Safety protection shed for pipeline groove deep foundation pit construction operation

Through the design of the construction operation of the deep foundation pit of the pipeline groove, the safety protective shed, and the structure of the top and side protective frames, protective boards, and baffles solves the problems of high protection costs, slow progress and safety hazards of the grooves. , Achieve safe and economical construction effects.

CN222413453UActive Publication Date: 2025-01-28CHINA RAILWAY NO 3 GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421083170.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-17
Publication Date
2025-01-28
Estimated Expiration
2034-05-17

AI Technical Summary

Technical Problem

In water pipeline projects, due to the base geological and environmental limitations of the base, it is difficult to carry out steel sheet pile protection construction, resulting in high cost of slope protection, slow progress, and idle work and safety hazards.

Method used

The construction operation safety protective shed of the deep foundation pit of pipeline grooves is designed, including the top protective frame, side protective frames, protective boards, baffles, escape holes and ladders. The sliding sand and stones on the side of the slope prevent falling and falling into the slope to ensure the safety of the construction staff.

Benefits of technology

Effectively reduce the cost of temporary support for the slope, improve the construction progress, ensure the safety of operators in the deep foundation pit of the groove, and avoid the occurrence of nesting work and safety accidents.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222413453U_ABST
    Figure CN222413453U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building construction, in particular to a pipeline groove deep foundation pit construction operation safety protection shed which comprises a portal frame body, a protection structure and an escape structure, the portal frame body comprises a top protection frame and side protection frames, and the side protection frames are arranged on the two sides, facing a slope, of the top protection frame; the protection structure comprises a protection plate and a baffle, the protection plate is arranged at the top end of the top protection frame, and the baffle is movably connected with the side protection frame; the escape structure comprises a safety cover and a crawling ladder, the safety cover is movably arranged on the protection plate, an escape through hole is formed in the position, corresponding to the safety cover, of the protection plate, the top end of the crawling ladder is arranged at the escape through hole, and the crawling ladder is arranged on the side protection frame. The construction progress of pipeline engineering is accelerated, the situation that mechanical equipment is damaged due to foundation pit protection construction is avoided, and constructors can evacuate in time to guarantee safety when encountering dangerous situations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a safety protection shed for pipeline trench deep foundation pit construction operations. Background Art

[0002] The Honghe construction section of the Yunnan Dianzhong Water Diversion Phase II supporting project has a total length of 205km, spanning three cities and two counties. Among them, there are 47 water pipes with a total length of 183km, accounting for 89%. The project has the characteristics of long water transmission lines, many points and wide areas, and a large management span. With the smooth progress of the project and the increase in pipeline working surfaces, the safety risks of pipeline deep foundation trench operations have gradually increased.

[0003] Specifically, in water pipeline projects, deep trench excavation in some sections cannot be sloped due to the surrounding environment and topography, and vertical surface excavation is required. Due to the limitations of the base geology and the surrounding environment of the operation, there are no conditions for steel sheet pile protection construction. However, temporary protection measures such as spraying concrete are used for vertical surface slope protection, which greatly increases construction costs and affects the progress of pipeline construction, causing idleness of on-site machinery and equipment, thereby affecting the overall benefits of the project. If no protective construction is carried out, the installation of pipeline steel pipes requires welding, anti-corrosion, concrete pouring and other construction processes in the deep trench foundation pit. The construction time is long, and the vertical surface slope is prone to landslides during long-term operation in the deep trench foundation pit, posing a great safety risk. Utility Model Content

[0004] In order to solve the above technical problems, the utility model provides a safety protection shed for pipeline trench deep foundation pit construction operations which reduces temporary slope support and ensures the safety of construction workers.

[0005] The utility model provides a safety protection shed for pipeline trench deep foundation pit construction work, comprising:

[0006] A gantry body, the gantry body comprising a top protection frame and a side protection frame, the side protection frames being arranged on both sides of the top protection frame facing the slope;

[0007] A protection structure, the protection structure comprising a protection plate and a baffle, the protection plate is arranged at the top of the top protection frame, and the baffle is movably connected to the side protection frame;

[0008] An escape structure, the escape structure includes a safety cover and a ladder, the safety cover is movably arranged on the protective plate, and an escape through hole is opened on the protective plate at a position corresponding to the safety cover, the top end of the ladder is arranged at the escape through hole, and the ladder is arranged on the side protective frame.

[0009] Optionally, it further includes a plurality of pulleys, wherein the plurality of pulleys are arranged at the bottom of the side protection frame, and the pulleys are connected to the side protection frame via angle steels.

[0010] Optionally, the side protection frame includes a plurality of vertical rods and horizontal rods vertically connected to each other, and the plurality of vertical rods are connected to the top protection frame.

[0011] Optionally, the gantry body further comprises an oblique brace, one end of the oblique brace is connected to the top protection frame, and the other end of the oblique brace is connected to the side protection frame;

[0012] The diagonal brace is made of I14 I-steel.

[0013] Optionally, a sealing member is provided on the circumference of the safety cover.

[0014] Optionally, the distance from the side protection frame to the slope is 20 cm, and the distance from the top protection frame to the top of the foundation pit is 50 cm.

[0015] Optionally, the top protection frame and the side protection frame are both made of I18 I-beam.

[0016] Optionally, the protective plate is made of steel plate, and the thickness of the protective plate is 3 mm.

[0017] Optionally, the baffle is made of bamboo plywood.

[0018] Optionally, the size of the escape hole is 80×80 cm.

[0019] Compared with the prior art, the technical solution provided by the embodiment of the utility model has the following beneficial effects:

[0020] The safety protection shed for pipeline trench deep foundation pit construction provided in the present embodiment can effectively block the mud and stones sliding down the slope by setting side protection frames on both sides of the top protection frame facing the slope, and baffles are movably set on the side protection frames, so as to prevent the slope from collapsing and blocks falling from the top of the slope, which may cause safety accidents to the construction workers, reduce the cost of temporary slope support, speed up the progress of pipeline construction, ensure that the trench can be backfilled in time to eliminate safety hazards, and at the same time, during the installation operation outside the protection shed, a baffle at the working position can be opened according to needs, and then plugged in after the construction is completed, which not only ensures the smooth completion of each process of pipeline installation and pipe concrete construction, but also ensures the safety of workers in the trench deep foundation pit, and by setting a protective plate on the top of the top protection frame, it can effectively block the sand and rainwater on the top of the slope, further improving the safety of the protection shed.

[0021] An escape hole suitable for workers to enter and exit is opened on the protective plate, and a safety cover is provided at the position corresponding to the escape hole. The setting of the safety cover ensures the integrity of the protective plate and the safety of the construction workers in the protective shed. The ladder is set below the escape hole and fixed on the side protective frame, which improves the stability of the ladder setting and enables workers to evacuate in time when encountering danger. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The accompanying drawings herein are incorporated in and constitute a part of the specification, illustrate embodiments consistent with the present utility model, and together with the description, are used to explain the principles of the present utility model.

[0023] In order to more clearly illustrate the technical solutions in the embodiments of the utility model or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.

[0024] Figure 1 This is a schematic structural diagram of a safety protection shed for pipeline trench deep foundation pit construction work according to an embodiment of the utility model;

[0025] Figure 2 This is a structural schematic diagram of a pipeline trench deep foundation pit construction safety protection shed without a baffle installed according to an embodiment of the utility model;

[0026] Figure 3 It is a side view of the safety protection shed for pipeline trench deep foundation pit construction work according to an embodiment of the utility model, which is set in the foundation pit;

[0027] Figure 4 It is a top view of the safety protection shed for pipeline trench deep foundation pit construction operations described in an embodiment of the utility model.

[0028] Among them, 1. Top protection frame; 2. Side protection frame; 201. Vertical rod; 202. Horizontal rod; 3. Protection plate; 4. Baffle; 5. Ladder; 6. Escape hole; 7. Pulley; 8. Diagonal brace. DETAILED DESCRIPTION

[0029] In order to more clearly understand the above-mentioned purpose, features and advantages of the utility model, the scheme of the utility model will be further described below. It should be noted that the embodiments of the utility model and the features in the embodiments can be combined with each other without conflict.

[0030] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein; obviously, the embodiments in the specification are only part of the embodiments of the present invention, rather than all of the embodiments.

[0031] Reference Figures 1 to 4 As shown, this embodiment provides a safety protection shed for pipeline trench deep foundation pit construction operations, including a gantry body, a protection structure and an escape structure.

[0032] Among them, the portal frame body includes a top protection frame 1 and a side protection frame 2. The side protection frame 2 is arranged on both sides of the top protection frame 1 facing the slope. The protection structure includes a protection plate 3 and a baffle 4. The protection plate 3 is arranged at the top of the top protection frame 1, and the baffle 4 is movably connected to the side protection frame 2. Specifically, the top protection frame 1 and the side protection frame 2 are connected together to form a door-type structure as the main body of the fireproof shed. The side protection frame 2 is arranged toward the slope, and a baffle 4 is movably arranged on the side protection frame 2, which can effectively block the mud and stones sliding down the slope, prevent the slope from collapsing and the top of the slope from falling off, causing safety accidents to the construction workers. During the installation operation on the outside of the protection shed, a baffle 4 at the working position is opened as needed, and then plugged in after the construction is completed, which not only ensures the smooth completion of each process of pipeline installation and pipe-wrapped concrete construction, but also ensures the safety of the workers in the deep foundation pit of the trench. The protective plate 3 is arranged at the top of the top protection frame 1, which can effectively block the sand and rain on the top of the slope, and further improves the safety of the protection shed. The baffle 4 in this embodiment is plug-in connected to the side protection frame 2, specifically, a baffle handle is welded on the outside of the side protection frame 2, and the baffle 4 is plug-in arranged in the baffle handle. Of course, the baffle 4 can also be buckled with the side protection frame 2 or other connection methods can be adopted.

[0033] Reference Figure 4 As shown, the escape structure includes a safety cover and a ladder 5. The safety cover is movably arranged on the protective plate 3, and an escape hole 6 is provided at the position of the protective plate 3 corresponding to the safety cover. The top of the ladder 5 is arranged at the escape hole 6, and the ladder 5 is arranged on the side protective frame 2. Specifically, an escape hole 6 suitable for workers to enter and exit is provided on the protective plate 3, and a safety cover is arranged at the position corresponding to the escape hole 6. The safety cover and the protective plate 3 can be hingedly connected or other connection methods can be adopted. By setting the safety cover, the integrity of the protective plate 3 is guaranteed, and the safety of the construction workers in the protective shed is guaranteed. The ladder 5 is arranged below the escape hole 6 and fixed on the side protective frame 2, which improves the stability of the ladder 5, so that the workers can evacuate in time when they encounter danger.

[0034] Furthermore, it also includes a plurality of pulleys 7, which are all arranged at the bottom of the side protection frame 2, and the pulleys 7 are connected to the side protection frame 2 through angle steel. Specifically, there are four pulleys 7, which are respectively arranged at the four bottom corners of the main body of the door frame, and are connected to the side protection frame 2 at the corresponding position through 5×5cm angle steel, so that the protection shed can be moved according to the working position, and can reach the designated position by mechanical traction when moving.

[0035] To ensure the stability of the main body of the gantry, the side protection frame 2 includes a plurality of vertical rods 201 and horizontal rods 202 connected perpendicularly to each other, and the plurality of vertical rods 201 are connected to the top protection frame 1. The plurality of vertical rods 201 are all connected to the top protection frame 1, and the plurality of horizontal rods 202 are evenly arranged along the length direction of the vertical rods 201, and the plurality of vertical rods 201 are connected to ensure the stability of the main body of the gantry. The plurality of vertical rods 201 and the horizontal rods 202 are connected to form a plurality of square frames, and each baffle 4 is suitable for completely covering each square frame.

[0036] Reference Figures 1 to 3 As shown, the main body of the portal frame also includes a diagonal brace 8, one end of the diagonal brace 8 is connected to the top protection frame 1, and the other end is connected to the side protection frame 2, and the diagonal brace 8 is made of I14 I-beam. Specifically, the two ends of the diagonal brace 8 are respectively welded to the top protection frame 1 and the vertical rod 201, or the two ends of the diagonal brace 8 are welded with connecting steel plates, and the connecting steel plates at both ends of the diagonal brace 8 are respectively connected to the top protection frame 1 and the vertical rod 201 by bolts, and the angles between the diagonal brace 8 and the top protection frame 1 and the vertical rod 201 are both 45°, forming two isosceles triangles, which improves the stability of the connection between the top protection frame 1 and the side protection frame 2, is not easy to deform, and thus ensures the safety of construction workers.

[0037] In some embodiments, a seal is provided on the circumference of the safety cover to prevent rainwater from flowing in through the gap between the safety cover and the protective plate.

[0038] Reference Figure 3 As shown, the distance from the side protection frame 2 to the slope is 20 cm, and the distance from the top protection frame 1 to the top of the foundation pit is 50 cm.

[0039] In other embodiments, the top protection frame 1 and the side protection frame 2 are both made of I18 I-beam, the protection plate 3 is made of steel plate, the thickness of the protection plate 3 is 3 mm, the baffle 4 is made of bamboo plywood, and the size of the escape hole 6 is 80×80 cm.

[0040] During the specific implementation, the protective shed is first assembled on the ground. After the foundation pit is completed according to the construction requirements, the entire protective shed is hoisted into the foundation pit, and the protective shed can be moved according to the work position. When the work in the foundation pit is completed, the protective shed is lifted as a whole and placed in the next foundation pit for use.

[0041] It should be noted that, in this article, relational terms such as "first" and "second" are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0042] The above description is only a specific embodiment of the present invention, so that those skilled in the art can understand or implement the present invention. Various modifications to these embodiments will be obvious to those skilled in the art, and the general principles defined herein can be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments described herein, but should conform to the widest scope consistent with the principles and novel features of the present invention.

Claims

1. A safety protection shed for pipeline trench deep foundation pit construction work, characterized in that: include: A portal frame body, the portal frame body comprising a top protection frame (1) and a side protection frame (2), the side protection frames (2) being arranged on both sides of the top protection frame (1) facing the slope; A protective structure, the protective structure comprising a protective plate (3) and a baffle (4), the protective plate (3) being arranged at the top end of the top protective frame (1), and the baffle (4) being movably connected to the side protective frame (2); An escape structure, the escape structure comprising a safety cover and a ladder (5), the safety cover being movably arranged on the protective plate (3), and an escape through hole (6) being provided on the protective plate (3) at a position corresponding to the safety cover, the top end of the ladder (5) being arranged at the escape through hole (6), and the ladder (5) being arranged on the side protective frame (2).

2. The safety protection shed for pipeline trench deep foundation pit construction work according to claim 1 is characterized in that: It also comprises a plurality of pulleys (7), wherein the plurality of pulleys (7) are all arranged at the bottom of the side protection frame (2), and the pulleys (7) are connected to the side protection frame (2) via angle steel.

3. The safety protection shed for pipeline trench deep foundation pit construction work according to claim 1 is characterized in that: The side protection frame (2) comprises a plurality of vertical rods (201) and horizontal rods (202) which are vertically connected to each other, and the plurality of vertical rods (201) are connected to the top protection frame (1).

4. The safety protection shed for pipeline trench deep foundation pit construction work according to claim 1 is characterized in that: The door frame body also includes an oblique brace (8), one end of the oblique brace (8) is connected to the top protection frame (1), and the other end is connected to the side protection frame (2); The diagonal brace (8) is made of I14 I-beam.

5. The safety protection shed for pipeline trench deep foundation pit construction work according to claim 1 is characterized in that: A sealing member is arranged on the circumference of the safety cover.

6. The safety protection shed for pipeline trench deep foundation pit construction work according to claim 1 is characterized in that: The distance between the side protection frame (2) and the slope is 20 cm, and the distance between the top protection frame (1) and the top of the foundation pit is 50 cm.

7. The safety protection shed for pipeline trench deep foundation pit construction work according to claim 1 is characterized in that: The top protection frame (1) and the side protection frame (2) are both made of I18 I-beam.

8. The safety protection shed for pipeline trench deep foundation pit construction work according to claim 1 is characterized in that: The protective plate (3) is made of a steel plate, and the thickness of the protective plate (3) is 3 mm.

9. The safety protection shed for pipeline trench deep foundation pit construction work according to claim 1 is characterized in that: The baffle (4) is made of bamboo plywood.

10. The safety protection shed for pipeline trench deep foundation pit construction work according to claim 1 is characterized in that: The size of the escape hole (6) is 80×80 cm.