Clamping and hanging type construction platform
By designing a clamp-mounted construction platform, using clamping devices and lifting devices, the problem of inconvenient placement of elevator beams is solved, the stable installation and convenient assembly and disassembly of beams is achieved, and construction efficiency and safety are improved.
Patent Information
- Application Number
- CN202420485700.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-13
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-03-13
AI Technical Summary
When installing elevator beams on the existing construction platform, the beams cannot be placed directly, resulting in need of binding, inconvenient installation and disassembly, and there are hidden dangers of stability and safety.
A clamp-hang construction platform is designed, including a frame, a lifting device and a clamping device. The clamping device consists of an upper clamp, a support rod and a lower clamp, which can be arranged parallel to the bottom of the frame to form a space for placing the elevator beam. The cavity has a large number of support rods. The support rod is arranged on both sides to support the beam and limit its swing. The lifting device adjusts the height through the wire rope and the control panel.
The direct placement and stable installation of elevator beams is realized without binding, easy installation and disassembly, improve construction efficiency and safety, and reduce labor costs.
Smart Images

Figure CN222120890U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction platforms, and more specifically, to a clamping and hanging type construction platform. Background Art
[0002] In today's society with tall buildings, elevators have become an indispensable equipment for every tall building. However, when installing an elevator shaft or an elevator, it is difficult to install the elevator shaft or the elevator because the floors are too high. Therefore, the installers often need to use a construction platform to install the elevator shaft or the elevator. However, in the process of installing the elevator upper beam, the elevator upper beam is too long to be directly placed in the frame of the construction platform. In the prior art, such as the Chinese utility model application No. 201620514379.2, which discloses an elevator construction platform for a narrow shaft, there is no device for placing the elevator upper beam, and the elevator upper beam is usually tied to the construction platform.
[0003] The prior art has the following defects: during the construction process, the upper crossbeam of the elevator is tied to the construction platform, which makes it inconvenient for people to install and remove the upper crossbeam of the elevator, so that the existing construction platform has certain defects. Utility Model Content
[0004] In order to overcome the above technical defects, the utility model provides a clamping and hanging type construction platform.
[0005] In order to solve the above problems, the utility model is implemented according to the following technical scheme: a clamping and hanging construction platform, comprising:
[0006] A frame, wherein the frame is provided with a workbench;
[0007] A lifting device, which is disposed in the frame and is used to lift the frame;
[0008] A clamping device, wherein the clamping device has a cavity for placing the upper cross beam of the elevator, and the number of the clamping devices is two, and the two clamping devices are respectively arranged in parallel at the bottom of the frame;
[0009] Wherein, the clamping device includes an upper clamp, a support rod and a lower clamp, the upper clamp is connected to the frame, the upper clamp is connected to the lower clamp through the support rod, the number of the support rods is multiple, and the multiple support rods are respectively arranged on both sides of the upper clamp and the lower clamp.
[0010] In some embodiments, the workbench includes a first workbench and a second workbench, and the first workbench and the second workbench are both connected to the frame through a telescopic rod or a slide rail.
[0011] In some embodiments, the lifting device includes a hoist, a control panel and a steel wire rope, the steel wire rope is arranged in the hoist, and the control panel is used to control the hoist to retract and release the steel wire rope.
[0012] In some embodiments, the upper clamp is provided with a connecting piece for connecting to the frame, the upper clamp is provided with a first through hole, the support rod is a double-headed screw, and the lower clamp is provided with a second through hole.
[0013] In some embodiments, the side walls of the first workbench and the second workbench are both provided with fastening devices for clamping on the elevator guide rails.
[0014] In some embodiments, the fastening device includes a fastener and a connecting plate, the connecting plate is connected to the side wall of the first workbench or the second workbench, and the fastener is clamped on the elevator guide rail.
[0015] In some embodiments, both the first workbench and the second workbench are provided with guardrail chains.
[0016] In some embodiments, a heightened platform is provided above the frame.
[0017] In some of the embodiments, a roof is installed on the elevated platform.
[0018] In some of the embodiments, the frame, workbench and ceiling are all made of metal materials.
[0019] Compared with the prior art, the beneficial effects of the utility model are:
[0020] The clamping and lifting construction platform includes a frame, a lifting device and a clamping device. The frame is provided with a workbench. The lifting device is arranged in the frame and is used to lift the frame. The clamping device has a cavity for placing the upper crossbeam of the elevator. There are two clamping devices, which are respectively arranged in parallel at the bottom of the frame. The clamping device includes an upper clamp, a support rod and a lower clamp. The upper clamp is connected to the frame, and the upper clamp is connected to the lower clamp through the support rod. There are multiple support rods, which are respectively arranged on both sides of the upper clamp and the lower clamp. Through the above-mentioned construction platform, construction workers can directly place the upper crossbeam of the elevator on the construction platform without bundling, which is convenient for people to install and disassemble the upper crossbeam of the elevator. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The specific implementation of the utility model is further described in detail below with reference to the accompanying drawings, wherein:
[0022] Figure 1 This is the main view of the clamp-and-hang construction platform;
[0023] Figure 2It is a side view of the clamp-and-hang construction platform;
[0024] Figure 3 This is a top view of the clamp-and-hang construction platform;
[0025] Figure 4 It is a three-dimensional diagram of the frame;
[0026] Figure 5 is a top view of the upper clamp;
[0027] Figure 6 It is the main view of the upper clamp;
[0028] Figure 7 It is a top view of the lower clamp.
[0029] In the figure:
[0030] 1. Frame; 2. Lifting device; 3. Clamping device; 4. Upper clamp; 5. Support rod; 6. Lower clamp; 7. First workbench; 8. Second workbench; 9. Connecting piece; 10. First through hole; 11. Second through hole; 12. Guardrail chain; 13. Heightening platform; 14. Upper crossbeam of elevator. DETAILED DESCRIPTION
[0031] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention. The directional words such as "upper" and "lower" involved in this article are all relative to the viewing angle of the accompanying drawings. They are only for the convenience of description and cannot be understood as limitations on the technical solution. The "first, second..." used are only used to distinguish the names and do not represent specific quantities and orders.
[0032] like Figure 1-7As shown, the utility model provides a clamping and lifting construction platform, which includes a frame 1, a lifting device 2 and a clamping device 3. The frame 1 is provided with a workbench, and the construction personnel work on the workbench. The lifting device 2 is arranged in the frame 1 and is used to lift the frame 1. The construction personnel can adjust the height of the frame 1 according to actual needs. Since the upper cross beam 14 of the elevator is long and cannot be placed in the frame 1 of the construction platform, the clamping device 3 is designed. The clamping device 3 has a cavity for placing the upper cross beam 14 of the elevator. The number of the clamping devices 3 is two, and the two clamping devices 3 are respectively arranged in parallel at the bottom of the frame 1, which is conducive to the upper cross beam 14 of the elevator being kept stable on the construction platform and prevents the upper cross beam 14 of the elevator from falling from the clamping device 3 during the lifting process. Specifically, the clamping device 3 includes an upper clamp 4, a support rod 5 and a lower clamp 6. The upper clamp 4 is connected to the frame 1, and the connection method of the upper clamp 4 and the frame 1 can be welding or detachable connection. The upper clamp 4 is connected to the lower clamp 6 by a supporting rod 5. There are multiple supporting rods 5, which are respectively arranged on both sides of the upper clamp 4 and the lower clamp 6, so as to form a cavity for placing the elevator upper beam 14 and limit the swing of the elevator upper beam 14. Therefore, through the above-mentioned construction platform, the construction workers can directly place the elevator upper beam 14 on the construction platform without bundling, which is convenient for people to install and remove the elevator upper beam 14.
[0033] In a specific embodiment, the workbench includes a first workbench 7 and a second workbench 8. The first workbench 7 and the second workbench 8 are both connected to the frame 1 through a telescopic rod or a slide rail. Construction workers can adjust the size of the workbench according to the size of the space on site, so that the construction platform can be applied to construction environments in different spaces.
[0034] In a specific embodiment, the lifting device 2 belongs to the prior art in this field. In the utility model, the lifting device 2 preferably includes a hoist, a control panel and a wire rope. The wire rope is arranged in the hoist, and the control panel is used to control the hoist to retract and release the wire rope. More specifically, when in use, one end of the wire rope is fixed to the top of the house or hung at the construction site through a support column. The construction personnel can adjust the height of the suspension of the construction platform according to actual needs on the frame 1, which is more convenient and saves labor costs than setting the lifting device 2 on the ground.
[0035] In a specific embodiment, the upper clamp 4 is provided with a connecting member 9 for connecting to the frame body 1, and the number of the connecting members 9 is preferably two. The connecting member 9 is fastened to the frame body 1 by screws, thereby realizing a detachable connection between the upper clamp 4 and the frame body 1. The upper clamp 4 is provided with a first through hole 10, the support rod 5 is a double-headed screw, and the lower clamp 6 is provided with a second through hole 11. The number of the first through hole 10 and the second through hole 11 are both multiple, and the double-headed screws are placed in the first through hole 10 and the second through hole 11 and fixed by nuts.
[0036] In a specific embodiment, during on-site construction, the construction platform may occasionally shake due to improper operation of the construction workers. Therefore, in order to ensure the stability of the construction platform, the side walls of the first workbench 7 and the second workbench 8 are provided with a fastening device (not shown in the figure) for clamping on the elevator guide rail. More specifically, the fastening device includes a fastener and a connecting plate, the connecting plate is connected to the side wall of the first workbench 7 or the second workbench 8, the fastener is clamped on the elevator guide rail, the fastener is provided with a clamping groove adapted to the elevator guide rail, and the fastener is clamped on the elevator guide rail through the clamping groove to prevent the construction platform from shaking during use. The first workbench 7 and the second workbench 8 are both provided with a guardrail chain 12, which can further improve the safety performance of the construction platform.
[0037] In a specific embodiment, a heightened platform 13 is provided above the frame 1. More specifically, the heightened platform 13 is provided with mounting holes to facilitate the installation of a ceiling (not shown in the figure) on the heightened platform 13. The supporting columns of the ceiling are telescopic rods. When an accident occurs on the construction platform, the construction workers can push open the ceiling. There are no guardrails around the ceiling, which makes it easy for the construction workers to quickly walk out of the construction platform.
[0038] In a specific embodiment, the frame 1, the workbench and the ceiling are all made of metal materials, and the metal material can be stainless steel, iron, aluminum alloy, etc. The utility model preferably uses stainless steel materials to ensure the firmness and corrosion resistance of the construction platform.
[0039] The use principle of the utility model: the frame 1 is provided with a workbench, which includes a first workbench 7 and a second workbench 8. The first workbench 7 and the second workbench 8 are connected to the frame 1 through a telescopic rod or a slide rail, and the construction personnel can adjust the size of the workbench according to the space size on site. The side walls of the first workbench 7 and the second workbench 8 are provided with a fastening device for clamping on the elevator guide rail to prevent the construction platform from shaking during use. The lifting device 2 is arranged in the frame 1, and the lifting device 2 includes a hoist, a control panel and a wire rope. The wire rope is arranged in the hoist, and the control panel is used to control the hoist to retract and release the wire rope. When in use, one end of the wire rope is fixed to the top of the house or suspended at the construction site through a support column, and the construction personnel can adjust the height of the construction platform suspension according to actual needs in the frame 1. The number of the clamping device 3 is two, and the two clamping devices 3 are respectively arranged in parallel at the bottom of the frame 1. The clamping device 3 includes an upper clamp 4, a support rod 5 and a lower clamp 6, and the upper clamp 4 is connected to the frame 1. The upper clamp 4 is connected to the lower clamp 6 by a supporting rod 5. There are multiple supporting rods 5, which are respectively arranged on both sides of the upper clamp 4 and the lower clamp 6, so as to form a cavity for placing the elevator upper beam 14 and limit the swing of the elevator upper beam 14. Therefore, through the above-mentioned construction platform, the construction workers can directly place the elevator upper beam 14 on the construction platform without bundling, which is convenient for people to install and remove the elevator upper beam 14.
[0040] The above are only preferred embodiments of the present invention and are not intended to limit the present invention in any form. Therefore, any modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the technical solution of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. A clamping and hanging construction platform, characterized in that: include: A frame, wherein the frame is provided with a workbench; A lifting device, which is disposed in the frame and is used to lift the frame; A clamping device, wherein the clamping device has a cavity for placing the upper cross beam of the elevator, and the number of the clamping devices is two, and the two clamping devices are respectively arranged in parallel at the bottom of the frame; Wherein, the clamping device includes an upper clamp, a support rod and a lower clamp, the upper clamp is connected to the frame, the upper clamp is connected to the lower clamp through the support rod, the number of the support rods is multiple, and the multiple support rods are respectively arranged on both sides of the upper clamp and the lower clamp.
2. The clamping and hanging construction platform according to claim 1 is characterized in that: The workbench comprises a first workbench and a second workbench, and the first workbench and the second workbench are both connected to the frame body through telescopic rods or slide rails.
3. The clamping and hanging construction platform according to claim 1 is characterized in that: The lifting device includes a hoist, a control panel and a steel wire rope. The steel wire rope is arranged in the hoist, and the control panel is used to control the hoist to retract and release the steel wire rope.
4. The clamping and hanging construction platform according to claim 1 is characterized in that: The upper clamp is provided with a connecting piece for connecting with the frame body, the upper clamp is provided with a first through hole, the support rod is a double-headed screw, and the lower clamp is provided with a second through hole.
5. The clamping and hanging construction platform according to claim 2 is characterized in that: The side walls of the first workbench and the second workbench are both provided with fastening devices for clamping on the elevator guide rails.
6. The clamping and hanging construction platform according to claim 5 is characterized in that: The fastening device comprises a fastener and a connecting plate, wherein the connecting plate is connected to the side wall of the first workbench or the second workbench, and the fastener is clamped on the elevator guide rail.
7. The clamping and hanging construction platform according to claim 6 is characterized in that: The first workbench and the second workbench are both provided with guardrail chains.
8. The clamping and hanging construction platform according to any one of claims 1 to 7, characterized in that: A heightening platform is arranged above the frame.
9. The clamping and hanging construction platform according to claim 8, characterized in that: A roof is installed on the height-enhancing platform.
10. The clamping and hanging construction platform according to claim 9, characterized in that: The frame, workbench and ceiling are all made of metal materials.