Vibration combined frame for preventing pump pipe pouring
By designing the anti -pump tube pouring, the vibration combination frame is used to solve the problem of steel bars spacing and protective layer thickness changes caused by pump tube vibration, realize the reliability and safety of the pump tube, and meet the needs of environmental protection and on -site safety protection.
Patent Information
- Application Number
- CN202421160456.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-27
- Publication Date
- 2025-01-28
- Estimated Expiration
- 2034-05-27
AI Technical Summary
During the pouring of basement floor and other large-area concrete areas, the vibration of the pump pipe causes changes in the spacing of steel bars and the thickness of the protective layer, increasing safety hazards and management difficulties during construction.
A vibration combination frame for pump pump pumping is designed, including the flat section of the steel bars and the steel bars of the bending pipe section. The pump tube is fixed through the combination of supporting columns, steel pipe storage cylinders and supporting steel bars to reduce vibration.
The reliability, convenience and security of the pump tube are realized, the needs of environmental protection and on -site safety protection have been met, and the necessity of artificial care management is reduced.
Smart Images

Figure CN222413023U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of vibration-proof combined frames for pump pipe pouring, and in particular relates to a vibration-proof combined frame for pump pipe pouring. Background Art
[0002] The use of pump pipes during concrete pouring in basement floors and other large areas is to ensure that the vibration of the pump pipes during the concrete pouring process will reduce the changes in the originally designed and tied steel bar spacing and protective layer thickness, reduce some necessary human care and management, or avoid hidden dangers.
[0003] In order to solve the above problem which may occur again during concrete pouring, a "combined frame to prevent pump pipe from vibrating during pouring" is invented and used to ensure the reliability of the pump pipe during concrete pouring, which is convenient, fast and safe.
[0004] Therefore, it is necessary to provide a new vibration-proof combined frame for pump pipe pouring to solve the above-mentioned technical problems. Utility Model Content
[0005] The technical problem solved by the utility model is to provide a vibration-proof combined frame for pump pipe pouring which has a simple structure, can be recycled, is energy-saving and environmentally friendly, and meets the current environmental protection requirements and on-site safety protection needs.
[0006] In order to solve the above technical problems, the utility model provides a vibration-proof combined frame for pump pipe pouring, which includes: a straight section steel bar frame, which includes four bases, four brackets 1 and two brackets 2, and the four brackets 1 are respectively arranged on the tops of the four bases, and the bracket 1 includes a support column, a steel pipe storage cylinder 1, a steel pipe storage cylinder 2, a steel pipe storage cylinder 3 and a steel pipe storage cylinder 4, and the support column is fixedly installed on the top of the base, and the steel pipe storage cylinder 1, the steel pipe storage cylinder 2, the steel pipe storage cylinder 3 and the steel pipe storage cylinder 4 are all fixedly installed on the support column;
[0007] The second bracket is composed of a first steel pipe storage cylinder, a second steel pipe storage cylinder and a third steel pipe storage cylinder.
[0008] As a further solution of the utility model, the four steel pipe storage cylinders 2 correspond to each other in pairs and are connected with two supporting steel bars 1, and the two ends of the supporting steel bars 1 are respectively slidably connected with the corresponding two steel pipe storage cylinders 2.
[0009] As a further solution of the utility model, the four steel pipe storage cylinders 1 correspond to each other in pairs and are connected with two supporting steel bars 2, and the two ends of the supporting steel bars 2 are respectively slidably connected with the corresponding two steel pipe storage cylinders 1.
[0010] As a further solution of the utility model, four steel pipe storage cylinders four are slidably installed with supporting steel bars three, and the top ends of the four supporting steel bars three are respectively connected to the corresponding two second steel pipe storage cylinders and the corresponding two third steel pipe storage cylinders.
[0011] As a further solution of the utility model, support steel bars four are slidably installed on the four steel pipe storage cylinders three, the same support steel bars five are slidably installed on the two first steel pipe storage cylinders, and the top ends of the four support steel bars four are fixedly connected to the support steel bars five.
[0012] As a further solution of the utility model, the steel pipe storage cylinder 1, steel pipe storage cylinder 2, steel pipe storage cylinder 3, steel pipe storage cylinder 4 and the supporting steel bar 1, supporting steel bar 2, supporting steel bar 3 and supporting steel bar 4 are all connected and fixed by adjusting bolts, and the supporting steel bar 5 is provided with a rubber protective sleeve.
[0013] As a further solution of the utility model, it also includes a curved pipe section steel bar frame, which includes two connecting steel bars one, two connecting steel bars two, two connecting steel bars three, a connecting steel bar four, two connecting steel bars five and a connecting steel bar six, the two ends of the two connecting steel bars one are respectively connected to the two ends of the two connecting steel bars two, the two connecting steel bars three are respectively installed at the corresponding connection points between the two connecting steel bars one and the two connecting steel bars two, the connecting steel bars four are installed on the two connecting steel bars three, the two connecting steel bars five are respectively installed at the corresponding connection points between the two connecting steel bars one and the two connecting steel bars two, and the connecting steel bars six are installed on the two connecting steel bars five.
[0014] Compared with the related art, the vibration-proof combined frame for pump pipe pouring provided by the utility model has the following beneficial effects:
[0015] 1. The utility model has a simple structure, can be recycled, is energy-saving and environmentally friendly, and meets the current environmental protection requirements and on-site safety protection needs. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to facilitate understanding by those skilled in the art, the present invention is further described below in conjunction with the accompanying drawings.
[0017] Figure 1 The structure of the utility model is shown in FIG. Figure 1 ;
[0018] Figure 2 The structure of the utility model is shown in FIG. Figure 2 ;
[0019] Figure 3 It is a schematic diagram of the assembly structure of the base and the bracket 1 of the utility model;
[0020] Figure 4It is a structural schematic diagram of the steel bar frame of the bent pipe section in the utility model.
[0021] In the figure: 1. base; 2. bracket one; 21. support column; 22. steel pipe storage tube one; 23. steel pipe storage tube two; 24. steel pipe storage tube three; 25. steel pipe storage tube four; 3. bracket two; 31. first steel pipe storage tube; 32. second steel pipe storage tube; 33. third steel pipe storage tube; 4. supporting steel bar one; 5. supporting steel bar two; 6. supporting steel bar three; 7. supporting steel bar four; 8. supporting steel bar five; 9. adjusting bolt; 10. rubber protective cover; 11. connecting steel bar one; 12. connecting steel bar two; 13. connecting steel bar three; 14. connecting steel bar four; 15. connecting steel bar five; 16. connecting steel bar six. DETAILED DESCRIPTION
[0022] Please refer to Figures 1 to 4 ,in, Figure 1 The structure of the utility model is shown in FIG. Figure 1 ; Figure 2 The structure of the utility model is shown in FIG. Figure 2 ; Figure 3 It is a schematic diagram of the assembly structure of the base and the bracket 1 of the utility model; Figure 4 It is a structural schematic diagram of the steel frame of the curved pipe section in the utility model. The vibration-proof combined frame for pump pipe pouring includes: a straight section steel frame, the straight section steel frame includes four bases 1, four brackets 1 2 and two brackets 2 3, the four brackets 1 2 are respectively arranged on the top of the four bases 1, the bracket 1 2 includes a support column 21, a steel pipe storage cylinder 1 22, a steel pipe storage cylinder 2 23, a steel pipe storage cylinder 3 24 and a steel pipe storage cylinder 4 25, the support column 21 is fixedly installed on the top of the base 1, and the steel pipe storage cylinder 1 22, the steel pipe storage cylinder 2 23, the steel pipe storage cylinder 3 24 and the steel pipe storage cylinder 4 25 are all fixedly installed on the support column 21;
[0023] Install the steel pipe storage tube 1 22, the steel pipe storage tube 2 23, the steel pipe storage tube 3 24 and the steel pipe storage tube 4 25 on the support column 21 to form a bracket 1 2;
[0024] The bracket 2 3 is composed of a first steel tube storage tube 31 , a second steel tube storage tube 32 and a third steel tube storage tube 33 .
[0025] The four steel pipe storage cylinders 23 correspond to each other in pairs and are connected to two supporting steel bars 1 4 , and the two ends of the supporting steel bars 1 4 are slidingly connected to the corresponding two steel pipe storage cylinders 23 .
[0026] The four steel pipe storage cylinders 22 correspond to each other in pairs and are connected with two supporting steel bars 5 , and the two ends of the supporting steel bars 5 are slidingly connected with the corresponding two steel pipe storage cylinders 22 .
[0027] Support steel bars 3 6 are slidably mounted on the four steel pipe storage cylinders 25 , and the top ends of the four support steel bars 3 6 are connected to the corresponding two second steel pipe storage cylinders 32 and the corresponding two third steel pipe storage cylinders 33 , respectively.
[0028] A supporting steel bar four 7 is slidably installed on each of the four steel pipe storage cylinders three 24 , and a same supporting steel bar five 8 is slidably installed on each of the two first steel pipe storage cylinders 31 . The top ends of the four supporting steel bars four 7 are fixedly connected to the supporting steel bar five 8 .
[0029] The steel pipe storage tube 1 22, steel pipe storage tube 2 23, steel pipe storage tube 3 24, steel pipe storage tube 4 25 and support steel bar 1 4, support steel bar 2 5, support steel bar 3 6 and support steel bar 4 7 are all connected and fixed by adjusting bolts 9, and the support steel bar 5 8 is provided with a rubber protective sleeve 10.
[0030] It also includes a curved pipe section steel bar frame, which includes two connecting steel bars 11, two connecting steel bars 2, two connecting steel bars 3, 13, a connecting steel bar 4, 14, two connecting steel bars 5, 15 and a connecting steel bar 6. The two ends of the two connecting steel bars 11 are respectively connected to the two ends of the two connecting steel bars 2, 12. The two connecting steel bars 3 13 are respectively installed at the corresponding connecting points between the two connecting steel bars 11 and the two connecting steel bars 2, 12. The connecting steel bars 4 14 are installed on the two connecting steel bars 3 13. The two connecting steel bars 5 15 are respectively installed at the corresponding connecting points between the two connecting steel bars 11 and the two connecting steel bars 2, 12. The connecting steel bars 6 16 are installed on the two connecting steel bars 5 15.
[0031] The rubber protective sleeve 10 is set on the steel bar to protect the pump pipe and prevent the pump pipe from rubbing against the support frame and wearing the pump pipe wall when the pump pipe vibrates. Steel bars with a diameter of more than 25 mm are used.
[0032] The anti-vibration combined frame consists of a straight section steel frame and a curved section steel frame, which are used to fix the straight section and curved section of the concrete pump pipe respectively. All materials can be obtained on site, and most of the pipe diameters are consistent, so the combined frame can be recycled.
[0033] It can be welded on site using the remaining scrap short steel bars and hollow steel pipes cut according to construction requirements, and can be completed according to the on-site construction situation, making it recyclable, energy-saving and environmentally friendly, meeting the current environmental protection requirements and on-site safety protection needs.
[0034] It should be noted that the equipment structure and drawings of the utility model mainly describe the principle of the utility model. In terms of the technology of the design principle, the settings of the power mechanism, power supply system and control system of the device are not fully described. On the premise that the technical personnel in this field understand the principle of the above utility model, the details of the power mechanism, power supply system and control system can be clearly known. The control method of the application document is automatic control through a controller, and the control circuit of the controller can be realized by simple programming by the technical personnel in this field;
[0035] The standard parts used therein can all be purchased from the market and can be customized according to the instructions and drawings. The specific connection methods of each part adopt conventional means such as mature bolts, rivets, welding, etc. in the prior art. The machinery, parts and equipment all adopt conventional models in the prior art, and the structures and principles of the components known to technical personnel in this field can be known by these technical personnel through technical manuals or through conventional experimental methods.
[0036] Although the embodiments of the present invention have been shown and described, it is understood by those skilled in the art that various changes, modifications, substitutions and variations or direct or indirect applications may be made to these embodiments without departing from the principles and spirit of the present invention. In other related technical fields, the scope of the present invention is defined by the attached claims and their equivalents, which are equally included in the scope of patent protection of the present invention.
Claims
1. A vibration-proof combined frame for pump pipe pouring, characterized in that: include: A straight section steel bar frame, the straight section steel bar frame comprises four bases, four brackets 1 and two brackets 2, the four brackets 1 are respectively arranged on the top of the four bases, the bracket 1 comprises a support column, a steel pipe storage cylinder 1, a steel pipe storage cylinder 2, a steel pipe storage cylinder 3 and a steel pipe storage cylinder 4, the support column is fixedly installed on the top of the base, and the steel pipe storage cylinder 1, the steel pipe storage cylinder 2, the steel pipe storage cylinder 3 and the steel pipe storage cylinder 4 are all fixedly installed on the support column; The second bracket is composed of a first steel pipe storage cylinder, a second steel pipe storage cylinder and a third steel pipe storage cylinder.
2. The vibration-proof combined frame for pump pipe pouring according to claim 1 is characterized in that: The four steel pipe storage cylinders 2 correspond to each other in pairs and are connected with two supporting steel bars 1, and the two ends of the supporting steel bars 1 are respectively slidably connected with the corresponding two steel pipe storage cylinders 2.
3. The vibration-proof combined frame for pump pipe pouring according to claim 1 is characterized in that: The four steel pipe storage cylinders 1 correspond to each other in pairs and are connected with two supporting steel bars 2, and the two ends of the supporting steel bars 2 are respectively slidably connected with the corresponding two steel pipe storage cylinders 1.
4. The vibration-proof combined frame for pump pipe pouring according to claim 1 is characterized in that: Support steel bars 3 are slidably mounted on the four steel pipe storage cylinders 4, and the top ends of the four support steel bars 3 are respectively connected to the corresponding two second steel pipe storage cylinders and the corresponding two third steel pipe storage cylinders.
5. The vibration-proof combined frame for pump pipe pouring according to claim 1, characterized in that: Support steel bars four are slidably installed on the four steel pipe storage cylinders three, the same support steel bars five are slidably installed on the two first steel pipe storage cylinders, and the top ends of the four support steel bars four are fixedly connected to the support steel bars five.
6. The vibration-proof combined frame for pump pipe pouring according to claim 5, characterized in that: The steel pipe storage cylinder 1, steel pipe storage cylinder 2, steel pipe storage cylinder 3, steel pipe storage cylinder 4 and the supporting steel bar 1, supporting steel bar 2, supporting steel bar 3 and supporting steel bar 4 are all connected and fixed by adjusting bolts, and the supporting steel bar 5 is provided with a rubber protective sleeve.
7. The vibration-proof combined frame for pump pipe pouring according to claim 1, characterized in that: It also includes a bent pipe section steel bar frame, which includes two connecting steel bars one, two connecting steel bars two, two connecting steel bars three, a connecting steel bar four, two connecting steel bars five and a connecting steel bar six, the two ends of the two connecting steel bars one are respectively connected to the two ends of the two connecting steel bars two, the two connecting steel bars three are respectively installed at the corresponding connection points between the two connecting steel bars one and the two connecting steel bars two, the connecting steel bars four are installed on the two connecting steel bars three, the two connecting steel bars five are respectively installed at the corresponding connection points between the two connecting steel bars one and the two connecting steel bars two, and the connecting steel bars six are installed on the two connecting steel bars five.