High-load-bearing ventilation pipe mounting bracket
By designing a high-load-bearing ventilation duct installation bracket, using a U-shaped carrier, side plate frame and pulling components, the problem of unstable ventilation duct installation in the tunnel is solved, achieving more stable ventilation duct connections and lower installation difficulty.
Patent Information
- Application Number
- CN202420997114.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-10
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-05-10
AI Technical Summary
Due to the large area and heavy weight of the ventilation duct in the tunnel, it is unstable to install through the steel frame, and the pipe shaking easily after the pressed airflow enters, which increases the load-bearing difficulty of the installation bracket.
A high load-bearing ventilation duct mounting bracket is designed, including a U-shaped carrier, a symmetrically arranged side panel rack, pull-out rack, auxiliary pull-out rod and nut, connecting screw, mounting ring and folding rack, providing additional Support and limit structures increase the load-bearing capacity of the carrier.
Through this bracket structure, the installation stability and load-bearing capacity of the ventilation duct are improved, the stable connection of the ventilation duct is ensured, and the installation difficulty is reduced.
Smart Images

Figure CN222121594U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of exhaust pipe installation, in particular to a high-load-bearing ventilation pipe installation bracket. Background Art
[0002] As tunnel excavation progresses, the depth of the tunnel gradually increases and the oxygen content in the air in the tunnel decreases. It is necessary to add ventilation equipment in the tunnel. The layout of the construction ventilation system must meet the minimum ventilation volume for normal breathing of construction personnel, dilution of mechanical exhaust and harmful gases, and cooling, and meet the minimum wind speed in the cavern to provide a more suitable working environment for the tunnel construction site.
[0003] Most of the existing tunnel ventilation structures are installed on the top of the safety hole. Due to the large area of the tunnel, the ventilation pipe area is large and heavy. The support structure installed only by the steel frame is unstable at the pipe connection. As the forced airflow enters the pipe, it is easy to cause the pipe to shake, making it more difficult for the installation bracket connection to fall off and bear the load. Utility Model Content
[0004] The purpose of the utility model is to provide a high-load-bearing ventilation duct mounting bracket to solve the problem in the above-mentioned background technology that the area inside the tunnel is large, which makes the ventilation duct area large and heavy, and the bracket structure installed only by the steel frame is unstable at the pipe connection. Moreover, as the forced airflow enters the pipe, the pipe is easily shaken, which increases the load-bearing difficulty of the mounting bracket.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a high-load-bearing ventilation pipe mounting bracket, comprising a bearing frame, which is arranged in a U-shaped frame result, and the bearing frame is installed at the bottom end of the ventilation duct;
[0006] Side plate frames are symmetrically arranged on both sides of the bearing frame, and the side plate frames and the bearing frame provide the main structure for the installation of the ventilation pipe;
[0007] A pulling frame is symmetrically arranged on the upper end of the U-shaped structure of the carrier frame, and a mounting plate is vertically installed on the top of the pulling frame, the side end of the side plate frame is threadedly connected with the bottom end of the auxiliary pulling rod, and a positioning nut is threadedly connected to the bottom end of the auxiliary pulling rod, and an auxiliary connecting plate is vertically arranged on the top end of the auxiliary pulling rod;
[0008] The connecting screw rod 1 is symmetrically connected to the surface of the mounting plate, and the two sides of the mounting plate are penetrated by the connecting screw rod 2, and the center of the connecting screw rod 2 is horizontally equidistant from the center of the connecting screw rod 1, and the surface of the connecting screw rod 2 is sleeved with
[0009] The auxiliary pulling assembly and the auxiliary bearing frame are used to limit the installation of the ventilation pipe, thereby increasing the load-bearing effect of the bearing frame.
[0010] The adoption of the above technical solution facilitates the provision of a bracket structure for installing the ventilation pipe, thereby improving the installation of the ventilation pipe.
[0011] Preferably, side rods are symmetrically and equidistantly arranged on both sides of the support frame, and the side rod ports are snap-connected to the inside of the side wall surface of the side arc plate, and the curvature of the side arc plate is consistent with the curvature of the support frame.
[0012] By adopting the above technical solution, the side arc plate and the supporting frame are matched to form an integral structure connected to the ventilation pipe.
[0013] Preferably, the side panel frame is arranged in parallel with the auxiliary connecting plate and the mounting plate, and the side panel frame and the supporting frame are an integral structure.
[0014] By adopting the above technical solution, the side panel frame and the supporting frame are integrated into an integral structure to provide a stable connection.
[0015] Preferably, the auxiliary pulling assembly comprises:
[0016] A mounting ring, which is arranged on the second surface of the connecting screw in a coaxial and vertical direction;
[0017] A folding frame, both ends of which are connected to the surface of one of the mounting rings, and two mounting rings arranged in a vertical direction and four folding frames form a group structure;
[0018] Mounting rods are symmetrically arranged at two upper ends of the side arc plates, and a stepped inner cavity structure is arranged inside the mounting rods;
[0019] The pulling ring is concentrically sleeved on the two surfaces of the connecting screw rod, and the pulling ring is arranged below the mounting plate.
[0020] By adopting the above technical solution, the auxiliary pulling assembly provides support for the ventilation pipe to perform the load-bearing work.
[0021] Preferably, each set of the mounting ring and the folding frame is located at a thread of a connecting screw rod 2 and is connected to the connecting screw rod 2.
[0022] By adopting the above technical solution, each group of two mounting rings and four folding frames are installed and held in position by two connecting screws.
[0023] Preferably, the stepped inner cavity structure inside the mounting rod is connected to the spherical structure at one end of the steel wire rope, and spherical structures are provided at both ends of the steel wire rope.
[0024] By adopting the above technical solution, the stepped inner cavity structure inside the mounting rod is used to limit the ball at one end of the wire rope.
[0025] Preferably, grooves connected to the sphere at the other end of the steel wire rope are symmetrically arranged on both sides of the pulling ring, and the connection between the pulling ring and the steel wire rope passes through the opening of the second plate body of the connecting screw.
[0026] By adopting the above technical solution, the pulling ring and the installation rod are connected and pulled through the spherical structures at both ends of the wire rope.
[0027] Compared with the prior art, the utility model has the following beneficial effects: the high load-bearing ventilation pipe mounting bracket:
[0028] 1. When in use, the ventilation pipe is wrapped and supported by the support frame and the side arc plate. The support frame and the side arc plate are stably installed through the side rods. The support frame forms a connection for pulling and bearing through the pulling frame arranged at the top and the mounting plate. The side plate frames on both sides of the support frame are connected to the tunnel compaction position by the auxiliary pulling rod and the positioning nut connecting frame, and are connected with the bolts through the auxiliary connecting plate to assist in providing support for the ventilation pipe on the support frame;
[0029] 2. Through a set of mounting rings, the folding frame is directly connected to the connection point of the second connecting screw rod. After the second connecting screw rod is rotated, it is installed on the top of the tunnel. The pulling ring at the bottom end of the second connecting screw rod is installed through the mounting rods on both sides of the opposite side arc plate of the wire rope to limit the side arc plate so that the side arc plate can bear the load at the installation point of the ventilation pipe. As the second connecting screw rod rotates, the two mounting rings in the same group are closed, so that the folding frame is folded outward, increasing the stability of the connection. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 This is a schematic diagram of the overall external three-dimensional structure of the utility model;
[0031] Figure 2 This is a schematic diagram of the overall internal three-dimensional structure of the utility model;
[0032] Figure 3 This is a schematic diagram of the overall internal side section stereoscopic structure of the utility model;
[0033] Figure 4 This is a schematic diagram of the three-dimensional structure of the mounting frame and the side rod of the utility model;
[0034] Figure 5 This is a schematic diagram of the three-dimensional structure of the installation position of the connecting screw rod 2 and the side arc plate of the utility model;
[0035] Figure 6 It is a schematic diagram of the three-dimensional structure of the steel wire rope and the installation rod of the utility model.
[0036] In the figure: 1. load-bearing frame; 2. side plate frame; 3. auxiliary pulling rod; 4. positioning nut; 5. auxiliary connecting plate; 6. side rod; 7. pulling frame; 8. mounting plate; 9. connecting screw rod 1; 10. connecting screw rod 2; 11. mounting ring; 12. folding frame; 13. wire rope; 14. mounting rod; 15. pulling ring; 16. side arc plate. DETAILED DESCRIPTION
[0037] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0038] See also Figure 1-6 The utility model provides a technical solution: a high-load-bearing ventilation pipe mounting bracket, including a bearing frame 1, a side plate frame 2, an auxiliary pulling rod 3, a positioning nut 4, an auxiliary connecting plate 5, a side rod 6, a pulling frame 7, a mounting plate 8, a connecting screw rod 1 9, a connecting screw rod 2 10, a mounting ring 11, a folding frame 12, a steel wire rope 13, a mounting rod 14, a pulling ring 15 and a side arc plate 16;
[0039] Among them, the support frame 1 is set as a U-shaped frame result, and the support frame 1 is installed at the bottom end of the ventilation duct, and the side rods 6 are symmetrically and equidistantly arranged on both sides of the support frame 1, and the ports of the side rods 6 are snap-connected to the inside of the side wall surface of the side arc plate 16, and the curvature of the side arc plate 16 is consistent with the curvature of the support frame 1;
[0040] The side plate frame 2 is symmetrically arranged on both sides of the bearing frame 1, and the side plate frame 2 and the bearing frame 1 provide a main structure for the ventilation pipe installation, the side plate frame 2 is arranged in parallel with the auxiliary connecting plate 5 and the mounting plate 8, and the side plate frame 2 and the bearing frame 1 are an integrated structure;
[0041] A pulling frame 7 is symmetrically arranged at the upper end of the U-shaped structure of the carrier frame 1, and a mounting plate 8 is vertically installed at the top of the pulling frame 7. The side end of the side plate frame 2 is threadedly connected to the bottom end of the auxiliary pulling rod 3, and a positioning nut 4 is threadedly connected to the bottom end of the auxiliary pulling rod 3, and an auxiliary connecting plate 5 is vertically arranged at the top end of the auxiliary pulling rod 3;
[0042] The connecting screw rod 1 9 is symmetrically connected to the surface of the mounting plate 8, and the two sides of the mounting plate 8 are penetrated by the connecting screw rod 2 10, and the center of the connecting screw rod 2 10 is horizontally equidistant from the center of the connecting screw rod 1 9, and the surface of the connecting screw rod 2 10 is sleeved with an auxiliary pulling component, and the auxiliary bearing frame 1 is limited for the installation of the ventilation pipe, so that the load-bearing effect of the bearing frame 1 is increased;
[0043] In conjunction with the accompanying drawings Figure 1-6 As shown, the side frame 2 installed on both sides of the carrier frame 1 is an integrated structure, and the auxiliary pulling rod 3 connected with the inner thread of the side frame 2 is tightly connected with the positioning nut 4, as shown in FIG. Figure 1-4 As shown, the auxiliary connecting plate 5 at the top of the auxiliary pulling rod 3 forms a T-shaped structure. As the auxiliary connecting plate 5 cooperates with the bolts, it is directly installed on the top of the tunnel. The pulling frame 7 and the mounting plate 8 arranged at the top of the supporting frame 1 are L-shaped structures, as shown in FIG. Figure 1-5 As shown, the pulling frame 7 is connected to the supporting frame 1 by bolts, the semicircular curvature of the supporting frame 1 is adjusted according to the diameter of different ventilation pipes, and the side rods 6 and side arc plates 16 arranged on both sides of the supporting frame 1 are installed, as shown in FIG. Figure 1-4 As shown, the curvature of the side arc plate 16 is consistent with that of the bearing frame 1, both are located at the bottom of the ventilation duct, bearing the ventilation duct, and simultaneously increasing the contact area between the bearing frame 1 and the side arc plate 16. The mounting plate 8 at the top of the pulling frame 7 is installed by connecting the screw rod 9, as shown in FIG. Figure 1-4 As shown, the connecting screw 1 9 penetrates the top of the tunnel hole for installation and positioning, so that the connecting screw 1 9 cooperates with the connecting screw 2 10 to support and install the pulling frame 7 and the bearing frame 1 to support the ventilation pipe, as shown in FIG. Figure 1-4 As shown, the installation position of the ventilation pipe is increased;
[0044] The auxiliary pulling components include:
[0045] The mounting ring 11 is coaxially arranged on the surface of the connecting screw rod 10 in a vertical direction, and each set of the mounting ring 11 and the folding frame 12 is located at the thread of one connecting screw rod 10, and the connecting screw rod 10;
[0046] The two ends of the folding frame 12 are respectively connected to the surface of a mounting ring 11, and the two mounting rings 11 arranged in a vertical direction and the four folding frames 12 form a group structure;
[0047] The mounting rods 14 are symmetrically arranged at two upper ends of the side arc plates 16, and a stepped inner cavity structure is arranged inside the mounting rods 14. The stepped inner cavity structure inside the mounting rods 14 is connected to the spherical structure at one end of the wire rope 13, and both ends of the wire rope 13 are provided with spherical structures;
[0048] The pulling ring 15 is concentrically sleeved on the surface of the connecting screw rod 10, and the pulling ring 15 is arranged below the mounting plate 8. The two sides of the pulling ring 15 are symmetrically provided with grooves connected to the ball at the other end of the wire rope 13, and the connection between the pulling ring 15 and the wire rope 13 passes through the opening of the connecting screw rod 10 plate;
[0049] In conjunction with the accompanying drawings Figure 1-6 As shown, a set of structures consisting of two vertically arranged mounting rings 11 and four folding frames 12 is installed outside the connecting screw rod 10, as shown in FIG. Figure 1-6 As shown, the pulling ring 15 is installed between the outer wall of the connecting screw 10 and the bottom end of the mounting plate 8, and the openings arranged on both sides of the pulling ring 15 are as shown in FIG. Figure 2-6 As shown, as the pulling ring 15 pulls one end of the two steel wire ropes 13 on the same side, the other end of the steel wire rope 13 is pulled with the mounting rod 14, so that the mounting rod 14 drives the side arc plate 16 to support the bottom end of the ventilation pipe, so that the side arc plate 16 cooperates with the supporting frame 1 to install and limit the ventilation pipe, thereby improving the load-bearing effect on the ventilation pipe. As the connecting screw rod 10 rotates, the two mounting rings 11 in the same group are brought closer, so that the folding frame 12 is folded and extended, so that the folding frame 12 is inserted into the tunnel installation position to maintain stability.
[0050] Working principle: When using the high-load-bearing ventilation pipe installation bracket, the side arc plate 16 is provided with an installation position through the support frame 1 and the side rods 6 symmetrically arranged on both sides, wherein the side arc plate 16 and the support frame 1 provide support and load-bearing for the ventilation duct installed at the top of the processing area, and the pulling frame 7 and the mounting plate 8 cooperate with the top of the support frame 1 to perform installation and limit, which is used to connect the support frame 1 and the top of the installation area for installation, and the connecting screw 9 penetrates the mounting plate 8 for positioning, and the auxiliary pulling rod 3 installed at the top of the side plate frame 2 is connected with the positioning nut 4 The auxiliary connecting plate 5 located at the top of the auxiliary pulling rod 3 increases the installation connection with the processed top to improve the load-bearing effect. The connecting screw 10 at the top of the mounting plate 8 is inserted through the pulling ring 15, and then a group of mounting rings 11 and a folding frame 12 are sleeved on the surface. The connecting screw 10 cooperates with the rotation of the connecting screw 10, so that the connecting screw 10 provides a limit for the installation of the mounting plate 8. The steel wire rope 13 connected to the bottom end of the pulling ring 15 pulls the side arc plate 16 when the mounting rod 14 is installed, so that the side arc plate 16 is used to pull the ventilation pipe, which increases the overall practicality.
[0051] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A high load-bearing ventilation pipe mounting bracket, comprising: The support frame (1) is arranged in a U-shaped frame body, and the support frame (1) is installed at the bottom end of the ventilation duct; Side plate frames (2) are symmetrically arranged on both sides of the supporting frame (1), and the side plate frames (2) and the supporting frame (1) provide a main structure for the installation of the ventilation pipe; The invention is characterized in that: a pulling frame (7) is symmetrically arranged at the upper end of the U-shaped structure of the carrier frame (1), and a mounting plate (8) is vertically installed at the top end of the pulling frame (7), the side end of the side plate frame (2) is threadedly connected to the bottom end of the auxiliary pulling rod (3), and a positioning nut (4) is threadedly connected to the bottom end of the auxiliary pulling rod (3), and an auxiliary connecting plate (5) is vertically installed at the top end of the auxiliary pulling rod (3); The connecting screw rod 1 (9) is symmetrically connected to the surface of the mounting plate (8), and the two sides of the mounting plate (8) are penetrated by the connecting screw rod 2 (10), and the center of the connecting screw rod 2 (10) is arranged horizontally equidistant from the center of the connecting screw rod 1 (9), and the surface of the connecting screw rod 2 (10) is sleeved with The auxiliary pulling assembly and the auxiliary bearing frame (1) are used to limit the installation of the ventilation pipe, thereby increasing the load-bearing effect of the bearing frame (1).
2. The high load-bearing ventilation pipe mounting bracket according to claim 1, characterized in that: Side rods (6) are symmetrically and equidistantly arranged on both sides of the support frame (1), and the ends of the side rods (6) are snap-connected to the inside of the side wall surface of the side arc plate (16), and the curvature of the side arc plate (16) is consistent with the curvature of the support frame (1).
3. The high load-bearing ventilation pipe mounting bracket according to claim 1, characterized in that: The side plate frame (2) is arranged in parallel with the auxiliary connecting plate (5) and the mounting plate (8), and the side plate frame (2) and the supporting frame (1) are an integral structure.
4. The high load-bearing ventilation pipe mounting bracket according to claim 2, characterized in that: The auxiliary pulling component comprises: A mounting ring (11) which is arranged on the surface of the second connecting screw rod (10) in a coaxial and vertical direction; A folding frame (12), both ends of which are respectively connected to the surface of one of the mounting rings (11), and two mounting rings (11) arranged in a vertical direction and four folding frames (12) form a group structure; Two mounting rods (14) are symmetrically arranged at the upper ends of the side arc plates (16), and a stepped inner cavity structure is arranged inside the mounting rods (14); The pulling ring (15) is concentrically sleeved on the surface of the second connecting screw rod (10), and the pulling ring (15) is located below the mounting plate (8).
5. The high load-bearing ventilation pipe mounting bracket according to claim 4, characterized in that: Each set of the mounting ring (11) and the folding frame (12) is located at the thread of a connecting screw rod (10) and is connected to the connecting screw rod (10).
6. The high load-bearing ventilation pipe mounting bracket according to claim 4, characterized in that: The stepped inner cavity structure inside the installation rod (14) is connected to the spherical structure at one end of the steel wire rope (13), and both ends of the steel wire rope (13) are provided with spherical structures.
7. The high load-bearing ventilation pipe mounting bracket according to claim 4, characterized in that: The pulling ring (15) is symmetrically provided with grooves connected to the ball at the other end of the steel wire rope (13) on both sides, and the connection between the pulling ring (15) and the steel wire rope (13) passes through the opening of the plate body of the second connecting screw rod (10).