Combined temporary bridge capable of being disassembled quickly

Through the design, the combined combined bridge can be disassembled, and the modular structure and docking structure can be used to achieve rapid assembly and disassembly. The water flow shock is reduced by separating the base module and the increase of modules. It improved the stability and safety of the bridge.

CN222390232UActive Publication Date: 2025-01-24ROAD & BRIDGE INT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421179004.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-27
Publication Date
2025-01-24
Estimated Expiration
2034-05-27

AI Technical Summary

Technical Problem

The existing detachable steel trestle is long during the disassembly, and the pile foundation is easily loosened by the impact of water flow, which poses safety hazards.

Method used

Design a fast -moving combined bridge, including the base module, the increase module, the support beam module, and the bridge deck module. It realizes the rapid assembly and disassembly through the docking structure, and reduces through the separation of the base module and the increase module to reduce the rainstorm season. Water flow shock.

Benefits of technology

The rapid assembly and disassembly of the bridge is realized, reducing the influence of pile foundation in the rainstorm season by the impact of water flow, and improving the stability and safety of the bridge.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222390232U_ABST
    Figure CN222390232U_ABST
Patent Text Reader

Abstract

A combined temporary bridge capable of being quickly disassembled comprises a base module, a heightening module, a supporting beam module and a bridge floor module, the heightening module is detachably connected to the top of the base module, the supporting beam module is detachably connected to the top of the heightening module, the bridge floor module is detachably connected to the top of the supporting beam module, and the bridge floor module is detachably connected to the top of the supporting beam module. A first butt joint structure is fixedly arranged between the base module and the heightening module, and a second butt joint structure is arranged between the heightening module and the supporting beam module. The temporary bridge is divided into several independent modules, so that the temporary bridge is simple and rapid to assemble; the height of the base module in water is small, the influence on the root of the base module is small when the base module is impacted by water flow, and stability of the whole base module is facilitated. The base module and the heightening module are separately arranged, so that the requirement for the height of the bridge floor in the non-rainstorm season can be met, and the impact force of water flow impact on the temporary bridge base can be reduced in the rainstorm season.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of bridge construction, and in particular to a quick-detachable modular temporary bridge. Background Art

[0002] Transportation infrastructure is an important foundation and forerunner of my country's national economic development. Building high-quality transportation infrastructure is an important part of promoting high-quality development. In the construction of cross-river bridges, targeted bridge construction based on the characteristics of different rivers is the future development direction of bridge construction.

[0003] In the prior art, for seasonal small rivers, such as the Shiguan River, the water surface width is about 200m and the water depth is about 0.5 to 3.m under normal circumstances. During the rainy season, the water surface width exceeds 250m, the water depth exceeds 3.0m, and the water flow speed increases significantly, which is a typical seasonal river. In view of the seasonal characteristics of this kind of river, and taking into account the actual local needs and the cost of bridge construction, the solution of building a "detachable steel trestle" to ensure the access to the temporary road was finally selected to meet local traffic needs. However, the traditional detachable temporary bridge has a complex disassembly structure, a long disassembly time, and the pile foundation cannot be removed. During the rainy season, the water surface covers the pile foundation and constantly hits and collides, causing the roots of the pile foundation to loosen and create danger.

[0004] Therefore, the inventor is necessary to design a new quick-detachable combined temporary bridge to overcome the above problems. Summary of the invention

[0005] The main purpose of the present application is to provide a quick-detachable modular temporary bridge to solve the problems in the related art that the detachable trestle takes a long time to disassemble and the pile foundation is easily loosened by the impact of water flow.

[0006] In order to achieve the above-mentioned objectives, the present application provides a quick-detachable modular bridge, including a base module, a heightening module, a support beam module and a bridge deck module, the heightening module being detachably connected to the top of the base module, the support beam module being detachably connected to the top of the heightening module, the bridge deck module being detachably connected to the top of the support beam module, a first docking structure being fixedly arranged between the base module and the heightening module, and a second docking structure being arranged between the heightening module and the support beam module.

[0007] Preferably, the base module comprises two groups of pile foundation columns which are parallel to each other and distributed in a linear array, and the pile foundation columns comprise an underground section and an above-ground section.

[0008] Preferably, the heightening module comprises a plurality of heightening columns, and the heightening columns are fixedly arranged on the top of the section fixedly arranged on the ground.

[0009] Preferably, the first docking structure comprises a limiting groove and a limiting pin which cooperate with each other, the limiting groove is opened at the top of the pile foundation column, and the limiting pin is fixedly arranged at the bottom of the heightening column.

[0010] Preferably, the support beam module includes two main support beams, the two main support beams are fixedly connected to the two groups of pile foundation columns respectively, and a plurality of connecting cross beams are fixedly arranged between the two main support beams.

[0011] Preferably, the second docking structure includes a slot and a pin that cooperate with each other, the slot is opened at the top of the heightening column, and the pin is fixedly arranged at the bottom of the main support beam.

[0012] Preferably, the bridge deck module includes a plurality of cover plates, which are mounted on top of the two main support beams and fixedly connected to the main support beams.

[0013] Preferably, the cross section of the pile foundation column is in the shape of a water drop, and the outer wall of the large end of the pile foundation column is the water-facing surface.

[0014] Preferably, a plurality of lifting ears are fixedly provided on the outer wall of the heightening column.

[0015] Preferably, a plurality of insert tubes are fixedly provided on the side walls of the main support beam, insert rods are inserted into the insert tubes, and blocking rods are provided between adjacent insert tubes.

[0016] The utility model provides a quick-detachable combined temporary bridge, which has the following beneficial effects compared with the prior art:

[0017] Dividing the temporary bridge into several separate modules makes it simple and quick to assemble; the height of the top of the heightening module exceeds the water surface in the non-rainstorm season. After the heightening module is removed in the rainstorm season, the base module is at a lower height in the water, and the impact on its roots when impacted by the water flow is relatively small, which is conducive to the stability of the entire base module. By separating the base module from the heightening module, the height requirement of the bridge deck in the non-rainstorm season can be guaranteed, and the impact force of the water flow on the temporary bridge base can be reduced in the rainstorm season. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The drawings constituting a part of this application are used to provide a further understanding of this application, so that other features, purposes and advantages of this application become more obvious. The schematic embodiment drawings and their descriptions of this application are used to explain this application and do not constitute an improper limitation on this application. In the drawings:

[0019] Figure 1 It is the overall structure diagram of the utility model;

[0020] Figure 2 This is an exploded view of the utility model from the first angle;

[0021] Figure 3 This utility model Figure 2 Schematic diagram of the structure at A in the middle;

[0022] Figure 4 This is the second angle exploded view of the utility model;

[0023] Figure 5 This utility model Figure 4 Exploded view of the structure at point B in the middle.

[0024] Among them: 1. Pile foundation column; 101. Underground section; 102. Above-ground section; 2. Heightening column; 3. Limiting groove; 301. Conical groove; 302. Positioning groove; 4. Limiting pin; 5. Main supporting beam; 6. Connecting beam; 7. Slot; 8. Pin; 9. Cover plate; 10. Lifting ear; 11. Insert tube; 12. Insert rod; 13. Stop rod. DETAILED DESCRIPTION

[0025] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.

[0026] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0027] In the present application, the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the present application and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.

[0028] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those of ordinary skill in the art, the specific meanings of these terms in this application can be understood according to specific circumstances.

[0029] In addition, the term "plurality" shall mean two or more.

[0030] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0031] like Figures 1 to 5 As shown, a quick-detachable combined temporary bridge includes a base module, a heightening module, a support beam module and a bridge deck module, wherein the heightening module is detachably connected to the top of the base module, the support beam module is detachably connected to the top of the heightening module, and the bridge deck module is detachably connected to the top of the support beam module. A first docking structure is fixedly arranged between the base module and the heightening module, and a second docking structure is arranged between the heightening module and the support beam module. When the temporary bridge is in operation, the base module is first connected to the heightening module through the first docking structure, and then the support beam module is connected to the heightening module through the second docking structure. Finally, the bridge deck module is laid on the support beam module to realize the assembly of the temporary bridge, and the temporary bridge is divided into several separate modules to make its assembly simple and fast. The base module here is only used in the area located in the river channel, and the shore area of ​​the temporary bridge is not considered here. When dismantling a temporary bridge, the bridge deck module, support beam module, and heightening module are removed in sequence. The height of the top of the heightening module exceeds the water surface in the non-rainstorm season. After the heightening module is removed in the rainstorm season, the base module is at a lower height in the water, and the impact on its root when impacted by the water flow is relatively small, which is conducive to the stability of the entire base module. By separating the base module from the heightening module, the height requirement of the bridge deck in the non-rainstorm season can be guaranteed, and the impact force of the water flow on the temporary bridge base can be reduced in the rainstorm season.

[0032] The base module includes two groups of pile foundation columns 1 which are parallel to each other and distributed in a linear array. The pile foundation column 1 includes an underground section 101 and an above-ground section 102. When in operation, the underground section 101 of the pile foundation column 1 is buried in a deeper position in the river channel during initial construction, and the above-ground section 102 is used to dock with the heightening module.

[0033] The heightening module includes a plurality of heightening columns 2, and the heightening columns 2 are fixedly arranged on the top of the fixed ground section 102; the first docking structure includes a limiting groove 3 and a limiting pin 4 that cooperate with each other, and the limiting groove 3 is opened on the top of the pile foundation column 1, and the limiting pin 4 is fixedly arranged at the bottom of the heightening column 2; when working, when assembling the heightening column 2 and the pile foundation column 1, it is only necessary to lift the heightening column 2 to align the limiting groove 3 with the limiting pin 4, and then put down the heightening column 2 to achieve installation. It should be noted that if Figure 3 As shown, the limiting groove 3 here includes a tapered groove 301 and a positioning groove 302. The tapered groove 301 is convenient for docking with the limiting pin 4. The positioning groove 302 positions the limiting pin 4 in the circumferential direction, so that the heightening column 2 docks with the pile foundation column 1 at the same position each time. The specific structure of the limiting groove 3 and the limiting pin 4 here can be used here as long as it meets the functions of convenient docking and circumferential positioning. The heightening column 2 here preferably adopts a reinforced concrete structure, and can also adopt a metal part.

[0034] The support beam module includes two main support beams 5, which are respectively fixedly connected to two groups of pile foundation columns 1, and a plurality of connecting cross beams 6 are fixedly arranged between the two main support beams 5; the second docking structure includes a slot 7 and a pin 8 that cooperate with each other, the slot 7 is provided at the top of the heightening column 2, and the pin 8 is fixedly arranged at the bottom of the main support beam 5; when working, the main support beam 5 is lifted, the pin 8 at the bottom of the main support beam 5 is aligned with the slot 7 of the corresponding group of pile foundation columns 1, and then it is lowered, and the main support beam 5 can be installed. When installing the heightening column 2, since the heightening column 2 has been circumferentially positioned, all the slots 7 are in the same straight line. After the main support beam 5 is erected, the connecting cross beam 6 is installed and connected by bolts. In addition, since this temporary bridge only assembles the part on the river channel, the structure on the bank can limit the main support beam 5 in the direction of the extension of the slide slot, or directly make the end of the main support beam 5 erected against the river bank on both sides of the river channel.

[0035] The bridge deck module includes a plurality of cover plates 9, which are mounted on the top of the two main support beams 5 and fixedly connected to the main support beams 5. When working, the cover plates 9 are in an inverted U shape and are inverted on the two main support beams 5. The bottom of the cover plates 9 is in contact with the top of the main support beams 5 and the top of part of the connecting beams 6. According to actual needs, a reinforcement structure can also be set between the connecting beams 6 and the main support beams 5, and the cover plates 9 can be fixed by fixing structures such as bolts.

[0036] The cross section of the pile foundation column 1 is in the shape of a water drop, and the outer wall of the large end of the pile foundation column 1 is the water-facing surface; when working, the pile foundation column 1 is designed to be in the shape of a water drop, and its streamlined shape can reduce the impact force of water on the pile foundation column 1 when flowing.

[0037] A plurality of lifting ears 10 are fixedly provided on the outer wall of the heightening column 2 ; during operation, the lifting ears 10 are used to lift or dismantle the heightening column 2 .

[0038] The side walls of the main support beam 5 are also fixedly provided with a plurality of insert tubes 11, in which insert rods 12 are inserted, and barrier rods 13 are also provided between adjacent insert tubes 11; when working, the insert rods 12 and barrier rods 13 form the guardrail of the temporary bridge, and the barrier rods 13 can also be replaced with cables, glass plates, etc. according to actual needs.

[0039] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A quick-detachable modular bridge, characterized in that: It includes a base module, a heightening module, a support beam module and a bridge deck module, the heightening module is detachably connected to the top of the base module, the support beam module is detachably connected to the top of the heightening module, the bridge deck module is detachably connected to the top of the support beam module, a first docking structure is fixedly arranged between the base module and the heightening module, and a second docking structure is arranged between the heightening module and the support beam module.

2. The quick-detachable combined temporary bridge according to claim 1, characterized in that: The base module comprises two groups of pile foundation columns (1) which are parallel to each other and distributed in a linear array. The pile foundation columns (1) comprise an underground section (101) and an above-ground section (102).

3. The quick-detachable combined temporary bridge according to claim 2, characterized in that: The heightening module comprises a plurality of heightening columns (2), wherein the heightening columns (2) are fixedly arranged on the top of the section (102) fixedly arranged on the ground.

4. The quick-detachable combined temporary bridge according to claim 3, characterized in that: The first docking structure comprises a limiting groove (3) and a limiting pin (4) which cooperate with each other, the limiting groove (3) being arranged at the top of the pile foundation column (1), and the limiting pin (4) being fixedly arranged at the bottom of the heightening column (2).

5. The quick-detachable combined temporary bridge according to claim 3, characterized in that: The support beam module comprises two main support beams (5), the two main support beams (5) are respectively fixedly connected to the two groups of pile foundation columns (1), and a plurality of connecting cross beams (6) are fixedly arranged between the two main support beams (5).

6. The quick-detachable combined temporary bridge according to claim 5, characterized in that: The second docking structure comprises a mutually matching slot (7) and a latch (8), wherein the slot (7) is provided at the top of the heightening column (2), and the latch (8) is fixedly arranged at the bottom of the main support beam (5).

7. The quick-detachable combined temporary bridge according to claim 5, characterized in that: The bridge deck module comprises a plurality of cover plates (9), wherein the cover plates (9) are mounted on the top of the two main support beams (5) and are fixedly connected to the main support beams (5).

8. The quick-detachable combined temporary bridge according to claim 2, characterized in that: The cross section of the pile foundation column (1) is in the shape of a water drop, and the outer wall of the large end of the pile foundation column (1) is the water-facing surface.

9. The quick-detachable combined temporary bridge according to claim 3, characterized in that: A plurality of lifting ears (10) are also fixedly arranged on the outer wall of the heightening column (2).

10. The quick-detachable combined temporary bridge according to claim 5, characterized in that: A plurality of insert tubes (11) are fixedly arranged on the side wall of the main support beam (5), an insert rod (12) is inserted into the insert tube (11), and a blocking rod (13) is arranged between adjacent insert tubes (11).