Anti-collapse fixing device for three-dimensional greening plant wall
By designing the three -dimensional green plant wall prevention and collapse fixed device, the problem that the plant wall cannot be fixed and collapsed during installation is solved, the reinforcement and rain protection of the carrier of the wall are extended, and the service life of the equipment is extended.
Patent Information
- Application Number
- CN202423224059.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-26
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2034-12-26
AI Technical Summary
In some relatively empty scenes, three-dimensional green plant walls cannot be fixed by the wall when installed, and the frame may easily collapse when installed using steel frames.
A three -dimensional green plant wall anti -collapse fixed device is designed, including the bottom fixed mechanism, the carrier of the wall, the top seal bearing mechanism, and the reinforcement mechanism. The device is fixed on the ground through the bottom fixed mechanism, carrying a reinforced film and reinforcement mechanism in the wall, and a suspension of the peripheral green plant, and a sealing mechanism is set on the top to prevent rainwater from entering.
Effectively prevent the collapse of the wall, increase the internal strength, prevent rainwater from entering, and provide additional reinforcement to the green plant suspension rod, extending the service life of the part.
Smart Images

Figure CN222396332U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of greening, in particular to a three-dimensional greening plant wall anti-collapse fixing device. Background Art
[0002] Three-dimensional green plant wall, also known as vertical garden or green wall, is a greening method that plants are planted on the wall of a building or a specially designed vertical structure. This form of greening not only beautifies the environment, but also brings a variety of ecological and economic benefits, such as improving air quality, reducing building energy consumption, and reducing urban heat island effect.
[0003] In some relatively open scenes, three-dimensional green plants cannot be installed and fixed on the wall during installation. If the green plants are installed directly using a steel frame, it is easy to cause the frame to collapse when there are too many green plants hung. For this reason, we propose a three-dimensional green plant wall anti-collapse fixing device. Utility Model Content
[0004] The utility model aims to provide a three-dimensional greening plant wall anti-collapse fixing device to solve the problems raised in the background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a three-dimensional green plant wall anti-collapse fixing device, including a bottom fixing mechanism, a bearing wall for placing green plants is arranged on the top of the bottom fixing mechanism, a top sealing bearing mechanism is arranged on the top of the bearing wall to prevent rainwater from entering the inside of the bearing wall, multiple groups of reinforcement plates made of rigid materials are fixedly installed on both sides of the inner wall of the bearing wall, the two sides of the inner wall of the bearing wall are fixedly connected by multiple groups of first reinforcement mechanisms, the two ends of the inner wall of the bearing wall are fixedly connected by multiple groups of second reinforcement mechanisms, and a green plant hanging rod for hanging green plants is fixedly installed on the outside of the bearing wall through a fixing plate.
[0006] Furthermore, the bottom fixing mechanism includes a base, mounting claws, a first positioning seat and a second positioning seat, two groups of mounting claws are fixedly installed on both sides of the base, two groups of first positioning seats are fixedly installed on both sides of the top of the base, and two groups of second positioning seats are fixedly installed at both ends of the top of the base, and the supporting wall is inserted into the inner walls of the first positioning seat and the second positioning seat.
[0007] Furthermore, the first reinforcement mechanism and the second reinforcement mechanism have the same structure and both include a positioning frame, a positioning block and a reinforcement rod. Two groups of positioning frames are fixedly installed inside the bearing wall. An avoidance groove is provided on one side of the positioning frame. A positioning block is clamped inside the positioning frame. The two groups of positioning blocks are fixedly connected by a reinforcement rod.
[0008] Furthermore, the top sealing bearing mechanism includes positioning grooves, a sealing cover plate and positioning columns. The top of the bearing wall is provided with multiple groups of positioning grooves, and the bottom of the sealing cover plate is fixedly provided with multiple groups of positioning columns inserted into the positioning grooves at positions corresponding to the positioning grooves.
[0009] Furthermore, a sealing gasket made of rubber material is arranged at the bottom of the sealing cover plate and at the top of the corresponding bearing wall.
[0010] Furthermore, a reinforcement plate is fixedly installed between adjacent fixing plates, and the green plant hanging rod, the reinforcement plate and the reinforcement rod are made of rigid materials.
[0011] Compared with the prior art, the utility model has the following beneficial effects: the bottom fixing mechanism provided in the utility model can be fixed on the ground by means of expansion screws, and then the bearing wall can be installed inside the bottom fixing mechanism, and the provided green plant hanging rod can hang the green plants that need to be placed, and the multiple groups of reinforcement plates provided inside the bearing wall can increase the internal strength of the bearing wall, and the first reinforcement mechanism and the second reinforcement mechanism provided inside the bearing wall can perform secondary reinforcement on the inside of the bearing wall, such a setting can prevent the possibility of collapse of the bearing wall, and the provided top sealing bearing mechanism can prevent rainwater from entering the bearing wall, and can also reinforce the top of the bearing wall again. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;
[0013] Figure 2 It is a schematic diagram of the cross-sectional structure of the utility model;
[0014] Figure 3 It is a schematic diagram of the three-dimensional structure of the first reinforcement mechanism of the utility model.
[0015] In the figure: 1 bottom fixing mechanism, 2 bearing wall, 3 top sealing bearing mechanism, 4 first reinforcement mechanism, 5 second reinforcement mechanism, 6 green plant hanging rod, 7 reinforcement sheet, 8 positioning frame, 9 avoidance groove, 10 positioning block, 11 reinforcement rod, 12 base, 13 mounting claw, 14 first positioning seat, 15 second positioning seat, 16 positioning groove, 17 sealing cover plate, 18 positioning column, 19 reinforcement plate, 20 fixing plate. DETAILED DESCRIPTION
[0016] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0017] See also Figure 1-Figure 3 The utility model provides a technical solution: a three-dimensional greening plant wall anti-collapse fixing device, including a bottom fixing mechanism 1, a bearing wall 2 for placing greening plants is arranged on the top of the bottom fixing mechanism 1, a top sealing bearing mechanism 3 for preventing rainwater from entering the inside of the bearing wall 2 is arranged on the top of the bearing wall 2, multiple groups of reinforcement plates 7 made of rigid materials are fixedly installed on both sides of the inner wall of the bearing wall 2, both sides of the inner wall of the bearing wall 2 are fixedly connected by multiple groups of first reinforcement mechanisms 4, the two ends of the inner wall of the bearing wall 2 are fixedly connected by multiple groups of second reinforcement mechanisms 5, and a greening plant hanging rod 6 for hanging greening plants is fixedly installed on the outside of the bearing wall 2 through a fixing plate 20.
[0018] Among them, the bottom fixing mechanism 1 can be fixed on the ground by using expansion screws, and then the bearing wall 2 can be installed inside the bottom fixing mechanism 1, and the green plant hanging rod 6 can hang the green plants that need to be placed, and the multiple groups of reinforcement plates 7 arranged inside the bearing wall 2 can increase the internal strength of the bearing wall 2, and the first reinforcement mechanism 4 and the second reinforcement mechanism 5 arranged inside the bearing wall 2 can perform secondary reinforcement on the inside of the bearing wall 2. Such a setting can prevent the possibility of collapse of the bearing wall 2, and the top sealing bearing mechanism 3 can prevent rainwater from entering the bearing wall 2, and can also reinforce the top of the bearing wall 2 again.
[0019] See also Figure 1 and Figure 2 The bottom fixing mechanism 1 includes a base 12, mounting claws 13, a first positioning seat 14 and a second positioning seat 15. Two groups of mounting claws 13 are fixedly installed on both sides of the base 12, two groups of first positioning seats 14 are fixedly installed on both sides of the top of the base 12, and two groups of second positioning seats 15 are fixedly installed at both ends of the top of the base 12. The supporting wall 2 is inserted into the inner wall of the first positioning seat 14 and the second positioning seat 15.
[0020] After the base 12 is installed, the base 12 can be installed on the ground by passing the expansion screws through the installation claws 13, and then the supporting wall 2 is placed between the first positioning seat 14 and the second positioning seat 15, so that the supporting installation of the supporting wall 2 can be completed.
[0021] See also Figure 1 , Figure 2 and Figure 3 The first reinforcement mechanism 4 and the second reinforcement mechanism 5 have the same structure and both include a positioning frame 8, a positioning block 10 and a reinforcement rod 11. Two groups of positioning frames 8 are fixedly installed inside the load-bearing wall 2. An avoidance groove 9 is opened on one side of the positioning frame 8. A positioning block 10 is clamped inside the positioning frame 8. The two groups of positioning blocks 10 are fixedly connected by a reinforcement rod 11.
[0022] When it is necessary to reinforce the inside of the load-bearing wall 2, the positioning blocks 10 on both sides of the reinforcement rod 11 are inserted into the interior of the positioning frame 8, and the reinforcement rod 11 can be placed in the inside of the avoidance groove 9. In this way, when one side of the load-bearing wall 2 is excessively pulled, the received force can be dispersed through the other load-bearing wall 2 to prevent the load-bearing wall 2 from deforming and collapsing due to the pulling.
[0023] See also Figure 1 and Figure 2 The top sealing bearing mechanism 3 includes positioning grooves 16, a sealing cover plate 17 and positioning columns 18. A plurality of positioning grooves 16 are provided on the top of the bearing wall 2. A plurality of positioning columns 18 inserted into the positioning grooves 16 are fixedly installed at the bottom of the sealing cover plate 17 and at positions corresponding to the positioning grooves 16. A sealing gasket made of rubber material is provided at the bottom of the sealing cover plate 17 and at the top of the bearing wall 2.
[0024] Among them, when it is necessary to place the top sealing bearing mechanism 3 on the top of the bearing wall 2 for installation, the positioning column 18 at the bottom of the sealing cover plate 17 is inserted into the inside of the positioning groove 16. At this time, the sealing gasket made of rubber material can prevent external rainwater from entering the inside of the bearing wall 2, and green plants can also be placed on the top of the sealing cover plate 17.
[0025] See also Figure 1 and Figure 2 A reinforcement plate 19 is fixedly installed between adjacent fixed plates 20, and the manufacturing materials of the greening plant hanging rod 6, the reinforcement sheet 7 and the reinforcement rod 11 are rigid materials. Among them, the set reinforcement plate 19 can prevent the greening plant hanging rod 6 from causing deformation and damage to the fixed plate 20 when it is pulled, and the greening plant hanging rod 6, the reinforcement sheet 7 and the reinforcement rod 11 made of rigid materials can increase the service life of the components to a certain extent.
[0026] When in use, first, the bottom fixing mechanism 1 can be fixedly installed on the ground by using expansion screws, and then the bearing wall 2 can be installed inside the bottom fixing mechanism 1, and the green plant hanging rod 6 can be used to hang the green plants that need to be placed, and the multiple groups of reinforcing plates 7 arranged inside the bearing wall 2 can increase the internal strength of the bearing wall 2, and the first reinforcing mechanism 4 and the second reinforcing mechanism 5 arranged inside the bearing wall 2 can perform secondary reinforcement on the inside of the bearing wall 2, such a setting can prevent the possibility of collapse of the bearing wall 2, and the top sealing bearing mechanism 3 can prevent rainwater from entering the bearing wall 2, and can also reinforce the top of the bearing wall 2 again. After the base 12 is installed, the base 12 can be installed on the ground by passing the expansion screws through the mounting claws 13, and then the bearing The load-bearing wall 2 is placed between the first positioning seat 14 and the second positioning seat 15, so that the support installation of the load-bearing wall 2 can be completed. When the inside of the load-bearing wall 2 needs to be reinforced, the positioning blocks 10 on both sides of the reinforcement rod 11 are inserted into the interior of the positioning frame 8, and the reinforcement rod 11 can be placed in the interior of the avoidance groove 9. In this way, when one side of the load-bearing wall 2 is excessively pulled, the received force can be dispersed through the other load-bearing wall 2 to prevent the load-bearing wall 2 from deforming and collapsing due to the pulling. When the top sealing load-bearing mechanism 3 needs to be placed on the top of the load-bearing wall 2 for installation, the positioning column 18 at the bottom of the sealing cover plate 17 is inserted into the interior of the positioning groove 16. At this time, the sealing gasket made of rubber material can prevent external rainwater from entering the interior of the load-bearing wall 2, and green plants can also be placed on the top of the sealing cover plate 17.
[0027] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A three-dimensional greening plant wall anti-collapse fixing device, comprising a bottom fixing mechanism (1), the top of the bottom fixing mechanism (1) is provided with a bearing wall (2) for placing greening plants, characterized in that: The top of the bearing wall (2) is provided with a top sealing bearing mechanism (3) for preventing rainwater from entering the interior of the bearing wall (2); a plurality of groups of reinforcing plates (7) made of rigid materials are fixedly installed on both sides of the inner wall of the bearing wall (2); the two sides of the inner wall of the bearing wall (2) are fixedly connected via a plurality of groups of first reinforcing mechanisms (4); the two ends of the inner wall of the bearing wall (2) are fixedly connected via a plurality of groups of second reinforcing mechanisms (5); and a greening plant hanging rod (6) for hanging greening plants is fixedly installed on the outside of the bearing wall (2) via a fixing plate (20).
2. The anti-collapse fixing device for a three-dimensional greening plant wall according to claim 1 is characterized in that: The bottom fixing mechanism (1) comprises a base (12), mounting claws (13), a first positioning seat (14) and a second positioning seat (15); two groups of mounting claws (13) are fixedly mounted on both sides of the base (12); two groups of first positioning seats (14) are fixedly mounted on both sides of the top of the base (12); two groups of second positioning seats (15) are fixedly mounted on both ends of the top of the base (12); and the bearing wall (2) is inserted into the inner walls of the first positioning seat (14) and the second positioning seat (15).
3. The anti-collapse fixing device for a three-dimensional greening plant wall according to claim 2 is characterized in that: The first reinforcement mechanism (4) and the second reinforcement mechanism (5) have the same structure and both comprise a positioning frame (8), a positioning block (10) and a reinforcement rod (11); two groups of positioning frames (8) are fixedly installed inside the bearing wall (2); a avoidance groove (9) is provided on one side of the positioning frame (8); a positioning block (10) is clamped inside the positioning frame (8); and the two groups of positioning blocks (10) are fixedly connected via the reinforcement rod (11).
4. The anti-collapse fixing device for a three-dimensional greening plant wall according to claim 3 is characterized in that: The top sealing bearing mechanism (3) comprises positioning grooves (16), a sealing cover plate (17) and positioning columns (18); a plurality of positioning grooves (16) are provided on the top of the bearing wall (2); a plurality of positioning columns (18) inserted into the positioning grooves (16) are fixedly installed at the bottom of the sealing cover plate (17) and at positions corresponding to the positioning grooves (16).
5. The anti-collapse fixing device for a three-dimensional greening plant wall according to claim 4 is characterized in that: A sealing pad made of rubber material is provided at the bottom of the sealing cover plate (17) and at the top of the corresponding bearing wall (2).
6. The anti-collapse fixing device for a three-dimensional greening plant wall according to claim 5, characterized in that: A reinforcement plate (19) is fixedly installed between adjacent fixing plates (20), and the greening plant hanging rod (6), the reinforcement plate (7) and the reinforcement rod (11) are made of a rigid material.