Concrete vertical wall formwork opposite-penetrating pull rod end detachable presetting device
By designing a preset device for detachable and detachable ends of the concrete vertical wall formwork including casting formwork and cavity blocking block, the problem of difficulty in neatness around the holes during concrete pouring is solved, and the concrete facade is flat and improved Viewing.
Patent Information
- Application Number
- CN202421115664.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-21
- Publication Date
- 2025-02-11
- Estimated Expiration
- 2034-05-21
AI Technical Summary
During the concrete pouring process, when the concrete surface is chiseled off at the through-tie rod position, it is difficult to be neat around the holes, which affects the appearance of the concrete facade.
A preset device for detachable end of concrete vertical wall formwork is designed, including cast formwork and cavity blockage block. The cavity block consists of preset steel thread nuts, outsourcing conical plastic sleeve head, connector head and connection groove. By rotating the outside of the cavity block, the outsourcing conical plastic sleeve head and concrete contact surface are peeled off. , separate the preset steel thread nut from the opposite pull rod body to achieve flat concrete facade.
Through this device, the cavity block can be easily removed after the concrete solidifies, revealing a round groove, ensuring that flat concrete surfaces are provided on both sides of the main body of the pull rod to enhance the appearance of the concrete facade.
Smart Images

Figure CN222456814U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of concrete pouring, in particular to a detachable preset device for the ends of tie rods of a concrete vertical wall template. Background Art
[0002] A through-tie rod is a commonly used support structure in building construction. It can provide stable support force and help maintain the stability of the building structure. This type of rod is usually used in the concrete pouring process to ensure the stability and safety of the formwork. When the through-tie rod is placed, the concrete surface is chiseled, but it is difficult to make the area around the hole neat, which affects the appearance of the concrete facade. Therefore, a detachable preset device for the through-tie rod end of the concrete facade formwork is required.
[0003] The application number currently retrieved is: CN201810692780.9, a building wall concrete formwork that reuses the through-pull rod, is easy to disassemble, has strong practicality, can be reused, and reduces the waste of resources.
[0004] However, the existing concrete pouring still has certain defects in actual use: the concrete surface is chiseled off at the through-tie rod position, but it is difficult to make the area around the hole neat, which affects the appearance of the concrete facade. For this reason, we propose a detachable preset device for the through-tie rod end of the concrete wall formwork. Utility Model Content
[0005] In order to make up for the above shortcomings, the utility model provides a concrete wall template that chisels away the concrete surface at the tie rod position, but it is difficult to make the periphery of the hole neat, which affects the appearance of the concrete facade.
[0006] The utility model realizes a detachable preset device for the end of the through-tie rod of a concrete vertical wall formwork through the following technical scheme, comprising a casting formwork and a cavity blocking block, wherein fixed erecting plates are installed on both sides of the casting formwork by bolts, and a clamping fixing plate is installed on the side of the fixed erecting plate away from the casting formwork by bolts, and a through-tie rod body is placed at the center of the two groups of the clamping fixing plates, and the cavity blocking blocks are arranged on both sides of the casting formwork and the through-tie rod body.
[0007] Furthermore, the cavity blocking block includes a preset steel threaded nut, an outer conical plastic sleeve cover, a connecting head and a connecting groove, and the outer surface of the preset steel threaded nut is filled with the outer conical plastic sleeve cover, and a connecting head is arranged at the center of the preset steel threaded nut and the outer conical plastic sleeve cover, and a connecting groove is arranged on the side of the outer conical plastic sleeve cover away from the preset steel threaded nut.
[0008] Furthermore, a concrete body is arranged at the center of the cavity blocking block, and the cavity blocking block is cone-shaped as a whole, and the fixed end of the cavity blocking block is located inside the concrete body.
[0009] The utility model provides a detachable preset device for the ends of the tie rods of the concrete vertical wall template, which has the following beneficial effects:
[0010] When the through-tie rod body is inserted into both sides of the casting template, cavity plugging blocks are respectively installed at both ends of the through-tie rod body, wherein the tip of the cavity plugging block is located at the inner wall of the casting template. When concrete is poured, the concrete contacts the cavity plugging block. After the concrete solidifies, the outer side of the cavity plugging block is rotated so that the outer conical plastic sleeve seal of the cavity plugging block is peeled off from the contact surface of the concrete, and the preset steel threaded nut of the cavity plugging block is separated from the through-tie rod body, so that when the cavity plugging block is separated, the concrete is away from the area of the cavity plugging block, exposing the cavity, so that rounded grooves are set on both sides of the through-tie rod body. The specific contents are as follows:
[0011] Fixed erecting plates are installed on both sides of the casting formwork by bolts, and a clamping fixing plate is installed on the side of the casting formwork away from the casting formwork by bolts, and a through-rod body is placed at the center of the two sets of clamping fixing plates, and a cavity blocking block is arranged on both sides of the casting formwork and the through-rod, and the cavity blocking block includes a preset steel threaded nut, an outer conical plastic sleeve head, a connecting head and a connecting groove, and the outer surface of the preset steel threaded nut is filled with an outer conical plastic sleeve head, and a connecting head is arranged at the center of the preset steel threaded nut and the outer conical plastic sleeve head, and a connecting groove is arranged on the side of the outer conical plastic sleeve head away from the preset steel threaded nut, a concrete body is arranged at the center of the cavity blocking block, and the cavity blocking block is cone-shaped as a whole, and the fixed end of the cavity blocking block is located inside the concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a schematic diagram of the overall structure of a detachable preset device for the end of a tie rod for a concrete vertical wall template according to the utility model;
[0013] Figure 2 It is a structural schematic diagram of a through-tie rod main body of a through-tie rod end of a concrete vertical wall formwork of the utility model;
[0014] Figure 3 It is a schematic diagram of the front cross-section structure of a cavity blocking block of a detachable preset device for penetrating the end of a tie rod of a concrete vertical wall formwork of the utility model;
[0015] Figure 4It is a structural schematic diagram of a front view section of a preset steel thread nut of a detachable preset device for penetrating the end of a tie rod of a concrete vertical wall formwork of the utility model;
[0016] Figure 5 The utility model is a detachable preset device for the end of the tie rod of the concrete vertical wall template Figure 2 Schematic diagram of the structure at A in the middle.
[0017] In the figure: 1. Casting formwork; 2. Fixed erecting plate; 3. Clamping fixing plate; 4. Through-rod body; 5. Cavity blocking block; 6. Concrete body; 7. Pre-set steel threaded nut; 8. Outer conical plastic sleeve head; 9. Connecting head; 10. Connecting groove. DETAILED DESCRIPTION
[0018] The following is a further detailed description of the implementation of the present invention in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but cannot be used to limit the scope of the present invention.
[0019] like Figure 1 - Figure 5 As shown, a detachable preset device for the end of the through-tie rod of a concrete vertical wall formwork comprises a casting formwork 1 and a cavity blocking block 5, both sides of the casting formwork 1 are fixed with erecting plates 2 by bolts, and the fixed erecting plates 2 are fixed with clamping fixing plates 3 by bolts on the side away from the casting formwork 1, and through-tie rod bodies 4 are placed at the centers of the two sets of clamping fixing plates 3, and the cavity blocking block 5 is arranged on both sides of the casting formwork 1 and the through-tie rod body 4, wherein the through-tie rod body 4 is used to fix the formwork and control the wall thickness before the concrete body 6 is cast, and at the same time, after the concrete body 6 solidifies, the through-tie rod can also withstand The lateral pressure and other loads of the concrete body 6 ensure that the spacing between the inner and outer formworks can meet the design requirements. It is also the fulcrum of the formwork and its supporting structure. At this time, when the concrete body 6 is poured inside the casting formwork 1, the through-tie rod body 4 is filled inside the casting concrete body 6. After the concrete body 6 solidifies, the through-tie rod remains inside the concrete body 6. Before pouring the concrete body 6, the two ends of the through-tie rod are in contact with the casting formwork 1 through the connecting groove 10 of the cavity blocking block 5, thereby blocking the casting formwork 1 while also fixing the through-tie rod body 4.
[0020] The cavity plugging block 5 includes a preset steel threaded nut 7, an outer conical plastic sleeve seal 8, a connector 9 and a connecting groove 10, and the outer surface of the preset steel threaded nut 7 is filled with an outer conical plastic sleeve seal 8, and the centers of the preset steel threaded nut 7 and the outer conical plastic sleeve seal 8 are both provided with a connector 9, and the outer conical plastic sleeve seal 8 is provided with a connecting groove 10 on the side away from the preset steel threaded nut 7, a concrete body 6 is provided at the center of the two groups of cavity plugging blocks 5, and the cavity plugging block 5 is cone-shaped as a whole, and the fixed end of the cavity plugging block 5 Located inside the concrete body 6, when the concrete body 6 is poured, the cavity plugging blocks 5 are used to fill the gaps on both sides of the pouring template 1 for inserting the through-pull rod body 4. Therefore, when the concrete body 6 is poured, when the concrete body 6 contacts the cavity plugging blocks 5, the concrete body 6 is restricted by the cavity plugging blocks 5. At this time, the cavity plugging blocks 5 reserved on the outside of the pouring template 1 are used for convenient clamping, thereby facilitating the clamping of the cavity plugging blocks 5. Since the outer conical plastic sleeve seal 8 is in contact with the concrete, when During the rotation, the area where the outer conical plastic sleeve seal 8 contacts the concrete is rotated, so that it is separated from the concrete body 6, thereby completing the peeling of the cavity blocking block 5, so that the wall of the concrete body 6 is located at the cavity where the outer surface of the through-tie rod body 4 is set, so that the through-tie rod body 4 on both sides of the extra concrete body 6 is cut, and the outer conical plastic sleeve seal 8 is a plastic structure. Due to the properties of its colloid structure, when it contacts the concrete body 6, the two are not easy to adhere, so that it can be When the cavity blocking block 5 is separated, it can be more convenient to separate the cavity blocking block 5, and the steel threaded nut is connected to the through-pull rod body 4 through the connecting groove 10, thereby completing the fixation of the through-pull rod body 4, and the steel threaded nut is clamped to the outer conical plastic sleeve head 8 through the connecting head 9, so that the outer conical plastic sleeve head 8 is clamped to the outer conical plastic sleeve head 8, and at the same time, by pulling, it is convenient to separate the steel threaded nut and the outer conical plastic sleeve head 8, so that the two can be disassembled and assembled.
[0021] In summary, the utility model uses a casting template 1 and a cavity blocking block 5, wherein the casting template 1 is fixed by fixing the erecting plate 2, so that a cavity is formed inside the casting template 1, and at this time, one end of the through-rod body 4 is connected to the cavity blocking block 5, and the other end of the through-rod body 4 is not connected to the cavity blocking block 5 and is inserted into the empty grooves on both sides of the casting template 1, so that the cavity blocking block 5 connected to one end of the through-rod body 4 is connected to the casting template 1, thereby completing the blocking of one side of the casting template 1, and the other end of the through-rod body 4 is inserted into the cavity blocking block 5 to fix the through-rod body 4, and is also used to insert one end of the tip area of the cavity blocking block 5 into the interior of the casting template 1, and at this time, the through-rod body 4 is fixed by clamping the fixing plate 3, this When the concrete body 6 is poured into the casting template 1, after the concrete body 6 is completely solidified, the clamping fixing plate 3 and the fixed erecting plate 2 are disassembled, and the outer surface of the outer conical plastic sleeve head 8 of the cavity blocking block 5 is clamped, and then the outer conical plastic sleeve head 8 is rotated. Due to the properties of the outer conical plastic sleeve head 8, the area of the concrete body 6 in contact with the outer conical plastic sleeve head 8 is peeled off during the rotation, so that the preset steel threaded nut 7 inside the outer conical plastic sleeve head 8 is peeled off outward along the through-rod body 4, so that a cavity is formed in the area of the concrete body 6 outside the through-rod. Therefore, when the through-rod body 4 is cut, the through-rod body 4 is made parallel to the concrete body 6.
Claims
1. A detachable preset device for the ends of tie rods for a concrete vertical wall formwork, comprising a casting formwork (1) and a cavity blocking block (5), characterized in that: Both sides of the casting template (1) are fixed with erection plates (2) by means of bolts, and the side of the fixed erection plates (2) away from the casting template (1) is fixed with clamping plates (3) by means of bolts, and a through-rod body (4) is placed at the center of the two sets of the clamping plates (3), and the cavity blocking blocks (5) are arranged on both sides of the casting template (1) and the through-rod body (4).
2. A detachable preset device for the ends of the tie rods of a concrete vertical wall formwork according to claim 1, characterized in that: The cavity blocking block (5) comprises a preset steel threaded nut (7), an outer conical plastic sleeve seal head (8), a connector (9) and a connecting groove (10), and the outer surface of the preset steel threaded nut (7) is filled with the outer conical plastic sleeve seal head (8), and the preset steel threaded nut (7) and the outer conical plastic sleeve seal head (8) are both provided with a connector (9) at the center, and the outer conical plastic sleeve seal head (8) is provided with a connecting groove (10) on a side away from the preset steel threaded nut (7).
3. A detachable preset device for the ends of the tie rods of a concrete vertical wall formwork according to claim 1, characterized in that: A concrete body (6) is arranged at the center of the two groups of cavity blocking blocks (5), and the cavity blocking blocks (5) are cone-shaped as a whole, and the fixed end of the cavity blocking block (5) is located inside the concrete body (6).
Citation Information
Patent Citations
Reutilized through pull rod of housing construction wall concrete formwork
CN108894492A