Platform canopy steel structure Y-shaped double column

By adopting a Y-shaped double-column structure and a temporary installation platform in the construction of the steel structure canopy on the railway platform, combined with the lower-mounted welding slag anti-fall technology, the problems of low construction quality and safety hazards are solved, and the construction accuracy and Efficiency ensures construction safety and quality.

CN222120735UActive Publication Date: 2024-12-06CONSTR & INSTALLATION ENG THE THIRD ENG GROUP OF CHINA RAILWAY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420254450.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-01
Publication Date
2024-12-06
Estimated Expiration
2034-02-01

AI Technical Summary

Technical Problem

During the construction of the steel structure awning on the railway platform, there are problems such as imperfect quality management system, different levels of production enterprises, and irregular construction, resulting in safety hazards and economic losses, and it is difficult for the existing technology to effectively improve construction quality and efficiency.

Method used

Adopt a Y-shaped double-column structure, including columns, stirrups, concrete slabs and cantilever beams. The verticality of the column is adjusted through longitudinal and transverse I-shaped steel, stretch rods and adjustable struts, and a temporary installation platform and upper steel beam installation construction are set up. The platform combines the anti-fall protection technology of lower-mounted welding slag to improve construction accuracy and safety.

Benefits of technology

The column installation accuracy and the construction quality of cantilever beams have been improved, construction efficiency and safety have been enhanced, the quality and safety of engineering construction have been ensured, and construction risks have been reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222120735U_ABST
    Figure CN222120735U_ABST
Patent Text Reader

Abstract

The utility model relates to a Y-shaped double column of a platform canopy steel structure. The Y-shaped double column comprises a Y-shaped double column body 1, stirrups 10, a concrete slab 22 and a cantilever beam 38. The Y-shaped double column 1 comprises a vertical column and a cantilever beam 38; and the top ends of the two upright posts are respectively connected with cantilever beams 38 in opposite directions. The device has the advantages that the temporary fixing structure of the stand column is arranged, the perpendicularity of the stand column is adjusted through the supporting pull rod and the adjustable supporting rod after temporary fixing, and the installation precision of the stand column is improved; for the cantilever beam with the Y-shaped double columns, the temporary installation platform fixed to the stand columns is adopted, the cantilever beam auxiliary supporting rods are used for supporting, and the construction quality and the construction efficiency of the cantilever beam are improved; and the upper steel beam installation construction platform used for installing the upper steel beam is arranged, the upper steel beam installation construction platform is fixed to the Y-shaped double-column cantilever beam, and the lower hanging type welding slag anti-falling protection technology is matched, so that the safety and the environmental protection property of construction are guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of railway transportation, and in particular comprises a Y-shaped double-column steel structure of a platform canopy. Background Art

[0002] In my country, the development of transportation is getting faster and faster, and railway station platforms are an important part of it. The understanding of platform-related construction technology needs to be further strengthened and improved. During the construction process, if the construction project cannot be reasonably and correctly guided, a little carelessness may cause unimaginable economic losses, bring engineering problems that could have been completely avoided, and even cause dangers to personal safety. Because of the large flow of people at the railway station, the quality of the steel structure canopy construction of the railway station platform is particularly important.

[0003] At present, the application of steel structure canopies is becoming more and more common, and the quality management system of steel structure canopy construction is constantly improving, but there are still certain problems in the actual construction process, which need to be further improved. However, due to the asynchronous progress of technological development, domestic steel structure production enterprises are of different levels, mixed with good and bad, which has buried certain safety hazards for the quality of engineering construction, and there are still common problems such as not strictly following relevant regulations and having a fluke mentality in the production and installation process. These small problems will accumulate more and more, and dripping water will wear away the stone, directly or indirectly causing the occurrence of engineering construction accidents. Causing economic losses and even fatal hidden dangers to personal safety. Therefore, it is of great significance to improve the construction technology of steel structure canopies on railway station platforms.

[0004] In view of this, it is urgent to propose a new steel structure canopy structure to address the shortcomings of the current steel structure canopy. Utility Model Content

[0005] The utility model aims to overcome the deficiencies in the prior art and provide a Y-shaped double-column steel structure for a platform canopy.

[0006] The platform canopy steel structure Y-shaped double columns include Y-shaped double columns, stirrups, concrete slabs and cantilever beams; the Y-shaped double columns include columns and cantilever beams; the tops of the two columns are respectively connected with cantilever beams in opposite directions;

[0007] The column bottom is welded and connected with a column foot, which is fixed on the stirrup. The stirrup and the column foot are integrally cast in the concrete slab. The two columns are horizontally provided with longitudinal I-beams and transverse I-beams. A bracing rod is provided between the longitudinal I-beam and the concrete slab, and an adjustable bracing rod is provided between the transverse I-beam and the concrete slab to adjust the verticality of the column.

[0008] A temporary installation platform is provided at the top of the column, which is used to set cantilever beams at the top of the two columns respectively, and a connecting beam is provided between the cantilever beams; a temporary support is provided at the end of the cantilever beam, and two upper trusses are provided above the cantilever beam. An upper steel beam installation construction platform is provided below the upper truss through a hanger, and upper steel beams are welded on both sides of the cantilever beam between the two upper trusses, and a welding slag collection bucket is hung below the upper steel beam.

[0009] Preferably, a column foot base plate is provided at the bottom of the column foot of the Y-shaped double column, the stirrup includes a steel frame and a base plate positioning ring, a temporary fixing plate with a rotatable screw is provided around the top of the stirrup, a rotating fixing rod is provided at the end of the temporary fixing plate, the column foot base plate is placed in the base plate positioning ring, and the temporary fixing plate is pressed above the column foot base plate; an anchor rod reinforcement plate is provided at the bottom of the stirrup, a stirrup anchor rod is provided on the anchor rod reinforcement plate, a steel frame is provided at the upper part, a stirrup stiffening ring is provided in the middle part, an anchor rod hole is provided on the stirrup stiffening ring, and stiffening ring ear plates are provided at the four corners of the end, and the stirrup stiffening ring is fixed to the steel frame by stiffening ring ear plate tension bolts.

[0010] Preferably, a Y-shaped double column ear plate is provided on the outer side of the Y-shaped double column, a longitudinal I-beam is provided on the Y-shaped double column ear plate, the longitudinal I-beam is fixed to the Y-shaped double column ear plate through the longitudinal I-beam clamp plate, a spirit level is provided on the longitudinal I-beam, a Y-shaped double column inner ear plate is provided between the two columns of the Y-shaped double column, a transverse I-beam is provided on the inner ear plate of the Y-shaped double column, the transverse I-beam is fixed to the inner ear plate of the Y-shaped double column through the inner clamp plate, a spirit level is provided on the end of the transverse I-beam, an upper pull ring is provided at the bottom of the longitudinal I-beam, a lower pull ring is provided on the concrete plate, a support rod is provided between the upper pull ring and the lower pull ring, an adjustable support rod is provided at the bottom of the transverse I-beam, a support rod base is provided at the bottom of the adjustable support rod, and the support rod base is placed on the concrete plate.

[0011] Preferably, the temporary installation platform includes a platform plate; the temporary installation platform is fixed to the top of the Y-shaped double column through a column clamp, supporting steel is arranged on both sides of the column clamp, reinforcing channel steel is arranged at the bottom of the supporting steel, a platform plate is arranged on the supporting steel, a guardrail sleeve is arranged on the platform plate, a cantilever beam auxiliary strut is arranged on the top surface of the supporting steel, a wedge-shaped top block is arranged between the end of the cantilever beam auxiliary strut and the cantilever beam, a bracket auxiliary plate is arranged at the lower part of the column clamp, the two bracket auxiliary plates are pulled together by auxiliary plate screws, a supporting truss is arranged on the bracket auxiliary plate, and platform struts and steel struts are arranged on the supporting truss.

[0012] Preferably, the end of the cantilever beam connecting the two upright columns of the Y-shaped double columns is provided with a side limit plate, and a connecting beam is provided between the cantilever beams. Both ends of the connecting beam are placed in the side limit plate and fixed by a connecting beam fixing piece, and an upper end plate and a lower end plate are provided on the cantilever beam for fixing the connecting beam.

[0013] Preferably, a temporary support is provided at the end of the cantilever beam, upper steel beams are provided on both sides of the cantilever beam, the upper steel beam is arranged perpendicular to the cantilever beam, the upper steel beam is provided with lifting ears for lifting, connecting rods are provided on the lifting ears, connecting rod end plates are provided at both ends of the connecting rods, lifting ropes are provided on the connecting rods, and welding slag collecting buckets are provided under the lifting ropes. End truss limit plates are provided on the cantilever beam, upper trusses are provided between the truss limit plates, two upper trusses are provided on both sides of the upper steel beam, hanging rods are provided at the four corners of the upper trusses, and the lower cross beam of the platform is welded under the hanging rods, cross beam reinforcement channel steels are provided between the lower cross beams of the platform, walkway boards are provided on the lower cross beams of the platform, walkway board limit plates are provided on both sides of the walkway boards, and guardrails are provided around the upper steel beam installation construction platform.

[0014] The beneficial effects of the utility model are:

[0015] 1) The utility model is provided with a temporary fixing structure of the column. After temporary fixing, the verticality of the column is adjusted by the support rod and the adjustable support rod, thereby improving the installation accuracy of the column.

[0016] 2) The utility model adopts a temporary installation platform fixed to the column for the cantilever beam of the Y-shaped double column, and supports the cantilever beam through auxiliary support rods, thereby improving the construction quality and construction efficiency of the cantilever beam.

[0017] 3) The utility model is provided with an upper steel beam installation construction platform for installing the upper steel beam. The upper steel beam installation construction platform is fixed to the Y-shaped double-column cantilever beam and cooperates with the lower-hanging welding slag anti-fall protection technology to ensure the safety and environmental protection of the construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0019] Figure 2 This is a schematic diagram of column foot installation;

[0020] Figure 3 It is a schematic diagram of the stirrup structure;

[0021] Figure 4 It is a schematic diagram of anchor rod reinforced bottom plate;

[0022] Figure 5 It is a schematic diagram of the stirrup stiffening ring;

[0023] Figure 6 It is a schematic diagram of column installation;

[0024] Figure 7 1. It is a schematic diagram of the structure of the support rod and the adjustable support rod;

[0025] Figure 8 It is a three-dimensional schematic diagram of cantilever beam installation;

[0026] Fig. 9 It is a three-dimensional schematic diagram of a temporary installation platform;

[0027] Fig.10 This is a schematic diagram of the connection beam installation;

[0028] Fig.11 This is a schematic diagram of the installation of the upper steel beam;

[0029] Fig.12 This is a schematic diagram of the upper steel beam installation construction platform.

[0030] Among them: 1. Y-shaped double column 2. Column foot 3. Column foot bottom plate 4. Rotatable bolt 5. Stirrup stiffening ring 6. Stirrup anchor rod 7. Anchor rod reinforcement bottom plate 8. Stirring ear plate tension bolt 9. Stirring ear plate 10. Stirrup 11. Rotating fixed rod 12. Rotatable temporary fixing plate 13. Bottom plate positioning ring 14. Anchor rod hole 15. Level 16. Horizontal I-beam 17. Longitudinal I-beam hoop plate 18. Upper pull ring 19. Y-shaped column ear plate 20. Adjustable support rod 21. Support rod base 22. Concrete plate 23. Lower pull ring 24. Support rod 25. Y-shaped column inner ear plate 26. Inner hoop plate 27. Longitudinal I-beam 28. Bracket auxiliary plate 29. Auxiliary plate Screw 30. Support truss 31. Platform support rod 32. Platform plate 33. Guardrail sleeve 34. Reinforced channel steel 35. Support steel section 36. Cantilever beam auxiliary support rod 37. Wedge-shaped top block 38. Cantilever beam 39. Column clamp 40. Steel section support rod 41. Connecting beam fixing 42. Connecting beam 43. Lower end plate 44. Side limit plate 45. Upper end plate 46. Platform lower cross beam 47. Cross beam reinforcement channel steel 48. Walkway plate 49. Walkway limit plate 50. Guardrail 51. Welding slag collection bucket 52. Upper steel beam 53. Hanging rod 54. End truss limit plate 55. Upper truss 56. Lifting rope 57. Connecting rod 58. Lifting ear 59. Connecting rod end plate 60. Temporary support. DETAILED DESCRIPTION

[0031] The utility model is further described below in conjunction with the embodiments. The description of the following embodiments is only used to help understand the utility model. It should be pointed out that for ordinary people in this technical field, the utility model can also be modified in some ways without departing from the principle of the utility model, and these improvements and modifications also fall within the scope of protection of the claims of the utility model.

[0032] As an example, Figures 1 to 12 As shown, this Y-shaped double column of the platform canopy steel structure mainly involves stirrup components with precise pre-embedded parts at the column base, factory virtual pre-assembly cradle technology, factory physical pre-assembly technology, a temporary fixing system for the installation of vertical columns, a temporary installation platform for the installation of cantilevered steel beams, a temporary connection structure between beams, an upper steel beam installation construction platform and a hanging welding slag anti-falling device.

[0033] like Figure 1 As shown, the Y-shaped double columns of the platform canopy steel structure include a Y-shaped double column 1, a stirrup 10, a concrete slab 22 and a cantilever beam 38; the Y-shaped double column 1 includes a column and a cantilever beam 38; the tops of the two columns are respectively connected to cantilever beams 38 in opposite directions;

[0034] like Figures 2 to 7 As shown, a column foot 2 is welded to the bottom of the column, and the column foot 2 is fixed on the stirrup 10. The stirrup 10 and the column foot 2 are integrally cast in the concrete slab 22. A longitudinal I-beam 27 and a transverse I-beam 16 are horizontally arranged on the two columns. A bracing rod 24 is arranged between the longitudinal I-beam 27 and the concrete slab 22, and an adjustable bracing rod 20 is arranged between the transverse I-beam 16 and the concrete slab 22 for adjusting the verticality of the column.

[0035] Specifically, a column foot base plate 3 is provided at the bottom of the column foot 2 of the Y-shaped double column 1, and the stirrup 10 includes a steel frame and a base plate positioning ring 13. A temporary fixing plate 12 with a rotatable screw 4 is provided around the top of the stirrup 10, and a rotating fixing rod 11 is provided at the end of the temporary fixing plate 12. The column foot base plate 3 is placed in the base plate positioning ring 13, and the temporary fixing plate 12 is pressed above the column foot base plate 3; an anchor rod reinforcement plate 7 is provided at the bottom of the stirrup 10, and a stirrup anchor rod 6 is provided on the anchor rod reinforcement plate 7, a steel frame is provided at the upper part, and two stirrup stiffening rings 5 ​​are provided in the middle part, and the stirrup stiffening ring 5 is provided with an anchor rod hole 14, and stiffening ring ear plates 9 are provided at the four corners of the end, and the stirrup stiffening ring 5 is fixed to the steel frame by stiffening ring ear plate tension bolts 8.

[0036] A Y-shaped double column ear plate 19 is arranged on the outer side of the Y-shaped double column 1, a longitudinal I-beam 27 is arranged on the Y-shaped double column ear plate 19, and the longitudinal I-beam 27 is fixed to the Y-shaped double column ear plate 19 through the longitudinal I-beam hoop plate 17, and a level 15 is arranged on the longitudinal I-beam 27. A Y-shaped double column inner ear plate 25 is arranged between the two columns of the Y-shaped double column 1, and a transverse I-beam 16 is arranged on the Y-shaped double column inner ear plate 25. The transverse I-beam 16 is fixed to the Y-shaped double column ear plate 19 through the longitudinal I-beam hoop plate 17. The inner hoop plate 26 is fixed on the inner ear plate 25 of the Y-shaped double column 1, a spirit level 15 is provided at the end of the transverse I-beam 16, an upper pull ring 18 is provided at the bottom of the longitudinal I-beam 27, a lower pull ring 23 is provided on the concrete slab 22, a support rod 24 is provided between the upper pull ring 18 and the lower pull ring 23, an adjustable support rod 20 is provided at the bottom of the transverse I-beam 16, a support rod base 21 is provided at the bottom of the adjustable support rod 20, and the support rod base 21 is placed on the concrete slab 22.

[0037] like Figures 8 to 12As shown, a temporary installation platform is provided at the top of the column, which is used to respectively set cantilever beams 38 at the top of the two columns, and a connecting beam 42 is provided between the cantilever beams 38; a temporary support 60 is provided at the end of the cantilever beam 38, two upper trusses 55 are provided above the cantilever beam 38, and an upper steel beam installation construction platform is provided below the upper truss 55 through a hanger 53, and upper steel beams 52 are welded on both sides of the cantilever beam 38 between the two upper trusses 55, and a welding slag collection bucket 51 is hung below the upper steel beam 52.

[0038] The temporary installation platform includes a platform plate 32; the temporary installation platform is fixed to the top of the column of the Y-shaped double column 1 through a column clamp 39, support steel 35 is arranged on both sides of the column clamp 39, and a reinforcing channel steel 34 is arranged at the bottom of the support steel 35. A platform plate 32 is arranged on the support steel 35, and a guardrail sleeve 33 is arranged on the platform plate 32. A cantilever beam auxiliary strut 36 is arranged on the top surface of the support steel 35, and a wedge-shaped top block 37 is arranged between the end of the cantilever beam auxiliary strut 36 and the cantilever beam 38. A support auxiliary plate 28 is arranged at the lower part of the column clamp 39, and the two support auxiliary plates 28 are pulled against each other by an auxiliary plate screw 29, a support truss 30 is arranged on the support auxiliary plate 28, and a platform strut 31 and a steel strut 40 are arranged on the support truss 30.

[0039] like Fig.10 As shown, the end of the cantilever beam 38 connecting the two upright columns of the Y-shaped double column 1 is provided with a side limit plate 44, and a connecting beam 42 is provided between the cantilever beams 38. Both ends of the connecting beam 42 are placed in the side limit plate 44 and fixed by a connecting beam fixing member 41. An upper end plate 45 and a lower end plate 43 are provided on the cantilever beam 38 for fixing the connecting beam 42.

[0040] like Fig.11 and Fig.12 As shown, a temporary support 60 is provided at the end of the cantilever beam 38, upper steel beams 52 are provided on both sides of the cantilever beam 38, the upper steel beams 52 are arranged perpendicular to the cantilever beam 38, the upper steel beams 52 are provided with lifting ears 58 for lifting, a connecting rod 57 is provided on the lifting ears 58, connecting rod end plates 59 are provided at both ends of the connecting rod 57, a lifting rope 56 is provided on the connecting rod 57, a welding slag collecting bucket 51 is provided under the lifting rope 56, and an end truss limit is provided on the cantilever beam 38. An upper truss 55 is arranged between the truss limiting plates 54, two upper trusses 55 are arranged on both sides of the upper steel beam 52, hangers 53 are arranged at the four corners of the upper truss 55, and the lower part of the hangers 53 is welded with a lower cross beam 46 of the platform, and a cross beam reinforcing channel steel 47 is arranged between the lower cross beams 46 of the platform, a walkway plate 48 is arranged on the lower cross beam 46 of the platform, and walkway plate limiting plates 49 are arranged on both sides of the walkway plate 48, and guardrails 50 are arranged around the upper steel beam installation construction platform.

Claims

1. A Y-shaped double column steel structure for a platform canopy, characterized in that: It includes a Y-shaped double column, a stirrup, a concrete slab and a cantilever beam; the Y-shaped double column includes a column and a cantilever beam; the tops of the two columns are respectively connected to cantilever beams in opposite directions; The column bottom is welded and connected with a column foot, which is fixed on the stirrup. The stirrup and the column foot are integrally cast in the concrete slab. The two columns are horizontally provided with longitudinal I-beams and transverse I-beams. A bracing rod is provided between the longitudinal I-beam and the concrete slab, and an adjustable bracing rod is provided between the transverse I-beam and the concrete slab to adjust the verticality of the column. A temporary installation platform is provided at the top of the column, which is used to set cantilever beams at the top of the two columns respectively, and a connecting beam is provided between the cantilever beams; a temporary support is provided at the end of the cantilever beam, and two upper trusses are provided above the cantilever beam. An upper steel beam installation construction platform is provided below the upper truss through a hanger, and upper steel beams are welded on both sides of the cantilever beam between the two upper trusses, and a welding slag collection bucket is hung below the upper steel beam.

2. The Y-shaped double columns of the platform canopy steel structure according to claim 1 are characterized in that: A column foot bottom plate is provided at the bottom of the column foot of the Y-shaped double column, and the stirrup includes a steel frame and a bottom plate positioning ring. A temporary fixing plate with a rotatable screw is provided around the top of the stirrup, a rotating fixing rod is provided at the end of the temporary fixing plate, the column foot bottom plate is placed in the bottom plate positioning ring, and the temporary fixing plate is pressed above the column foot bottom plate; an anchor rod reinforcement plate is provided at the bottom of the stirrup, a stirrup anchor rod is provided on the anchor rod reinforcement plate, a steel frame is provided at the upper part, a stirrup stiffening ring is provided in the middle part, an anchor rod hole is provided on the stirrup stiffening ring, and stiffening ring ear plates are provided at the four corners of the end, and the stirrup stiffening ring is fixed to the steel frame by stiffening ring ear plate tension bolts.

3. The Y-shaped double columns of the platform canopy steel structure according to claim 1 are characterized in that: A Y-shaped double-column ear plate is arranged on the outer side of the Y-shaped double-column, a longitudinal I-beam is arranged on the Y-shaped double-column ear plate, the longitudinal I-beam is fixed to the Y-shaped double-column ear plate through a longitudinal I-beam clamp plate, a spirit level is arranged on the longitudinal I-beam, a Y-shaped double-column inner ear plate is arranged between the two upright columns of the Y-shaped double column, a transverse I-beam is arranged on the inner ear plate of the Y-shaped double column, the transverse I-beam is fixed to the inner ear plate of the Y-shaped double column through an inner clamp plate, a spirit level is arranged on the end of the transverse I-beam, an upper pull ring is arranged at the bottom of the longitudinal I-beam, a lower pull ring is arranged on the concrete plate, a support rod is arranged between the upper pull ring and the lower pull ring, an adjustable support rod is arranged at the bottom of the transverse I-beam, a support rod base is arranged at the bottom of the adjustable support rod, and the support rod base is placed on the concrete plate.

4. The Y-shaped double columns of the platform canopy steel structure according to claim 1 are characterized in that: The temporary installation platform includes a platform plate; the temporary installation platform is fixed to the top of the column of the Y-shaped double column through the column clamp, supporting steel is arranged on both sides of the column clamp, reinforcing channel steel is arranged at the bottom of the supporting steel, and the platform plate is arranged on the supporting steel, and a guardrail sleeve is arranged on the platform plate, and a cantilever beam auxiliary strut is arranged on the top surface of the supporting steel, and a wedge-shaped top block is arranged between the end of the cantilever beam auxiliary strut and the cantilever beam, and a bracket auxiliary plate is arranged at the lower part of the column clamp, and the two bracket auxiliary plates are pulled together by auxiliary plate screws, and a supporting truss is arranged on the bracket auxiliary plate, and a platform strut and a steel strut are arranged on the supporting truss.

5. The Y-shaped double columns of the platform canopy steel structure according to claim 1 are characterized in that: The ends of the cantilever beams connecting the two upright columns of the Y-shaped double columns are provided with side limit plates, and connecting beams are provided between the cantilever beams. Both ends of the connecting beams are placed in the side limit plates and fixed by connecting beam fixing members, and the cantilever beams are provided with upper end plates and lower end plates for fixing the connecting beams.

6. The Y-shaped double columns of the platform canopy steel structure according to claim 1 are characterized in that: A temporary support is provided at the end of the cantilever beam, and upper steel beams are provided on both sides of the cantilever beam. The upper steel beam is arranged perpendicular to the cantilever beam, and the upper steel beam is provided with lifting ears for lifting, and connecting rods are provided on the lifting ears, and connecting rod end plates are provided at both ends of the connecting rods, and a lifting rope is provided on the connecting rod, and a welding slag collecting bucket is provided under the lifting rope. An end truss limiting plate is provided on the cantilever beam, and an upper truss is provided between the truss limiting plates. Two upper trusses are provided on both sides of the upper steel beam, and hanging rods are provided at the four corners of the upper truss. The lower cross beam of the platform is welded under the hanging rod, and a cross beam reinforcing channel steel is provided between the cross beams under the platform, and a walkway board is provided on the cross beam under the platform, and walkway board limiting plates are provided on both sides of the walkway board. Guardrails are provided around the upper steel beam installation construction platform.