Aluminum alloy template structure

By adding structures such as pull components and PVC ducts to the bottom of the aluminum alloy template, the problem of lining slices of aluminum alloy templates in high shear walls to bear the problem of large tensile capacity caused by large tensile power, realizing the ability to improve the loading capacity of the template and reduce explosion explosion Effect of modular risk.

CN222390985UActive Publication Date: 2025-01-24CQC CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420868770.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-24
Publication Date
2025-01-24
Estimated Expiration
2034-04-24

AI Technical Summary

Technical Problem

When pouring high shear walls, the pull tab at the bottom of the aluminum alloy template needs to withstand a large tension, which causes the pull tab to be broken by the standard plate, increasing the risk of the aluminum alloy template bursting.

Method used

Add the pull -up assembly at the bottom of the aluminum alloy template, including the pull bolt and the pull -up nut. Use the tensile resistance of the pull bolt to share the tension of the tensor, and separate the pull bolt from the PVC catheter and rubber case. Easy to pull away.

Benefits of technology

It reduces the risk of the pull tab being broken by the standard plate, reduces the risk of the aluminum alloy formwork exploding, simplifies the demoulding process, and reduces the work intensity of the staff.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222390985U_ABST
    Figure CN222390985U_ABST
Patent Text Reader

Abstract

The utility model relates to an aluminum alloy formwork structure. The aluminum alloy formwork structure comprises an outer wall formwork, an inner wall formwork, pulling pieces and opposite-pulling assemblies, wherein the outer wall formwork and the inner wall formwork are formed by splicing a plurality of standard plates; the outer wall formwork and the inner wall formwork are oppositely arranged, and a containing cavity for containing concrete is defined by the outer wall formwork and the inner wall formwork; the pulling piece is arranged between the outer wall formwork and the inner wall formwork. The opposite-pulling assembly is arranged at the bottoms of the outer wall formwork and the inner wall formwork; the opposite-pulling assembly comprises an opposite-pulling bolt and an opposite-pulling nut, third through holes for the opposite-pulling bolt to penetrate through are formed in the standard plates, the opposite-pulling bolt penetrates through the oppositely-arranged standard plates, the end of the opposite-pulling bolt is in threaded connection with the opposite-pulling nut, and the opposite-pulling nut abuts against the standard plates. According to the aluminum alloy formwork, the opposite-pulling assembly is additionally arranged at the bottom of the aluminum alloy formwork, the opposite-pulling bolt has high tensile performance, and therefore the tensile bolt is used for sharing the tensile force borne by the pulling piece; therefore, the risk that the pull piece is snapped by the standard plate is reduced, and the risk that the aluminum alloy formwork explodes is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building construction, and in particular to an aluminum alloy formwork structure. Background Art

[0002] In the prior art, building formworks suitable for concrete pouring generally include wooden formworks, steel formworks, aluminum alloy formworks, etc. Aluminum alloy formworks have the advantages of better mechanical properties, simple construction and installation, no construction waste, high turnover rate, and high recycling value; they occupy a certain market share in the construction market.

[0003] When pouring shear walls, aluminum alloy formwork generally includes standard plates, pull tabs and diagonal braces. Several standard plates are arranged opposite to each other, and the oppositely arranged standard plates enclose a receiving cavity for concrete pouring; the pull tab is arranged between the opposite standard plates, and the pull tab and the standard plates are fixedly connected by pins, and the pull tab is used to pull the lateral pressure of concrete on the standard plates; one end of the diagonal brace is fixedly connected to the floor, and the other end is abutted against the standard plate to further improve the stability of the aluminum alloy standard plate.

[0004] When the shear wall is high, the pull tabs at the bottom of the aluminum alloy formwork need to withstand greater tensile force; however, the tensile performance of the aluminum alloy pull tabs is limited, so there is a risk that the pull tabs will be broken by the standard plate, resulting in the risk of explosion of the aluminum alloy formwork. Utility Model Content

[0005] In order to further improve the bearing capacity of the aluminum alloy formwork and reduce the risk of explosion of the aluminum alloy formwork, the present application provides an aluminum alloy formwork structure.

[0006] The present application provides an aluminum alloy template structure, which adopts the following technical solution:

[0007] An aluminum alloy formwork structure, comprising a plurality of standard plates, pull tabs, pins, locking plates, tensioning assemblies and diagonal braces; the standard plate comprises a panel and an end plate, the end plates are fixed to both sides of the panel, and the end plates abut against the panel, the panel is used to contact with concrete, the end plates are vertically arranged, and the end plates of adjacent standard plates abut against each other; along the length direction of the end plates, the side of the end plates away from the panel is provided with a plurality of grooves for the pull tabs to pass through; the end plates are provided with a plurality of first through holes for the pins to pass through, the pull tabs are provided with a second through hole for the pins to pass through, and the ends of the pins are provided with a plurality of through holes for the pins to pass through. A fixing hole for a locking plate to pass through; a plurality of standard plates are spliced ​​into an exterior wall formwork and an interior wall formwork, the exterior wall formwork and the interior wall formwork are arranged opposite to each other, and the exterior wall formwork and the interior wall formwork are arranged to form a holding cavity for holding concrete; the pull tab is arranged between the exterior wall formwork and the interior wall formwork; the tension assembly is arranged at the bottom of the exterior wall formwork and the interior wall formwork; the tension assembly includes a tension bolt and a tension nut, the panel is provided with a third through hole for the tension bolt to pass through, the tension bolt is passed through the oppositely arranged panel, the end of the tension bolt is threadedly connected with the tension nut, and the tension nut abuts against the panel.

[0008] By adopting the above technical solution, when the workers pour the shear wall concrete into the accommodating cavity, the standard plate at the bottom of the aluminum alloy formwork will be subjected to a large lateral pressure, causing the bottom pull tab to be subjected to a large tensile force. By adding a tension assembly at the bottom of the aluminum alloy formwork, the tension bolts have a strong tensile performance, so that the tensile bolts can be used to share the tensile force on the pull tab; thereby reducing the risk of the pull tab being broken by the standard plate and reducing the risk of the aluminum alloy formwork exploding.

[0009] Optionally, the tension assembly further includes a PVC conduit, which is disposed between the exterior wall formwork and the interior wall formwork, the PVC conduit abuts against the panel, and the PVC conduit is sleeved on the outer periphery of the tension bolt.

[0010] By adopting the above technical solution, a PVC conduit is sleeved on the outer periphery of the tension bolts, and the tension bolts are separated from the concrete by the PVC conduit; thereby, it is convenient for workers to remove the tension bolts from the shear wall, facilitate demoulding for workers, and reduce the work intensity of workers.

[0011] Optionally, the tension assembly further includes a rubber sleeve, the rubber sleeve is fixed to both sides of the PVC conduit, the rubber sleeve is provided with a connecting hole for the tension bolt to pass through; the rubber sleeve is in contact with the panel.

[0012] By adopting the above technical solution, rubber sleeves are arranged on both sides of the PVC conduit, so that the rubber sleeves are used to block the possible gap between the PVC conduit and the standard plate, further reducing the occurrence of slurry in the concrete entering the interior of the PVC conduit, so that the staff can easily remove the tension bolts from the PVC conduit.

[0013] Optionally, the rubber sleeve is plugged and fixed to the PVC conduit.

[0014] By adopting the above technical solution, the rubber sleeve is plugged and fixed to the PVC conduit, and then the staff removes the standard plate and the tension assembly; the staff can use special tools to clamp the rubber sleeve, thereby pulling the rubber sleeve out of the shear wall; so that the staff can use mortar or other sealing materials to seal the sleeve.

[0015] Optionally, the rubber sleeve includes an abutment portion and an insertion portion, the abutment portion and the insertion portion are integrally formed; the insertion portion is plugged and fixed to the PVC conduit, and the abutment portion abuts against the panel; along the direction away from the panel, the distance from the outer periphery of the abutment portion to the central axis decreases.

[0016] By adopting the above technical solution, the outer periphery of the abutment portion of the rubber sleeve is inclined, so as to utilize the lateral pressure of the concrete on the abutment portion to increase the degree of extrusion between the rubber sleeve and the standard plate, and further reduce the occurrence of slurry in the concrete flowing into the PVC conduit.

[0017] Optionally, the plug-in portion abuts against the inner circumferential wall of the PVC conduit.

[0018] By adopting the above technical solution, the plug-in portion of the rubber sleeve is plugged and fixed with the inner peripheral wall of the PVC conduit to reduce the contact area between the rubber sleeve and the concrete, thereby facilitating the staff to remove the rubber sleeve. Optionally, notches are provided on both sides of the pull tab, and the notches are arranged between the exterior wall formwork and the interior wall formwork; and the edges of the notches abut against the panel.

[0019] By adopting the above technical solution, notches are provided on both sides of the pull tab, so that workers can use tools to pull off the pull tab on the outer periphery of the shear wall.

[0020] Optionally, the notch is a V-shaped notch.

[0021] By adopting the above technical solution, when the staff uses tools to pull off the pull tabs on the outer periphery of the shear wall, the V-shaped notch is conducive to stress concentration, so that the pull tabs break along the outer periphery of the shear wall.

[0022] In summary, the present application includes at least one of the following beneficial technical effects:

[0023] 1. By adding a tension assembly at the bottom of the aluminum alloy formwork, the tension bolts have strong tensile resistance, so that the tension bolts can be used to share the tensile force on the pull tabs; thereby reducing the risk of the pull tabs being broken by the standard plate and reducing the risk of the aluminum alloy formwork exploding;

[0024] 2. Rubber sleeves are set on both sides of the PVC conduit to block the possible gap between the PVC conduit and the standard plate, further reducing the occurrence of slurry in the concrete entering the PVC conduit, so that the staff can easily remove the tension bolts from the PVC conduit;

[0025] 3. When the staff use tools to pull off the pull tabs on the outer periphery of the shear wall, the V-shaped notch is conducive to stress concentration, causing the pull tabs to break along the outer periphery of the shear wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 Schematic diagram of the aluminum alloy template structure in this embodiment.

[0027] Figure 2 Schematic diagram of the standard plate structure in this embodiment.

[0028] Figure 3 yes Figure 1 Enlarged view of point A in the middle.

[0029] Figure 4 yes Figure 3 Enlarged view of point B in the middle.

[0030] Figure 5 It is a schematic diagram of the tension assembly structure in this embodiment.

[0031] Figure 6 yes Figure 5 Enlarged view of point C in the middle.

[0032] Explanation of the reference numerals: 1. Exterior wall formwork; 2. Interior wall formwork; 3. Standard block; 31. Panel; 311. Third through hole; 32. End plate; 321. Groove; 322. First through hole; 33. Transverse rib; 34. Longitudinal rib; 4. Pull tab; 41. Second through hole; 42. Notch; 5. Tension assembly; 51. Tension bolt; 52. Tension nut; 53. PVC conduit; 54. Rubber sleeve; 541. Connecting hole; 542. Abutment portion; 543. Insertion portion; 6. Pin; 7. Locking plate; 8. Back rib; 9. Square buckle; 10. Diagonal brace; 11. Accommodation cavity. DETAILED DESCRIPTION

[0033] The following is combined with Figure 1-6 This application is described in further detail.

[0034] The present application embodiment discloses an aluminum alloy template structure. Figure 1 The aluminum alloy formwork structure includes an exterior wall formwork 1 and an interior wall formwork 2 that are arranged opposite to each other, a pull tab 4 and a pull assembly 5 arranged between the exterior wall formwork 1 and the interior wall formwork 2, and a diagonal brace 10 arranged outside the exterior wall formwork 1 and the interior wall formwork 2. The exterior wall formwork 1 and the interior wall formwork 2 are arranged to form a receiving cavity 11 for receiving concrete. The exterior wall formwork 1, the interior wall formwork 2 and the pull tab 4 are all made of aluminum alloy material.

[0035] Reference Figure 1 and Figure 2 , the exterior wall formwork 1 and the interior wall formwork 2 are both made of a number of standard blocks 3. Figure 2 The standard plate includes a panel 31, an end plate 32, a transverse rib 33 and a longitudinal rib 34. The end plates 32 are fixed to both sides of the panel 31, and the end plates 32 abut against the panel 31. In this embodiment, the end plates 32 and the panel 31 are integrally formed. The panel 31 is used to contact with concrete. The end plates 32 are arranged vertically, and the end plates 32 of adjacent standard plates abut against each other. The transverse rib 33 and the longitudinal rib 34 are arranged between the oppositely arranged end plates 32, and the transverse rib 33 is arranged perpendicular to the longitudinal rib 34. The transverse rib 33 and the longitudinal rib 34 are used to improve the rigidity of the panel 31.

[0036] Reference Figure 1 and Figure 3 The standard plates are connected into a piece by pins 6 and locking plates 7. The relatively arranged standard plates are connected and fixed by pull tabs 4.

[0037] Reference Figure 3 and Figure 4 Along the length direction of the end plate 32, a plurality of grooves 321 for the pull tab 4 to pass through are provided at intervals on the side of the end plate 32 away from the panel 31; a plurality of first through holes 322 for the pin 6 to pass through are provided at intervals on the end plate 32, the pull tab 4 is provided with a second through hole 41 for the pin 6 to pass through, and a fixing hole for the locking piece 7 to pass through is provided at the end of the pin 6. Thus, the position of the standard plate and the pull tab 4 is fixed by the cooperation of the pin 6 and the locking piece 7.

[0038] The outer side of the standard plate on the same side is provided with a back rib 8 and a square buckle 9, which is plugged and fixed with the first through hole 322, and the back rib 8 is fixedly connected to the standard plate through the square buckle 9; thereby improving the structural rigidity of the aluminum alloy formwork. The back rib 8 and the square buckle 9 are prior art, and the specific structure of the square buckle 9 is not described in detail in this embodiment. One end of the diagonal brace 10 is fixedly connected to the embedded part of the floor slab, and the other end is connected to the back rib 8 through a connecting piece to improve the stability of the aluminum alloy formwork.

[0039] Reference Figure 3 The tensioning assembly 5 is arranged at the bottom of the exterior wall formwork 1 and the interior wall formwork 2. Figure 3 , Figure 5 and Figure 6The tension assembly 5 includes a tension bolt 51, a tension nut 52, a PVC conduit 53 and a rubber sleeve 54. The panel 31 is provided with a third through hole 311 for the tension bolt 51 to pass through. The tension bolt 51 is passed through the panel 31 arranged opposite to each other. The end of the tension bolt 51 is threadedly connected with the tension nut 52, and the tension nut 52 abuts against the panel 31. In this embodiment, the tension bolt 51 is arranged between two back ribs 8; and the tension nut 52 abuts against the back ribs 8 through a gasket; thereby increasing the tension effect of the tension bolt 51 on the standard plate. The tension nut 52 and the tension bolt 51 are made of steel.

[0040] When workers pour shear wall concrete into the accommodating cavity 11, the standard plate at the bottom of the aluminum alloy formwork will be subjected to a large lateral pressure, causing the bottom pull tab 4 to be subjected to a large tensile force. By adding a tension assembly 5 at the bottom of the aluminum alloy, the tension bolts 51 have a strong tensile performance, so that the tensile bolts are used to share the tensile force on the pull tab 4; thereby reducing the risk of the pull tab 4 being broken by the standard plate and reducing the risk of the aluminum alloy formwork exploding.

[0041] The PVC conduit 53 is arranged between the exterior wall formwork 1 and the interior wall formwork 2, and the PVC conduit 53 is in contact with the panel 31, and the PVC conduit 53 is sleeved on the outer periphery of the tension bolt 51. The rubber sleeve 54 is fixed on both sides of the PVC conduit 53, and the rubber sleeve 54 is provided with a connecting hole 541 for the tension bolt to pass through; the rubber sleeve 54 is in contact with the panel 31. The tension bolt 51 is separated from the concrete by the PVC conduit 53; thereby, it is convenient for the staff to remove the tension bolt 51 from the shear wall, facilitate the demoulding of the staff, and reduce the work intensity of the staff. At the same time, rubber sleeves 54 are arranged on both sides of the PVC conduit 53, so as to use the rubber sleeves 54 to block the gap that may appear between the PVC conduit 53 and the standard plate, further reducing the occurrence of slurry in the concrete entering the interior of the PVC conduit 53, so as to facilitate the staff to remove the tension bolt 51 from the PVC conduit 53.

[0042] In this embodiment, the rubber sleeve 54 includes an abutment portion 542 and an insertion portion 543, and the abutment portion 542 and the insertion portion 543 are integrally formed; the insertion portion 543 is plugged and fixed to the inner circumferential wall of the PVC conduit 53, and the abutment portion 542 abuts against the panel 31. And along the direction away from the panel 31, the distance from the outer periphery of the abutment portion 542 to the central axis decreases. The outer periphery of the abutment portion 542 of the rubber sleeve 54 is inclined, so as to utilize the lateral pressure of the concrete on the abutment portion 542 to increase the degree of extrusion between the rubber sleeve 54 and the standard plate, and further reduce the occurrence of slurry in the concrete flowing into the PVC conduit 53. The insertion portion 543 of the rubber sleeve 54 is plugged and fixed to the inner circumferential wall of the PVC conduit 53 to reduce the contact area between the rubber sleeve 54 and the concrete, thereby facilitating the staff to pull out the rubber sleeve 54. Refer to Figure 3 and Figure 4 At the same time, notches 42 are provided on both sides of the pull tab 4, and the notches 42 are provided between the exterior wall formwork 1 and the interior wall formwork 2; and the edges of the notches 42 abut against the panel 31. After the staff removes the standard plate, the pull tab 4 on the periphery of the shear wall needs to be removed. By providing notches 42 on both sides of the pull tab 4, it is convenient for the staff to use tools to pull off the pull tab 4 on the periphery of the shear wall. In this embodiment, the notch 42 is a V-shaped notch 42; so as to improve the stress concentration effect at the notch 42, so that the pull tab 4 breaks along the periphery of the shear wall.

[0043] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. An aluminum alloy template structure, characterized in that: The invention comprises a plurality of standard plates, pull tabs (4), pins (6), locking plates (7), a tensioning assembly (5) and a diagonal brace (10); the standard plate comprises a panel (31) and an end plate (32); the end plates (32) are fixed to both sides of the panel (31), and the end plates (32) abut against the panel (31); the panel (31) is used to contact concrete; the end plates (32) are arranged vertically, and the end plates (32) of adjacent standard plates abut against each other; along the length direction of the end plates (32), a side of the end plates (32) away from the panel (31) is provided with a plurality of grooves (321) for the pull tabs (4) to penetrate; the end plates (32) are provided with a plurality of first through holes (322) for the pins (6) to penetrate; the pull tab (4) is provided with a second through hole (41) for the pins (6) to penetrate; the end of the pin (6) is provided with a locking plate (42) for the locking plate (43) to penetrate; The invention relates to a method of manufacturing a concrete mortar board (1) and a concrete mortar board (2). The method comprises: manufacturing a plurality of standard plates to form an exterior wall formwork (1) and an interior wall formwork (2), wherein the exterior wall formwork (1) and the interior wall formwork (2) are arranged opposite to each other, and the exterior wall formwork (1) and the interior wall formwork (2) are arranged to form a receiving cavity (11) for receiving concrete; the pull tab (4) is arranged between the exterior wall formwork (1) and the interior wall formwork (2); the tensioning assembly (5) is arranged at the bottom of the exterior wall formwork (1) and the interior wall formwork (2); the tensioning assembly (5) comprises a tensioning bolt (51) and a tensioning nut (52); the panel (31) is provided with a third through hole (311) for the tensioning bolt (51) to pass through; the tensioning bolt (51) is passed through the panel (31) arranged opposite to each other; the end of the tensioning bolt (51) is threadedly connected to the tensioning nut (52), and the tensioning nut (52) abuts against the panel (31).

2. The aluminum alloy template structure according to claim 1, characterized in that: The tension assembly (5) further comprises a PVC conduit (53), wherein the PVC conduit (53) is arranged between the exterior wall formwork (1) and the interior wall formwork (2), the PVC conduit (53) is in contact with the panel (31), and the PVC conduit (53) is sleeved on the outer circumference of the tension bolt (51).

3. The aluminum alloy template structure according to claim 2, characterized in that: The tensioning assembly (5) further comprises a rubber sleeve (54), the rubber sleeve (54) being fixed to both sides of the PVC conduit (53), the rubber sleeve (54) being provided with a connecting hole (541) for the tensioning bolt to pass through; the rubber sleeve (54) is in contact with the panel (31).

4. The aluminum alloy template structure according to claim 3, characterized in that: The rubber sleeve (54) is plugged and fixed to the PVC conduit (53).

5. The aluminum alloy template structure according to claim 3, characterized in that: The rubber sleeve (54) comprises an abutting portion (542) and an inserting portion (543); the abutting portion (542) and the inserting portion (543) are integrally formed; the inserting portion (543) is plugged and fixed to the PVC conduit (53), and the abutting portion (542) abuts against the panel (31); along a direction away from the panel (31), the distance from the outer periphery of the abutting portion (542) to the central axis decreases.

6. The aluminum alloy template structure according to claim 5, characterized in that: The plug-in portion (543) abuts against the inner peripheral wall of the PVC conduit (53).

7. The aluminum alloy template structure according to claim 1, characterized in that: Notches (42) are provided on both sides of the pull tab (4); the notches (42) are arranged between the exterior wall formwork (1) and the interior wall formwork (2); and the edges of the notches (42) are in contact with the panel (31).

8. The aluminum alloy template structure according to claim 7, characterized in that: The notch (42) is a V-shaped notch (42).