Dredging equipment for hydraulic engineering construction

By adopting roof, cylinder and mesh structures in the silting equipment for water conservancy engineering construction and combining isolation boards, the problems of equipment wear and blockage during hard debris treatment are solved, and uninterrupted sludge extraction and long-term mechanical operation are achieved. run.

CN222120350UActive Publication Date: 2024-12-06益阳市赫山区湖区水利工程建设站
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420815632.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-19
Publication Date
2024-12-06
Estimated Expiration
2034-04-19

AI Technical Summary

Technical Problem

When the existing silting equipment for water conservancy construction is treated with hard debris, the crushing knife is prone to wear, and incomplete breakage causes debris to clog the pipeline, affecting the efficiency of silting.

Method used

A silting equipment for water conservancy engineering construction was designed, using a roof plate, cylinder and mesh plate structure. The cylinder extension causes the mesh plate to lose suction and impurities to fall. The top plate protrusion is inserted into the mesh hole to clean and block, and combined with the isolation plate to prevent suction and seal it. , ensure long-term operation.

Benefits of technology

It achieves the effect of uninterrupted sludge extraction, extends the service life of the equipment, avoids impurities blockage, and improves dredging efficiency and mechanical durability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222120350U_ABST
    Figure CN222120350U_ABST
Patent Text Reader

Abstract

The utility model provides desilting equipment for hydraulic engineering construction, and relates to the field of hydraulic engineering desilting. The desilting equipment for hydraulic engineering construction comprises an extraction pipe, an adsorption cavity communicating with the extraction pipe is formed in the bottom of the extraction pipe, two screen plates distributed left and right are installed on the bottom face of the adsorption cavity, mesh holes penetrating up and down are formed in the screen plates, the mesh holes communicate the interior and the exterior of the adsorption cavity, and a separation plate is fixed to the outer side of the bottom end of the adsorption cavity; a top plate is arranged in the adsorption cavity and located above the net plate, the bottom face of the top plate is matched with the net holes, one side of the top plate is hinged to the adsorption cavity, and a hinge shaft of the top plate and the adsorption cavity extends out of the adsorption cavity and is fixedly provided with a rocker arm; two sliding blocks sliding up and down are installed on the front face of the extraction pipe, ejector rods are hinged to the bottoms of the sliding blocks, and the other ends of the ejector rods are hinged to the rocker arm; and the sliding block moves to the lowest end. According to the dredging equipment for hydraulic engineering construction, the top plate, the air cylinder and the screen plates are arranged, so that the left screen plate and the right screen plate are regularly and alternately cleaned, and the effect of uninterruptedly pumping sludge can be well achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of water conservancy silt removal, in particular to silt removal equipment for water conservancy project construction. Background Art

[0002] Water conservancy projects are projects built to eliminate water disasters and develop and utilize water resources. According to the objects they serve, they are divided into flood control projects, farmland water conservancy projects, hydroelectric power generation projects, waterway and port projects, water supply and drainage projects, environmental water conservancy projects, and sea reclamation projects.

[0003] During the construction of water conservancy projects, silt removal equipment is usually used to remove silt from rivers and ditches. The patent announcement number is CN214994210U, which is a river silt removal equipment for water conservancy project construction. In the above patent, a longitudinal moving structure of the silt suction pipe is provided, so that the height of the silt suction port can be adjusted. The device is provided with a crushing telescopic rod and a crushing knife, so that strip-shaped impurities can be removed separately to avoid clogging the filter plate. There is still room for improvement in the above device during use: Typically, the crushing knife of the existing device breaks up the debris in the processing box, and often encounters some harder debris. After long-term use, the crushing knife will wear out, reducing the crushing ability of the crushing knife. Incomplete crushing can easily cause debris to block the pipeline.

[0004] In view of this, the present utility model is proposed. Utility Model Content

[0005] In view of the deficiencies in the prior art, the utility model provides a dredging device for water conservancy project construction, which solves the problems raised in the background technology.

[0006] To achieve the above purpose, the utility model is implemented through the following technical solutions: a dredging equipment for water conservancy project construction, including an extraction pipe, an adsorption chamber connected to the extraction pipe is installed at the bottom of the extraction pipe, two mesh plates distributed left and right are installed on the bottom surface of the adsorption chamber, and mesh holes penetrating up and down are provided on the mesh plates, and the mesh holes connect the inside and outside of the adsorption chamber, and an isolation plate is fixed to the outside of the bottom end of the adsorption chamber, and a top plate is provided on the inside of the adsorption chamber above the mesh plate, and the bottom surface of the top plate is matched with the mesh holes, and one side of the top plate is hinged to the adsorption chamber, and the hinge axis of the two extends to the outside of the adsorption chamber and is fixed with a rocker arm, and two sliders that slide up and down are installed on the front of the extraction pipe, and the bottom of the slider is hinged with a push rod, and the other end of the push rod is hinged with the rocker arm. When the slider moves to the lowermost end, the push rod pushes the rocker arm to make the top plate contact with the mesh plate, and two cylinders are fixed on the front of the extraction pipe, and the output shaft of the cylinder is connected to the slider.

[0007] Preferably, the mesh holes are evenly distributed on the mesh plate, and the upper ends of the mesh holes are trumpet-shaped structures.

[0008] Preferably, the bottom of the isolation plate is provided with isolation grooves communicating with the inside and the outside, and the isolation grooves are arranged at equal distances.

[0009] Preferably, a plurality of protrusions are provided at the bottom of the top plate, and the protrusion structure cooperates with the mesh holes.

[0010] Preferably, the left and right rocker arms are symmetrically arranged with respect to the longitudinal center line of the adsorption chamber, and the left and right push rods are symmetrically arranged.

[0011] Preferably, the output shaft of the cylinder faces downward and is fixedly mounted with a spring, and the other end of the spring is fixed to the slider.

[0012] The utility model provides a dredging device for water conservancy project construction. It has the following beneficial effects:

[0013] The dredging equipment for water conservancy project construction is provided with a top plate, a cylinder and a mesh plate. When extracting sludge, the two mesh plates can be extracted together, and then a cylinder is driven to extend regularly. When the cylinder extends, the slider can push the push rod to make the top plate move closer to the mesh plate. After moving closer, the mesh plate loses suction, and impurities attached to it can fall off. Then the protrusions on the top plate can be inserted into the mesh holes of the mesh plate, so that impurities blocked inside the mesh holes can be taken out. Therefore, the left and right mesh plates are cleaned alternately regularly to achieve the effect of uninterrupted sludge extraction.

[0014] The dredging equipment used in the construction of the water conservancy project is equipped with an isolation plate. When the adsorption chamber contacts the hard riverbed, the sludge can enter from the isolation groove on the isolation plate, and the suction force will not be blocked, thus ensuring the long-term operation of the machine and preventing it from being easily damaged. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the structure of the utility model;

[0016] Figure 2 It is a structural schematic diagram of the adsorption chamber of the utility model;

[0017] Figure 3 This is a structural diagram of the mesh plate and the top plate of the utility model;

[0018] Figure 4 For this utility model Figure 1 A magnified view of the structure at center.

[0019] Among them, 1 is an extraction tube, 2 is an adsorption chamber, 3 is a mesh plate, 4 isolating plates, 5 is a top plate, 6 is a rocker arm, 7 is a slider, 8 is a push rod, 9 is a cylinder, 10 isolating grooves, and 11 is a spring. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] The utility model provides a desilting device for water conservancy project construction:

[0022] like Figure 1-4 As shown, it includes an extraction pipe 1, the upper end of the extraction pipe 1 is used to contact the silt extraction machine, the bottom of the extraction pipe 1 is installed with an adsorption chamber 2 connected thereto, and the bottom surface of the adsorption chamber 2 is installed with two mesh plates 3 distributed left and right, and the mesh plates 3 are provided with mesh holes penetrating up and down, and the mesh holes are evenly distributed on the mesh plates 3, and the upper end of the mesh holes is a trumpet-shaped structure, and the mesh holes connect the inside and outside of the adsorption chamber 2, and an isolation plate 4 is fixed to the outside of the bottom end of the adsorption chamber 2, and the bottom of the isolation plate 4 is provided with isolation grooves 10 connected inside and outside, and the isolation grooves 10 are arranged and distributed at equal distances, and the interior of the adsorption chamber 2 is provided with a top plate 5 on the mesh plate 3, and the bottom surface of the top plate 5 is matched with the mesh holes, and the bottom of the top plate 5 is provided with a plurality of protrusions, and the protrusion structure is matched with the mesh holes, and when the top plate 5 is attached to the mesh plate 3, the protrusion can be just inserted into the mesh hole, and one side of the top plate 5 is hinged to the adsorption chamber 2, The hinge axes of the two extend outside the adsorption chamber 2 and are fixed with a rocker arm 6. Two sliders 7 that slide up and down are installed on the front of the extraction tube 1. The bottom of the slider 7 is hinged with a push rod 8. A limit rod is provided on one side of the hinge position of the slider 7 and the push rod 8 to prevent the push rod from being excessively transferred and longitudinally stuck. The other end of the push rod 8 is hinged to the rocker arm 6. The left and right rocker arms 6 are symmetrically arranged with respect to the longitudinal center line of the adsorption chamber 2. The left and right push rods 8 are symmetrically arranged. When the slider 7 moves to the lower end, the push rod 8 pushes the rocker arm 6 to make the top plate 5 contact with the mesh plate 3. Two cylinders 9 are fixed on the front of the extraction tube 1. The cylinder 9 can be remotely driven by a control device above the water surface. The output shaft of the cylinder 9 is connected to the slider 7. The output shaft of the cylinder 9 is downward and fixed with a spring 11. The other end of the spring 11 is fixed to the slider 7.

[0023] When in use, when extracting sludge, the two mesh plates 3 can be extracted together, and then a cylinder 9 is regularly driven to extend. When it extends, the slider 7 can push the push rod 8 to make the top plate 5 close to the mesh plate 3. After the mesh plate 3 is close, the impurities attached to it can fall off, and then the protrusions on the top plate 5 can be inserted into the mesh of the mesh plate 3, so that the impurities blocked inside the mesh can be taken out, so that the left and right mesh plates 3 are regularly cleaned alternately. When the adsorption chamber 2 contacts the hard riverbed, the sludge can also enter from the isolation groove 10 on the isolation plate 4, and the suction will not be blocked, ensuring the long-term operation of the machine.

[0024] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A dredging device for water conservancy project construction, comprising an extraction pipe (1), characterized in that: The bottom of the extraction tube (1) is provided with an adsorption chamber (2) connected thereto, and the bottom surface of the adsorption chamber (2) is provided with two mesh plates (3) distributed left and right, and the mesh plates (3) are provided with mesh holes penetrating from top to bottom, and the mesh holes are connected to the inside and outside of the adsorption chamber (2), and an isolation plate (4) is fixed to the outside of the bottom end of the adsorption chamber (2), and a top plate (5) is provided inside the adsorption chamber (2) on the mesh plate (3), and the bottom surface of the top plate (5) is matched with the mesh holes, and one side of the top plate (5) is hinged to the adsorption chamber (2), and the two are connected. The hinge shaft extends outside the adsorption chamber (2) and is fixed with a rocker arm (6). Two sliders (7) that slide up and down are installed on the front of the extraction tube (1). The bottom of the sliders (7) are hinged with push rods (8). The other end of the push rod (8) is hinged with the rocker arm (6). When the slider (7) moves to the lowermost end, the push rod (8) pushes the rocker arm (6) so that the top plate (5) contacts the mesh plate (3). Two cylinders (9) are fixed on the front of the extraction tube (1). The output shafts of the cylinders (9) are connected to the sliders (7).

2. A dredging device for water conservancy project construction according to claim 1, characterized in that: The mesh holes are evenly distributed on the mesh plate (3), and the upper ends of the mesh holes are trumpet-shaped structures.

3. A dredging device for water conservancy project construction according to claim 2, characterized in that: The bottom of each of the isolation plates (4) is provided with isolation grooves (10) communicating with the inside and the outside, and the isolation grooves (10) are arranged at equal distances.

4. The dredging equipment for water conservancy project construction according to claim 3 is characterized in that: The bottom of the top plate (5) is provided with a plurality of protrusions, and the protrusion structure cooperates with the mesh holes.

5. A dredging device for water conservancy project construction according to claim 4, characterized in that: The left and right rocker arms (6) are symmetrically arranged about the longitudinal center line of the adsorption chamber (2), and the left and right push rods (8) are symmetrically arranged.

6. A dredging device for water conservancy project construction according to claim 5, characterized in that: The output shaft of the cylinder (9) faces downward and is fixedly mounted with a spring (11), and the other end of the spring (11) is fixed to the slider (7).

Citation Information

Cited By

  • Dredging equipment for hydraulic engineering construction