Rapid assembling device for fabricated bridge and culvert
By using a combination of fixed frame, connecting frame and clamping assembly in the bridge and culvert assembly device, the problem of inaccurate calibration of bridge and culvert components is solved, and high-precision docking and construction efficiency of bridge and culvert components are achieved.
Patent Information
- Application Number
- CN202420361715.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-27
- Publication Date
- 2025-02-07
- Estimated Expiration
- 2034-02-27
AI Technical Summary
During the assembly process of prefabricated bridge and culverts, the position relationship of artificially calibrated bridge and culvert components is not accurate enough, resulting in inefficient construction.
A quick assembly device including a fixing frame, a connecting frame and a clamping assembly is adopted to clamp the passively connected bridge and culvert components through the clamping assembly, and the position of the active connecting parts is adjusted by a rotating wheel to ensure accurate docking between the bridge and culvert components.
It realizes high-precision docking of the positional relationship of bridge and culvert components, reduces the time and labor of manual calibration, and improves construction efficiency.
Smart Images

Figure CN222435070U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to an assembling device, in particular to a quick assembling device for a prefabricated bridge and culvert, belonging to the technical field of bridge and culvert construction. Background Art
[0002] Bridges and culverts are collectively referred to as bridges and culverts. Bridges are buildings built on rivers, lakes, and seas to allow vehicles and pedestrians to pass smoothly, and are mainly used to cross obstacles. In the construction of bridges and culverts, in order to facilitate use and improve construction efficiency, an assembled bridge and culvert was invented. Its function is a bridge and culvert structure that is pre-processed and manufactured in a prefabrication yard and then transported to the site for assembly. This structure has the advantages of fast construction speed, good engineering quality, and little impact on the environment.
[0003] In the process of using prefabricated bridges and culverts, various prefabricated panels, prefabricated piers, prefabricated abutments or other bridge and culvert components are generally processed on-site and then transported to off-site construction sites for coordinated assembly. However, in the process of assembling some components with smaller tonnage, two need to be placed relative to each other, and then the two are aligned end to end, and then connected by welding or concrete connectors. However, in the process of docking the end faces of one end of the two bridge and culvert components, manual assistance is required to calibrate the relative positions of the docking components to ensure the accuracy between the bridge and culvert components in the subsequent connection process. However, the manual calibration method is not accurate enough, and the bridge and culvert components need to be moved by naked eye observation or rough estimation of the size, which is time-consuming and labor-intensive, thereby affecting construction efficiency.
[0004] Therefore, there is an urgent need to improve the rapid assembly device of the prefabricated bridge and culvert to solve the above-mentioned problems. Utility Model Content
[0005] The purpose of the utility model is to provide a rapid assembly device for an assembled bridge culvert, which clamps the passively connected bridge culvert component through a clamping assembly, thereby fixing a fixing frame on the bridge culvert component, further fixing the connecting frame through a fixed connecting plate, adjusting the positional relationship between two rotating wheels according to the size of the actively connected bridge culvert component, and facilitating the movement and adjustment of the actively connected bridge culvert component during the docking of the two bridge culvert components, so that the positional relationship between the two bridge culvert components corresponds and is located at the same center line position. In this process, manual calibration of the positional relationship between the two bridge culvert components is eliminated, and the device has higher accuracy, saves time and effort, and can improve construction efficiency.
[0006] In order to achieve the above-mentioned purpose, the main technical solutions adopted by the utility model include: comprising a fixing frame and a connecting frame, characterized in that: the fixing frame includes two vertical plates 1 and a horizontal plate 1, the two vertical plates 1 are fixedly connected to the horizontal plate 1 by bolts, and a clamping assembly for clamping the passively connected bridge culvert components is provided in the fixing frame;
[0007] The connecting frame comprises two vertical plates 2 and a horizontal plate 2, the two vertical plates 2 are fixedly connected to the horizontal plate 2 by bolts, the lower end surface of the horizontal plate 2 is fixedly connected with a track strip block, a long groove is provided in the track strip block, a double-headed threaded rod is rotatably connected in the long groove, a sliding block is threadedly connected on the double-headed threaded rod, a rotating wheel base is fixedly connected to the sliding block, a rotating shaft is rotatably connected to the rotating wheel base, and a rotating wheel is fixedly connected to the rotating shaft;
[0008] A fixed connecting plate is fixedly connected to the side wall of one side of the two vertical plates one by bolts, and one end of the fixed connecting plate away from the vertical plate one is fixedly connected to the side wall of one side of the vertical plate two by bolts.
[0009] Preferably, a threaded rod is threadedly connected to the vertical plate 1, one end of which is fixedly connected to a rotating shaft 1, two sliding rods are slidably connected to the vertical plate 1, and both sliding rods pass through the vertical plate 1, one end of the sliding rod is fixedly connected to a movable plate, and one end of the rotating shaft 1 away from the threaded rod passes through the movable plate and is rotatably connected to the movable plate.
[0010] Preferably, two threaded rods 2 are threadedly connected on the movable plate, and the two threaded rods 2 are symmetrical and respectively located at the upper and lower positions of the threaded rod 1, the two threaded rods 2 both penetrate the movable plate, the end of the threaded rod 2 away from the movable plate penetrates the vertical plate 1, and the threaded rod 2 does not contact the vertical plate 1.
[0011] Preferably, the clamping assembly includes a clamping plate 1 and two clamping plates 2, the two clamping plates 2 are symmetrical and respectively located at the upper and lower positions of the clamping plate 1, the side walls of one side of the two clamping plates 2 are respectively hinged to the side walls of both sides of the clamping plate 1, the clamping plate 1 is rotatably connected to one end of the threaded rod 1 passing through the movable plate, and the clamping plate 2 is hinged to one end of the threaded rod 2 passing through the movable plate.
[0012] Preferably, the ends of the threaded rod 1 and the threaded rod 2 away from the movable plate are fixedly connected with a spline 1 for connecting external power input and a hand wheel for manual rotation.
[0013] Preferably, one end of the double-headed threaded rod passes through the long track strip and is fixedly connected to spline 2, a rotating through hole is opened on the vertical plate 2, a torsion shaft is movably connected in the rotating through hole, one end of the torsion shaft is clamped with spline 2, and the other end of the torsion shaft is fixedly connected to a handle.
[0014] Preferably, elastic anti-skid pads are fixedly connected to the side surfaces of the clamping plate 1 and the clamping plate 2 away from the movable plate.
[0015] The utility model has at least the following beneficial effects:
[0016] 1. Clamp the passively connected bridge and culvert components through the clamping assembly, so that the fixing frame is fixedly connected to the bridge and culvert components, and the connecting frame is further fixed by the fixed connecting plate. According to the size of the actively connected bridge and culvert components, the positional relationship between the two rotating wheels is adjusted. During the docking process of the two bridge and culvert components, the rotating wheels facilitate the movement and adjustment of the actively connected bridge and culvert components. Finally, the positional relationship between the two bridge and culvert components corresponds and is located at the same center line position. In this process, manual calibration of the positional relationship between the two bridge and culvert components is eliminated, and the process has higher accuracy, saves time and effort, and can improve construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0018] Figure 1 An isometric structural schematic diagram provided for the utility model;
[0019] Figure 2 A left side view provided for the utility model;
[0020] Figure 3 A bottom view provided for the utility model;
[0021] Figure 4 Partial structure diagram provided for the utility model Figure 1 ;
[0022] Figure 5 Partial structure diagram provided by the utility model Figure 2 ;
[0023] Figure 6 This is a partial structural cross-sectional schematic diagram provided by the utility model.
[0024] In the figure, 1, fixed frame; 101, vertical plate 1; 102, horizontal plate 1; 2, connecting frame; 201, vertical plate 2; 202, horizontal plate 2; 3, clamping assembly; 301, clamping plate 1; 302, clamping plate 2; 4, track strip block; 5, long groove; 6, double-headed threaded rod; 7, sliding block; 8, turntable base; 9, rotating shaft; 91, rotating shaft 1; 10, rotating wheel; 11, fixed connecting plate; 12, threaded rod 1; 13, sliding rod; 14, moving plate; 15, threaded rod 2; 16, spline 1; 17, spline 2; 18, hand wheel; 19, rotating through hole; 20, torsion shaft; 21, handle; 22, elastic anti-skid pad. DETAILED DESCRIPTION
[0025] The following will describe the implementation methods of the present application in detail with the help of accompanying drawings and examples, so that the implementation process of how the present application uses technical means to solve technical problems and achieve technical effects can be fully understood and implemented accordingly.
[0026] like Figure 1-Figure 6 As shown, the quick assembly device of the assembled bridge culvert provided in this embodiment includes a fixing frame 1 and a connecting frame 2. The fixing frame 1 includes two vertical plates 101 and a horizontal plate 102. The two vertical plates 101 are fixedly connected with the horizontal plate 102 by bolts. A clamping assembly 3 for clamping the passively connected bridge culvert components is provided in the fixing frame 1. Different vertical plates 101 or horizontal plates 102 are used according to the approximate size of the bridge culvert components, and then they are mechanically connected by bolts for easy replacement.
[0027] The connection frame 2 includes two vertical plates 201 and a horizontal plate 202. The two vertical plates 201 are fixedly connected to the horizontal plate 202 by bolts. Different vertical plates 201 or horizontal plates 202 are used according to the approximate size of the bridge culvert components, and then bolts are used to mechanically connect them. The lower end surface of the horizontal plate 202 is fixedly connected with a track strip block 4. A long groove 5 is provided in the track strip block 4. A double-headed threaded rod 6 is rotatably connected in the long groove 5. A sliding block 7 is threadedly connected on the double-headed threaded rod 6. A rotating wheel base 8 is fixedly connected to the sliding block 7. A rotating shaft 9 is rotatably connected to the rotating wheel base 8. A rotating wheel 10 is fixedly connected to the rotating shaft 9. By rotating the double-headed threaded rod 6, the two sliding blocks 7 can move in opposite or opposite directions at the same time.
[0028] The two vertical plates 101 are both fixedly connected with a fixed connecting plate 11 on one side of the side wall by bolts, and the end of the fixed connecting plate 11 away from the vertical plate 101 is fixedly connected with the side wall of the vertical plate 201 by bolts, and the fixed frame 1 is placed on the passively connected bridge culvert component, and then the passively connected bridge culvert component is clamped by the clamping assembly 3, so that the fixed frame 1 can be fixed, and the connecting frame 2 can be fixed by the fixed connecting plate 11, and then according to the size and width of the bridge culvert component that is actively connected, the double-headed threaded rod 6 is rotated through the sliding block 7 to adjust the two rotating wheels 1 0, and then move the actively connected bridge culvert component from the space between the rotating wheels 10. While moving, the side walls of the bridge culvert component rub against the rotating wheels 10, and the rotating wheels 10 can fix the positional relationship of the bridge culvert component, so that it can move along the center line of the passively connected bridge culvert component, and stop after moving to the moving position. At this time, the device can be removed, or the status quo can be maintained. While maintaining the status quo, it can effectively prevent the position between the components from being displaced due to other factors on the construction site, avoiding the trouble of subsequent movement.
[0029] Further, such as Figure 1 as well as Figure 5 As shown, a threaded rod 12 is threadedly connected to the vertical plate 101, one end of the threaded rod 12 is fixedly connected to the rotating shaft 191, two sliding rods 13 are slidably connected to the vertical plate 101, and the two sliding rods 13 both penetrate the vertical plate 101, one end of the sliding rod 13 is fixedly connected to the moving plate 14, the end of the rotating shaft 91 away from the threaded rod 12 penetrates the moving plate 14 and is rotatably connected to the moving plate 14, two threaded rods 2 15 are threadedly connected to the moving plate 14, and the two threaded rods 2 15 are symmetrical and respectively located at the upper and lower positions of the threaded rod 12, and the end of the threaded rod 2 15 away from the moving plate 14 penetrates the vertical plate 10 1, and the threaded rod 15 is not in contact with the vertical plate 101. Both threaded rods 15 penetrate the movable plate 14. The threaded rod 12 and the end of the threaded rod 15 away from the movable plate 14 are fixedly connected with a spline 16 for connecting external power for input and a hand wheel 18 for manual rotation. Rotating the threaded rod 12 can drive the movable plate 14 to move, and then drive the two threaded rods 15 to move. When moving, they do not contact the vertical plate 101, and the spline 16 is convenient for external power equipment to input power, or use the hand wheel 18 to manually rotate the threaded rod 12 or the threaded rod 15.
[0030] Furthermore, Figure 1 , Figure 2 as well as Figure 4As shown, the clamping assembly 3 includes a clamping plate 1 301 and two clamping plates 2 302. The two clamping plates 2 302 are symmetrical and respectively located at the upper and lower positions of the clamping plate 1 301. The side walls of the two clamping plates 2 302 are respectively hinged to the side walls of the clamping plate 1 301. The clamping plate 1 301 is rotatably connected to one end of the rotating shaft 1 91 passing through the movable plate 14. The clamping plate 2 302 is hinged to one end of the threaded rod 2 15 passing through the movable plate 14. The side surfaces of the clamping plate 1 301 and the clamping plate 2 302 away from the movable plate 14 are fixedly connected with elastic anti-skid pads 22. When the threaded rod 12 is moved, the moving plate 14 is driven to move, and then the clamping plate 1 301 and the clamping plate 2 302 are driven to move. When the clamping plate 1 301 contacts the bridge culvert component, according to the shape of the bridge culvert component, if the outer surface is circular, the threaded rod 2 15 can be used to drive the clamping plate 2 302 to move and deflect until it contacts and fits with the outer surface of the bridge culvert component. At this time, the bridge culvert component can be clamped, thereby improving the stability and tightness of the fixed connection of the fixing frame 1 on the bridge culvert component, and facilitating the connection and movement of the bridge culvert component that is actively connected later.
[0031] Furthermore, if Figure 3 as well as Figure 6 As shown, one end of the double-headed threaded rod 6 passes through the long track block 4 and is fixedly connected to the second spline 17. A rotating through hole 19 is opened on the second vertical plate 201. A torsion shaft 20 is movably connected in the rotating through hole 19. One end of the torsion shaft 20 is snap-fitted with the second spline 17, and the other end of the torsion shaft 20 is fixedly connected with a handle 21. The torsion shaft 20 is placed in the rotating through hole 19 and snap-fitted with the second spline 17. Then the handle 21 is used to rotate the double-headed threaded rod 6, which is convenient for loading and unloading and use.
[0032] like Figure 1-Figure 6 As shown, the principle of the quick assembly device of the assembled culvert provided in this embodiment is as follows: when in use, the fixing frame 1 is placed on the passively connected culvert component, and then the clamping assembly 3 is used to clamp the passively connected culvert component, so that the fixing frame 1 can be fixed, and the connecting frame 2 is fixed by fixing the connecting plate 11. According to the size and shape of the passively connected culvert component, the clamping plate 2 302 is used to further tighten it to improve the tightness of the fixing frame 1 fixedly connected to the culvert component. Then, according to the size and width of the actively connected culvert component, the double-headed threaded rod 6 is rotated through the sliding block 7 to adjust the positional relationship between the two rotating wheels 10, and then the actively connected culvert component is moved from the space between the rotating wheels 10. While moving, the side walls of the culvert component on both sides rub against the rotating wheels 10, and the rotating wheels 10 can fix the positional relationship of the culvert component, so that it can move along the center line of the passively connected culvert component, and stop after moving to the moving position. At this time, the positions of the two culvert components correspond.
Claims
1. A rapid assembly device for a prefabricated bridge culvert, comprising a fixing frame (1) and a connecting frame (2), characterized in that: The fixing frame (1) comprises two vertical plates (101) and a horizontal plate (102), the two vertical plates (101) being fixedly connected to the horizontal plate (102) by bolts, and a clamping assembly (3) for clamping the passively connected culvert components is provided in the fixing frame (1); The connection frame (2) comprises two second vertical plates (201) and a second horizontal plate (202), the two second vertical plates (201) are fixedly connected to the second horizontal plate (202) by bolts, the lower end surface of the second horizontal plate (202) is fixedly connected with a track strip block (4), a long groove (5) is provided in the track strip block (4), a double-headed threaded rod (6) is rotatably connected in the long groove (5), a sliding block (7) is threadedly connected on the double-headed threaded rod (6), a rotating wheel base (8) is fixedly connected to the sliding block (7), a rotating shaft (9) is rotatably connected to the rotating wheel base (8), and a rotating wheel (10) is fixedly connected to the rotating shaft (9); A fixed connection plate (11) is fixedly connected to the side wall of one side of the two vertical plates (101) by bolts, and one end of the fixed connection plate (11) away from the vertical plate (101) is fixedly connected to the side wall of one side of the vertical plate (201) by bolts.
2. The rapid assembly device for a prefabricated bridge and culvert according to claim 1 is characterized in that: A threaded rod (12) is threadedly connected to the vertical plate (101), one end of which is fixedly connected to a rotating shaft (91). Two sliding rods (13) are slidably connected to the vertical plate (101), and both sliding rods (13) penetrate the vertical plate (101). One end of the sliding rod (13) is fixedly connected to a movable plate (14). One end of the rotating shaft (91) away from the threaded rod (12) penetrates the movable plate (14) and is rotatably connected to the movable plate (14).
3. The rapid assembly device for a prefabricated bridge and culvert according to claim 2 is characterized in that: The movable plate (14) is threadedly connected with two threaded rods (15), and the two threaded rods (15) are symmetrical and respectively located at upper and lower positions of the threaded rod (12), and the two threaded rods (15) both penetrate the movable plate (14), and one end of the threaded rod (15) away from the movable plate (14) penetrates the vertical plate (101), and the threaded rod (15) does not contact the vertical plate (101).
4. The rapid assembly device for a prefabricated bridge and culvert according to claim 3 is characterized in that: The clamping assembly (3) includes a clamping plate 1 (301) and two clamping plates 2 (302), the two clamping plates 2 (302) are symmetrical and respectively located at the upper and lower positions of the clamping plate 1 (301), the side walls of the two clamping plates 2 (302) are respectively hinged to the side walls of the clamping plate 1 (301), the clamping plate 1 (301) is rotatably connected to one end of the threaded rod 1 (12) passing through the movable plate (14), and the clamping plate 2 (302) is hinged to one end of the threaded rod 2 (15) passing through the movable plate (14).
5. The rapid assembly device for a prefabricated bridge and culvert according to claim 3 is characterized in that: The ends of the threaded rod 1 (12) and the threaded rod 2 (15) away from the movable plate (14) are fixedly connected with a spline 1 (16) for connecting external power input and a hand wheel (18) for manual rotation.
6. The rapid assembly device for a prefabricated bridge and culvert according to claim 1 is characterized in that: One end of the double-threaded rod (6) passes through the track strip (4) and is fixedly connected to the second spline (17); a rotation through hole (19) is provided on the second vertical plate (201); a torsion shaft (20) is movably connected in the rotation through hole (19); one end of the torsion shaft (20) is clamped with the second spline (17); and the other end of the torsion shaft (20) is fixedly connected to a handle (21).
7. The rapid assembly device for a prefabricated bridge and culvert according to claim 4, characterized in that: An elastic anti-skid pad (22) is fixedly connected to the side surfaces of the clamping plate 1 (301) and the clamping plate 2 (302) away from the movable plate (14).