Overlapped prefabricated part construction structure
By designing detachable prefabricated frame members and side fixing structures, the problems of large weight and unadjustable length of the superimposed beam prefabricated components in the prior art are solved, and flexible combination and stable stacking of superimposed beams are realized, and construction efficiency is improved. Flexibility to use.
Patent Information
- Application Number
- CN202420515102.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-18
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-03-18
AI Technical Summary
The existing reinforced concrete stacked beam prefabricated components have large weight, inconvenient transportation, and unadjustable lengths due to the integrated structure. They have low flexibility in use, making it difficult to quickly adjust them to stacked beams of different lengths.
Adopt detachable prefabricated frame members, the vertical stacking and combination of side fixing plates and docking grooves/blocks, etc., combine fixed anchor rods and mounting plates to achieve stable fixing, which is convenient for assembly and disassembly, and is suitable for stacking beams of different lengths. Production.
It realizes flexible combination and stable stacking of prefabricated components, simplifies the construction process, reduces transportation needs, and improves the flexibility and construction efficiency of stacked beams.
Smart Images

Figure CN222115461U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field related to construction structures, in particular to a superimposed prefabricated component construction structure. Background Art
[0002] Existing reinforced concrete composite beams usually adopt rectangular reinforced concrete precast components. During construction, the side formwork is first supported on the rectangular reinforced concrete precast components, and then the steel bars are arranged, and then concrete is poured to form a composite beam. In this way, the concrete composite beam can be quickly formed, which has the advantages of convenient operation and easy use. However, the following problems are still found during use: the precast components used for pouring are mostly one-piece structures, the precast components are heavy, and it is inconvenient to lift and transport them. Moreover, the precast size cannot be adjusted to cast composite beams of different lengths, and the flexibility of use is low. For this reason, technical personnel in this field have proposed a composite precast component construction structure to solve the problems raised in the above background. Utility Model Content
[0003] The purpose of the utility model is to provide a composite prefabricated component construction structure to solve the problems raised in the above background technology.
[0004] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0005] A stacked prefabricated component construction structure comprises a prefabricated frame component, wherein the number of the prefabricated frame components is set to be several, the prefabricated frame components are installed on a filling layer arranged on a base layer, and the several prefabricated frame components can be stacked in a vertical direction, and the side of the prefabricated frame component is detachably installed with a side fixing plate, the side fixing plate is inclined, the top of the side fixing plate is cooperatively connected with the outer side wall of the prefabricated frame component, and the bottom of the side fixing plate is installed on the base layer of the side of the prefabricated frame component, and the prefabricated frame component comprises several prefabricated frame plates which are connected to each other in sequence.
[0006] As a further solution of the utility model: a first docking groove is arranged at one end of the prefabricated frame plate, and a first docking block matching with the first docking groove is arranged at the other end of the prefabricated frame plate.
[0007] As a further solution of the utility model: a second docking groove is arranged at the bottom end of the prefabricated frame plate, and a second docking block matched with the second docking groove is arranged at the top end of the prefabricated frame plate.
[0008] As a further solution of the utility model: a buckle plate is arranged at the top end of the side fixing plate, and a right-angle plate which is buckled with the buckle plate is arranged on the outer wall of the prefabricated frame plate.
[0009] As a further solution of the utility model: a mounting plate is arranged at the bottom end of the side fixing plate, a plurality of mounting holes are evenly distributed on the mounting plate, fixing anchor rods are installed in the mounting holes, and the lower part of the fixing anchor rods is inserted into the base layer.
[0010] As a further solution of the utility model: the top of the side fixing plate is connected with a docking sleeve, and the bottom of the side fixing plate is connected with a docking rod matched with the docking sleeve.
[0011] The utility model has the following advantages: the prefabricated frame components of the construction structure can be stacked in the vertical direction, which is convenient for casting and producing composite beams of different lengths. The prefabricated frame components are composed of a number of prefabricated frame plates, which are convenient for disassembly and assembly, and do not require the use of large-scale equipment for transportation. The construction is convenient, and each prefabricated frame component is fixed by a side fixing plate to ensure that the stacking stability of the prefabricated frame components is high, the construction effect is better, the overall construction structure is simple and easy to install, and it is suitable for different types of concrete composite beam manufacturing occasions, and has stronger practicality. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a front view of the overall structure of an embodiment of the utility model.
[0013] Figure 2 It is a schematic diagram of the structure of the side fixing plate in an embodiment of the utility model.
[0014] Figure 3 It is a top view of the prefabricated frame component in the embodiment of the utility model.
[0015] In the figure: base layer-1, filling layer-2, prefabricated frame component-3, prefabricated frame plate-301, first docking groove-302, first docking block-303, second docking block-304, second docking groove-305, right-angle plate-306, side fixing plate-4, buckle plate-401, mounting plate-402, mounting hole-403, docking sleeve-404, docking rod-405, fixing anchor rod-5. DETAILED DESCRIPTION
[0016] The technical solution of the utility model is further described in detail below in conjunction with specific implementation methods.
[0017] Example 1: Please refer to Figures 1 to 3, a composite prefabricated component construction structure, comprising a prefabricated frame component 3, the number of the prefabricated frame components 3 is set to be several, the prefabricated frame component 3 is installed on a filling layer 2 set on a foundation layer 1, the filling layer 2 is a construction area filled on the foundation layer 1, the filling layer 2 is formed by compacting and leveling the filling soil, the composite beam is made on the filling layer 2, and several of the prefabricated frame components 3 can be stacked in the vertical direction, the side of the prefabricated frame component 3 is detachably installed with a side fixing plate 4, the side fixing plate 4 is inclined, the top of the side fixing plate 4 is matched and connected with the outer side wall of the prefabricated frame component 3, and the bottom of the side fixing plate 4 is installed on the foundation layer 1 at the side of the prefabricated frame component 3, the prefabricated frame component 3 includes several prefabricated frame panels 301 that are connected in sequence, and the prefabricated frame components 3 composed of the prefabricated frame panels 301 are stacked and installed on the filling layer 2 in sequence.
[0018] See also Figure 1 , Figure 3 A first docking groove 302 is provided at one end of the prefabricated frame plate 301, and a first docking block 303 cooperating with the first docking groove 302 is provided at the other end of the prefabricated frame plate 301. A plurality of prefabricated frame plates 301 are docked and combined in sequence in the first position through the first docking groove 302 and the first docking block 303, thereby forming a prefabricated frame component 3. A second docking groove 305 is provided at the bottom end of the prefabricated frame plate 301, and a second docking block 304 cooperating with the second docking groove 305 is provided at the top end of the prefabricated frame plate 301. The corresponding prefabricated frame plates 301 on the upper and lower adjacent prefabricated frame components 3 are docked through the second docking groove 305 and the second docking block 304.
[0019] Example 2: See Figures 1 to 3 On the basis of Example 1, a buckle plate 401 is provided at the top of the side fixing plate 4, and a right-angle plate 306 that is buckled with the buckle plate 401 is provided on the outer wall of the prefabricated frame plate 301. A mounting plate 402 is provided at the bottom end of the side fixing plate 4, and a plurality of mounting holes 403 are evenly distributed on the mounting plate 402. Fixed anchor rods 5 are installed in the mounting holes 403, and the lower part of the fixed anchor rods 5 is inserted into the foundation layer 1.
[0020] See also Figure 1 , Figure 2 In this embodiment, the top of the side fixing plate 4 is connected to a docking sleeve 404, and the bottom of the side fixing plate 4 is connected to a docking rod 405 that cooperates with the docking sleeve 404. When the multi-layer prefabricated frame components 3 are stacked for construction, multiple side fixing plates 4 on the same side can be docked with each other, thereby enhancing the stability of the overall construction structure.
[0021] Working principle: When in use, a prefabricated frame component 3 is assembled on the filling layer 2, and the prefabricated frame component 3 is assembled by connecting several prefabricated frame panels 301 in sequence, and then the side fixing plate 4 is installed on the side of the prefabricated frame panel 301, first buckle the buckle plate 401 to the right-angle plate 306, and then install the installation plate 402 to the base layer 1 through the fixing anchor rod 5, and then stack and install the next prefabricated frame component 3, and then install the side fixing plate 4 to fix the next prefabricated frame component 3. The lengths of the side fixing plates 4 used to fix the prefabricated frame components 3 at different positions are different. Different numbers of prefabricated frame components 3 are selected according to the manufactured length of the composite beam, and then concrete and other materials are poured inside the prefabricated frame component 3 to manufacture the composite beam. After the composite beam is manufactured, the side fixing plates 4 and the prefabricated frame panels 301 can be removed in sequence.
[0022] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
[0023] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A composite prefabricated component construction structure, comprising a prefabricated frame component, characterized in that: The number of the prefabricated frame components is set to be several, and the prefabricated frame components are installed on a filling layer arranged on a base layer, and several of the prefabricated frame components can be stacked in a vertical direction. The side of the prefabricated frame component is detachably installed with a side fixing plate, and the side fixing plate is inclined. The top of the side fixing plate is matched and connected with the outer side wall of the prefabricated frame component, and the bottom of the side fixing plate is installed on the base layer of the side of the prefabricated frame component. The prefabricated frame component includes several prefabricated frame plates that are connected to each other in sequence.
2. A composite prefabricated component construction structure according to claim 1, characterized in that: One end of the prefabricated frame plate is provided with a first docking groove, and the other end of the prefabricated frame plate is provided with a first docking block matched with the first docking groove.
3. A composite prefabricated component construction structure according to claim 2, characterized in that: The bottom end of the prefabricated frame plate is provided with a second docking groove, and the top end of the prefabricated frame plate is provided with a second docking block matched with the second docking groove.
4. The composite prefabricated component construction structure according to claim 1, characterized in that: A buckle plate is arranged at the top end of the side fixing plate, and a right-angle plate buckled with the buckle plate is arranged on the outer wall of the prefabricated frame plate.
5. The composite prefabricated component construction structure according to claim 4, characterized in that: A mounting plate is arranged at the bottom end of the side fixing plate, and a plurality of mounting holes are evenly distributed on the mounting plate. Fixing anchor rods are installed in the mounting holes, and the lower part of the fixing anchor rods is inserted into the foundation layer.
6. The composite prefabricated component construction structure according to claim 4, characterized in that: The top of the side fixing plate is connected with a docking sleeve, and the bottom of the side fixing plate is connected with a docking rod matched with the docking sleeve.