Movable scaffold

By designing the base frame and extension components of the mobile scaffolding, the installation is simplified by using connecting screws and bump positioning grooves, the existing combined scaffolding is solved, the installation efficiency and safety performance are improved, and the construction needs of different heights are adapted.

CN222120875UActive Publication Date: 2024-12-06LONGXIN CONSTR GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420656214.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-12-06
Estimated Expiration
2034-03-29

AI Technical Summary

Technical Problem

When existing combined scaffolding needs to extend the height, the operation is cumbersome and the installation efficiency is low.

Method used

A mobile scaffolding is designed, including a base frame and an extension assembly. The base frame is composed of a fixing frame, a connecting rod and a first vertical rod. The extension assembly is composed of an extension frame, a second vertical rod and a connecting screw pipe, through a connecting screw pipe and bump positioning slot design simplifies installation steps and improves stability and safety through moving wheels and anti-slip pads.

Benefits of technology

It achieves simple operation, high installation efficiency, high stability and improved safety performance, and adapts to construction needs of different heights.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222120875U_ABST
    Figure CN222120875U_ABST
Patent Text Reader

Abstract

The utility model relates to a movable scaffold, and relates to the technical field of building construction. The bottom frame comprises a fixed frame, a connecting rod and four groups of first vertical rods; the fixing frame is rectangular, the first vertical rods are located at the four corners of the fixing frame respectively, and the ends of the first vertical rods are fixedly connected to the fixing frame. Four groups of connecting rods are arranged, and the connecting rods are used for connecting two adjacent groups of first vertical rods; the extension assembly comprises two groups of oppositely arranged extension frames, and the extension frames are mounted at the ends, away from the fixing frame, of the first vertical rods; the bottom of the fixed frame is provided with a movable part; the combined scaffold has the effect of improving the installation convenience of the combined scaffold.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building construction, and in particular to a mobile scaffolding. Background Art

[0002] Scaffolding is a common term in the construction industry, referring to the scaffolding used on construction sites for exterior walls, interior decoration or places with high floor heights that cannot be directly constructed. It is mainly used for construction workers to go up and down or for external safety net enclosures and high-altitude installation structures.

[0003] In the prior art, a combined scaffolding includes columns, a plug-in frame, and a ladder. The columns are long steel pipes, the plug-in frame is a horizontal square steel structure frame, the plug-in frame is composed of a crossbeam and a plug-in rod, the crossbeam is a long steel pipe, the plug-in rod is a short steel pipe or a round steel rod, the outer diameter of the plug-in rod matches the inner diameter of the column, four crossbeams form the four sides of the plug-in frame, four plug-in rods are located at the four corners of the plug-in frame, the plug-in rods are perpendicular to the crossbeams, the two ends of the four crossbeams are respectively welded to the middle of the four plug-in rods, the inner holes at the two ends of the column are respectively plugged with the upper plug-in rod or the lower plug-in rod of the plug-in frame, and a hook is provided at the upper end of the ladder, and the hook is hung on the crossbeam of the plug-in frame.

[0004] Regarding the above-mentioned related technologies, when the overall height of the combined scaffolding needs to be extended, the operator needs to first install the plug-in frame, and then plug the columns into the plug-in rods of the plug-in frame to complete the multi-layer construction in this way. The operation is relatively cumbersome and needs to be improved. Utility Model Content

[0005] In order to improve the convenience of installation of combined scaffolding, the present application provides a mobile scaffolding.

[0006] The mobile scaffolding provided in this application adopts the following technical solution:

[0007] A mobile scaffolding comprises a base frame and an extension assembly, wherein the base frame comprises a fixed frame, a connecting rod and four groups of first upright poles; the fixed frame is rectangular, the first upright poles are respectively located at the four corners of the fixed frame, and the ends of the first upright poles are fixedly connected to the fixed frame; four groups of connecting rods are provided, and the connecting rods are used to connect two adjacent groups of first upright poles; the extension assembly comprises two groups of extension frames arranged opposite to each other, and the extension frames are installed at one end of the first upright pole away from the fixed frame; movable wheels are provided at the bottom of the fixed frame.

[0008] By adopting the above technical solution, the operator only needs to install the two sets of extension frames correspondingly on the first vertical pole to complete the installation of the extension assembly. The operation is convenient, the installation steps are few, and the installation efficiency is high. The setting of the connecting rod helps to improve the stability of the position between the four sets of vertical poles. At the same time, the connecting rod also acts as a ladder, which has certain practical significance.

[0009] Preferably, the extension frame comprises a cross bar and two groups of second vertical poles, the cross bar is used to connect the two groups of second vertical poles; one end of the second vertical pole close to the first vertical pole is threadedly connected with a connecting screw, and the second vertical pole is connected to the first vertical pole through the connecting screw.

[0010] By adopting the above technical solution, the connecting screw is rotated to connect the end of the second vertical pole with the top of the first vertical pole, thereby realizing the installation of the second vertical pole, that is, realizing the installation of the extension frame; the setting of the connecting screw helps to improve the stability of the connection between the first vertical pole and the second vertical pole, has a simple structure, is easy to operate, and helps to improve the installation efficiency.

[0011] Preferably, the cross-sectional diameter of the first upright pole is the same as the cross-sectional diameter of the second upright pole.

[0012] By adopting the above technical solution, the operator rotates the connecting screw tube and moves it downward, and the top end of the first vertical pole enters into the connecting screw tube. Since the second vertical pole and the first vertical pole have the same diameter, the connecting screw tube and the first vertical pole are highly adapted to each other, so as to reduce the situation where the second vertical pole shakes on the first vertical pole due to the large gap between the first vertical pole and the inner wall of the connecting screw tube, thereby helping to improve the stability of the position of the second vertical pole on the first vertical pole.

[0013] Preferably, a first protrusion is provided at one end of the first vertical pole away from the fixing frame, and a positioning groove for inserting the first protrusion is provided at one end of the second vertical pole close to the first vertical pole.

[0014] By adopting the above technical solution, the first protrusion is inserted into the positioning groove to limit the position of the second upright pole at the top end of the first upright pole, thereby helping to improve the installation efficiency of the second upright pole.

[0015] Preferably, a second protrusion is provided at one end of the second upright pole away from the first upright pole, and the second protrusion is matched with the positioning groove.

[0016] By adopting the above technical solution, multiple groups of extension components can be built layer by layer according to actual needs. When two adjacent groups of second uprights are installed in the height direction, the second protrusion of the second upright located at the bottom is inserted into the positioning groove at the lower end of the second upright located at the top, so as to realize the positioning of the second upright located at the top. The operation is convenient and it is convenient to install multiple groups of first uprights according to needs.

[0017] Preferably, the extension assembly further comprises a pedal, and both ends of the pedal are correspondingly mounted on the cross bar.

[0018] By adopting the above technical solution, the setting of the pedal is convenient for the operator to place the construction tools. At the same time, the operator can also walk on the pedal, which has certain practicality.

[0019] Preferably, the pedal is provided with snap-fitting protrusions at both ends, and the cross bar is provided with snap-fitting grooves for inserting the snap-fitting protrusions.

[0020] By adopting the above technical solution, the clamping protrusions at both ends of the pedal are inserted into the clamping grooves, so as to achieve the installation of the pedal. The setting of the clamping groove helps to improve the stability of the connection between the clamping protrusion and the cross bar.

[0021] Preferably, an anti-slip pad is provided on the cross bar.

[0022] By adopting the above technical solution, when the operator climbs up by stepping on the cross bar, the provision of the anti-slip pad helps to increase the friction between the operator's feet and the cross bar, thereby helping to reduce the operator's sliding on the cross bar, thereby improving the safety performance of the modular scaffolding when in use.

[0023] In summary, the present application includes at least one of the following beneficial technical effects:

[0024] 1. The operator only needs to install the two sets of extension frames on the first vertical pole to complete the installation of the extension assembly. The operation is convenient, the installation steps are few, and the installation efficiency is high;

[0025] 2. The setting of the connecting screw tube helps to improve the stability of the connection between the first vertical pole and the second vertical pole, has a simple structure, is easy to operate, and helps to improve the installation efficiency;

[0026] 3. The setting of the pedal makes it convenient for operators to place construction tools. At the same time, operators can also walk on the pedal, which has certain practicality. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram for reflecting a movable scaffolding structure in an embodiment.

[0028] Figure 2 It is an exploded schematic diagram for reflecting a movable scaffolding structure in an embodiment.

[0029] Description of reference numerals:

[0030] 1. Base frame; 11. Fixed frame; 12. Connecting rod; 13. First vertical pole; 131. First protrusion; 2. Extension assembly; 21. Extension frame; 211. Cross bar; 212. Second vertical pole; 2121. Second protrusion; 213. Connecting screw; 22. Pedal; 221. Snap-on protrusion; 3. Moving wheel; 4. Positioning groove; 5. Snap-on groove; 6. Anti-slip pad. DETAILED DESCRIPTION

[0031] The following is combined with Figure 1-2 This application is described in further detail.

[0032] The present application embodiment discloses a mobile scaffold. Figure 1 A mobile scaffolding includes a base frame 1, and the base frame 1 includes a fixed top frame. Specifically, movable wheels 3 are arranged at the four corners of the bottom of the fixed frame 11.

[0033] Reference Figure 1 The base frame 1 also includes four groups of first vertical poles 13. Specifically, the four groups of first vertical poles 13 are respectively located at the four corners of the fixed frame 11, and the ends of the first vertical poles 13 are fixedly connected to the fixed frame 11; specifically, the bottom ends of the first vertical poles 13 are welded to the fixed frame 11.

[0034] Reference Figure 1 The base frame 1 further includes four groups of connecting rods 12 , and the connecting rods 12 are used to connect two adjacent groups of first vertical rods 13 . Specifically, both ends of the connecting rods 12 are welded to the corresponding first vertical rods 13 .

[0035] Reference Figure 1 and Figure 2 A mobile scaffold also includes an extension component 2, the extension component 2 includes two groups of relatively arranged extension frames 21, the extension frames 21 include a cross bar 211 and two groups of second vertical poles 212; specifically, the cross bar 211 is located between the two groups of second vertical poles 212, and the cross bar 211 is used to connect the two groups of second vertical poles 212, and the two ends of the cross bar 211 are correspondingly welded to the two groups of second vertical poles 212.

[0036] Reference Figure 1 A non-slip pad 6 is provided on the cross bar 211. Specifically, the non-slip pad 6 is adhered to the cross bar 211 by hot melt adhesive. When the operator climbs up by stepping on the cross bar 211, the provision of the non-slip pad 6 helps to increase the friction at the contact point between the operator's foot and the cross bar 211, thereby helping to reduce the operator's sliding on the cross bar 211, that is, improving the safety performance of the modular scaffolding when in use.

[0037] Reference Figure 1 The second vertical rod 212 is located at the end of the first vertical rod 13 away from the fixed frame 11, and the end of the second vertical rod 212 close to the first vertical rod 13 is threadedly connected with a connecting screw 213, and the second vertical rod 212 is connected to the first vertical rod 13 through the connecting screw; specifically, the end of the second vertical rod 212 close to the first vertical rod 13 is provided with a threaded section adapted to the connecting screw 213, and the diameters of the second vertical rod 212 and the first vertical rod 13 are the same.

[0038] Reference Figure 1 and Figure 2A first protrusion 131 is provided at one end of the first vertical rod 13 away from the fixed frame 11, and a positioning groove 4 for inserting the first protrusion 131 is provided at one end of the second vertical rod 212 close to the first vertical rod 13; the first protrusion 131 is inserted into the positioning groove 4 to limit the position of the second vertical rod 212 on the first vertical rod 13, so that the operator can install the second vertical rod 212 on the first vertical rod 13, thereby helping to improve the installation efficiency.

[0039] Reference Figure 2 A second protrusion 2121 is provided at one end of the second vertical pole 212 away from the first vertical pole 13, and the second protrusion 2121 is adapted to the positioning groove 4; when multiple groups of extension components 2 need to be installed along the height direction, the operator can build the corresponding second vertical poles 212 layer by layer along the height direction, so as to extend the height of the combined scaffolding to meet the construction needs of different heights.

[0040] Reference Figure 2 The extension component 2 also includes a pedal 22, and both ends of the pedal 22 are provided with a snap-on protrusion 221. Specifically, the snap-on protrusion 221 is integrally formed with the pedal 22; a snap-on groove 5 for inserting the snap-on protrusion 221 is correspondingly provided on the cross bar 211; according to actual needs, the operator installs the pedal 22 after building the multi-layer extension frame 21. The setting of the pedal 22 can facilitate the operator to place construction tools.

[0041] The implementation principle of a mobile scaffolding in the embodiment of the present application is as follows: the operator first installs a set of extension frames 21, installs the bottom end of the second vertical pole 212 on the top of the first vertical pole 13, and inserts the first protrusion 131 on the first vertical pole 13 into the positioning groove 4, then rotates the connecting screw 213 at the bottom end of the second vertical pole 212, so that the connecting screw 213 moves toward the direction close to the first vertical pole 13, thereby realizing the connection between the second vertical pole 212 and the first vertical pole 13; then installs another set of extension frames 21 in the same way, and after the two sets of extension frames 21 are installed, the clamping protrusions 221 at both ends of the pedal 22 are correspondingly inserted into the clamping grooves 5 to complete the installation of the pedal 22, and thereby complete the installation of a set of extension components 2; according to actual needs, multiple sets of extension components 2 can be installed along the height direction to meet the construction needs of different heights.

[0042] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A mobile scaffold, characterized in that: The invention comprises a base frame (1) and an extension assembly (2), wherein the base frame (1) comprises a fixed frame (11), a connecting rod (12) and four groups of first vertical rods (13); the fixed frame (11) is rectangular, the first vertical rods (13) are respectively located at four corners of the fixed frame (11), and the ends of the first vertical rods (13) are fixedly connected to the fixed frame (11); four groups of connecting rods (12) are provided, and the connecting rods (12) are used to connect two adjacent groups of first vertical rods (13); the extension assembly (2) comprises two groups of extension frames (21) arranged opposite to each other. ), and the extension frame (21) is installed at one end of the first vertical pole (13) away from the fixed frame (11); a moving wheel (3) is arranged at the bottom of the fixed frame (11); the extension frame (21) also includes a cross bar (211) and two groups of second vertical poles (212), and the cross bar (211) is used to connect the two groups of second vertical poles (212); one end of the second vertical pole (212) and the first vertical pole (13) is threadedly connected with a connecting screw (213), and the second vertical pole (212) is connected to the first vertical pole (13) through the connecting screw (213).

2. A mobile scaffold according to claim 1, characterized in that: The cross-sectional diameter of the first upright pole (13) is the same as the cross-sectional diameter of the second upright pole (212).

3. A mobile scaffold according to claim 1, characterized in that: A first protrusion (131) is provided at one end of the first vertical rod (13) away from the fixed frame (11), and a positioning groove (4) for inserting the first protrusion (131) is provided at one end of the second vertical rod (212) close to the first vertical rod (13).

4. A mobile scaffold according to claim 3, characterized in that: A second protrusion (2121) is provided at one end of the second upright pole (212) away from the first upright pole (13), and the second protrusion (2121) is matched with the positioning groove (4).

5. The mobile scaffold according to claim 1, characterized in that: The extension assembly (2) further comprises a pedal (22), and two ends of the pedal (22) are correspondingly mounted on the crossbar (211).

6. A mobile scaffold according to claim 5, characterized in that: The pedal (22) is provided with clamping protrusions (221) at both ends, and the crossbar (211) is correspondingly provided with clamping grooves (5) for the clamping protrusions (221) to be inserted.