Ecological balanced high slope sash beam structural form

By designing the water-absorbing wick rope structure in cross beams, vertical ribs and PVC pipes in slope protection, the integrity of the ecosystem is restored, the problem of concrete beam segmentation ecosystem is solved, the sustainable development of ecological landscape is achieved and the maintenance cost is reduced .

CN222349717UActive Publication Date: 2025-01-14SHENZHEN HUAYUE CONSTR ENG
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420252155.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-01
Publication Date
2025-01-14
Estimated Expiration
2034-02-01

AI Technical Summary

Technical Problem

The crisscrossing concrete beams divide the ecosystem in the slope protection slope, hinder the circulation of material energy and soil microorganisms, and affect the sustainable development of ecological landscape and later maintenance costs.

Method used

Design an ecologically balanced high-slope frame beam structure, adopting cross beams, vertical ribs and PVC pipes, and an absorbent wick rope is installed inside to form a crisscrossing wick rope net to restore the integrity of the ecosystem, and through the absorbent wick rope It absorbs rainwater in the rainy season and absorbs water from the ground during the dry season.

Benefits of technology

Maintain the circulation of material energy and soil microorganisms, promote the stable and sustainable development of the ecological environment, reduce the cost of later maintenance, and protect the ecological balance of the slope.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222349717U_ABST
    Figure CN222349717U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of ecological side slope lattice beams, in particular to an ecological balance high side slope lattice beam structure which comprises a side slope and an underground water level, a cross beam is arranged at the front end of the side slope, a vertical rib is arranged at the front end of the side slope, a PVC pipe is installed on the inner side of the vertical rib, a water absorption wick rope is arranged on the inner side of the PVC pipe, and the lower end of the water absorption wick rope is embedded in the underground water level. According to the lattice beam construction structure, the cross beams, the vertical ribs, the PVC pipes and the water absorption wick ropes are arranged, so that a high slope constructed through the lattice beam is restored into a complete ecological system, circulation of material energy and soil microorganisms is maintained, and a stable and sustainable ecological environment can be created; and the water absorption wick ropes absorb rainwater in rainy seasons and absorb water from underground water in dry seasons to supply the water to the whole slope ecological system, so that the ecological balance of the slope is protected, and the later maintenance cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of ecological side slope lattice beams, in particular to an ecologically balanced high side slope lattice beam structure. Background Art

[0002] Frame beam slope protection is a roadbed support structure with high practical value. It adopts a special grid structure design, which can effectively disperse the foundation load pressure and ensure the stability and safety of the road. Moreover, frame beam slope protection has the advantages of low maintenance cost, convenient construction, environmental protection and energy saving. It will surely have more extensive applications and development in the future.

[0003] According to the search of the existing technical field, the application number is 201720438002.8, and the name of a drainage system for a lattice beam slope is announced. The drainage system includes: a vertical groove, a horizontal groove, a left oblique groove and a right oblique groove. One side of the horizontal groove is adjacent to the lower edge of the lattice beam and extends in the horizontal direction, and the horizontal groove is connected to an external water reservoir. The vertical groove is embedded in the lattice beam slope along the vertical direction of the lattice beam, and passes through the lower edge of the lattice beam to be connected to the horizontal groove. The left oblique groove and the right oblique groove are respectively located on both sides of the vertical groove and embedded in the slope of the lattice beam. The vertical groove is respectively connected to the left oblique groove and the right oblique groove, and the left oblique groove and the right oblique groove are both oriented towards the lattice. The upper edge of the beam extends upward in an inclined direction. The drainage system can effectively protect the stability of the slope and will not cause unsafe factors due to rain erosion, resulting in slope collapse. However, the criss-crossing concrete beams artificially divide the slope's originally integrated ecosystem into small pieces, hindering the circulation of material energy (water, nutrients, etc.) and soil microorganisms, which is not conducive to creating a stable and sustainable habitat, and is also not conducive to the sustainable development of the slope's ecological landscape, affecting the later effects and maintenance costs. Therefore, in response to the above problems, we proposed an ecologically balanced high-slope frame beam structure. Utility Model Content

[0004] The purpose of the utility model is to provide an ecologically balanced high slope frame beam structure to solve the problem that the criss-cross concrete beams artificially divide the slope surface, which is originally a complete ecosystem, into small pieces, hindering the circulation of material energy (water, nutrients, etc.) and soil microorganisms, which is not conducive to creating a stable and sustainable habitat, and is also not conducive to the sustainable development of the slope ecological landscape, affecting the later effects and maintenance costs.

[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0006] An ecologically balanced high slope frame beam structure comprises a slope and a groundwater level, wherein a cross beam is arranged at the front end of the slope, a vertical rib is arranged at the front end of the slope, a PVC pipe is installed inside the vertical rib, a water-absorbing wick rope is arranged inside the PVC pipe, and the lower end of the water-absorbing wick rope is buried inside the groundwater level.

[0007] Preferably, the vertical ribs are in a plurality and arranged in an array, and the cross beams are in a plurality.

[0008] Preferably, the beams are arranged in an array, the beams and the groundwater level are arranged in a staggered manner, and the angle between the beams and the groundwater level is ninety degrees.

[0009] Preferably, PVC pipes are installed on the inner side of the cross beam, and there are a plurality of PVC pipes arranged in an array.

[0010] Preferably, the lower end portion of the cross beam is buried in the slope, the water-absorbing wick ropes are in a plurality and arranged in an array, and the water-absorbing wick ropes pass through the cross beam and vertical ribs.

[0011] Compared with the prior art, the beneficial effects of the utility model are:

[0012] In the utility model, by arranging cross beams, vertical ribs, PVC pipes and water-absorbing wick ropes, the high slope constructed by the frame beams is restored to a complete ecosystem, the circulation of material energy and soil microorganisms is maintained, and it is beneficial to create a stable and sustainable ecological environment, and further beneficial to the sustainable development of the slope ecological landscape. The water-absorbing wick rope absorbs rainwater in the rainy season and absorbs water from groundwater in the dry season to supply the entire slope ecosystem, thereby protecting the ecological balance of the slope and reducing the later maintenance cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0014] Figure 2 The utility model is a schematic diagram of the structure of the water-absorbing wick rope.

[0015] In the figure: 1. Slope; 2. Groundwater level; 3. Crossbeam; 4. Vertical ribs; 5. PVC pipe; 6. Water-absorbing wick rope. DETAILED DESCRIPTION

[0016] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0017] See also Figure 1-2 , the utility model provides a technical solution:

[0018] An ecologically balanced high slope frame beam structure comprises a slope 1 and a groundwater table 2. A cross beam 3 is provided at the front end of the slope 1. A vertical rib 4 is provided at the front end of the slope 1. A PVC pipe 5 is installed inside the vertical rib 4. A water-absorbing wick rope 6 is provided inside the PVC pipe 5. The lower end of the water-absorbing wick rope 6 is buried inside the groundwater table 2.

[0019] A crossbeam 3 is provided at the front end of the slope 1, which is convenient for setting the crossbeam 3, vertical ribs 4, PVC pipes 5 and water-absorbing wick ropes 6, so that the high slope 1 constructed by the frame beam is restored to a complete ecosystem, maintaining the circulation of material energy, water, nutrients, etc. and soil microorganisms, which is conducive to creating a stable and sustainable ecological environment, and then conducive to the sustainable development of the slope ecological landscape. The water-absorbing wick rope 6 absorbs rainwater in the rainy season and absorbs water from groundwater in the dry season to supply the entire slope 1 ecosystem, protect the ecological balance of the slope 1, and reduce the later maintenance cost; the front end of the slope 1 is provided with vertical ribs 4, and the number of vertical ribs 4 is several , vertical ribs 4 are arranged in an array, a number of cross beams 3 are arranged in an array, the cross beams 3 and the groundwater level 2 are arranged alternately, the angle between the cross beams 3 and the groundwater level 2 is ninety degrees, PVC pipes 5 are installed on the inside of the cross beams 3, a number of PVC pipes 5 are arranged in an array, the lower end of the cross beams 3 is buried in the slope 1, a number of water-absorbing wick ropes 6 are arranged in an array, the water-absorbing wick ropes 6 pass through the cross beams 3 and the vertical ribs 4, PVC pipes 5 are installed on the inside of the vertical ribs 4, water-absorbing wick ropes 6 are provided on the inside of the PVC pipes 5, and the lower end of the water-absorbing wick rope 6 is buried inside the groundwater level 2.

[0020] Working process: When the device is in use, the main structure is a reinforced concrete lattice beam of a high slope 1, which is divided into a horizontal beam 3 and a vertical rib 4. The horizontal beam 3 and the vertical rib 4 are arranged vertically and horizontally on the slope 1. A PVC pipe 5 is pre-installed when the concrete structure is poured. After the component is completed, a water-absorbing wick rope 6 is inserted into the inside of the PVC pipe 5, and then the planting soil is backfilled. The lower end of the water-absorbing wick rope 6 is buried inside the groundwater level 2 to form a criss-crossing wick rope network. Finally, green plants are planted on the slope 1, so that the lattice beam cells are connected into an ecological whole. Material energy, water, nutrients, etc. and soil microorganisms flow left and right and up and down along the PVC pipe 5. Some small animals can flow along the gap between the PVC pipe 5 and the water-absorbing wick rope 6 to form an ecological cycle. In the rainy season, the water-absorbing wick rope 6 absorbs rainfall. In the dry season, the water-absorbing wick rope 6 uses the capillary action of the water-absorbing wick rope 6 to absorb water from the groundwater to supply the green plants and microorganisms on the slope 1, thereby effectively maintaining the ecological balance of the slope 1.

[0021] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. An ecologically balanced high slope lattice beam structure, comprising a slope (1) and a groundwater table (2), characterized in that: The front end of the side slope (1) is provided with a crossbeam (3), the front end of the side slope (1) is provided with a vertical rib (4), a PVC pipe (5) is installed inside the vertical rib (4), a water-absorbing wick rope (6) is provided inside the PVC pipe (5), and the lower end of the water-absorbing wick rope (6) is buried inside the groundwater level (2).

2. The ecologically balanced high slope lattice beam structure according to claim 1 is characterized by: The vertical ribs (4) are in a certain number and arranged in an array, and the cross beams (3) are in a certain number.

3. The ecologically balanced high slope lattice beam structure according to claim 1 is characterized by: The cross beams (3) are arranged in an array, the cross beams (3) and the groundwater level (2) are arranged in a staggered manner, and the angle between the cross beams (3) and the groundwater level (2) is ninety degrees.

4. The ecologically balanced high slope lattice beam structure according to claim 1 is characterized by: A PVC tube (5) is installed inside the crossbeam (3), and the PVC tubes (5) are in a certain number and arranged in an array.

5. The ecologically balanced high slope lattice beam structure according to claim 1 is characterized by: The lower end portion of the cross beam (3) is buried in the slope (1), the water-absorbing wick ropes (6) are of a certain number, the water-absorbing wick ropes (6) are arranged in an array, and the water-absorbing wick ropes (6) pass through the cross beam (3) and the vertical ribs (4).

Citation Information

Patent Citations

  • Drainage system of lattice girder side slope

    CN206736935U