Prefabricated box girder top plate reinforcing steel bar binding movable trolley

By designing a mobile trolley for tying steel bars on the top plate of the prefabricated box girder, the problem of laborious and unsafe walking on the steel bars during the construction process was solved, and convenient and safe steel bar tying and hoisting operations were realized.

CN222387261UActive Publication Date: 2025-01-24THE THIRD ENG CO LTD OF CCCC SECOND HIGHWAY ENG BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420953874.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-06
Publication Date
2025-01-24
Estimated Expiration
2034-05-06

AI Technical Summary

Technical Problem

During the construction of the steel bars on the roof of the prefabricated box beam, due to the large volume and long length of the prefabricated box beam, the staff need to walk on the steel bars, which makes walking difficult and unsafe.

Method used

Design a mobile trolley for tying prefabricated box girder roof steel bars, which includes a roof lashing tire frame, an angle steel track and a trolley body. The trolley body is slidingly connected through the angle steel track, and the supporting feet roll with the angle steel track to realize the movement of the trolley.

Benefits of technology

Through the mobile platform, the construction process can be moved with the direction of the cross point of the steel bars. The operators do not need to walk on the reinforcement. The operation is convenient and safe. After the reinforcement of the prefabricated box beams is completed, the mobile car can be lifted for steel bars for reinforced bars for reinforced bars. Cage hanging.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222387261U_ABST
    Figure CN222387261U_ABST
Patent Text Reader

Abstract

The utility model discloses a prefabricated box girder top plate steel bar binding movable trolley which comprises a top plate binding jig frame, the top plate binding jig frame is vertically supported by channel steel, channel steel rail supporting beams are arranged on the left side and the right side of the top of the top plate binding jig frame, and angle steel rails are fixed to the channel steel rail supporting beams. Meanwhile, a trolley body is slidably connected to the angle steel rail; top plate steel bar bodies are symmetrically fixed to the two sides of the middle of the top face of the angle steel rail, and clamping grooves are formed in the tops of the top plate steel bar bodies at equal intervals. The trolley further comprises supporting legs symmetrically welded and fixed to the bottom of the trolley body, and three walking wheels are connected to the bottoms of the supporting legs at equal intervals through bearings. The prefabricated box girder top plate reinforcing steel bar binding movable trolley can move in the reinforcing steel bar intersection binding direction in the construction process, an operator does not need to walk and work on reinforcing steel bars, after prefabricated box girder top plate reinforcing steel bars are installed, a reinforcing steel bar cage can be hoisted by hoisting the movable trolley, and operation is convenient and fast.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction of an intelligent annular production line for prefabricated box girders, and in particular to a mobile trolley for tying reinforcement bars on a top plate of a prefabricated box girder. Background Art

[0002] In bridge construction, the prefabricated box girder ring production line is an important part. The prefabricated box girder is a bending member that is prefabricated by pre-tensioning or post-tensioning the steel bars, and then transported to the construction site for installation.

[0003] However, the existing prefabricated box girder top plate steel bar binding work still has the following problems: during the prefabricated box girder top plate steel bar binding construction process, due to the large size and long length of the prefabricated box girder, the workers need to walk on the bundled steel bars when binding at the intersection of the steel bars, and gradually complete the entire prefabricated box girder. During the operation, the workers need to step on the right position to avoid stepping on air, which is laborious and unsafe. Therefore, it is necessary to design a mobile trolley. The mobile trolley of the prefabricated box girder top plate binding frame spans the top plate steel bars. During the construction process, it can move along the binding direction of the steel bar intersection. The workers do not need to walk or work on the steel bars. After the installation of the prefabricated box girder top plate steel bars is completed, the mobile trolley is lifted away to carry out the lifting of the steel cage.

[0004] Therefore, we proposed a mobile trolley for tying reinforcement bars of the top slab of prefabricated box beams in order to solve the above-mentioned problems. Utility Model Content

[0005] The purpose of the utility model is to provide a mobile trolley for tying the top slab steel bars of a prefabricated box girder, so as to solve the problem of the existing top slab steel bar tying work of a prefabricated box girder on the market in the above-mentioned background technology. During the construction process of tying the top slab steel bars of a prefabricated box girder, due to the large volume and long length of the prefabricated box girder, the workers need to walk on the tied steel bars when tying at the intersection of the steel bars, and gradually complete the processing of the entire prefabricated box girder. During the operation, the workers need to step on the correct position to avoid stepping on air, which is laborious and unsafe. Therefore, it is necessary to design a mobile trolley. The mobile trolley for tying the top slab of the prefabricated box girder crosses the top slab steel bars, and can move along the tying direction of the intersection of the steel bars during the construction process. The workers do not need to walk or work on the steel bars. After the installation of the top slab steel bars of the prefabricated box girder is completed, the mobile trolley can be lifted away to carry out the lifting of the steel cage.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a mobile trolley for tying steel bars of a prefabricated box girder top plate, comprising a tyre frame for tying steel bars of a top plate, wherein the tyre frame for tying steel bars of a top plate adopts a channel steel to establish a vertical support, and channel steel track support beams are arranged on the left and right sides of the top of the tyre frame for tying steel bars of a top plate, and angle steel tracks are fixed on the channel steel track support beams, and a trolley body is slidably connected to the angle steel tracks;

[0007] The top plate steel bar bodies are symmetrically fixed on both sides of the middle of the top surface of the angle steel track, and the top of the top plate steel bar bodies is provided with slots at equal intervals;

[0008] It also includes: support feet are symmetrically welded and fixed on the bottom of the trolley body, and three walking wheels are connected to the bottom of the support feet with equally spaced bearings, and the support feet roll on the angle steel track, and the angle steel track is inverted to form a triangular structure.

[0009] Preferably, the support foot is arranged as a "C"-shaped structure, and the walking wheel at the bottom of the support foot is arranged as a waist drum-shaped structure which is wide at both sides and narrow in the middle, and the support foot rolls in contact with the top outer side of the angle steel track.

[0010] Preferably, oil tanks are installed on the inner sides of the left and right support feet, and a piston plate is slidably connected through the top of the oil tank, and the bottom of the piston plate slides in contact with the inner wall of the oil tank, and the penetration point between the top of the piston plate and the oil tank is set as a rectangular structure.

[0011] Preferably, a screw is threadedly connected to the middle of the top surface of the piston plate, and the screw on the left side passes through the bearing to be connected to the top of the trolley body, the screw on the right side passes through the bearing to be connected to the inside of the trolley body, and the screws on the left and right sides are connected by a sprocket mechanism.

[0012] Preferably, the piston plate pushes the lubricating oil in the oil tank to be injected into the smear wipe block, and the smear wipe block is fixed to the bottom of the supporting foot, and the smear wipe block is in contact with the surface of the angle steel track, and the smear wipe block is arranged as an inverted "Y" shape structure.

[0013] Preferably, positioning rods are symmetrically hinged on the left and right sides of the trolley body, and torsion springs are installed at the hinges between the positioning rods and the trolley body, and the positioning rods are supported by the ground after rotation.

[0014] Preferably, a magnetic block is installed in the middle of the positioning rod, and the magnetic poles of the magnetic blocks on the positioning rods on opposite sides are opposite, and the magnetic attraction force of the magnetic block is greater than the elastic force of the torsion spring.

[0015] Compared with the prior art, the utility model has the following beneficial effects: when in use, the construction process can be moved along the binding direction of the steel bar intersection, and the operators do not need to walk or work on the steel bars. After the steel bars of the prefabricated box girder top plate are installed, the mobile trolley can be hoisted to carry out the hoisting of the steel bar cage, and the operation is convenient. The specific contents are as follows:

[0016] 1. Through the trolley body and the angle steel track, during the binding operation, the support of the angle steel track and the top plate binding frame are integrated, and the mobile trolley body of the prefabricated box girder top plate binding frame spans the top plate steel bar body. During the construction process, it can move along the binding direction along the steel bar intersection, and the operators do not need to walk and work on the steel bars;

[0017] Furthermore, the angle steel track forms the angle steel track of the mobile trolley body for tying the prefabricated box girder top plate, and the angle steel track can prevent the walking wheels at the bottom of the supporting foot from derailing. Slots are arranged on both sides of the top plate steel bar body, and the spacing of the slots is consistent with the spacing of the top plate steel bar body. After the prefabricated box girder top plate steel bar body is installed, the mobile trolley body can be hoisted to carry out the hoisting of the steel cage, which is convenient to operate.

[0018] 2. Through the setting of the piston plate and the smearing wiper, the angle steel rail can be lubricated in time, thereby reducing the mechanical friction during walking. After the screw rotates, it drives the piston plate to move in the oil tank, and the lubricating oil in the oil tank is injected into the smearing wiper. Then, when the trolley body moves, the lubricating oil will be smeared on the angle steel rail, thereby increasing the service life of the trolley body and the angle steel rail;

[0019] 3. By setting the positioning rod, the trolley body can be positioned during the tying operation to prevent sliding and affecting the tying operation;

[0020] Furthermore, after the positioning rod is rotated, the torsion spring reverses, and the adjacent magnetic blocks will be adsorbed and fixed, thereby fixing the position of the trolley body to prevent the trolley body from sliding during the binding operation. When moving, the positioning rod is lifted, the magnetic blocks are separated, and the torsion spring will drive the positioning rod to rotate back to a horizontal state, thereby facilitating subsequent use. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 This is a three-dimensional top view of the structure of the top plate binding tire frame and the trolley body of the utility model;

[0022] Figure 2 This is a schematic diagram of the three-dimensional front view structure of the trolley body of the utility model;

[0023] Figure 3 This is a schematic diagram of the overall front view structure of the utility model;

[0024] Figure 4For this utility model Figure 3 The enlarged structural diagram at A in the middle;

[0025] Figure 5 This is a three-dimensional side view of the structure of the smear wiper of the utility model in the installed state;

[0026] Figure 6 For this utility model Figure 3 The enlarged structural diagram at B in the middle;

[0027] Figure 7 It is a side view structural diagram of the positioning rod of the utility model in the supporting state.

[0028] In the figure: 1. Top plate tying frame; 2. Angle steel track; 3. Top plate steel bar body; 4. Slot; 5. Trolley body; 6. Support feet; 7. Traveling wheels; 8. Applicator wiper; 9. Screw; 10. Piston plate; 11. Oil tank; 12. Positioning rod; 13. Torsion spring; 14. Magnetic block. DETAILED DESCRIPTION

[0029] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0030] Embodiment 1: In order to facilitate the operation of the prefabricated box girder top plate reinforcement binding work without walking on the reinforcement, the following solution is proposed. Figure 1-Figure 5 As shown,

[0031] It includes a top plate tyre frame 1, and the top plate tyre frame 1 is supported vertically by channel steel, and channel steel track support beams are arranged on the left and right sides of the top of the top plate tyre frame 1, and an angle steel track 2 is fixed on the channel steel track support beam, and a trolley body 5 is slidably connected to the angle steel track 2, and a top plate steel bar body 3 is symmetrically fixed on both sides of the middle of the top surface of the angle steel track 2, and slots 4 are evenly spaced on the top of the top plate steel bar body 3, and it also includes: support feet 6 are symmetrically welded and fixed to the bottom of the trolley body 5, and three running wheels 7 are connected to the bearings at equal intervals at the bottom of the support feet 6, and the support feet 6 roll on the angle steel track 2, and the angle steel track 2 is inverted into a triangular structure, the support feet 6 are arranged in a "C" shape, and the running wheels 7 at the bottom of the support feet 6 are arranged in a waist drum-shaped structure with wide sides and narrow middle, and the support The feet 6 roll in contact with the top outer side of the angle rail 2. When in use, the channel steel and angle rail 2 are longitudinally arranged on both sides of the transverse support beam of the top plate tyre frame 1 to form the angle rail 2 of the mobile trolley body 5 of the prefabricated box girder top plate tyre frame 1. At the same time, the angle rail 2 can prevent the walking wheels 7 at the bottom of the supporting feet 6 from derailing. Slots 4 are set on both sides of the top plate steel bar body 3. The spacing of the slots 4 is consistent with the spacing of the top plate steel bar body 3. After the installation of the prefabricated box girder top plate steel bar body 3 is completed, the mobile trolley body 5 can be lifted and moved to carry out the lifting of the steel cage. The operation is convenient. The support of the angle rail 2 is integrated with the top plate tyre frame 1. The mobile trolley body 5 of the prefabricated box girder top plate tyre frame 1 spans the top plate steel bar body 3. The construction process can move along the binding direction along the intersection of the steel bars, and the operators do not need to walk or work on the steel bars.

[0032] Embodiment 2: In order to protect the angle steel rail 2 and reduce mechanical wear, lubrication is required. Therefore, the following solution is proposed. For details, please refer to Figure 3-Figure 5 As shown,

[0033] Oil tanks 11 are installed on the inner sides of the left and right supporting feet 6, and the top of the oil tank 11 is penetrated and slidably connected with a piston plate 10, and the bottom of the piston plate 10 fits and slides with the inner wall of the oil tank 11, and the penetration between the top of the piston plate 10 and the oil tank 11 is set to a rectangular structure, and a screw rod 9 is threadedly connected to the middle of the top surface of the piston plate 10, and the screw rod 9 on the left side penetrates the bearing and is connected to the top of the trolley body 5, and the screw rod 9 on the right side penetrates the bearing and is connected to the inside of the trolley body 5, and the screw rods 9 on the left and right sides are connected by a sprocket mechanism, and the piston plate 10 pushes the lubricating oil in the oil tank 11 to be injected into the smear wiper 8, and the smear wiper 8 is formed. The wiping block 8 is fixed to the bottom of the supporting foot 6, and the wiping block 8 is in contact with the surface of the angle steel rail 2, and the wiping block 8 is arranged as an inverted "Y" shape structure. When the angle steel rail 2 needs to be maintained, the screw 9 on the rotating trolley body 5 is rotated. After the screw 9 rotates, it will drive the piston plate 10 to move in the oil tank 11 through the sprocket mechanism, and then the lubricating oil in the oil tank 11 is injected into the wiping block 8, and then when the trolley body 5 moves, the lubricating oil will be applied to the angle steel rail 2, thereby reducing the mechanical wear caused by the movement and improving the service life of the trolley body 5 and the angle steel rail 2.

[0034] Embodiment 3: In order to maintain the stability of the trolley body 5 during the tying operation, the following solution is proposed. For details, please refer to Figure 3 and Figure 6-Figure 7 As shown,

[0035] The left and right sides of the trolley body 5 are symmetrically hinged with positioning rods 12, and the hinges of the positioning rods 12 and the trolley body 5 are installed with torsion springs 13, and the positioning rods 12 are in conflict with the ground support after rotation, and a magnetic block 14 is installed in the middle of the positioning rod 12, and the magnetic poles of the magnetic blocks 14 on the positioning rods 12 on the opposite sides are opposite, and the magnetic attraction force of the magnetic blocks 14 is greater than the elastic force of the torsion spring 13. When the binding operation is performed, the positioning rods 12 on both sides of the trolley body 5 are rotated from a horizontal state to a state of conflict with the ground. After the positioning rods 12 are rotated, the torsion springs 13 will be reversed, and after the positioning rods 12 are rotated, the adjacent magnetic blocks 14 will be adsorbed and fixed, thereby fixing the position of the trolley body 5 to prevent the trolley body 5 from sliding during the binding operation. When moving, the positioning rods 12 are lifted, the magnetic blocks 14 are separated, and the torsion springs 13 will drive the positioning rods 12 to rotate to a horizontal state, which is convenient for subsequent use.

[0036] The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field.

[0037] Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art may still modify the technical solutions described in the aforementioned embodiments, or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.

Claims

1. A mobile trolley for tying steel bars on the top plate of a prefabricated box beam, comprising a tyre frame (1) for tying steel bars on the top plate, wherein the tyre frame (1) is vertically supported by channel steel, and channel steel track support beams are arranged on the left and right sides of the top of the tyre frame (1), and angle steel tracks (2) are fixed on the channel steel track support beams, and a trolley body (5) is slidably connected to the angle steel track (2); A top plate steel bar body (3) is symmetrically fixed on both sides of the middle of the top surface of the angle steel track (2), and slots (4) are provided at equal intervals on the top of the top plate steel bar body (3); Features: Also includes: The bottom of the trolley body (5) is symmetrically welded with support feet (6), and the bottom of the support feet (6) is connected to three running wheels (7) at equally spaced bearings, and the support feet (6) roll on the angle steel track (2), and the angle steel track (2) is inverted to form a triangular structure.

2. The mobile trolley for tying reinforcement bars of the top plate of a prefabricated box beam according to claim 1 is characterized in that: The support foot (6) is configured as a "C"-shaped structure, and the walking wheel (7) at the bottom of the support foot (6) is configured as a waist drum-shaped structure that is wide at both sides and narrow in the middle, and the support foot (6) is adapted to roll in contact with the top outer side of the angle steel track (2).

3. The mobile trolley for tying reinforcement bars of the top plate of a prefabricated box beam according to claim 1 is characterized in that: An oil tank (11) is installed on the inner side of the support legs (6) on the left and right sides, and a piston plate (10) is slidably connected to the top of the oil tank (11), and the bottom of the piston plate (10) slides against the inner wall of the oil tank (11), and the penetration point between the top of the piston plate (10) and the oil tank (11) is set as a rectangular structure.

4. The mobile trolley for tying reinforcement bars of the top plate of a prefabricated box beam according to claim 3 is characterized in that: A screw rod (9) is threadedly connected to the middle of the top surface of the piston plate (10), and the screw rod (9) on the left side passes through a bearing and is connected to the top of the trolley body (5), and the screw rod (9) on the right side passes through a bearing and is connected to the inside of the trolley body (5), and the screw rods (9) on the left and right sides are connected via a sprocket mechanism.

5. The mobile trolley for tying reinforcement bars of the top plate of a prefabricated box beam according to claim 4, characterized in that: The piston plate (10) pushes the lubricating oil in the oil tank (11) to be injected into the smearing wipe block (8), and the smearing wipe block (8) is fixed to the bottom of the supporting foot (6), and the smearing wipe block (8) is in contact with the surface of the angle steel track (2), and the smearing wipe block (8) is arranged in an inverted "Y"-shaped structure.

6. The mobile trolley for tying reinforcement bars of the top plate of a prefabricated box beam according to claim 1, characterized in that: Positioning rods (12) are symmetrically hinged on the left and right sides of the trolley body (5), and a torsion spring (13) is installed at the hinge between the positioning rod (12) and the trolley body (5), and the positioning rod (12) contacts the ground support after rotation.

7. The mobile trolley for tying reinforcement bars of the top plate of a prefabricated box beam according to claim 6, characterized in that: A magnetic block (14) is installed in the middle of the positioning rod (12), and the magnetic poles of the magnetic blocks (14) on the positioning rods (12) on opposite sides are opposite, and the magnetic attraction force of the magnetic blocks (14) is greater than the elastic force of the torsion spring (13).