tools, improving machining efficiency and accuracy, and realizing a processing process without disassembling and assembly of tools.

CN222094749UActive Publication Date: 2024-12-03SHENZHEN GUOZHI INTELLIGENT EQUIP CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420577935.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-21
Publication Date
2024-12-03
Estimated Expiration
2034-03-21

AI Technical Summary

Technical Problem

The number of tool mounting tools on CNC lathes is limited, which leads to frequent disassembly and assembly of tools during the process of workpieces from blank processing to finished products, which easily leads to errors and affects processing efficiency and accuracy.

Method used

Design a double row tool holder, including a base and multiple fixed components, with mounting grooves on the fixing components, and the slider can drive multiple fixed components to move at the same time, providing multiple tools to avoid disassembly and assemble the tool during processing. , improve processing efficiency and accuracy.

Benefits of technology

It realizes that there is no need to disassemble and assemble the tool during the processing process, improves the processing efficiency and accuracy of the workpiece, provides more tool selection, and meets diverse processing needs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222094749U_ABST
    Figure CN222094749U_ABST
Patent Text Reader

Abstract

The double-row tool apron comprises a base, a plurality of first guide rails are arranged on the base, each first guide rail is slidably connected with a sliding part, the sliding parts on the different first guide rails slide independently, each sliding part is connected with a plurality of fixing assemblies arranged at intervals, and the fixing assemblies are arranged on the base. The fixing assembly is provided with an installation groove used for installing a cutter. The numerical control lathe comprises a rack, a first main shaft unit, a second main shaft unit and the double-row tool apron, a second guide rail extending in the second direction is arranged on the rack, the first main shaft unit and the second main shaft unit are both in sliding connection with the second guide rail, and the first main shaft unit comprises a first mounting base and a first rotating shaft; the second main shaft unit comprises a second mounting seat and a second rotating shaft; and the base is connected with the rack. According to the double-row tool apron and the numerical control lathe, the machining efficiency and the machining precision can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of processing equipment, and in particular to a double-row tool holder and a CNC lathe. Background Art

[0002] In processing technology, a workpiece needs to undergo multiple processes in the process of processing from a blank to a finished product. In each processing process, the workpiece and one of the tools installed on the tool holder are moved to the processing position together. The workpiece and the tool are in contact at the processing position, and processing is achieved by the relative movement of the workpiece and the tool at the processing position. Currently, the number of tools installed on the tool holder on a CNC lathe is relatively limited. In the process of processing the workpiece from a blank to a finished product, the tool on the tool holder needs to be disassembled, assembled and replaced, and the tool needs to be re-calibrated after replacing the tool, which is prone to errors and affects the processing efficiency and accuracy of the workpiece. Utility Model Content

[0003] The present application aims to solve at least one of the technical problems existing in the prior art. To this end, the present application proposes a double-row tool holder, which can improve machining efficiency and machining accuracy.

[0004] The present application also proposes a CNC lathe having the above-mentioned double-row tool holder.

[0005] According to the first aspect of the present application, the double-row tool holder includes a base and a plurality of fixing components;

[0006] Multiple fixing components are provided with mounting grooves, and the mounting grooves are used to install cutting tools;

[0007] The base is provided with a plurality of first guide rails extending along a first direction, each of the first guide rails is slidably connected to a sliding member, the sliding members on different first guide rails are independent of each other, each of the sliding members is connected to a plurality of fixing components, and the plurality of fixing components on the same sliding member are spaced apart along the first direction;

[0008] Among them, the second direction is perpendicular to the first direction, the sliding member can simultaneously drive multiple fixed components to move along the first direction, the fixed components are configured to drive the tool to move along the first direction to the processing position to process the workpiece moved along the second direction to the processing position, and the intervals between the fixed components are used to avoid other tools when the tool in contact with the workpiece processes the workpiece.

[0009] The double-row tool holder according to the embodiment of the present application has at least the following beneficial effects: each fixed component is provided with an installation groove, the installation groove is used to install the tool, and along the first direction, multiple fixed components are arranged at intervals on the same sliding member, so that the same sliding member can simultaneously drive multiple tools to move along the first direction to the processing position to process the workpiece moved along the second direction to the processing position, and the intervals between the fixed components are used to avoid other tools when one of the tools on the sliding member processes the workpiece. Therefore, the double-row tool holder can provide a larger number of tools for selection in different processing steps to contact the workpiece for processing without the need to disassemble and replace the tools during the processing, which is beneficial to improving the processing efficiency and processing accuracy.

[0010] According to some embodiments of the present application, the sliding member is provided with a guide portion, the fixing assembly includes a fixing seat and a locking member, the fixing seat is provided with a fixing groove and an installation groove, the locking member is provided with a locking portion and a holding portion, and the fixing seat and the locking member are detachably connected;

[0011] Among them, the locking part is configured to be inserted into the fixing groove when the fixing seat is connected to the locking piece, and the abutting part abuts the guiding part to limit the movement of the fixing seat relative to the guiding part. The fixing seat and the abutting part enclose the guiding groove, and the guiding groove is embedded with the guiding part.

[0012] According to some embodiments of the present application, the fixing assembly includes a fixing seat, on which a first fixing portion and a second fixing portion are provided, the first fixing portion is connected to the second fixing portion, and along a first direction, the first fixing portion protrudes outward from the second fixing portion, and the first fixing portion and the second fixing portion are both provided with mounting grooves, and extension directions of the mounting grooves on the first fixing portion and the mounting grooves on the second fixing portion are parallel to each other, and the extension direction of each mounting groove is configured to be perpendicular to the second direction.

[0013] According to some embodiments of the present application, the double-row tool holder includes two sliding members, the two sliding members are spaced apart along the second direction, a plurality of fixing components are connected to the two sliding members, and extension directions of the mounting grooves on different sliding members are perpendicular to each other.

[0014] A CNC lathe according to a second aspect of the present application includes a frame, a first spindle unit, a second spindle unit, and a double-row tool holder in any of the above embodiments;

[0015] The frame is provided with a second guide rail extending along a second direction;

[0016] A first spindle unit is slidably connected to the second guide rail;

[0017] A second spindle unit is slidably connected to the second guide rail;

[0018] In any of the above embodiments, the double-row tool holder, the base is fixedly connected to the frame, along the second direction, the base is located between the first spindle unit and the second spindle unit, and the processing position includes the first station and the second station;

[0019] Among them, the first spindle unit is used to clamp the workpiece and drive the workpiece to rotate, and to move the workpiece to the first workstation along the second direction. At least one sliding member can drive the tool to move along the first direction to the first workstation to process the workpiece. The second spindle unit is used to receive the workpiece on the first spindle unit and drive the workpiece to rotate, and to move the workpiece to the second workstation along the second direction. At least one sliding member can drive the tool to move along the first direction to the second workstation to process the workpiece.

[0020] According to the CNC lathe of the embodiment of the present application, there are at least the following beneficial effects: the first spindle unit and the second spindle unit can both move along the second direction, and the docking and material transfer of the workpiece on the first spindle unit and the second spindle unit can be realized. The base of the double-row tool holder is located between the first spindle unit and the second spindle unit, and the double-row tool holder can drive the tool to move along the first direction, thereby cooperating with the first spindle unit and the second spindle unit to process the workpiece. Therefore, there is no need to disassemble the workpiece and the tool during the processing, which is beneficial to improving the processing efficiency and accuracy.

[0021] According to some embodiments of the present application, the CNC lathe further includes a feeding device, the feeding device is provided with a feeding channel extending along the second direction, the first spindle unit includes a first rotating shaft, a first clamping portion is provided on the first rotating shaft, a first channel extending along the second direction is provided on the first rotating shaft, and the feeding device is located on a side of the first rotating shaft away from the first clamping portion;

[0022] Among them, the feeding device is connected to the end of the first rotating shaft away from the first clamping part so that the feeding channel is coaxially connected with the first channel. The feeding channel and the first channel are used to insert the workpiece in sequence, and the first clamping part can clamp the workpiece and rotate synchronously with the first rotating shaft.

[0023] According to some embodiments of the present application, the CNC lathe further includes a tool detection device, the first spindle unit includes a first mounting seat, the tool detection device is connected to the first mounting seat, the tool detection device includes a first driving member, a connecting member and a first guide rod, a probe is provided at the end of the first guide rod, and the first driving member is connected to the first guide rod through the connecting member;

[0024] The first driving member can drive the connecting member to move along the second direction, so that the connecting member drives the first guide rod to approach the tool, and detects the position information of the tool through the probe.

[0025] According to some embodiments of the present application, the second spindle unit further includes a second rotating shaft and a material ejecting device, the second rotating shaft is provided with a second clamping portion, the material ejecting device includes a second driving member and a second guide rod, the second driving member is slidably connected to the second guide rod, and the second rotating shaft is provided with a second channel extending along the second direction;

[0026] The second guide rod is inserted into the second channel, and a pin is provided at one end of the second guide rod facing the second clamping portion. The second driving member can drive the second guide rod to move in the second direction so that the pin can abut against the workpiece at the second clamping portion.

[0027] According to some embodiments of the present application, the CNC lathe further includes a material unloading device, which is disposed adjacent to the second spindle unit along the first direction, and includes a material receiving assembly and a transmission assembly, and the material receiving assembly includes a first material receiving piece and a second material receiving piece, the first material receiving piece is provided with an inner cavity, and the second material receiving piece is disposed in the inner cavity and is slidably connected to the first material receiving piece;

[0028] Among them, there is an angle between the material receiving component and the transmission component. The second material receiving component can slide relative to the first material receiving component to the location of the workpiece on the second spindle unit to receive the workpiece. The first material receiving component is used to receive the workpiece on the second spindle unit and can transfer the workpiece to the transmission component.

[0029] According to some embodiments of the present application, a chip box is further provided on the frame, and the chip box is located below the double-row tool holder, and the chip box is used to receive processing debris.

[0030] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] The present application is further described below with reference to the accompanying drawings and embodiments, wherein:

[0032] Figure 1 This is a schematic diagram of the structure of a double-row tool holder according to an embodiment of the present application;

[0033] Figure 2 A top view of a double-row tool holder according to an embodiment of the present application;

[0034] Figure 3 This is a front view of a double-row knife holder according to an embodiment of the present application;

[0035] Figure 4 for Figure 2 A local enlarged schematic diagram of the middle A;

[0036] Figure 5 for Figure 3 A partial enlarged schematic diagram of point B in the middle;

[0037] Figure 6 This is a partial structural schematic diagram of a CNC lathe according to an embodiment of the present application;

[0038] Figure 7 This is a front view of a CNC lathe according to an embodiment of the present application;

[0039] Figure 8 for Figure 7 A partial enlarged schematic diagram of point C in the middle;

[0040] Fig. 9 This is a schematic diagram of the structure of the first spindle unit in an embodiment of the present application;

[0041] Fig.10 This is a schematic diagram of the structure of a tool detection device and a material ejection device according to an embodiment of the present application;

[0042] Fig.11 This is a schematic diagram of the structure of the second spindle unit in an embodiment of the present application;

[0043] Fig.12 This is a schematic diagram of the structure of the feeding device in the embodiment of the present application;

[0044] Fig.13 This is a schematic diagram of the structure of the CNC lathe according to the embodiment of the present application.

[0045] Reference numerals: base 100 , first guide rail 110 , slide 120 , guide portion 121 , tool 130 , workpiece 140 , processing position 150 , first station 151 , second station 152 ;

[0046] The fixing assembly 200, the fixing seat 210, the mounting groove 211, the fixing groove 212, the first fixing portion 213, the second fixing portion 214, the guide groove 215, the locking member 220, the locking portion 221, and the abutting portion 222;

[0047] Frame 300, second guide rail 310, chip box 320;

[0048] A first spindle unit 400 , a first mounting seat 410 , a first rotating shaft 420 , a first clamping portion 421 , and a first channel 422 ;

[0049] A second spindle unit 500, a second mounting seat 510, a second rotating shaft 520, a second clamping portion 521, and a second channel 522;

[0050] A feeding device 600 and a feeding channel 610;

[0051] Tool detection device 700, first driving member 710, connecting member 720, first guide rod 730, probe 731;

[0052] The ejector device 800, the second driving member 810, the second guide rod 820, and the ejector pin 821;

[0053] A material unloading device 900 , a material receiving assembly 910 , a first material receiving piece 911 , a second material receiving piece 912 , and a conveying assembly 920 . DETAILED DESCRIPTION

[0054] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.

[0055] In the description of the present application, it should be understood that descriptions involving orientation, such as up, down, front, back, left, right, etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0056] In the description of this application, "several" means more than one, "more" means more than two, "greater than", "less than", "exceed", etc. are understood to exclude the number itself, and "above", "below", "within", etc. are understood to include the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing technical features, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0057] In the description of this application, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in this application based on the specific content of the technical solution.

[0058] In the description of the present application, the description with reference to the terms "one embodiment", "some embodiments", "illustrative embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials, or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.

[0059] The following is an introduction to the embodiments of the present application in conjunction with the accompanying drawings:

[0060] refer to Figures 1 to 7According to the double-row tool holder of the first aspect of the present application, the double-row tool holder comprises a plurality of fixing components 200 and a base 100, each fixing component 200 is provided with a mounting groove 211, the mounting groove 211 is used to mount a tool 130, a plurality of first guide rails 110 extending along a first direction are provided on the base 100, each first guide rail 110 is slidably connected with a sliding member 120, the sliding members 120 located on different first guide rails 110 can slide independently of each other, that is, the sliding of the sliding members 120 slidably connected with different first guide rails 110 does not affect each other, and each sliding member 120 is connected with a plurality of fixing components 200, Multiple fixed components 200 located on the same sliding member 120 are arranged at intervals along the first direction. The sliding member 120 can simultaneously drive the multiple fixed components 200 to move along the first direction to simultaneously drive multiple tools 130 to move along the first direction. The workpiece 140 can move along a second direction perpendicular to the first direction. The workpiece 140 and the tool 130 are in contact at a processing position 150, and the workpiece 140 is processed by the relative movement of the workpiece 140 and the tool 130. The double-row tool holder can provide more tool 130 options for the processing of the workpiece 140, avoid disassembly and assembly of the tool 130 during the processing, and is beneficial to improving the processing efficiency.

[0061] It should be understood that when performing processing operations, one of the multiple tools 130 on the sliding member 120 contacts the workpiece 140. In multiple processing operations, the same tool 130 can be used according to the processing requirements of the workpiece 140, or a tool 130 can be replaced after each processing. The multiple fixed components 200 arranged at intervals along the first direction on the sliding member 120 can install a larger number of tools 130. Compared with ordinary tool holders, the required tools 130 can be installed in the installation groove 211 before the start of processing, and the tool 130 can be avoided from being disassembled and assembled from the tool holder during the processing as much as possible. During the processing operation, the tool 130 is moved along the first direction to cooperate with the workpiece 140 moving along the second direction, so that the tool 130 required for the current process is in contact with the workpiece 140, and the processing operation is completed by generating a relative displacement between the two, which is beneficial to improving the processing efficiency and processing accuracy.

[0062] Specifically, during processing, the sliding member 120 slides along a first direction relative to the first guide rail 110, and the workpiece 140 moves along a second direction so that the workpiece 140 contacts the tool 130 required in the current process. The workpiece 140 and the tool 130 are processed by relative movement, and during the processing, at least one of the tool 130 and the workpiece 140 moves. The interval between the fixed component 200 on which the tool 130 required for the current process is installed and the adjacent fixed component 200 is used to avoid other tools 130 to prevent the workpiece 140 from contacting tools 130 other than the tool 130 used for the current processing during the processing. The workpiece 140 includes two actions during the processing, namely, movement along the second direction and rotation of the workpiece 140. During the rotation of the workpiece 140, the sliding member 120 slides along the first direction relative to the first guide rail 110 to adjust the feed amount of the tool 130 relative to the workpiece 140. After the current process is completed, the workpiece 140 moves away from the tool 130 along the second direction, and the sliding member 120 moves along the first direction to replace another tool 130 for the next processing of the workpiece 140 until the processing of the current process is completed. The tools 130 in different installation slots 211 can be of different types, or they can be tools 130 of the same type with different angle parameters, which is beneficial to meet diverse processing needs.

[0063] It should be noted that the first direction may have an angle with the horizontal line, and the second direction is parallel to the horizontal line. One of the above-mentioned multiple processing includes but is not limited to rough turning, fine turning, grooving, cutting, partial rough turning, partial fine turning and other processes of the workpiece 140. The angle parameters of the tool 130 include but are not limited to parameters such as the front angle, the back angle, the main deflection angle and the secondary deflection angle.

[0064] In other embodiments, a plurality of sliding members 120 are slidably connected to the same first guide rail 110, and each sliding member 120 can slide along the first guide rail 110 independently of each other. Each sliding member 120 is connected to a plurality of fixing components 200, and the plurality of fixing components 200 are arranged on the sliding member 120 at intervals along the first direction. When the sliding member 120 slides relative to the first guide rail 110, it can simultaneously drive a plurality of tools 130 to move along the first direction. In one machining operation, a tool 130 on the sliding member 120 contacts the workpiece 140, the tool 130 moves along the first direction, and the workpiece 140 moves along the second direction. The tool 130 and the workpiece 140 achieve machining operations through relative motion.

[0065] refer to Figures 1 to 5In some embodiments, the sliding member 120 is provided with a guide portion 121, the fixing assembly 200 includes a fixing seat 210 and a locking member 220, the fixing seat 210 is provided with a fixing groove 212 and an installation groove 211, the locking member 220 is provided with a locking portion 221 and a holding portion 222, the fixing seat 210 and the locking member 220 are detachably connected, the locking portion 221 is configured to be inserted into the fixing groove 212 when the fixing seat 210 and the locking member 220 are connected, and at the same time, the holding portion 222 also holds the guide Towards the portion 121, so as to limit the movement of the fixed seat 210 relative to the guide portion 121, the fixed seat 210 and the supporting portion 222 enclose a guide groove 215, and the guide groove 215 can be a dovetail groove. The guide portion 121 is embedded in the guide groove 215, and the guide portion 121 extends along the first direction. The detachable connection between the fixed seat 210 and the locking member 220 can adjust the interval between the multiple fixed components 200 on the sliding member 120, so as to facilitate the disassembly and maintenance of the tool 130 before the processing operation.

[0066] refer to Figures 1 to 7 In some embodiments, the fixing assembly 200 includes a fixing seat 210, and a first fixing portion 213 and a second fixing portion 214 are provided on the fixing seat 210. The first fixing portion 213 is connected to the second fixing portion 214. Along the first direction, the first fixing portion 213 protrudes from the second fixing portion 214. The first fixing portion 213 and the second fixing portion 214 are both provided with a mounting groove 211. The number of mounting grooves 211 provided may be multiple. The mounting grooves 211 on the first fixing portion 213 and the mounting grooves 211 on the second fixing portion 214 extend in parallel with each other. The tool 130 installed in the mounting groove 211 on the first fixing portion 213 and the tool 130 installed in the mounting groove 211 on the second fixing portion 214 may be different tools 130. The extending direction of each mounting groove 211 is configured to be perpendicular to the second direction. It should be understood that each mounting groove 211 may extend along the first direction, and the first direction is perpendicular to the second direction. By providing the first fixing portion 213 protruding outwardly in the first direction, the blade portions of the tool 130 located on the first fixing portion 213 and the second fixing portion 214 are staggered in the first direction, so as to facilitate processing of the workpiece 140 .

[0067] It should be noted that the above-mentioned different tools 130 can be tools 130 of the same type with different angle parameters, or they can be tools 130 of different types. For example, a grooving tool is installed in the mounting groove 211 on the first fixed part 213, and an external cylindrical turning tool is installed in the mounting groove 211 on the second fixed part 214. The external cylindrical turning tool on the second fixed part 214 is used to process the end face and outer circle of the workpiece 140, and the grooving tool on the first fixed part 213 is used to cut off the workpiece 140 after the end face and outer circle processing of the workpiece 140 is completed.

[0068] refer to Figures 1 to 5In some embodiments, the double-row tool holder includes a base 100, on which two first guide rails 110 extending along a first direction are provided, each of which is slidably connected to a sliding member 120, and the two first guide rails 110 are spaced apart along a second direction, and the two sliding members 120 respectively located on the two first guide rails 110 have a gap, and the sliding members 120 located on the two first guide rails 110 slide independently of each other, and each sliding member 120 is connected to a plurality of fixing components 200, and the plurality of fixing components 200 on the same sliding member 120 are spaced apart along the first direction, and an installation groove 211 is provided on the fixing component 200, and the installation groove 211 is used to install a tool 130, so that the sliding member 120 can simultaneously drive multiple tools 130 to move along the first direction, and the gap is used to avoid other tools 130 when one of the tools 130 processes a workpiece 140, to ensure that any tool 130 on the sliding member 120 will not be interfered by other tools 130 when processing the workpiece 140.

[0069] Specifically, the first direction is perpendicular to the second direction, and the extension directions of the mounting grooves 211 of the fixing components 200 located on different sliding members 120 are perpendicular to each other. It should be understood that the mounting grooves 211 on the multiple fixing components 200 connected to one of the sliding members 120 all extend along the first direction, and the mounting grooves 211 on the multiple fixing components 200 connected to the other sliding member 120 all extend along the second direction, and the workpiece 140 can move along the second direction. The tool 130 installed in the mounting groove 211 extending along the first direction can perform radial processing on the workpiece 140, and the tool 130 installed in the mounting groove 211 extending along the second direction can perform axial processing on the workpiece 140. The radial processing method has higher processing efficiency and higher cutting surface flatness. According to different processing requirements of the workpiece 140, the tool 130 can choose different installation methods, which is beneficial to improving the processing efficiency of the workpiece 140.

[0070] refer to Figures 1 to 8According to the second aspect of the present application, the CNC lathe comprises a frame 300, a first spindle unit 400, a second spindle unit 500 and a double-row tool holder in any of the above embodiments, the frame 300 is provided with a second guide rail 310 extending along a second direction, the first spindle unit 400 is slidably connected to the second guide rail 310, the first spindle unit 400 comprises a first mounting seat 410 and a first rotating shaft 420, the first rotating shaft 420 is rotatably connected to the first mounting seat 410, and the second spindle unit 500 is slidably connected to the second guide rail 310. The second spindle unit 500 includes a second mounting seat 510 and a second rotating shaft 520, and the second rotating shaft 520 is rotatably connected to the second mounting seat 510. The double-row tool holder includes a base 100, and the base 100 is fixedly connected to the frame 300, and along the second direction, the base 100 is located between the first spindle unit 400 and the second spindle unit 500. The first spindle unit 400 can move closer to or away from the base 100 along the second direction, and the second spindle unit 500 can also move closer to or away from the base 100 along the second direction. The above-mentioned processing position 150 includes a first workstation 151 and a second workstation 152. The intersection of the first spindle unit 400 and the base 100 is the first workstation 151, and the intersection of the second spindle unit 500 and the base 100 is the second workstation 152. The first spindle unit 400 processes the workpiece 140 at the first workstation 151. After processing, the first spindle unit 400 and the second spindle unit 500 approach each other along the second direction to realize the material transfer of the workpiece 140 without manual disassembly and assembly of parts, which is beneficial to improving production efficiency.

[0071] The first rotating shaft 420 can rotate relative to the first mounting seat 410, and the second rotating shaft 520 can rotate relative to the second mounting seat 510. The first rotating shaft 420 is provided with a first clamping portion 421 at one end thereof facing the second rotating shaft 520, and the second rotating shaft 520 is provided with a second clamping portion 521 at one end thereof facing the first rotating shaft 420. The first clamping portion 421 is used to clamp the workpiece 140 and drive the workpiece 140 to rotate together with the first rotating shaft 420. Under the clamping of the first clamping portion 421, the workpiece 140 can move along the second direction to the first station 151, and at least one The sliding member 120 can drive the tool 130 to move along the first direction to the first station 151 to process the workpiece 140. The second clamping portion 521 is used to receive the workpiece 140 on the first clamping portion 421 after the workpiece 140 is processed by the first spindle unit 400, so as to clamp the workpiece 140 and rotate together with the second rotating axis 520. Under the clamping of the second clamping portion 521, the workpiece 140 can move along the second direction to the second station 152. At least one sliding member 120 can drive the tool 130 to move along the first direction to the second station 152 to process the workpiece 140.

[0072] refer to Figures 6 to 9In some embodiments, the CNC lathe further comprises a feeding device 600, the feeding device 600 is provided with a feeding channel 610 extending along the second direction, the first rotating shaft 420 is provided with a first channel 422 extending along the second direction, the feeding device 600 is located at a side of the first rotating shaft 420 away from the first clamping portion 421, wherein the feeding device 600 is docked with an end of the first rotating shaft 420 away from the first clamping portion 421, so that the feeding channel 610 is connected with the first channel 422. The feeding channel 610 and the first channel 422 are used to sequentially penetrate the workpiece 140, the penetrated workpiece 140 can be clamped by the first clamping portion 421, and the part of the workpiece 140 to be processed is exposed to the first channel 422, and the first clamping portion 421 clamps the workpiece 140 and rotates synchronously with the first rotating shaft 420. The workpiece 140 to be processed by the CNC lathe can be a longer bar, and the final product required is a shorter bar. The longer bar is inserted into the loading channel 610 and the first channel 422 in turn. Through the loading device 600, the longer bar workpiece 140 can be moved a set distance along the second direction, so that the workpiece 140 passes through the first clamping part 421 and is exposed to the first channel 422, and is cut off after the processing of the exposed part of the workpiece 140 is completed, thereby realizing continuous loading and processing, which is beneficial to improving processing efficiency.

[0073] refer to Figures 7 to 11 In some embodiments, the CNC lathe further includes a tool detection device 700, which is connected to the first mounting seat 410. The tool detection device 700 includes a first driving member 710, a connecting member 720 and a first guide rod 730. A probe 731 is provided at the end of the first guide rod 730. The first driving member 710 is connected to the first guide rod 730 through the connecting member 720. The first driving member 710 can drive the connecting member 720 to move along the second direction so that the connecting member 720 drives the first guide rod 730 to approach the tool 130. The probe 731 at the end of the first guide rod 730 is used to detect the position information of the tool 130 to determine whether the tool 130 is damaged, so as to facilitate timely shutdown and replacement of the tool 130 when the tool 130 is damaged, which is beneficial to ensure the continuous operation of the processing operation.

[0074] Specifically, the first driving member 710 can be one of a pneumatic cylinder, a hydraulic cylinder or an electric push rod. A photoelectric sensor can be installed on the probe 731. The tool 130 is moved to the theoretical position through the CNC program. The probe 731 compares the actual position of the tool 130 with the theoretical position difference. If the difference is too large, the tool detection device 700 will feed back the damage information to the CNC system, and the CNC system will issue a reminder to replace the tool 130. If the difference is within the preset range, the tool detection device 700 returns to the initial position and the CNC lathe can operate normally.

[0075] refer to Figures 10 to 13In some embodiments, the second spindle unit 500 also includes a ejection device 800, which includes a second driving member 810 and a second guide rod 820. The second driving member 810 is slidably connected to the second guide rod 820. The second rotating shaft 520 is provided with a second channel 522 extending along the second direction. The second guide rod 820 is inserted into the second channel 522. An ejector pin 821 is provided at one end of the second guide rod 820 facing the second clamping portion 521. The second driving member 810 can drive the second guide rod 820 to move along the second direction. The second guide rod 820 drives the ejector pin 821 to resist the workpiece 140 located at the second clamping portion 521. When the second clamping portion 521 releases the workpiece 140, the ejector pin 821 resists the workpiece 140 to make the workpiece 140 detach from the second clamping portion 521, thereby realizing automatic unloading of the workpiece 140 after machining is completed, which is beneficial to improving the machining efficiency of the CNC lathe.

[0076] Specifically, the second clamping portion 521 clamps the workpiece 140 and rotates together with the second rotating axis 520, and the first mounting seat 410 slides on the second guide rail 310 along the second direction relative to the frame 300, so that the workpiece 140 moves along the second direction. After the workpiece 140 is processed, the CNC lathe also includes a feeding device 900, and the material receiving assembly 910 of the feeding device 900 partially moves to the location of the second clamping portion 521, and the second clamping portion 521 releases the workpiece 140. The second driving member 810 drives the second guide rod 820 to move in the second direction, so that the ejector pin 821 on the second guide rod 820 pushes the workpiece 140 into the material receiving assembly 910, and the workpiece 140 received by the material receiving assembly 910 is transferred to the conveying assembly 920 of the feeding device 900 for transmission to the next process.

[0077] refer to Fig.13 In some embodiments, the CNC lathe further includes a material unloading device 900. The material unloading device 900 is disposed adjacent to the second spindle unit 500 along the first direction. The material unloading device 900 includes a material receiving component 910 and a transmission component 920. The material receiving component 910 is used to receive the workpiece 140 that has been processed. The transmission component 920 is used to receive the workpiece 140 from the material receiving component 910 and transfer the workpiece 140 to the next process. The material receiving component 910 includes a first material receiving member 911 and a second material receiving member 912. The first material receiving member 911 is provided with an inner cavity. The second material receiving piece 912 is arranged in the inner cavity of the first material receiving piece 911, and the second material receiving piece 912 is slidably connected to the first material receiving piece 911. There is an angle between the material receiving component 910 and the transmission component 920. The second material receiving piece 912 can slide relative to the first material receiving piece 911 to the location of the second clamping portion 521 to receive the processed workpiece 140. The workpiece 140 received by the second material receiving piece 912 is transferred to the first material receiving piece 911, and the first material receiving piece 911 then transfers the workpiece 140 to the transmission component 920, thereby realizing the acceptance and transmission of the material.

[0078] It should be noted that the angle between the material receiving component 910 and the conveying component 920 includes two situations: the material receiving component 910 is perpendicular to the conveying component 920, and the angle between the material receiving component 910 and the conveying component 920 is an obtuse angle. Compared with the vertical arrangement of the material receiving component 910 and the conveying component 920, the angle between the material receiving component 910 and the conveying component 920 enables the second material receiving member 912 to move relative to the first material receiving member 911 simultaneously including movement along the first direction and movement along the second direction. The conveying component 920 is arranged along the second direction, which is beneficial to shorten the length of the conveying component 920 and make the structure of the unloading device 900 more compact.

[0079] refer to Figure 5 In some embodiments, the CNC lathe includes a frame 300, and the frame 300 is also provided with a chip box 320. The chip box 320 is located below the double-row tool holder. The chip box 320 is used to store processing debris. When performing processing operations, the generated debris naturally falls into the chip box 320 under the action of gravity. The chip box 320 can be removed from the frame 300 to clean the processing debris in the chip box 320.

[0080] refer to Figures 1 to 13 The processing method using the CNC lathe in any of the above embodiments includes three steps: first end processing, docking and material transfer, and second end processing. In the first end processing step, the first spindle unit 400 clamps the workpiece 140 and can drive the workpiece 140 to rotate. At least one sliding member 120 drives multiple tools 130 to move along the first direction to the first station 151. The first spindle unit 400 moves the workpiece 140 to the first station 151 along the second direction. One of the multiple tools 130 contacts the workpiece 140, and the two process the workpiece 140 through relative movement. Specifically, the sliding member 120 moves along the first direction so that the tool 130 generates a feed amount relative to the workpiece 140. After the tool 130 is stationary, the workpiece 140 moves relative to the tool 130 along the second direction for processing.

[0081] Alternatively, the workpiece 140 moves along the second direction to the first workstation 151. After the workpiece 140 stops, the tool 130 moves along the first direction to process the workpiece 140. It should be noted that the movement sequence of the tool 130 and the workpiece 140 can be adjusted according to actual processing requirements. In addition, during the processing, the tool 130 and the workpiece 140 can move simultaneously to achieve processing of the workpiece 140.

[0082] In the docking and material transfer step, after the workpiece 140 clamped on the first spindle unit 400 is processed at the first workstation 151, the second clamping portion 521 on the second spindle unit 500 is opened, and the second clamping portion 521 maintains the same rotation speed as the workpiece 140 on the first spindle unit 400, and the first spindle unit 400 and the second spindle unit 500 approach each other along the second direction so that the workpiece 140 on the first spindle unit 400 is inserted into the second clamping portion 521, and the second clamping portion 521 clamps the workpiece 140, and the first spindle unit 400 releases the workpiece 140, and the first spindle unit 400 and the second spindle unit 500 move away from each other to complete the docking and material transfer, and keep the workpiece 140 rotating for docking and material transfer, which is beneficial to improving processing efficiency.

[0083] In other embodiments, after the workpiece 140 clamped on the first spindle unit 400 is processed at the first workstation 151, the first spindle unit 400 stops rotating the workpiece 140, the second clamping portion 521 on the second spindle unit 500 opens, the first spindle unit 400 and the second spindle unit 500 approach each other along the second direction so that the workpiece 140 on the first spindle unit 400 is inserted into the second clamping portion 521, the second clamping portion 521 clamps the workpiece 140, the first spindle unit 400 releases the workpiece 140, and the first spindle unit 400 and the second spindle unit 500 move away from each other to complete the docking and material transfer.

[0084] It should be noted that, in the second end processing step, the workpiece 140 and the tool 130 contact and generate relative movement at the second station 152 to process one end of the workpiece 140 toward the first spindle unit 400, that is, the unprocessed part at the first station 151. Similarly, referring to the first end processing step, the relative movement between the tool 130 and the workpiece 140 can be achieved by a combination of the movement of the tool 130 along the first direction and the movement of the workpiece 140 along the second direction, and the movement sequence of the two can be adjusted according to the processing requirements.

[0085] refer to Figures 1 to 13In some embodiments, in the first end processing step, the first clamping portion 421 clamps the workpiece 140, driving the workpiece 140 to rotate synchronously with the first rotating shaft 420, and the double-row tool holder includes two slides 120. Along the second direction, the two slides 120 are divided into a slide 120 close to the first spindle unit 400 and a slide 120 close to the second spindle unit 500. The slide 120 close to the first spindle unit 400 simultaneously drives multiple tools 130 to move along the first direction, and the first mounting seat 410 drives the workpiece 140 to move along the second direction. The tool 130 and the workpiece 140 are in contact at the first station 151, and the first end processing step is completed by the relative movement of the tool 130 and the workpiece 140. It should be noted that the first end processing step includes multiple processing sequences, and in each processing sequence, a tool 130 is used to process the workpiece 140. The multiple tools 130 on the slide 120 can provide a variety of options for the processing of the workpiece 140, which is beneficial to provide a richer processing method.

[0086] In the docking and material transfer step, the workpiece 140 has completed the first end processing step, the first clamping part 421 clamps the workpiece 140, the first rotating shaft 420 and the second rotating shaft 520 maintain the same rotation speed, and in order to ensure the stability of docking, the rotation speed can be selected to be lower, the axis of the first rotating shaft 420 and the second rotating shaft 520 should coincide, the first mounting seat 410 and the second mounting seat 510 approach each other along the second direction, and the second clamping part 521 remains in an open state, so that the processed end of the workpiece 140 can be inserted into the second clamping part 521, because the first rotating shaft 4 20 and the second rotating shaft 520 maintain the same rotation speed, therefore, the second clamping part 521 and the second rotating shaft 520 are relatively stationary, the second clamping part 521 clamps the processed end of the workpiece 140, and the first clamping part 421 releases the workpiece 140, and the workpiece 140 is transferred from the first clamping part 421 to the second clamping part 521. After the material transfer, the first mounting seat 410 and the second mounting seat 510 move away from each other along the second direction, thereby realizing the docking and material transfer of the workpiece 140 after the processing is completed. Compared with the manual disassembly and assembly of the workpiece 140 for material transfer, it is beneficial to improve the processing efficiency of the CNC lathe.

[0087] In the second end processing step, the workpiece 140 clamped by the second clamping part 521 rotates with the second rotating axis 520, and along the second direction, the sliding member 120 close to the side of the second spindle unit 500 drives multiple tools 130 to move along the first direction, and the second mounting seat 510 drives the workpiece 140 to move along the second direction, so that the workpiece 140 and the tool 130 are in contact at the second station 152, and the workpiece 140 is processed by the relative movement between the workpiece 140 and the tool 130. Similarly, processing at the second station 152 may include multiple processing sequences, and in each processing sequence, a tool 130 is used to process the workpiece 140. In the second end processing step, one end of the workpiece 140 facing the first spindle unit 400 is processed, thereby realizing the processing of the entire workpiece 140.

[0088] It should be noted that the processing at the first station 151 and the processing at the second station 152 are independent of each other, that is, when the second end processing step is performed at the second station 152, the first end processing step of the next workpiece 140 can be performed at the first station 151 at the same time. The processing at the first station 151 is achieved by the first spindle unit 400 and a plurality of tools 130 on the sliding member 120 close to the first spindle unit 400, and the processing at the second station 152 is achieved by the second spindle unit 500 and a plurality of tools 130 on the sliding member 120 close to the second spindle unit 500. The first spindle unit 400 and the second spindle unit 500 only cooperate with each other during docking and material transfer to transfer the workpiece 140 processed at the first station 151 to the second station 152 for further processing.

[0089] refer to Figures 6 to 9In some embodiments, a loading step is included before the first end processing step. The loading step is suitable for automatic loading of longer bars. In the loading step, the CNC lathe includes a loading device 600. The loading device 600 is provided with a loading channel 610 extending along the second direction. The longer bar can be inserted into the loading channel 610. The first rotating shaft 420 is provided with a first channel 422 extending along the second direction. The loading channel 610 is coaxially arranged with the first channel 422. The loading channel 610 is connected with the first channel 422 so that the longer bar can be inserted into the loading channel 610 and the first channel 422 in sequence. Along the second direction, one end of the first channel 422 is provided with a first clamping portion 421. The loading channel 610 is located on the side of the first channel 422 away from the first clamping portion 421, and is inserted in sequence. The longer bar material entering the loading channel 610 and the first channel 422 is clamped by the first clamping part 421, and part of the longer bar material is exposed outside the first channel 422, and the exposed part is the processed part. After processing, the part of the workpiece 140 exposed outside the first channel 422 can be cut off, and the first clamping part 421 releases the longer bar material. The loading device 600 then drives the unprocessed part of the workpiece 140 to move along the second direction, so that part of the longer bar material is exposed again at one end of the first channel 422 provided with the first clamping part 421, and the first clamping part 421 clamps the workpiece 140 for processing. In this way, continuous loading and processing of the workpiece 140 can be realized until the processing of the current longer bar material is completed, without the need to frequently disassemble and assemble the workpiece 140 after the processing process, which is beneficial to improving processing efficiency.

[0090] It should be noted that the first rotating shaft 420 defines a first channel 422, and a first clamping portion 421 is provided at one end of the first rotating shaft 420, which clamps the first rod. During processing, the first rotating shaft 420 rotates relative to the first fixed seat 210, and the first clamping portion 421 clamps the workpiece 140 and rotates synchronously with the first rotating shaft 420. The loading channel 610 of the loading device 600 corresponds to the first channel 422, that is, the axes of the two are on the same straight line. When the workpiece 140 rotates, the loading channel 610 can be in a non-rotating state, or it can rotate together with the first rotating shaft 420.

[0091] refer to Figures 6 to 13In some embodiments, after the second end processing step, a blanking step is also included. The blanking step is suitable for blanking the workpiece 140 processed by the three steps of first end processing, docking transfer and second end processing. In the blanking step, the CNC lathe includes a feeding device 800 and a blanking device 900. The feeding device 800 includes a second driving member 810 and a second guide rod 820. The second rotating shaft 520 is provided with a second channel 522 extending along the second direction. The second driving member 810 is connected to the second rotating shaft 520 and can rotate with the second rotating shaft 520 during processing. The second guide rod 820 is penetrated in the second channel 522. The blanking device 900 includes a material receiving assembly 910 and a material transmission assembly. Before the part 521 releases the workpiece 140, the material receiving component 910 moves to the location of the second clamping part 521. The material receiving component 910 is provided with a material receiving port, and the workpiece 140 is aligned with the material receiving port. After the second clamping part 521 releases the workpiece 140, the second driving member 810 drives the second guide rod 820 to move along the second direction. The second guide rod 820 is provided with a ejector pin 821, and the workpiece 140 can be ejected by the ejector pin 821, so that the workpiece 140 is separated from the second clamping part 521. The workpiece 140 enters the material receiving component 910 from the material receiving port and is received by the material receiving component 910. The material receiving component 910 then transfers the received workpiece 140 to the material transfer component, thereby realizing automatic unloading of the workpiece 140 after processing is completed, which is beneficial to improving unloading efficiency.

[0092] refer to Figures 1 to 7 In some embodiments, the workpiece 140 is processed by a CNC lathe. In the docking and material transfer step, for the longer bar workpiece 140, the first clamping portion 421 clamps the workpiece 140. The longer bar workpiece 140 includes a portion received in the first channel 422 and a portion exposed outside the first channel 422. The first mounting seat 410 moves relative to the frame 300 along the second direction, thereby driving the workpiece 140 to move along the second direction. The portion of the workpiece 140 exposed in the first channel 422 completes the first end processing step at the first station 151. The first mounting seat 410 and the second mounting seat 510 approach each other along the second direction. When the two mounting seats 510 approach each other, the second clamping portion 521 is in an open state, so that the workpiece 140 clamped by the first clamping portion 421 is inserted into the second clamping portion 521, and the second clamping portion 521 clamps the workpiece 140 to complete the docking. It should be understood that at this time, the first clamping portion 421 and the second clamping portion 521 clamp the workpiece 140 at the same time, and the first rotating shaft 420 and the second rotating shaft 520 are on the same axis, and the first rotating shaft 420 and the second rotating shaft 520 maintain the same rotation speed. When docking and transferring materials, the first rotating shaft 420 and the second rotating shaft 520 can maintain a relatively low rotation speed, which is beneficial to ensuring the stability of the docking of the workpiece 140.

[0093] When the first clamping portion 421 and the second clamping portion 521 clamp the workpiece 140 at the same time, the tool 130 moves along the first direction to approach the workpiece 140, and cuts off the workpiece 140 at the end of the workpiece 140 close to the first clamping portion 421. At this time, the second clamping portion 521 clamps the workpiece 140 processed at the first station 151, the first clamping portion 421 clamps the workpiece 140 located in the first channel 422, and the second clamping portion 521 clamps the workpiece 140 processed at the first station 151 and moves it to the second station 152 for processing, so as to complete the second end processing step. When the tool 130 cuts off the workpiece 140, the first clamping portion 421 releases the workpiece 140 in the first channel 422, and the workpiece 140 in the first channel 422 moves along the second direction to expose the first channel 422. The first clamping portion 421 clamps the workpiece 140 and moves to the first station 151 to perform the first end processing step. It should be understood that the processing at the first station 151 and the second station 152 are independent of each other. There is no need to disassemble and assemble the workpiece 140 during the processing, so continuous processing of the workpiece 140 can be achieved, which is beneficial to improving processing efficiency.

[0094] It should be noted that during docking and material transfer, the first rotating shaft 420 and the second rotating shaft 520 are docked while maintaining a rotating state, which is beneficial to improving the material transfer efficiency compared to stopping the rotation of the first rotating shaft 420 and the second rotating shaft 520 before docking and material transfer.

[0095] The embodiments of the present application are described in detail above in conjunction with the accompanying drawings, but the present application is not limited to the above embodiments. Various changes can be made within the knowledge of ordinary technicians in the relevant technical field without departing from the purpose of the present application. In addition, the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.

Claims

1. A double-row tool holder, characterized in that: include: A plurality of fixing components are provided with mounting slots, wherein the mounting slots are used for mounting cutting tools; A base, provided with a plurality of first guide rails extending along a first direction, each of the first guide rails being slidably connected to a sliding member, the sliding members on different first guide rails being independent of each other, each of the sliding members being connected to a plurality of the fixing components, and the plurality of the fixing components on the same sliding member being spaced apart along the first direction; The second direction is perpendicular to the first direction, the sliding member can simultaneously drive multiple fixed components to move along the first direction, the fixed components are configured to drive the tool to move along the first direction to a processing position to process a workpiece moved along the second direction to the processing position, and the intervals between the fixed components are used to avoid other tools when the tool in contact with the workpiece processes the workpiece.

2. The double-row tool holder according to claim 1, characterized in that: The sliding member is provided with a guide portion, the fixing assembly comprises a fixing seat and a locking member, the fixing seat is provided with a fixing groove and the mounting groove, the locking member is provided with a locking portion and a holding portion, and the fixing seat is detachably connected to the locking member; Wherein, the locking portion is configured to be inserted into the fixing groove when the fixing seat is connected to the locking member, and the abutting portion abuts the guiding portion to limit the movement of the fixing seat relative to the guiding portion, the fixing seat and the abutting portion enclose a guiding groove, and the guiding portion is embedded in the guiding groove.

3. The double-row tool holder according to claim 1, characterized in that: The fixing assembly includes a fixing seat, on which a first fixing portion and a second fixing portion are provided, the first fixing portion is connected to the second fixing portion, and along the first direction, the first fixing portion protrudes outward from the second fixing portion, and the first fixing portion and the second fixing portion are both provided with the mounting groove, and extension directions of the mounting groove on the first fixing portion and the mounting groove on the second fixing portion are parallel to each other, and the extension direction of each mounting groove is configured to be perpendicular to the second direction.

4. The double-row tool holder according to claim 1, characterized in that: The double-row tool holder includes two sliding members, the two sliding members are spaced apart along the second direction, a plurality of fixing components are connected to the two sliding members, and extension directions of the mounting grooves on different sliding members are perpendicular to each other.

5. A CNC lathe, characterized in that: include: The frame is provided with a second guide rail extending along the second direction; A first spindle unit is slidably connected to the second guide rail; A second spindle unit is slidably connected to the second guide rail; The double-row tool holder according to any one of claims 1 to 4, wherein the base is fixedly connected to the frame, and along the second direction, the base is located between the first spindle unit and the second spindle unit, and the processing position includes a first station and a second station; Among them, the first spindle unit is used to clamp the workpiece and drive the workpiece to rotate, and to move the workpiece to the first workstation along the second direction, and at least one of the sliding members can drive the tool to move along the first direction to the first workstation to process the workpiece; the second spindle unit is used to receive the workpiece on the first spindle unit and drive the workpiece to rotate, and to move the workpiece to the second workstation along the second direction, and at least one of the sliding members can drive the tool to move along the first direction to the second workstation to process the workpiece.

6. The CNC lathe according to claim 5, characterized in that: The CNC lathe further comprises a feeding device, the feeding device is provided with a feeding channel extending along the second direction, the first spindle unit comprises a first rotating shaft, a first clamping portion is provided on the first rotating shaft, a first channel extending along the second direction is provided on the first rotating shaft, and the feeding device is located at a side of the first rotating shaft away from the first clamping portion; Among them, the feeding device is docked with one end of the first rotating shaft away from the first clamping part, so that the feeding channel is coaxially connected with the first channel, and the feeding channel and the first channel are used to penetrate the workpiece in sequence, and the first clamping part can clamp the workpiece and rotate synchronously with the first rotating shaft.

7. The CNC lathe according to claim 5, characterized in that: The CNC lathe further comprises a tool detection device, the first spindle unit comprises a first mounting seat, the tool detection device is connected to the first mounting seat, the tool detection device comprises a first driving member, a connecting member and a first guide rod, a probe is provided at the end of the first guide rod, and the first driving member is connected to the first guide rod through the connecting member; The first driving member can drive the connecting member to move along the second direction, so that the connecting member drives the first guide rod to approach the tool, and detects the position information of the tool through the probe.

8. The CNC lathe according to claim 5, characterized in that: The second spindle unit includes a second rotating shaft and a material ejecting device, the second rotating shaft is provided with a second clamping portion, the material ejecting device includes a second driving member and a second guide rod, the second driving member is slidably connected to the second guide rod, and the second rotating shaft is provided with a second channel extending along the second direction; The second guide rod is inserted into the second channel, and a pin is provided at one end of the second guide rod facing the second clamping portion. The second driving member can drive the second guide rod to move along the second direction so that the pin can abut against the workpiece located at the second clamping portion.

9. The CNC lathe according to claim 5, characterized in that: The CNC lathe further comprises a material unloading device, which is arranged adjacent to the second spindle unit along the first direction, and comprises a material receiving assembly and a transmission assembly, wherein the material receiving assembly comprises a first material receiving member and a second material receiving member, wherein the first material receiving member is provided with an inner cavity, and the second material receiving member is arranged in the inner cavity and is slidably connected to the first material receiving member; There is an angle between the material receiving component and the transmission component, and the second material receiving component can slide relative to the first material receiving component to the location of the workpiece on the second spindle unit to receive the workpiece, and the first material receiving component is used to receive the workpiece on the second spindle unit and can transfer the workpiece to the transmission component.

10. The CNC lathe according to claim 5, characterized in that: The frame is also provided with a chip box, which is located below the double-row tool holder and is used for storing processing debris.