Efficient tunnel sewage integrated equipment
By using a liquid level sensor to control the combination of automatic replenishment of potions and power generators in the integrated tunnel sewage equipment, the problems of high manpower and power consumption during equipment operation are solved, and automated management and energy-saving effects are achieved.
Patent Information
- Application Number
- CN202421066255.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-16
- Publication Date
- 2025-02-11
- Estimated Expiration
- 2034-05-16
AI Technical Summary
The existing tunnel sewage integrated equipment requires operators to stay next to the medicine system for a long time to observe the amount of potion storage, resulting in large labor consumption and lack of energy-saving devices, which makes power consumption serious, resulting in high processing costs.
A high-efficiency tunnel sewage integrated equipment is designed, using a liquid level sensor to control the operation of the pump pump and the medicine system, automatically replenish the potion and optimize the water circulation, combined with the power generation impeller and generator in the sewage treatment system, and use water flow energy to generate Power, reduce system power consumption.
It realizes automated management, reduces manpower consumption, reduces power consumption, reduces tunnel sewage treatment costs, and improves equipment operation efficiency and energy-saving effects.
Smart Images

Figure CN222454594U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel projects, in particular to a high-efficiency tunnel sewage integrated equipment. Background Art
[0002] The tunnel sewage integrated equipment collects domestic sewage from each household into a water collection tank. A screen is installed at the entrance of the water collection tank to remove large granular and fibrous impurities in the sewage. The screen residue intercepted by the screen is manually removed and transported regularly. The sewage in the water collection tank is sent to the sewage regulating tank by gravity through the water collection tank. In the sewage regulating tank, the sewage flow is homogenized, the water volume is adjusted, and the organic matter is initially degraded. Then, the domestic sewage is input into the domestic sewage treatment system through the sewage pump. The domestic sewage treatment system consists of anoxic tanks, contact oxidation tanks, sedimentation tanks, and disinfection and discharge tanks. In the anoxic tank, the original sewage is fully mixed with the return mixed liquid, and denitrification is carried out through the action of anaerobic microorganisms.
[0003] The existing integrated tunnel sewage equipment requires operators to stay beside the medicine application system to observe the remaining amount of medicine in order to replenish it at any time. The manpower consumption is relatively serious when treating tunnel sewage for a long time. The existing integrated tunnel sewage equipment has no auxiliary energy-saving devices, the electricity consumption is relatively serious, and the cost of tunnel sewage treatment is relatively high. Utility Model Content
[0004] The technical problem to be solved by the utility model is that the existing tunnel sewage integrated equipment requires operators to stay beside the medicine application system to observe the remaining amount of medicine in order to replenish the medicine at any time. The manpower consumption is relatively serious when treating tunnel sewage for a long time. The existing tunnel sewage integrated equipment has no auxiliary energy-saving device, the electricity consumption is relatively serious, and the cost of tunnel sewage treatment is relatively high.
[0005] In order to solve the above technical problems, the technical solution of the utility model is a high-efficiency tunnel sewage integrated equipment, including a base, a load-bearing platform and a sewage treatment system, the load-bearing platform is installed on the upper wall of the base, the sewage treatment system is installed on the upper wall of the load-bearing platform, the front wall of the sewage treatment system is connected to a plurality of outlet pipes, the upper wall of the sewage treatment system is installed with a pipe positioning frame, the inner wall of the pipe positioning frame is installed with a guide structure, the front end of the guide structure is provided with a medicine-applying structure, and the rear end of the guide structure is provided with a drainage structure.
[0006] As a further solution of the utility model: the guiding structure comprises: two guiding pipes and two water pumps; the two guiding pipes are respectively installed on the inner wall surface of the pipe positioning frame, and the two water pumps are respectively connected to the outer wall surface of the two guiding pipes.
[0007] As a further solution of the utility model: the medicine applying structure includes: a mixing barrel, a plurality of agitators, two lower liquid level sensors, two upper liquid level sensors, a drainage pump and a medicine applying pipe; the mixing barrel is connected to the lower wall surface of the two water pumps, the plurality of agitators are respectively installed on the lower wall surface inside the mixing barrel, the two lower liquid level sensors are respectively installed on the inner wall surface of the mixing barrel, the two upper liquid level sensors are respectively installed on the inner wall surface of the mixing barrel, the drainage pump is installed on the front wall surface of the mixing barrel, and the medicine applying pipe is installed on the inner wall surface of the drainage pump and is connected to the mixing barrel.
[0008] As a further solution of the utility model: the drainage structure includes: a water storage power generation box, a drainage pipe and a power generation impeller; the water storage power generation box is mounted on the outer wall of a plurality of water outlet pipes and two guide pipes, the drainage pipe is connected to the front wall of the water storage power generation box, and the power generation impeller is installed on the inner wall of the water storage power generation box.
[0009] As a further solution of the utility model: the two lower liquid level sensors and the two upper liquid level sensors are installed diagonally in the mixing barrel.
[0010] As a further solution of the utility model: the medicine upper pipe is located below the lower liquid level sensor.
[0011] As a further solution of the utility model: a generator is installed in the water storage power generation box, and the power generation impeller is connected to the generator in the water storage power generation box.
[0012] The utility model adopts the above technical solution, and has the following advantages compared with the prior art:
[0013] When the two lower liquid level sensors cannot detect the medicine, the two lower liquid level sensors trigger the switches of the two water pumps, and the two water pumps guide the water in the water storage power generation box into the mixing barrel through two guide pipes. At the same time, the medicine application system sends the medicine powder into the mixing barrel in proportion, and it is mixed by several agitators to form the medicine again. When the two upper liquid level sensors detect the medicine, the two upper liquid level sensors trigger the switches of the two water pumps, and the two water pumps stop running to form a cycle. This solves the problem that the existing tunnel sewage integrated equipment requires operators to stay by the medicine application system to observe the remaining amount of medicine in order to replenish the medicine at any time, and the manpower consumption is relatively serious when treating tunnel sewage for a long time.
[0014] When the sewage treatment system introduces the treated water into the water storage power generation box through several outlet pipes, the water flow hits the power generation impeller. The power generation impeller converts kinetic energy into electrical energy through the generator installed in the water storage power generation box, and supplies power to the two lower liquid level sensors and the two upper liquid level sensors, thereby reducing the system's power consumption and solving the problem that the existing tunnel sewage integrated equipment has no auxiliary energy-saving devices, the power consumption is relatively serious, and the cost of tunnel sewage treatment is relatively high. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 This is a schematic diagram of the structure of a high-efficiency tunnel sewage integrated equipment in an embodiment of the utility model;
[0016] Figure 2 This is a schematic diagram of a guide structure of a high-efficiency tunnel sewage integrated equipment in an embodiment of the utility model;
[0017] Figure 3 This is a schematic diagram of the medicine-applying structure of a high-efficiency tunnel sewage integrated equipment in an embodiment of the utility model;
[0018] Figure 4 It is a schematic diagram of the drainage structure of a high-efficiency tunnel sewage integrated equipment in an embodiment of the utility model.
[0019] In the figure: 1. base; 2. load-bearing platform; 3. sewage treatment system; 4. outlet pipe; 5. pipe positioning frame; 6. guide pipe; 7. water pump; 8. mixing barrel; 9. agitator; 10. lower liquid level sensor; 11. upper liquid level sensor; 12. drainage pump; 13. medicine pipe; 14. water storage power generation box; 15. drainage pipe; 16. power generation impeller. DETAILED DESCRIPTION
[0020] The specific implementation methods of the present invention are further described below in conjunction with the accompanying drawings. It should be noted that the description of these implementation methods is used to help understand the present invention, but does not constitute a limitation of the present invention. In addition, the technical features involved in each implementation method of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0021] Example 1, please refer to Figure 1-Figure 4 A high-efficiency tunnel sewage integrated equipment includes a base 1, a bearing platform 2 and a sewage treatment system 3, the bearing platform 2 is installed on the upper wall of the base 1, the sewage treatment system 3 is installed on the upper wall of the bearing platform 2, a front wall of the sewage treatment system 3 is connected with a plurality of outlet pipes 4, a pipe positioning frame 5 is installed on the upper wall of the sewage treatment system 3, a guide structure is installed on the inner wall of the pipe positioning frame 5, a medicine-applying structure is mounted on the front end of the guide structure, and a drainage structure is mounted on the rear end of the guide structure.
[0022] See also Figure 2 The guiding structure includes: two guiding pipes 6 and two water pumps 7; the two guiding pipes 6 are respectively installed on the inner wall surface of the pipe positioning frame 5, and the two water pumps 7 are respectively connected to the outer wall surface of the two guiding pipes 6.
[0023] See also Figure 3 The medicine applying structure includes: a mixing barrel 8, a plurality of agitators 9, two lower liquid level sensors 10, two upper liquid level sensors 11, a drainage pump 12 and a medicine applying pipe 13; the mixing barrel 8 is connected to the lower wall surfaces of the two water pumps 7, the plurality of agitators 9 are respectively installed on the lower wall surfaces inside the mixing barrel 8, the two lower liquid level sensors 10 are respectively installed on the inner wall surfaces of the mixing barrel 8, the two upper liquid level sensors 11 are respectively installed on the inner wall surfaces of the mixing barrel 8, the drainage pump 12 is installed on the front wall surface of the mixing barrel 8, and the medicine applying pipe 13 is installed on the inner wall surface of the drainage pump 12 and is connected to the mixing barrel 8.
[0024] See also Figure 3 The two lower liquid level sensors 10 and the two upper liquid level sensors 11 are installed diagonally in the mixing barrel 8. In this embodiment, the diagonal installation can make the detection more accurate.
[0025] See also Figure 3 The upper medicine pipe 13 is located below the lower liquid level sensor 10. In this embodiment, the upper medicine pipe 13 is located below the lower liquid level sensor 10 to prevent the medicine water in the mixing barrel 8 from being drained, resulting in suspension of work.
[0026] In this embodiment, when the two lower liquid level sensors 10 cannot detect the medicine liquid, the two lower liquid level sensors 10 trigger the switches of the two water pumps 7, and the two water pumps 7 guide the water in the water storage power generation box 14 into the mixing barrel 8 through the two guide pipes 6. At the same time, the medicine feeding system delivers the powder into the mixing barrel 8 in proportion, and the medicine liquid is formed again after being mixed by several agitators 9. When the two upper liquid level sensors 11 detect the medicine liquid, the two upper liquid level sensors 11 trigger the switches of the two water pumps 7, and the two water pumps 7 stop running to form a cycle.
[0027] Specifically, the operator starts the drug application system, which introduces the drug powder and water into the mixing barrel 8, and then the several agitators 9 start to stir. After a certain period of time, the drainage pump 12 is started, and the drainage pump 12 sends the drug solution to the sewage treatment system 3 through the drug application pipe 13 to start tunnel sewage treatment. The treated clean water enters the water storage power generation box 14 through the several outlet pipes 4. After the drug application system inputs the drug powder and water into the mixing barrel 8 for the first time, it only inputs the drug powder into the mixing barrel 8 before stopping. When the two lower parts When the liquid level sensor 10 cannot detect the medicine liquid, the two lower liquid level sensors 10 trigger the switches of the two water pumps 7, and the two water pumps 7 guide the water in the water storage power generation box 14 into the mixing barrel 8 through the two guide pipes 6. At the same time, the medicine feeding system sends the powder into the mixing barrel 8 in proportion, and the medicine liquid is formed again after being mixed by several stirrers 9. When the two upper liquid level sensors 11 detect the medicine liquid, the two upper liquid level sensors 11 trigger the switches of the two water pumps 7, and the two water pumps 7 stop running to form a cycle.
[0028] Example 2, please refer to Figure 2 The drainage structure includes: a water storage power generation box 14, a drainage pipe 15 and a power generation impeller 16; the water storage power generation box 14 is mounted on the outer wall of a plurality of water outlet pipes 4 and two guide pipes 6, the drainage pipe 15 is connected to the front wall of the water storage power generation box 14, and the power generation impeller 16 is installed on the inner wall of the water storage power generation box 14.
[0029] See also Figure 4 A generator is installed in the water storage power generation box 14, and the power generation impeller 16 is connected to the generator in the water storage power generation box 14. In this embodiment, the power generation impeller 16 converts kinetic energy into electrical energy through the generator installed in the water storage power generation box 14, and supplies power to the two lower liquid level sensors 10 and the two upper liquid level sensors 11, thereby reducing the power consumption of the system.
[0030] In this embodiment, when the sewage treatment system 3 introduces the treated water into the water storage power generation box 14 through a plurality of outlet pipes 4, the water flow impacts the power generation impeller 16. The power generation impeller 16 converts the kinetic energy into electrical energy through the generator installed in the water storage power generation box 14, and supplies power to the two lower liquid level sensors 10 and the two upper liquid level sensors 11, thereby reducing the power consumption of the system.
[0031] Specifically, when the sewage treatment system 3 introduces the treated water into the water storage power generation box 14 through a plurality of outlet pipes 4, the water flow impacts the power generation impeller 16, and the power generation impeller 16 converts the kinetic energy into electrical energy through the generator installed in the water storage power generation box 14, and supplies power to the two lower liquid level sensors 10 and the two upper liquid level sensors 11, thereby reducing the power consumption of the system. When the water level in the water storage power generation box 14 is higher than the drain pipe 15, the stored water is discharged through the drain pipe 15.
[0032] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the described embodiments. For those skilled in the art, various changes, modifications, substitutions and variations of these embodiments are made without departing from the principles and spirit of the present invention, and still fall within the scope of protection of the present invention.
Claims
1. An efficient tunnel sewage integrated equipment, comprising a base (1), a bearing platform (2) and a sewage treatment system (3), characterized in that: The load-bearing platform (2) is mounted on the upper wall surface of the base (1); the sewage treatment system (3) is mounted on the upper wall surface of the load-bearing platform (2); a plurality of water outlet pipes (4) are connected to the front wall surface of the sewage treatment system (3); a pipe positioning frame (5) is mounted on the upper wall surface of the sewage treatment system (3); a guide structure is mounted on the inner wall surface of the pipe positioning frame (5); a medicine-applying structure is mounted on the front end of the guide structure; and a drainage structure is mounted on the rear end of the guide structure.
2. The high-efficiency tunnel sewage integrated equipment according to claim 1 is characterized in that: The guide structure comprises: two guide pipes (6) and two water pumps (7); The two guide pipes (6) are respectively mounted on the inner wall surface of the pipe positioning frame (5), and the two water pumps (7) are respectively connected to the outer wall surfaces of the two guide pipes (6).
3. The high-efficiency tunnel sewage integrated equipment according to claim 2 is characterized in that: The drug applying structure comprises: a stirring barrel (8), a plurality of stirrers (9), two lower liquid level sensors (10), two upper liquid level sensors (11), a drainage pump (12) and a drug applying pipe (13); The mixing barrel (8) is connected to the lower wall surfaces of the two water pumps (7), the plurality of stirrers (9) are respectively mounted on the lower wall surfaces inside the mixing barrel (8), the two lower liquid level sensors (10) are respectively mounted on the inner wall surfaces of the mixing barrel (8), the two upper liquid level sensors (11) are respectively mounted on the inner wall surfaces of the mixing barrel (8), the drainage pump (12) is mounted on the front wall surface of the mixing barrel (8), and the medicine supply pipe (13) is mounted on the inner wall surface of the drainage pump (12) and is connected to the mixing barrel (8).
4. The high-efficiency tunnel sewage integrated equipment according to claim 2 is characterized in that: The drainage structure comprises: a water storage power generation box (14), a drainage pipe (15) and a power generation impeller (16); The water storage power generation box (14) is sleeved on the outer wall surfaces of a plurality of water outlet pipes (4) and two guide pipes (6); the drainage pipe (15) is connected to the front wall surface of the water storage power generation box (14); and the power generation impeller (16) is installed on the inner wall surface of the water storage power generation box (14).
5. The high-efficiency tunnel sewage integrated equipment according to claim 3 is characterized in that: The two lower liquid level sensors (10) and the two upper liquid level sensors (11) are installed diagonally in the mixing barrel (8).
6. The high-efficiency tunnel sewage integrated equipment according to claim 3 is characterized in that: The medicine supply pipe (13) is located below the lower liquid level sensor (10).
7. The high-efficiency tunnel sewage integrated equipment according to claim 4 is characterized in that: A generator is installed in the water storage power generation box (14), and the power generation impeller (16) is connected to the generator in the water storage power generation box (14).