Buffer gas power generation system
The buffer gas power generation system optimizes gas utilization by controlling flow through a time comparator to generate electricity during peaks, enhancing economic value and reducing costs.
Patent Information
- Application Number
- CN202420571918.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-03-21
AI Technical Summary
The gas stored in the gas tank of long-process metallurgical casting enterprises cannot be utilized to maximize its economic value due to being consumed continuously, leading to inefficiencies in electricity cost management, especially during peak and valley electricity prices.
A buffer gas power generation system that includes a gas tank, generator set, and flow regulating valve, controlled by a time comparator to optimize gas flow during peak electricity periods, ensuring maximum power generation and storage during off-peak periods.
Maximizes the economic value of stored gas by generating electricity during peak periods, reducing enterprise electricity costs and minimizing gas waste.
Smart Images

Figure CN222122897U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of energy saving, in particular to a buffer gas power generation system. Background Art
[0002] Long-process metallurgical casting enterprises have main production processes such as coking, ironmaking and steelmaking. Coke coal is distilled in a coke oven in an air-tight manner to produce coke oven gas; blast furnace gas is produced during blast furnace smelting; and converter gas is produced during converter steelmaking. These three types of gas are supplied to production equipment such as hot blast stoves and heating furnaces through the enterprise's gas pipeline network to provide thermal energy for the production equipment. The remaining gas after use by the production unit will be stored in the gas tank and burned in a gas boiler to generate electricity, thereby reducing the company's purchase of electricity and reducing the company's electricity costs.
[0003] Since the gas in the gas tank needs to maintain a low pressure state so that the gas in the enterprise's gas pipeline network can flow from the gas production equipment through the production equipment and finally be collected in the gas tank, the gas stored in the current gas tank is used as needed. The gas in the gas tank is continuously consumed by the generator set so that the pressure in the gas tank is always lower than the pressure at various locations in the enterprise's gas pipeline network. Ultimately, the gas in the enterprise's gas pipeline network can be collected in the gas tank under the action of system pressure, thereby avoiding gas overflow in the enterprise's gas pipeline network and causing gas waste.
[0004] However, the gas in the gas tank cannot correspond to the peak and valley electricity prices if it is stored and used at any time, so the gas cannot play the greatest economic value. Utility Model Content
[0005] In order to overcome the problem in the prior art that the gas stored in the gas tank can be used at any time and cannot exert its maximum economic value, the utility model provides a buffer gas power generation system, which includes a flow regulating valve, and controls the flow regulating valve by setting a comparator, thereby controlling the buffer gas power generation system to increase the power generation during peak power periods, so as to reduce the electricity costs of the enterprise.
[0006] In order to achieve the above-mentioned purpose, the utility model provides a buffer gas power generation system, which includes a gas tank, a generator set and a gas transmission pipe for connecting the gas tank and the generator set, the gas tank is connected to the enterprise gas pipeline network to buffer the excess gas in the enterprise gas pipeline network, and the generator set is connected to the power grid;
[0007] The gas delivery pipe is provided with a flow regulating valve for regulating the flow of gas in the gas delivery pipe;
[0008] The buffer gas power generation system also includes a time comparator, which compares the current absolute time with the standard time set in the comparator and controls the flow control valve according to the comparison result.
[0009] Preferably, the gas tank is provided with a pressure gauge for detecting the gas pressure in the gas tank.
[0010] Preferably, the buffer gas power generation system further comprises a second comparator, which compares the current value of the pressure gauge with the standard pressure set in the comparator;
[0011] The second comparator is used to end the control of the flow regulating valve by the time comparator.
[0012] Preferably, a flow meter is provided at the inlet of the gas tank.
[0013] According to the above technical solution, the generator set is connected to the gas tank through a gas transmission pipe. The generator set continuously consumes the gas in the gas tank to keep the gas in the gas tank in a low-pressure state, so that excess gas in the enterprise's gas pipeline network will be collected in the gas tank, thereby realizing the collection of excess gas.
[0014] A flow regulating valve is provided on the gas transmission pipe, which controls the amount of gas flowing into the generator set. When the gas flowing into the gas tank increases, the flow rate of the flow regulating valve can be increased to consume more gas. When the gas flowing into the gas tank decreases, the flow rate of the flow regulating valve can be reduced to avoid exhausting the gas in the gas tank.
[0015] The buffer gas power generation system is equipped with a time comparator, which enables the buffer gas power generation system to control the flow regulating valve according to the actual time so as to reduce the flow rate of the flow regulating valve before the peak electricity arrives, so that the gas in the gas tank continues to increase, and the gas is stored in the gas tank so that when the peak electricity arrives, the gas tank can store enough gas. The time comparator compares the current absolute time with the set standard time to confirm that the peak electricity has begun, and then controls the flow regulating valve to open to the maximum value, and the generator set generates electricity at the maximum power. By using gas to generate electricity autonomously, during the peak electricity period, the enterprise can obtain as much self-generated electricity as possible through the gas stored in the gas tank, so as to reduce the enterprise's consumption of peak electricity, thereby reducing the enterprise's electricity cost.
[0016] Therefore, by setting a time comparator in the buffer gas power generation system, the power generation of gas during peak power can be maximized, so that the gas in the gas tank can obtain the maximum economic value. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1It is a schematic diagram of a buffered gas power generation system.
[0018] Description of Reference Numerals
[0019] 1 Gas tank 2 Generator set
[0020] 3 Gas delivery pipe 4 Flow control valve DETAILED DESCRIPTION
[0021] In the present invention, unless otherwise stated, directional words such as "away from, up, down, sideways, both ends" generally refer to the orientation of the term in normal use, or are common names understood by those skilled in the art, and should not be regarded as limitations on the term.
[0022] See also Figure 1 The buffer gas power generation system includes a gas tank 1, a generator set 2 and a gas delivery pipe 3 for connecting the gas tank 1 and the generator set 2. The gas tank 1 is connected to the enterprise gas pipeline network and is used to buffer excess gas in the enterprise gas pipeline network. The generator set 2 is connected to the power grid.
[0023] The gas delivery pipe 3 is provided with a flow regulating valve 4 for regulating the flow of gas in the gas delivery pipe 3;
[0024] The buffer gas power generation system also includes a time comparator, which compares the current absolute time with the standard time set in the comparator and controls the flow control valve 4 according to the comparison result.
[0025] Through the implementation of the above technical solution, the generator set 2 is connected to the gas tank 1 through the gas delivery pipe 3. The generator set 2 continuously consumes the gas in the gas tank 1 so that the gas in the gas tank 1 is maintained at a low pressure state, so that the excess gas in the enterprise's gas pipeline network will be collected in the gas tank 1, thereby realizing the collection of excess gas.
[0026] A flow regulating valve 4 is provided on the gas delivery pipe 3, and the flow regulating valve 4 regulates the pressure of the gas stored in the gas tank 1 by controlling the amount of gas flowing into the generator set 2. When the gas flowing into the gas tank 1 increases, the amount of gas flowing through the flow regulating valve 4 can be increased to consume more gas, and when the gas flowing into the gas tank 1 decreases, the amount of gas flowing through the flow regulating valve 4 can be reduced to avoid exhausting the gas in the gas tank 1.
[0027] The buffer gas power generation system is provided with a time comparator, so that the buffer gas power generation system can control the flow regulating valve 4 according to the actual time, so as to reduce the flow rate of the flow regulating valve 4 before the peak electricity arrives, so that the gas in the gas tank 1 is continuously increased, and the gas is stored in the gas tank 1, so that when the peak electricity arrives, the gas tank 1 can store enough gas. The time comparator confirms that the peak electricity has begun by comparing the current absolute time with the set standard time, and will control the flow regulating valve 4 to open to the maximum value, and the generator set 2 will generate electricity at the maximum power. By using gas to generate electricity autonomously, the enterprise can obtain as much electricity as possible through the gas stored in the gas tank 1 during the peak electricity period, so as to reduce the consumption of peak electricity in the enterprise's production, thereby reducing the enterprise's electricity cost.
[0028] Therefore, by setting a time comparator in the buffer gas power generation system, the power generation of the gas during peak power can be maximized, so that the gas in the gas tank 1 can obtain the maximum economic value.
[0029] The buffered gas power generation system also includes a control system, which is provided with a buffer zone. In the buffer zone, there is a physical address for storing the current absolute time. The time comparator reads the current absolute time in the physical address. At the same time, the time comparator is also provided with a standard time. The comparator continuously compares the current absolute time with the standard time. Once the comparison result is satisfied, an action instruction is outputted, and the flow regulating valve 4 is controlled through the control system, thereby changing the power generation of the generator set 2.
[0030] In one embodiment, the peak power time is 17:00 in the afternoon, so the standard time in the comparator can be set to 17:00, or slightly later than 17:00. When the current absolute time is equal to the standard time built into the comparator, the comparator will output an action instruction, and the control system will open the flow regulating valve 4 to the maximum value according to the action instruction, so that the generator set 2 starts to generate electricity at full power. Then, more self-generated electricity can be obtained during the peak power period, and the company's production consumption of purchased electricity will be reduced. Therefore, the corresponding electricity cost will be reduced.
[0031] Preferably, in order to enable the generator set 2 to generate more electricity during peak power hours, gas storage can be started after the peak power ends, so that the gas storage capacity in the gas tank 1 reaches the maximum value when the peak power arrives.
[0032] In this embodiment, preferably, the gas tank 1 is provided with a pressure gauge for detecting the gas pressure in the gas tank 1 .
[0033] Since gas holder 1 needs to store gas before the arrival of peak electricity, the pressure value in gas holder 1 will continue to increase during the process of storing gas. However, the gas in the enterprise's gas pipeline network is driven by the pressure difference in the system. Therefore, when the pressure in gas holder 1 increases, the ability of gas holder 1 to collect gas will decrease, that is, excess gas in the enterprise's gas pipeline network may not be able to flow effectively toward gas holder 1. Therefore, when the pressure in gas holder 1 continues to increase to a certain level, the gas in the enterprise's gas pipeline network cannot reach gas holder 1, but overflows everywhere in the enterprise's gas pipeline network, causing waste.
[0034] Therefore, a pressure gauge is required to be installed in the gas tank 1 to detect the gas pressure in the gas tank 1, and a maximum pressure value of the gas tank 1 is set in the control system. Once the actual pressure in the gas tank 1 is higher than the maximum pressure value, it is necessary to control the flow regulating valve 4 to increase the gas flow rate and increase the gas consumption of the generator set 2 to reduce the pressure value in the gas tank 1 and avoid the problem of gas overflow in the enterprise gas pipeline network.
[0035] When the equipment producing gas fails, the gas in the gas tank 1 will flow into the production equipment to provide energy for the production equipment to maintain the normal operation of production. Therefore, a certain amount of gas needs to be stored in the gas tank 1. Therefore, the control system also needs to set the minimum pressure value of the gas tank 1. Once the actual pressure in the gas tank 1 is lower than the minimum pressure value, it is necessary to control the flow regulating valve 4 to reduce the amount of gas passing through, reduce the gas consumption of the generator set 2, so as to increase the pressure value in the gas tank 1, and avoid the problem of production being affected by the lack of gas in the enterprise gas pipeline network.
[0036] In this embodiment, preferably, the buffer gas power generation system further comprises a second comparator, which compares the value of the current pressure gauge with the standard pressure set in the comparator;
[0037] The second comparator is used to end the control of the flow regulating valve 4 by the time comparator.
[0038] The time comparator confirms that the peak power has begun by comparing the current absolute time with the set standard time, and will control the flow control valve 4 to open to the maximum value, and the generator set 2 will generate electricity at the maximum power. Subsequently, the amount of gas in the gas tank 1 will gradually be consumed, and the pressure value in the gas tank 1 will gradually decrease until the pressure value in the gas tank 1 drops to the minimum pressure value.
[0039] The second comparator is provided with a standard pressure value, which is the minimum pressure value of the gas tank 1 or slightly higher than the minimum pressure value of the gas tank 1. The second comparator will compare the real-time value of the pressure gauge with the standard pressure value. Once it is found that the actual pressure value is equal to the standard pressure value, the flow regulating valve 4 will be controlled to reduce the flow rate, thereby reducing the consumption of gas in the gas tank 1 by the generator set 2, so as to ensure that there is still enough gas in the gas tank 1 to deal with emergencies.
[0040] Therefore, even in the peak power phase, once the second comparator finds that the pressure in the gas tank 1 is lower than the standard pressure value, the amount of gas provided by the gas tank 1 to the generator set 2 will be reduced, and the full-power power generation instruction set by the time comparator will no longer be executed.
[0041] If the second comparator still does not act after the peak power time ends, the control system will still execute the setting of the time comparator, and the generator set 2 will still generate power at full power until the gas in the gas tank 1 is consumed to the minimum pressure value, triggering the second comparator to act.
[0042] In this embodiment, preferably, a flow meter is provided at the inlet of the gas tank 1 .
[0043] By providing a flow meter at the entrance of the gas tank 1 , the control system can understand the amount of gas flowing into the gas tank 1 per unit time, and adjust the flow regulating valve 4 according to the inflow amount, thereby achieving the purpose of storing gas in the gas tank 1 .
[0044] After the peak power period ends, especially during the valley power period, the control system needs to adjust the flow regulating valve 4 according to the value of the flow meter, so that the flow rate of the flow regulating valve 4 is less than the value of the flow meter, so that the amount of gas entering the gas tank 1 is greater than the amount of gas flowing out, thereby realizing the storage of gas.
[0045] Due to the different daily production, the actual amount of gas produced and the amount of gas that can be stored are very different. Therefore, it is impossible to accurately specify the storage speed of the gas tank 1 when storing gas. However, the storage process of the gas tank 1 can be roughly divided into two stages. The first stage is the normal storage stage. After the second comparator is activated until 1 hour before the peak electricity arrives, the flow rate of the flow regulating valve 4 in the first stage is set to be slightly smaller than the value of the flow meter, that is, the gas tank 1 stores gas at a lower speed until 1 hour before the peak electricity, and the gas storage enters the second stage. In the second stage, the flow regulating valve 4 is adjusted to the smallest value possible so that the gas can be stored at the fastest speed, so that the pressure in the gas tank 1 reaches the maximum pressure value before the peak electricity arrives. On the one hand, it can meet the requirements of storing gas at the maximum load before the peak electricity, and on the other hand, it can also avoid the waste of gas caused by long-term gas overflow caused by the premature increase of the pressure in the gas tank 1.
[0046] Preferably, the opening time of the second stage of gas storage can be set according to the production situation. If the value displayed by the flow meter of the gas tank 1 is large on that day, the opening time of the second stage can be postponed because there is enough gas flowing in, which can shorten the time required for storage. If the value displayed by the flow meter of the gas tank 1 is small on that day, the opening time of the second stage needs to be advanced, and it is even possible to increase the storage speed of the first stage to ensure that the pressure in the gas tank 1 can reach the maximum pressure value when the peak electricity arrives.
[0047] More preferably, the control system can track the state of gas storage in the gas tank 1 in real time. Specifically, with absolute time as the horizontal axis and the pressure in the gas tank 1 as the vertical axis, the control system can draw an actual state diagram of gas storage in the gas tank 1 according to the actual situation. The control system can also fit an ideal state interval diagram of gas storage in the gas tank 1 based on past production experience. The ideal state interval diagram sets a minimum value and a maximum value for the pressure in the gas tank 1 at any time, and the ideal state is between the minimum value and the maximum value. If the pressure data at a certain absolute time of the actual state diagram does not fall within the ideal state interval diagram, the system will issue a reminder to the staff so that the staff can pay attention to the storage state of the gas tank 1 and start to correct the data of the flow control valve 4 based on the current actual production situation, so that the storage state in the gas tank 1 can be restored to the ideal state as soon as possible.
[0048] The company put the buffer gas power generation system into use in May 2023 and completed the commissioning of the buffer gas power generation system in September 2023. In October 2023, the buffer gas power generation system began to work normally.
[0049] Serial number time Electricity expenses (10,000 yuan) Peak power generation ratio Creation of benefits (ten thousand yuan) 1 January 2023 to April 2023 17146.9 33.33% 0 2 May 2023 to September 2023 23915.6 34.43% 138.3 3 October 2023 to February 2024 23908.6 36.29% 359.1
[0050] Table 1
[0051] As shown in Table 1, from January to April 2023, the buffer gas power generation system had not yet been put into use. During this period, the company paid a total of approximately RMB 170 million in production electricity fees, and the peak gas power generation accounted for 33.3% of the total peak electricity consumption.
[0052] Between May and September 2023, the buffer gas power generation system began to be put into use. However, since various system parameters are still in the debugging stage, during this period, the proportion of gas peak power generation to total peak electricity consumption was 34.43%. Compared with the case when the buffer gas power generation system was not used, the ratio increased by about one percentage point. Compared with not using the buffer gas power generation system, it actually saved about 1.383 million yuan in electricity bills. The economic benefits brought by the use of the buffer gas power generation system have begun to emerge.
[0053] From October 2023 to February 2024, the system parameters of the buffer gas power generation system have been set more reasonably. Therefore, during this period, the proportion of gas peak power generation to total peak electricity consumption was 36.29%, which was about three percentage points higher than when the buffer gas power generation system was not used. Compared with the previous debugging stage, the ratio also increased by nearly two percentage points, actually saving about 3.591 million yuan in electricity bills. Therefore, the economic benefits brought by the use of the buffer gas power generation system have begun to take shape, and it can be expected that in future production processes, the buffer gas power generation system will continue to create economic value for the company.
[0054] The preferred embodiments of the present invention are described in detail above in conjunction with the accompanying drawings. However, the present invention is not limited to the specific details in the above embodiments. Within the technical concept of the present invention, the technical solution of the present invention can be subjected to a variety of simple modifications, and these simple modifications all belong to the protection scope of the present invention.
[0055] It should also be noted that the various specific technical features described in the above specific embodiments can be combined in any suitable manner without contradiction. In order to avoid unnecessary repetition, the present utility model will not further describe various possible combinations.
[0056] In addition, various embodiments of the present invention may be arbitrarily combined, and as long as they do not violate the concept of the present invention, they should also be regarded as the contents disclosed by the present invention.
Claims
1. A buffer gas power generation system, characterized in that: The buffer gas power generation system comprises a gas tank (1), a generator set (2) and a gas transmission pipe (3) for connecting the gas tank (1) and the generator set (2); the gas tank (1) is connected to the enterprise gas pipeline network and is used to buffer excess gas in the enterprise gas pipeline network; the generator set (2) is connected to the power grid; The gas delivery pipe (3) is provided with a flow regulating valve (4) for regulating the flow of gas in the gas delivery pipe (3); The buffer gas power generation system also includes a time comparator, which compares the current absolute time with the standard time set in the comparator, and controls the flow control valve (4) according to the comparison result.
2. The buffer gas power generation system according to claim 1, characterized in that: The gas cabinet (1) is provided with a pressure gauge for detecting the gas pressure in the gas cabinet (1).