Long arch protection structure for shallow-buried unsymmetrical-pressure tunnel portal

By using the method of setting up arch guards and cast-injected piles in sections in the long arch guard structure of shallow buried bias tunnel opening, the problems of low construction efficiency and high cost are solved, the construction safety and efficiency are improved, and the structure is ensured. Stability and durability.

CN222121539UActive Publication Date: 2024-12-06CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420863422.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-24
Publication Date
2024-12-06
Estimated Expiration
2034-04-24

AI Technical Summary

Technical Problem

The construction efficiency and cost of the long arch protection structure of the existing shallow buried bias tunnel opening is low in construction and has a high cost, especially in areas with complex terrain and poor surrounding rock stability, making it difficult to complete the construction quickly and safely.

Method used

Design a long arch protection structure of shallow buried bias tunnel opening including ground lines and foundations, using steel arch frames, arch protection ear walls, cast-injected piles, locking anchors, pipe shed pillars and initial support components. The section is equipped with arch guards and cast-injected piles to reduce disturbances to the excavated side slope and surrounding rock, and improve construction efficiency and safety.

Benefits of technology

By setting up arch guards and cast-in piles in sections, the cost of materials is reduced, construction period is saved, construction disturbances are reduced, construction safety and efficiency are improved, and structure stability and durability are ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222121539U_ABST
    Figure CN222121539U_ABST
Patent Text Reader

Abstract

The utility model discloses a shallow-buried unsymmetrical-pressure tunnel portal long arch protection structure which comprises a ground line and a foundation and is characterized in that a steel arch frame and an arch protection ear wall are fixedly connected to the foundation, a first arch protection, a second arch protection and a third arch protection are fixedly connected to the steel arch frame, a cast-in-place pile is arranged below the foundation, the top of the cast-in-place pile is embedded into the foundation, and the top of the cast-in-place pile is fixedly connected with the ground line. The cast-in-place piles are distributed at equal intervals in the longitudinal direction, the other end of the first protective arch is fixedly connected with two feet-lock bolts, the feet-lock bolts are fixed to a rock mass in the unsymmetrical pressure landslide zone, a row of small guide pipes are arranged on the unsymmetrical pressure landslide zone, and the small guide pipes are vertically driven into the unsymmetrical pressure landslide zone to be fixed in a grouting mode. A primary support is arranged below the steel arch frame, the bottom of the primary support is reinforced through a small grouting guide pipe, a secondary lining structure is arranged in the primary support, a backfill groove is formed below the ground line, C15 concrete is backfilled in the backfill groove, and the device solves the problems that a current construction site is long in construction period and high in cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical direction of a long protective arch structure for a shallow buried bias pressure tunnel opening, and specifically relates to a long protective arch structure for a shallow buried bias pressure tunnel opening. Background Art

[0002] With the continuous advancement of the long arch structure at the entrance of shallow biased tunnel, how to complete the construction more quickly, efficiently and with quality has been a question that people have been discussing.

[0003] Therefore, the utility model designs a long arch protection structure for a shallow buried biased tunnel portal, which is suitable for the construction of shallow buried biased tunnel portals located on slopes with long influence distances and complex terrain. It makes full use of the stability of the tunnel terrain and the surrounding rock itself, sets up arch protection in sections, reduces disturbances to the excavation side slope and surrounding rock, reduces construction costs, and improves construction efficiency. Utility Model Content

[0004] The utility model aims to provide a shallow buried biased tunnel opening long arch structure for existing devices to solve the problems raised in the above background technology.

[0005] In order to solve the above technical problems, the utility model provides the following technical solutions: a long guard arch structure for a shallow buried biased tunnel entrance, comprising a ground line and a foundation, characterized in that a steel arch frame and a guard arch ear wall are fixedly connected to the foundation, guard arch one, guard arch two and guard arch three are fixedly connected to the steel arch frame, and a support end is arranged on the left side of the guard arch ear wall.

[0006] Cast-in-place piles are arranged under the foundation. The cast-in-place piles are reinforced concrete bored cast-in-place piles. The tops of the cast-in-place piles are embedded in the foundation. The cast-in-place piles are distributed at equal intervals along the longitudinal direction.

[0007] One side of the arch guard one, the arch guard two and the arch guard three is on the supporting end, and the other end of the arch guard one is fixedly connected with two locking anchor rods, and the locking anchor rods are fixed on the rock mass in the biased landslide zone.

[0008] A row of pipe shed pillars are connected through the first, second and third protective arches, and a row of small pipes are arranged on the biased landslide zone. The small pipes are vertically driven into the biased landslide zone and fixed by grouting.

[0009] An initial support is provided under the steel arch frame. The tunnel side wall on the mountain side of the initial support is supported by steel mesh and sprayed concrete. The bottom of the initial support is reinforced with a small grouting pipe. A secondary lining structure is provided in the initial support. The secondary lining structure is made of concrete and can effectively withstand external loads and groundwater pressure.

[0010] A backfill groove is opened below the ground line. After the secondary lining structure is completed through the initial support, the backfill groove is backfilled with C15 concrete.

[0011] Compared with the prior art, the beneficial effects achieved by the utility model are as follows: the utility model reduces material costs and saves construction time by providing a protective arch with three sections of different arc lengths, with the arc lengths decreasing successively; the arc length and length of the protective arch are set in sections according to the terrain, thereby reducing disturbance to the excavation side slope and surrounding rock and ensuring construction safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0013] Figure 1 It is a schematic diagram of the main view structure of the utility model;

[0014] Figure 2 It is a schematic diagram of the enlarged structure of the main view of the utility model;

[0015] Figure 3 It is a schematic diagram of the top view structure of the utility model;

[0016] In the figure: 1. Ground line; 2. Cast-in-place piles; 3. Foundation; 4. Arch ear wall; 5. Support end; 6. Arch one; 601. Arch two; 602. Arch three; 7. Locking anchor rod; 8. Eccentric landslide zone; 9. Small guide tube; 10. Backfill groove; 11. Steel arch frame; 12. Initial support; 13. Secondary lining structure; 14. Pipe shed pillar. DETAILED DESCRIPTION

[0017] The following is a further non-limiting detailed description of the technical solution of the utility model in conjunction with the preferred embodiments and the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0018] See also Figure 1-3 The utility model provides a technical solution: a shallow buried biased tunnel portal long arch structure, including a ground line 1 and a foundation 3, a cast-in-place pile 2 is arranged under the foundation 3, the cast-in-place pile 2 is a reinforced concrete bored cast-in-place pile, the top of the cast-in-place pile 2 is embedded in the foundation 3, and the cast-in-place pile 2 is evenly spaced along the longitudinal direction.

[0019] The foundation 3 is a reinforced concrete structure, on which a steel arch frame 11 and an arch ear wall 4 are fixedly connected, a support end 5 is provided on the left side of the arch ear wall 4, and an arch guard 1 6, an arch guard 2 601 and an arch guard 3 602 are fixedly connected to the steel arch frame 11.

[0020] One side of the arch guard 1 6, the arch guard 2 601 and the arch guard 3 602 is on the support end 5, and the other end of the arch guard 1 6 is fixedly connected with two locking anchor rods 7, and the locking anchor rods 7 are fixed on the rock mass in the bias landslide zone 8. A row of pipe rack pillars 14 are connected through the arch guard 1 6, the arch guard 2 601 and the arch guard 3 602, and a row of small guide tubes 9 are provided on the bias landslide zone 8, and the small guide tubes 9 are vertically driven into the bias landslide zone 8 and fixed by grouting.

[0021] An initial support 12 is provided under the steel arch frame 11. The tunnel side wall of the initial support 12 on the mountain side is supported by steel mesh and sprayed concrete. The bottom of the initial support 12 is reinforced by grouting with a small grouting pipe to improve the bearing capacity of the tunnel opening base. A secondary lining structure 13 is provided in the initial support 12. The secondary lining structure 13 is made of concrete and can effectively withstand external loads and groundwater pressure to ensure the stability and durability of the structure.

[0022] A backfilling groove 10 is opened below the ground line 1. After the secondary lining structure 13 is completed by the initial support 12, C15 concrete can be backfilled in the backfilling groove 10.

[0023] Working principle:

[0024] Before tunnel construction, first clear the floating dangerous rocks on the slope of the ground line 1, level the ground to provide an operating platform, brush the slope and protect the sliding edges that affect the tunnel construction range, and inject grout into the small guide tube 9 vertically to the biased landslide zone 8 for reinforcement.

[0025] A groove is made at the position of the foundation 3, and reinforced concrete bored piles 2 are driven into the groove. After the foundation 3 is poured with reinforced concrete, the tops of the bored piles 2 are embedded in the foundation 3, and the bored piles 2 are evenly spaced along the longitudinal direction.

[0026] A steel arch frame 11 is arranged on the foundation 3 to protect the arch ear wall 4. The steel arch frame 11 can bear a heavy load in a large-span building and can disperse the load to make the building more stable.

[0027] An initial support 12 is provided under the steel arch frame 11. The tunnel side wall of the initial support 12 on the mountain side is supported by steel mesh and sprayed concrete. The bottom of the initial support 12 is reinforced by grouting with a small grouting pipe to improve the bearing capacity of the tunnel opening base. A secondary lining structure 13 is provided in the initial support 12. The secondary lining structure 13 is composed of concrete and can effectively withstand external loads and groundwater pressure to ensure the stability and durability of the structure. The secondary lining structure 13 helps to optimize the tunnel's drainage system, ensure the dryness of the tunnel interior, and prevent structural damage caused by water infiltration.

[0028] A row of pipe-roof pillars 14 are connected through the middle of the guard arch 1 6, the guard arch 2 601 and the guard arch 3 602. The pipe-roof pillars 14 are used to prevent soil collapse and ground subsidence. One end of the guard arch 1 6, the guard arch 2 601 and the guard arch 3 602 is on the support end 5, and the other end of the guard arch 1 6, the guard arch 2 601 and the guard arch 3 602 is fixed to the rock mass in the biased landslide zone 8 through a fixedly connected locking anchor pipe 7. The locking anchor rod 7 passes through the rock and soil mass to form a compression zone within a certain range, driving the loose soil layer to be reinforced by the anchor rod.

[0029] The cross-sectional dimensions of guard arch 1 6 are 2m×0.7m, with an arc length of 14.4m; the cross-sectional dimensions of guard arch 2 601 are 6m×0.7m, with an arc length of 12.3m; the cross-sectional dimensions of guard arch 3 602 are 12m×0.7m, with an arc length of 7.7m. The arc lengths of the guard arches decrease successively, which reduces material costs and saves construction time. The arc length and length of the guard arches are set in sections according to the terrain to reduce disturbance to the excavation side slope and surrounding rock, and ensure construction safety.

[0030] A backfilling groove 10 is opened below the ground line 1. After the secondary lining structure 13 is completed in the initial support 12, the backfilling groove 10 is backfilled with C15 concrete.

[0031] In the description of the present invention, it should be understood that the terms "upper", "lower", "front", "back", "left", "right", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.

[0032] Finally, it should be pointed out that the above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit them. Although the utility model is described in detail with reference to the above embodiments, a person skilled in the art should understand that the technical solutions described in the above embodiments can still be modified, or some of the technical features can be replaced by equivalents, and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the utility model.

Claims

1. A shallow buried biased tunnel portal long arch structure, comprising a ground line (1) and a foundation (3), characterized in that: The foundation (3) is fixedly connected to a steel arch frame (11) and an arch protection ear wall (4); an arch protection first (6), an arch protection second (601) and an arch protection third (602) are fixedly connected to the steel arch frame (11); and a support end (5) is provided on the left side of the arch protection ear wall (4).

2. A shallow buried biased tunnel portal long arch structure according to claim 1, characterized in that: Cast-in-place piles (2) are arranged under the foundation (3). The cast-in-place piles (2) are reinforced concrete bored cast-in-place piles. The tops of the cast-in-place piles (2) are embedded in the foundation (3). The cast-in-place piles (2) are distributed at equal intervals in the longitudinal direction.

3. The shallow buried biased tunnel portal long arch structure according to claim 2 is characterized by: One side of the arch guard one (6), the arch guard two (601) and the arch guard three (602) is on the support end (5), and the other end of the arch guard one (6) is fixedly connected to two locking anchor rods (7), and the locking anchor rods (7) are fixed on the rock mass in the biased landslide zone (8).

4. The shallow buried biased tunnel portal long arch structure according to claim 3 is characterized by: A row of pipe support pillars (14) are connected through the first protective arch (6), the second protective arch (601) and the third protective arch (602), and a row of small pipes (9) are provided on the biased landslide zone (8). The small pipes (9) are vertically driven into the biased landslide zone (8) and fixed by grouting.

5. The shallow buried biased tunnel portal long arch structure according to claim 4, characterized in that: An initial support (12) is provided under the steel arch frame (11), and the tunnel side wall of the initial support (12) is supported by a steel mesh and sprayed concrete. The bottom of the initial support (12) is reinforced by a small grouting pipe. A secondary lining structure (13) is provided inside the initial support (12), and the secondary lining structure (13) is made of concrete and can effectively withstand external loads and groundwater pressure.

6. The shallow buried biased tunnel portal long arch structure according to claim 5, characterized in that: A backfill groove (10) is provided below the ground line (1), and after the secondary lining structure (13) is completed by the initial support (12), the backfill groove (10) is backfilled with C15 concrete.