Full-assembly type prefabricated parapet wall structure

Through the combination of bolted connection and anchored steel bars, the problem of insufficient temporary support fixing points caused by the lack of external scaffolding in the fully equipped concrete wall panel structure is solved, and the construction stability and anti-population capacity are improved, while simplifying the construction process and Reduced costs.

CN222101318UActive Publication Date: 2024-12-03CHANGSHA BROAD HOMES IND GRP CO LED
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420201200.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-26
Publication Date
2024-12-03
Estimated Expiration
2034-01-26

AI Technical Summary

Technical Problem

In the fully-prefabricated concrete wall panel structure, the lack of external scaffolding leads to the lack of temporary support fixing points for the prefabricated daughter wall, affecting the construction quality.

Method used

The dry connection method of bolt rod, connecting box and embedded sleeve is adopted to connect the daughter wall, floor slab and load-bearing wall through bolts to ensure structural stability, and anchored steel bars are installed in the structural columns to enhance stiffness and stability.

Benefits of technology

Effectively constrain the displacement of the daughter wall, avoid the problem of lack of temporary support fixing points, improve construction stability and anti-overturning ability, and simplify the construction process and reduce costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222101318U_ABST
    Figure CN222101318U_ABST
Patent Text Reader

Abstract

The utility model provides a full-assembly type prefabricated parapet wall structure. The full-assembly type prefabricated parapet wall structure is used for connecting a parapet wall, a floor slab and a bearing wall and comprises a bolt rod, a connecting box and an embedded sleeve, the connecting box is arranged at the lower end, close to the floor slab, of the parapet wall, the embedded sleeve is arranged at the upper end, close to the floor slab, of the bearing wall, one end of the bolt rod is connected with the embedded sleeve, and the other end of the bolt rod is connected with the connecting box. And the other end of the bolt rod penetrates through the floor slab and is fixed in the connecting box. The stability of the parapet wall in the construction process can be guaranteed, and the problem that temporary supporting and fixing point positions of prefabricated parts are lacked on site due to the fact that an external scaffold is not adopted in a full-assembly type concrete wall plate structure is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a fully assembled prefabricated parapet structure. Background Art

[0002] At present, most of the connections of prefabricated parapets in prefabricated buildings are formed by a single cast-in-place concrete structural column to tie the prefabricated parapet. This method is suitable for prefabricated monolithic concrete structures with external scaffolding. The construction method of fully prefabricated concrete wall panel structure buildings is quite different from that of prefabricated monolithic concrete structure buildings. Fully prefabricated buildings eliminate on-site concrete wet operations. All load-bearing components are completely pre-produced by the factory and then transported to the construction site for hoisting and assembly to form the entire building. There is no need for secondary superposition and casting, so there is no need to set up external scaffolding.

[0003] When a building adopts a fully assembled concrete wall panel structure, if the roof parapet is constructed according to the connection structure of the existing technology, it is difficult to ensure the construction quality of the secondary post-cast concrete structural column due to the lack of external scaffolding at the construction site and the lack of fixed points for setting temporary supports on the prefabricated parapet. Utility Model Content

[0004] The utility model aims to provide a fully assembled prefabricated parapet structure to solve the shortcoming that the existing parapet relies on additionally setting up external scaffolding of the building to meet the construction stability of the prefabricated components.

[0005] The technical solution of the utility model is: a fully assembled prefabricated parapet structure, used for connecting parapets, floor slabs and load-bearing walls, which includes a bolt rod, a connecting box and an embedded sleeve. The connecting box is arranged at the lower end of the parapet close to the floor slab, and the embedded sleeve is arranged at the upper end of the load-bearing wall close to the floor slab. One end of the bolt rod is connected to the embedded sleeve, and the other end of the bolt rod passes through the floor slab and is fixed in the connecting box.

[0006] In the above scheme, the parapet, floor slab and load-bearing wall are connected by bolts. After the bolts are tightened, the displacement of the parapet caused by wind load, construction load and other temporary live loads can be effectively restrained, thereby ensuring the stability of the parapet during construction and avoiding the problem of lack of temporary support fixing points for prefabricated components on site due to the fact that the fully assembled concrete wall panel structure does not use external scaffolding.

[0007] Preferably, a plurality of distribution steel bars are arranged longitudinally and transversely inside the parapet, and the parapet is butted against the floor slab. In two adjacent parapets, the distribution steel bars in one parapet extend into the other parapet and are connected to the distribution steel bars in the parapet.

[0008] Preferably, the parapet is further provided with tie bars for connecting the distributed steel bars.

[0009] Preferably, a sandwich layer is provided in the parapet, and the sandwich layer is fixed in the parapet by fiber reinforcement.

[0010] Preferably, the parapet walls are butted against the floor slab in a plurality, and the butt joints between two adjacent parapet walls form glue grooves.

[0011] In a specific technical solution, the parapet is butt-jointed in an L-shape on the floor slab, a structural column is provided inside one end of the parapet close to the butt joint, the distribution steel bars pass through the structural column and extend into the other parapet, vertically arranged stress-bearing steel bars and horizontally arranged anchor steel bars are provided in the structural column, and the anchor steel bars, distribution steel bars and stress-bearing steel bars are connected by tension bars.

[0012] In another specific technical solution, the parapet walls are connected in a straight line on the floor slab, and structural columns are provided at the joints of the two parapet walls. The distribution steel bars pass through the structural columns and extend into the other parapet wall. Vertically arranged stress-bearing steel bars and horizontally arranged anchor steel bars are provided in the structural columns. The anchor steel bars, distribution steel bars and stress-bearing steel bars are connected by tension bars.

[0013] Compared with the related art, the beneficial effects of the utility model are:

[0014] 1. In the fully assembled prefabricated parapet structure, the parapet, floor slab and load-bearing wall are connected by bolts. After the bolts are tightened, the displacement of the parapet caused by wind load, construction load and other temporary live loads can be effectively restrained, thereby ensuring the stability of the parapet during construction and avoiding the problem of lack of temporary support fixing points of prefabricated components on site due to the fact that the fully assembled concrete wall panel structure does not use external scaffolding;

[0015] Second, anchor steel bars are arranged in the structural columns, and the anchor steel bars are in the form of open steel bars with hooks, which can ensure that the structural stress performance remains unchanged while reducing the problem of steel bar interference in on-site operations;

[0016] 3. The distributed steel bars in the parapet are connected with the structural columns, which can tie the prefabricated components to form a whole, enhance the rigidity and stability of the parapet, and improve the ability to resist overturning and continuous damage;

[0017] 4. The parapet, floor slab and load-bearing wall are connected by dry bolts, which is simple to operate and easy to install. It effectively improves the construction efficiency while ensuring the structural stability of the connection node, greatly saving costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1This is a structural schematic diagram of Embodiment 1 of the fully assembled prefabricated parapet structure provided by the utility model;

[0019] Figure 2 For along Figure 1 A schematic cross-sectional view of AA in FIG.

[0020] Figure 3 For along Figure 1 A schematic cross-sectional view of BB in FIG.

[0021] Figure 4 For along Figure 1 A cross-sectional schematic diagram of CC in FIG.

[0022] Figure 5 A structural schematic diagram of the second embodiment of the fully assembled prefabricated parapet structure provided by the utility model;

[0023] Figure 6 For along Figure 5 A cross-sectional schematic diagram of DD in FIG.

[0024] Figure 7 For along Figure 5 A cross-sectional schematic diagram of EE in FIG.

[0025] Figure 8 For along Figure 5 Schematic cross-sectional view of FF in FIG.

[0026] In the attached figure: 1. Parapet; 2. Connection box; 3. Tie rod; 4. Anchor steel bar; 5. Structural column; 6. Distribution steel bar; 7. Glue groove; 8. Fiber reinforcement; 9. Sandwich layer; 10. Floor slab; 11. Bolt rod; 12. Embedded sleeve; 13. Load-bearing steel bar; 14. Load-bearing wall. DETAILED DESCRIPTION

[0027] The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict. For the convenience of description, if the words "upper", "lower", "left" and "right" appear in the following text, they only indicate that the upper, lower, left and right directions are consistent with the drawings themselves, and do not limit the structure.

[0028] Embodiment 1

[0029] like Figure 1-Figure 4As shown, a fully assembled prefabricated parapet structure provided in this embodiment is used for connecting a parapet 1, a floor 10 and a load-bearing wall 14. The fully assembled prefabricated parapet structure includes a bolt rod 11, a connection box 2 and an embedded sleeve 12. The connection box 2 is arranged at the lower end of the parapet 1 close to the floor 10, and the embedded sleeve 12 is arranged at the upper end of the load-bearing wall 14 close to the floor 10. One end of the bolt rod 11 is connected to the embedded sleeve 12, and the other end of the bolt rod 11 passes through the floor 10 and is fixed in the connection box 2. Finally, mortar is filled in the connection box 2.

[0030] like Figure 1 As shown, the parapet 1 is connected to the floor 10 in an L-shape, at least two connection boxes 2 are provided on each parapet 1, and bolt rods 11 and embedded sleeves 12 are provided in the same number and position as the connection boxes 2. Figure 2 As shown, a plurality of distribution steel bars 6 and tie bars 3 for connecting the distribution steel bars 6 are arranged in the longitudinal and transverse directions inside the parapet 1. In two adjacent parapets 1, the distribution steel bars 6 in one parapet 1 extend into the other parapet 1 and are connected to the distribution steel bars 6 in the parapet 1. A glue groove 7 is formed at the joint between the two adjacent parapets 1, mortar is filled in the glue groove 7, and waterproof sealant is added to the side of the glue groove 7 close to the outer wall. This structure of the glue groove 7 is also used between the parapet 1 and the floor slab 10, and between the load-bearing wall 14 and the floor slab 10.

[0031] like Figure 2 As shown, a sandwich layer 9 is provided in the parapet 1, and the sandwich layer 9 is a heat-insulating material. The sandwich layer 9 is fixed in the parapet 1 by fiber bars 8.

[0032] like Figure 1 , Figure 3 As shown, a structural column 5 is provided inside one end of the parapet 1 near the joint, and the distribution steel bars 6 pass through the structural column 5 and extend into the other parapet 1. Figure 1 , Figure 4 As shown, the structural column 5 is provided with vertically arranged stress-bearing steel bars 13 and horizontally arranged anchoring steel bars 4 , and the anchoring steel bars 4 , the distribution steel bars 6 and the stress-bearing steel bars 13 are connected by the tension bars 3 .

[0033] like Figure 1As shown, the anchoring steel bar 4 adopts the form of open steel bar with hook, and the stability and bearing capacity of the structural column 5 are strengthened by the force-bearing steel bar 13 and the tension bar 3 in the structural column 5. According to the principle of calculating the anchoring length of steel bars in concrete components, the anchoring steel bar 4 is an extended straight anchor structure, and a small number of hooks are set at the end of the anchoring steel bar 4 to meet the requirements of the concrete anchoring length. While ensuring that the stress performance of the structure remains unchanged, the problem of steel bar interference in on-site operations can be reduced, and the requirements for on-site construction accuracy can be greatly reduced.

[0034] Embodiment 2

[0035] like Figure 5-Figure 8 As shown, Example 1 is repeated, with the difference that the parapet 1 in the fully assembled prefabricated parapet structure provided in this embodiment is butted in a straight line on the floor 10, and structural columns 5 are provided at the butt joints of the two parapets 1. The distribution steel bars 6 pass through the structural columns 5 and extend into the other parapet 1. The structural columns 5 are provided with vertically arranged stress-bearing steel bars 13 and horizontally arranged anchor steel bars 4. The anchor steel bars 4, the distribution steel bars 6 and the stress-bearing steel bars 13 are connected by tension bars 3.

[0036] The utility model adopts a dry-type bolt connection method to replace the method of setting up a building external scaffolding and adding temporary supports to fix the prefabricated parapet wall body, thereby reducing the use of building external scaffolding; the anchoring steel bars are replaced from closed stirrups to lengthened straight anchor steel bars to avoid interference with steel bars; compared with ordinary prefabricated wall panel structures, local post-cast structural columns are added to enhance the overall stability of the prefabricated parapet and improve the ability to resist overturning and continuous damage.

[0037] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A fully assembled prefabricated parapet structure, used for connecting a parapet (1), a floor slab (10) and a load-bearing wall (14), characterized in that: The invention comprises a bolt rod (11), a connection box (2) and an embedded sleeve (12); the connection box (2) is arranged at the lower end of the parapet wall (1) close to the floor slab (10); the embedded sleeve (12) is arranged at the upper end of the load-bearing wall (14) close to the floor slab (10); one end of the bolt rod (11) is connected to the embedded sleeve (12); the other end of the bolt rod (11) passes through the floor slab (10) and is fixed in the connection box (2).

2. The fully assembled prefabricated parapet structure according to claim 1, characterized in that: A plurality of distributed steel bars (6) are arranged longitudinally and transversely inside the parapet (1), and the parapet (1) is butted against a plurality of distributed steel bars (6) on the floor slab (10). In two adjacent parapets (1), the distributed steel bars (6) in one parapet (1) extend into the other parapet (1) and are connected to the distributed steel bars (6) in the parapet (1).

3. The fully assembled prefabricated parapet structure according to claim 2, characterized in that: The parapet wall (1) is also provided with tie bars (3) for connecting the distribution steel bars (6).

4. The fully assembled prefabricated parapet structure according to claim 1, characterized in that: A sandwich layer (9) is provided in the parapet wall (1), and the sandwich layer (9) is fixed in the parapet wall (1) via fiber reinforcements (8).

5. The fully assembled prefabricated parapet structure according to claim 1, characterized in that: The parapet walls (1) are butt-jointed in a plurality on the floor slab (10), and the butt joints between two adjacent parapet walls (1) form glue grooves (7).

6. The fully assembled prefabricated parapet structure according to claim 2 or 3, characterized in that: The parapet wall (1) is butt-jointed in an L-shape on the floor slab (10); a structural column (5) is provided inside one end of the parapet wall (1) close to the butt joint; the distribution steel bars (6) pass through the structural column (5) and extend into the other parapet wall (1); vertically arranged stress-bearing steel bars (13) and horizontally arranged anchor steel bars (4) are provided inside the structural column (5); the anchor steel bars (4), the distribution steel bars (6) and the stress-bearing steel bars (13) are connected via tension bars (3).

7. The fully assembled prefabricated parapet structure according to claim 2 or 3, characterized in that: The parapet walls (1) are butt-jointed on the floor slab (10) in a straight line, and a structural column (5) is provided at the joint of the two parapet walls (1). The distribution steel bars (6) pass through the structural columns (5) and extend into the other parapet wall (1). The structural columns (5) are provided with vertically arranged stress-bearing steel bars (13) and horizontally arranged anchor steel bars (4). The anchor steel bars (4), the distribution steel bars (6) and the stress-bearing steel bars (13) are connected via tension bars (3).