Pipeline outer seam processing mechanism

By using a combined structure of the grouting belt of the closed-cell foam plate and bamboo sheets connected to the peripheral skeleton, the problems of grouting and slurry leakage in the outer joints of the PCCP pipeline are solved, and the construction efficiency and quality are improved.

CN222122567UActive Publication Date: 2024-12-06中国水利水电第七工程局有限公司
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202323669966.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-30
Publication Date
2024-12-06
Estimated Expiration
2033-12-30

AI Technical Summary

Technical Problem

In the PCCP pipeline external joint treatment, flexible formwork materials are prone to bulging and leaking slurry when wrapped and grouting, which affects construction efficiency and quality.

Method used

The combined structure of closed-cell foam board grouting belt, peripheral frame, wire tightener, wire wire and connecting bolt is adopted. The grouting belt is made close to the outer wall of the pipe through a tensioning mechanism, and the peripheral frame and grouting formed by bamboo slicing are used to connect the bamboo. Check the holes to ensure that the mortar does not flow out easily.

Benefits of technology

Effectively prevent mortar leakage, improve the construction efficiency and quality of the outer joints of the pipeline, and ensure that the mortar in the filling joint is full and not easy to leak slurry.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222122567U_ABST
    Figure CN222122567U_ABST
Patent Text Reader

Abstract

The utility model discloses a pipeline outer seam processing mechanism which is used for auxiliary grouting sealing of a large-pipe-diameter PCCP (prestressed concrete cylinder pipe) connector circular seam outer seam and comprises a grouting wrapping tape and a peripheral framework. The grouting wrapping belt is arranged around the circumferential seam wall of the pipeline connector through an elastic closed-cell foam plate, the outer wall of the grouting wrapping belt tightly covers the peripheral framework, and a grouting inlet is pre-formed between the grouting wrapping belt and the peripheral framework connector; two sets of tighteners are arranged at the position of a grouting inlet, the two sets of tighteners are connected through steel wires, the other ends of the two sets of tighteners are connected with a grouting wrapping tape and a peripheral framework in a tensioning mode through steel wires, and the grouting wrapping tape and the peripheral framework are arranged around a pipeline connector circular seam in a tensioning and attaching mode. The closed-cell foam board grouting wrapping tape is of a flexible structure and can fill the concave portion of the outer wall of the pipeline under the action of external force of the peripheral framework, mortar is not prone to flowing out, the closed-cell foam board grouting wrapping tape is light in self weight and has elasticity and strength, it can be guaranteed that the mortar in a pouring crack is full and not prone to leakage, and the construction efficiency and quality of the outer joint of the pipeline are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipeline inner and outer seam processing, and more specifically to a high-efficiency pipeline outer seam processing mechanism. Background Art

[0002] PCCP pipe is a prestressed steel cylinder concrete pipe, which belongs to rigid pipe material and is a concrete steel cylinder with high strength. PCCP pipe is a type of water pipe made by surrounding the pipe core with annular prestressed steel wire and then spraying a fine cement mortar protective layer. After the PCCP pipe is laid and installed, it is usually necessary to seal the outer and inner seams of the pipe to prevent water leakage from the gaps in the pipe.

[0003] At present, the inner and outer seams of large-diameter PCCP pipes are usually treated separately. When the outer seam is treated, a flexible formwork material is usually used as a wrapping tape to wrap the outer seam of the PCCP pipe for grouting. However, when the flexible formwork material is used for wrapping and grouting, the grouting mortar will bulge and leak due to the softness of the flexible formwork material, affecting the construction efficiency and quality of the outer seam. Summary of the invention

[0004] The utility model discloses a pipeline outer seam processing mechanism. The utility model aims to provide a pipeline outer seam processing mechanism to solve the problem of bulging and leakage of grouting mortar in pipeline outer seam processing, which affects the construction efficiency and quality of the outer seam.

[0005] The utility model provides the following technical solutions:

[0006] A pipeline outer seam processing mechanism, characterized in that: the processing mechanism is used for auxiliary grouting and sealing of the outer seam of the annular seam of a large-diameter PCCP pipeline interface, comprising a grouting bag and an outer peripheral frame;

[0007] The grouting tape is composed of an elastic closed-cell foam board and is arranged around the annular seam wall of the pipe interface. The outer wall of the grouting tape tightly covers the peripheral frame, and a grouting inlet is pre-arranged between the joint of the grouting tape and the peripheral frame. Two sets of tensioners are arranged at the grouting inlet, and the two sets of tensioners are connected by steel wires. The other ends of the two sets of tensioners are tensioned and connected to the grouting tape and the peripheral frame by steel wires, so that the grouting tape and the peripheral frame are tensioned and arranged around the annular seam of the pipe interface.

[0008] The peripheral frame is formed by connecting bamboo pieces in series.

[0009] Furthermore, connecting bolts are arranged at the joints on both sides of the grouting belt and the peripheral frame. The connecting bolts pass through the bamboo pieces at the joint ends of the peripheral frame and are connected and fixed to the grouting belt. The steel wire at the other end of the tensioner is tensioned and connected to the connecting bolts.

[0010] Furthermore, six openable and closable grouting inspection holes are arranged at intervals on the grouting bag.

[0011] Furthermore, the thickness of the bamboo pieces is one centimeter, the length direction of the bamboo pieces is arranged parallel to the axial direction of the pipeline, and is connected in series through two steel wire ropes arranged parallel to the circumference of the pipeline to form a wrappable soft armor structure.

[0012] Technical effects and advantages of the utility model:

[0013] The utility model facilitates the construction of the outer seam of the outer wall of the pipeline by adopting the cooperation of a closed-cell foam board grouting tape, an outer peripheral skeleton, a tightening device, a steel wire, a connecting bolt and a grouting inspection hole. The closed-cell foam board grouting tape is made of a flexible material and can fill the concave part of the outer wall of the pipeline under the external force of the outer peripheral skeleton, so that the mortar is not easy to flow out. The closed-cell foam board material is used as the grouting tape, and the template of the outer peripheral skeleton composed of a closed-cell foam board and a plurality of bamboo boards is used. The closed-cell foam board has its own light weight and has certain elasticity and strength, which ensures that the mortar in the grouting seam is full and not easy to leak, thereby improving the construction efficiency and quality of the outer seam of the pipeline. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a schematic diagram of the overall structure of the utility model.

[0015] Figure 2 It is a partial schematic diagram of the pipeline outer seam structure of the utility model.

[0016] Figure 3 It is a schematic diagram of the grouting inspection hole structure of the utility model.

[0017] Figure 4 It is a top view schematic diagram of the outer seam mechanism structure of the utility model.

[0018] The accompanying drawings are marked as follows: 1 is a large-diameter PCCP pipeline, 2 is an outer seam of the pipeline, 21 is a grouting tape, 211 is a grouting inlet, 22 is an outer peripheral frame, 23 is a tensioner, 24 is a steel wire, 25 is a connecting bolt, and 26 is a grouting inspection hole. DETAILED DESCRIPTION

[0019] The present invention is further described below in conjunction with specific implementation methods. The specific implementation methods are further descriptions of the principles of the present invention and do not limit the present invention in any way. Technologies that are the same or similar to the present invention do not exceed the scope of protection of the present invention.

[0020] like Figure 1-4 As shown, the efficient pipeline outer seam processing mechanism of this embodiment includes a large-diameter PCCP pipeline 1, and a pipeline outer seam 2 included in the outer wall of the pipeline is formed between adjacently installed large-diameter PCCP pipelines 1.

[0021] When grouting the outer seam 2 of the pipe is performed, the processing mechanism of the present embodiment is adopted, and the processing mechanism includes a closed-cell foam board grouting tape 21, and the closed-cell foam board grouting tape 21 is arranged around the outer wall of the outer seam 2 of the large-diameter PCCP pipe 1, and the outer wall of the closed-cell foam board grouting tape 21 is surrounded by an outer peripheral skeleton 22, and the outer peripheral skeleton 22 is made of a plurality of bamboo pieces, and the thickness of the bamboo pieces is one centimeter. There is no closed connection between the two ends of the closed-cell foam board grouting tape 21 and the outer peripheral skeleton 22, and a circumferential gap is reserved as a grouting inlet 211, and two tensioners 23 are installed at the grouting inlet 211, and the two tensioners 23 are connected by a steel wire 24, and each tensioner 23 is provided with a steel wire 24 on the other side, and is tensioned and connected with a connecting bolt 25 on one side through the tensioner 23. There are multiple connecting bolts 25 fixedly connected to the peripheral frame 22, each connecting bolt 25 passes through the bamboo piece at the end of the peripheral frame 22, and the lower part is fixedly connected to the outer wall of the closed-cell foam board grouting tape 21; the inner wall of the closed-cell foam board grouting tape 21 is coated with a release agent, and the closed-cell foam board grouting tape 21 is provided with grouting inspection holes 26, the number of the grouting inspection holes 26 is six, and the aperture of the six grouting inspection holes 26 is twenty millimeters.

[0022] In this embodiment, since the outer surface of the large-diameter PCCP pipe 1 is relatively rough and uneven, the material close to the outer wall of the pipe 1 must be flexible and can fill the concave part of the outer wall of the pipe under the action of external pressure to prevent the mortar from flowing out. A closed-cell foam board material is used as the grouting tape 21. The closed-cell foam board has an independent closed-cell bubble structure, and the honeycomb-like holes are evenly distributed. It is firmly and tightly integrated with the cement adhesive, and naturally adapts to the changes in expansion and contraction, thereby enhancing the expansion and water-stopping effect. It is also light in weight, has a certain elasticity and strength, and ensures that the mortar in the grouting is full and not easy to leak. The grouting mortar must have a large The fluidity can ensure dense grouting. In the top grouting, the mortar will first flow into the bottom of the pipe 1 and then gradually rise. The closed-cell foam board grouting belt 21 must not only bear the weight of the mortar but also the impact of the mortar fluidity, which cannot be borne by a single closed-cell foam board. The utility model adds a layer of rigid soft armor structure on the outside of the peripheral skeleton 22, and adopts a bamboo string with high strength and light weight as the peripheral skeleton 22. A plurality of grouting inspection holes 26 are provided on the closed-cell foam board grouting belt 21. The grouting inspection hole 26 is usually in a closed state. The grouting inspection hole 26 can be opened for inspection to check whether the outer seam grouting is full.

[0023] like Figures 1 to 4As shown, the efficient pipeline outer seam processing mechanism of this embodiment, when constructing the pipeline outer seam 2 of the large-diameter PCCP pipeline 1, first use a brush or other tools to clean the soil, debris, etc. in the pipeline outer seam 2, and use a high-pressure water gun to clean it when necessary, and then surround the closed-cell foam board grouting tape 21 around the pipeline outer seam 2 wall installed at the interface of the pipeline 1, and tighten the steel wire 24 through the tensioner 23, so that the outer peripheral skeleton 22 and the closed-cell foam board grouting tape 21 are tensioned and squeezed to fix the closed-cell foam board grouting tape 21 tightly to the outer wall of the pipeline 1, and then use 1:2.5 cement mortar with high fluidity to grout through the grouting inlet 211 for grouting, the mortar will first flow into the bottom of the pipeline, and then gradually rise, and after the mortar is filled, the grouting inlet 211 is filled and smoothed with dry hard mortar.

[0024] Finally, a few points should be explained: First, in the description of this application, it should be noted that, unless otherwise specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, and can be mechanical or electrical connections, or internal connectivity between two components, or direct connections. "Up", "down", "left", "right", etc. are only used to indicate relative position relationships. When the absolute position of the object being described changes, the relative position relationship may change.

Claims

1. A pipeline outer seam processing mechanism, characterized in that: The treatment mechanism is used for auxiliary grouting and sealing of the outer seam of the annular seam of the large-diameter PCCP pipeline interface, including a grouting bag and an outer peripheral frame; The grouting tape is composed of an elastic closed-cell foam board and is arranged around the annular seam wall of the pipe interface. The outer wall of the grouting tape tightly covers the peripheral frame, and a grouting inlet is pre-arranged between the joint of the grouting tape and the peripheral frame. Two sets of tensioners are arranged at the grouting inlet, and the two sets of tensioners are connected by steel wires. The other ends of the two sets of tensioners are tensioned and connected to the grouting tape and the peripheral frame by steel wires, so that the grouting tape and the peripheral frame are tensioned and arranged around the annular seam of the pipe interface.

2. The pipeline outer seam processing mechanism according to claim 1, characterized in that: The peripheral frame is formed by connecting bamboo pieces in series.

3. The pipeline outer seam processing mechanism according to claim 2, characterized in that: Connecting bolts are arranged at the joints on both sides of the grouting belt and the peripheral frame. The connecting bolts pass through the bamboo pieces at the joint ends of the peripheral frame and are connected and fixed to the grouting belt. The steel wire at the other end of the tensioner is tensioned and connected to the connecting bolts.

4. The pipeline outer seam processing mechanism according to claim 2, characterized in that: The grouting bag is provided with six openable and closable grouting inspection holes at intervals.

5. The pipeline outer seam processing mechanism according to claim 2, characterized in that: The thickness of the bamboo pieces is one centimeter. The length direction of the bamboo pieces is arranged parallel to the axial direction of the pipeline and is connected in series through two steel wire ropes arranged in parallel around the circumference of the pipeline to form a wrappable soft armor structure.

Citation Information

Cited By

  • Method and device for filling mortar for crack pouring of pipeline butt joint

    CN120777430A

  • Pipeline butt joint gap filling mortar filling method and filling device

    CN120777430B

  • Movable cement stirring and crack pouring device

    CN122191373A