Tool box for power line repair
By designing buffer mechanisms in the power emergency tool box, including rectangular frames, damping rods, springs, rubber blocks and sponge blocks, the problem of the lack of buffering function in the existing tool box has been solved, and the detection instrument damage has been achieved, achieving higher safety of use sex.
Patent Information
- Application Number
- CN202420278988.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-05
- Publication Date
- 2025-02-14
- Estimated Expiration
- 2034-02-05
AI Technical Summary
The existing toolbox for power emergency repair lacks buffering function and cannot effectively protect the detection instruments in the toolbox from damage caused by accidental collisions and vibrations.
A tool box with a buffer mechanism is designed. The main body of the tool box is equipped with a rectangular frame and a damping rod. The outer periphery of the damping rod is equipped with a spring. The bottom of the rectangular frame is fixedly connected with rubber blocks and sponge blocks. Through the combination of these components, A buffer mechanism is formed to absorb the impact when the toolbox falls.
It effectively reduces the risk of damage to the detection instruments in the toolbox due to accidental collisions and vibrations, and improves the safety of the toolbox during emergency repairs.
Smart Images

Figure CN222472465U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of power emergency repair equipment, in particular to a tool box for power emergency repair. Background Art
[0002] The power emergency repair toolbox is a power emergency repair device used for power distribution network. When using the toolbox, the tools and instruments needed for power emergency repair are directly placed inside the toolbox body, so that the emergency repair tools can be carried well, and power emergency repair related to power distribution network can be carried out well.
[0003] The inventor has found in his daily work that there are still at least the following problems with the power repair toolbox: when using the repair toolbox, the repair tools and instruments are directly placed inside the toolbox body, but in actual use, the toolbox is carried by using a portable handle, and the portable handle can easily cause the toolbox to be bumped and dropped, which will generate large vibrations and may damage the detection instruments inside the toolbox.
[0004] At present, a Chinese patent has been retrieved for a multifunctional power emergency repair tool box, with announcement number CN216940616U, which includes: a box body; four rotating slots, each of which is opened on the box body, and each of the four rotating slots is rotatably connected to a connecting leg, a supporting leg is fixedly connected to the bottom of the connecting leg, a connecting rod is fixedly connected to one side of the supporting leg, and an insulating anti-skid pad is fixedly connected to the bottom end of the supporting leg; although the multifunctional power emergency repair tool box of this patent rotates the supporting legs so that the supporting legs on both sides are rotated to be perpendicular to the box body, and the two connecting rods are connected by a connecting belt, so that the tool box becomes a temporary heightening ladder, so that personnel can stand on the tool box, contact and repair power components at higher places, effectively avoiding the trouble of inconvenience of carrying heightening tools after carrying the tool box, so that maintenance personnel can perform power maintenance work more conveniently; but the tool box does not have a buffer function and cannot ensure the safe use of the detection instruments in the tool box. Utility Model Content
[0005] The utility model aims to solve the deficiencies in the prior art and to provide a tool box for power emergency repairs. The tool box has a buffering function inside, thereby avoiding or reducing accidental damage to detection instruments inside the tool box.
[0006] In order to achieve the above-mentioned purpose, the utility model adopts the following technical scheme: a tool box for power emergency repair, a connecting cover is provided on the top of the tool box body, a handle is provided on the top of the connecting cover, a buffer mechanism is provided inside the tool box body, a fixing mechanism is provided on the inner bottom of the tool box body, the buffer mechanism includes a rectangular frame, the rectangular frame is provided inside the tool box body, a first damping rod is fixedly connected to the inner bottom of the tool box body, an end of the first damping rod away from the tool box body is fixedly connected to the outer bottom of the rectangular frame, and a first spring is provided on the outer periphery of the first damping rod.
[0007] The effect achieved by the above components is: when the buffer mechanism is used, the emergency repair instrument is directly placed inside the rectangular frame. When the tool box slips from the hands of the emergency repair personnel due to an accidental collision with the handle, the tool box body falls vertically, causing the bottom of the tool box body to be hit, thereby causing the first damping rod and the first spring to contract. This can play a buffering role to a certain extent and can prevent the emergency repair instrument from being damaged due to vibration to a certain extent.
[0008] Preferably, a second damping rod is fixedly connected to the inner side of the connecting cover, an end of the second damping rod away from the connecting cover is fixedly connected to a connecting plate, a second spring is sleeved on the outer periphery of the second damping rod, and the connecting plate is relatively sleeved with the inner wall of the rectangular frame.
[0009] The effect achieved by the above components is: through the squeezing effect of the second damping rod and the second spring, the connecting plate can be well confined inside the rectangular frame. When the bottom of the toolbox body is hit, the second damping rod and the second spring contract, thereby playing a certain buffering role.
[0010] Preferably, one end of the connecting plate away from the second damping rod is evenly and fixedly connected with a sponge block.
[0011] The effect achieved by the above components is: when the connecting plate is sleeved inside the rectangular frame, the sponge block is stuffed into the inside of the rectangular frame, and then the emergency repair instruments and tools inside the rectangular frame are squeezed by the sponge block, thereby effectively preventing the emergency repair instruments and tools from sliding or moving inside the rectangular frame, thereby preventing the emergency repair instruments from bumping into the inside of the rectangular frame and being damaged.
[0012] Preferably, a rubber block is fixedly connected to the outer bottom of the rectangular frame, and round holes are evenly penetrated through one side of the rubber block.
[0013] The effect achieved by the above components is that when the first damping rod contracts, the rubber block squeezes the bottom of the toolbox body, causing the rubber block to be squeezed and deformed. Because circular holes are evenly opened on the sides of the rubber block, the deformation degree of the rubber block is increased, thereby playing a certain degree of buffering role.
[0014] Preferably, the fixing mechanism includes a U-shaped plate, the inner wall of the U-shaped plate is fixedly connected to a rotating rod, the surface of the rotating rod is rotatably sleeved with a support rod, the end of the support rod away from the U-shaped plate is fixedly connected to a first semicircular plate, and the end of the first semicircular plate away from the support rod is provided with a second semicircular plate.
[0015] The effect achieved by the above components is: when using the fixing mechanism, when performing emergency repairs at the top of the utility pole, the support rod is manually controlled to rotate on the surface of the rotating rod, so that the support rod is moved away from the tool box body, and then the first semicircular plate is sleeved on the surface of the top of the utility pole, and then the second semicircular plate is sleeved on the surface of the top of the utility pole, and then the tool box body is set on the surface of the top of the utility pole through the circle formed by the first semicircular plate and the second semicircular plate, so that it is very convenient for emergency repair personnel to take tools.
[0016] Preferably, a threaded rod is threadedly inserted through one side of the second semicircular plate, the threaded rod is threadedly inserted through one side of the first semicircular plate, and a nut is threadedly sleeved on one end of the threaded rod close to the first semicircular plate.
[0017] The effect achieved by the above components is: the threaded rod is threadedly inserted through the second semicircular plate and the first semicircular plate in sequence, and then the nut is threadedly sleeved on one end of the threaded rod close to the first semicircular plate, thereby well fixing the first semicircular plate and the second semicircular plate together.
[0018] Preferably, a locking plate is slidably inserted into one side of the U-shaped plate, and the locking plate is arranged on the surface of the support rod.
[0019] The effect achieved by the above components is: when the fixing mechanism is not in use, the support rod is manually controlled to rotate relative to the rotating rod, so that the support rod is close to the bottom of the tool box body, and then the positioning plate is inserted into the inside of the U-shaped plate, and then the positioning plate is limited and set on the surface of the support rod, so that the support rod can be well fixed on the surface of the rotating rod.
[0020] Preferably, one end of the positioning plate away from the U-shaped plate is fixedly connected to the first end of the third spring, and the second end of the third spring is fixedly connected to one side of the U-shaped plate.
[0021] The effect achieved by the above components is: the third spring pulls the locking plate away from one end of the U-shaped plate, thereby effectively restricting the locking plate inside the U-shaped plate.
[0022] In the utility model, a buffer mechanism is provided. When the buffer mechanism is used, the emergency repair instrument is directly placed inside the rectangular frame. When the tool box accidentally slips from the hands of the emergency repair personnel due to a collision with the handle, the tool box body falls vertically, and the bottom of the tool box body is collided, which causes the first damping rod and the first spring to contract. This can play a buffering role to a certain extent, and can prevent the emergency repair instrument from being damaged due to vibration to a certain extent. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 The utility model provides a three-dimensional structural schematic diagram of a tool box for power emergency repair;
[0024] Figure 2 A three-dimensional structural schematic diagram of a novel rectangular frame proposed for the utility model;
[0025] Figure 3 The three-dimensional structural diagram of the novel rubber block proposed in the utility model;
[0026] Figure 4 The utility model provides a three-dimensional structural schematic diagram of a novel U-shaped plate.
[0027] Legend: 1. Toolbox body; 2. Connecting cover; 3. Handle; 4. Buffer mechanism; 401. Rectangular frame; 402. First damping rod; 403. First spring; 404. Second damping rod; 405. Second spring; 406. Connecting plate; 407. Sponge block; 408. Rubber block; 409. Round hole; 5. Fixing mechanism; 501. U-shaped plate; 502. Rotating rod; 503. Support rod; 504. First semicircular plate; 505. Second semicircular plate; 506. Threaded rod; 507. Nut; 508. Positioning plate; 509. Third spring. DETAILED DESCRIPTION
[0028] Embodiment 1, as Figure 1-4 As shown, a tool box for power emergency repair is provided with a connecting cover 2 on the top of the tool box body 1. Specifically, the connecting cover 2 can be hinged to the tool box body 1 by hinges or loose-leafs, a handle 3 is provided on the top of the connecting cover 2, a buffer mechanism 4 is provided inside the tool box body 1, and a fixing mechanism 5 is provided on the inner bottom of the tool box body 1. When using the tool box, the tools and instruments needed for power emergency repair are directly placed inside the tool box body 1, so that the emergency repair tools can be well carried, and power emergency repair related to the power distribution network can be well carried out.
[0029] Reference Figure 2 and Figure 3The buffer mechanism 4 includes a rectangular frame 401, which is arranged inside the toolbox body 1. A first damping rod 402 is fixedly connected to the inner bottom of the toolbox body 1. One end of the first damping rod 402 away from the toolbox body 1 is fixedly connected to the outer bottom of the rectangular frame 401. A first spring 403 is sleeved on the outer periphery of the first damping rod 402. When the buffer mechanism 4 is used, the emergency repair instrument is directly placed inside the rectangular frame 401. When the handle 3 accidentally slips from the hands of the emergency repair personnel due to a collision, the toolbox body 1 falls vertically, thereby causing the toolbox body 1 to fall. The bottom of the rectangular frame 401 is collided, thereby causing the first damping rod 402 (which can be made of rubber, silicone or sponge and other materials) and the first spring 403 to contract, which can play a buffering role to a certain extent, and can avoid the repair instrument from being damaged due to vibration to a certain extent. The inner side of the connecting cover 2 is fixedly connected with a second damping rod 404, and the end of the second damping rod 404 away from the connecting cover 2 is fixedly connected with a connecting plate 406. The surface of the second damping rod 404 is sleeved with a second spring 405, and the connecting plate 406 is relatively sleeved with the inner wall of the rectangular frame 401. Through the second damping rod 404 and the first The squeezing effect of the second spring 405 can well restrict the connecting plate 406 inside the rectangular frame 401. When the bottom of the tool box body 1 is hit, the second damping rod 404 and the second spring 405 contract, which can play a certain buffering role. The end of the connecting plate 406 away from the second damping rod 404 is evenly fixedly connected with a sponge block 407. When the connecting plate 406 is slid into the interior of the rectangular frame 401, the sponge block 407 is slid into the interior of the rectangular frame 401, and then the repair instruments and tools inside the rectangular frame 401 are squeezed by the sponge block 407, so that it is very In order to prevent the emergency repair instruments and tools from moving inside the rectangular frame 401, and thus prevent the emergency repair instruments from bumping into the inside of the rectangular frame 401 and being damaged, a rubber block 408 is fixedly connected to the bottom of the rectangular frame 401, and a circular hole 409 is evenly penetrated on one side of the rubber block 408. When the first damping rod 402 contracts, the rubber block 408 squeezes the bottom of the tool box body 1, so that the rubber block 408 is squeezed and deformed. Because the circular holes 409 are evenly penetrated on the side of the rubber block 408, the deformation degree of the rubber block 408 is increased, thereby playing a certain degree of buffering effect.
[0030] Reference Figure 4The fixing mechanism 5 includes a U-shaped plate 501, the inner wall of the U-shaped plate 501 is fixedly connected with a rotating rod 502, the surface of the rotating rod 502 is rotatably sleeved with a support rod 503, the end of the support rod 503 away from the U-shaped plate 501 is fixedly connected with a first semicircular plate 504, and the end of the first semicircular plate 504 away from the support rod 503 is provided with a second semicircular plate 505. When the fixing mechanism 5 is used, when emergency repairs are carried out on the top of the electric pole, the support rod 503 is manually controlled to rotate on the surface of the rotating rod 502, so that the support rod 503 is away from the tool box body 1, and then The first semicircular plate 504 is then sleeved on the surface of the top of the electric pole, and then the second semicircular plate 505 is sleeved on the surface of the top of the electric pole, and then the tool box body 1 is set on the surface of the top of the electric pole through the circle formed by the first semicircular plate 504 and the second semicircular plate 505, so that it is very convenient for emergency repair personnel to take tools. A threaded rod 506 is inserted through a thread on one side of the second semicircular plate 505, and the threaded rod 506 is inserted through a thread on one side of the first semicircular plate 504. A nut 507 is threadedly sleeved on one end of the threaded rod 506 close to the first semicircular plate 504. 6 is threadedly inserted through the second semicircular plate 505 and the first semicircular plate 504 in sequence, and then the nut 507 is threadedly sleeved on one end of the threaded rod 506 close to the first semicircular plate 504, so that the first semicircular plate 504 and the second semicircular plate 505 are well fixed together. A positioning plate 508 is slidably inserted on one side of the U-shaped plate 501, and the positioning plate 508 is set on the surface of the support rod 503. When the fixing mechanism 5 is not used, the support rod 503 is manually controlled to rotate on the surface of the rotating rod 502, so that the support rod 503 is close to the outer bottom of the tool box body 1. Then, the locking plate 508 is inserted into the interior of the U-shaped plate 501, and then the locking plate 508 is set on the surface of the support rod 503, so that the support rod 503 can be well fixed on the surface of the rotating rod 502, and the end of the locking plate 508 away from the U-shaped plate 501 is fixedly connected to the third spring 509, and the end of the third spring 509 away from the top of the locking plate 508 is fixedly connected to one side of the U-shaped plate 501, and the third spring 509 pulls the end of the locking plate 508 away from the U-shaped plate 501, thereby well restricting the locking plate 508 to the inside of the U-shaped plate 501.
[0031] exist Figure 4 When the workstation position is shown, the surface of the support rod 503 located inside the U-shaped plate 501 is lower than the lower surface of the positioning plate 508. Figure 4 When the support rod 503 is rotated 180 degrees so that the first semicircular plate 504 and the second semicircular plate 505 are stored in the outer bottom of the tool box body 1, similarly, the surface of the support rod 503 located inside the U-shaped plate 501 is lower than the lower surface of the locking plate 508, so that the support rod 503 can be restricted inside the U-shaped plate 501 by the locking plate 508.
[0032] Working principle: when using the toolbox, the tools and instruments needed for power emergency repair are directly placed inside the toolbox body 1, so that the emergency repair tools can be carried well, and the power emergency repair related to the power distribution network can be well carried out. When using the buffer mechanism 4, the emergency repair instruments are directly placed inside the rectangular frame 401. When the handle 3 slips from the hands of the repair personnel due to an accidental collision, the toolbox body 1 falls vertically, and the bottom of the toolbox body 1 is hit, which causes the first damping rod 402 and the first spring 403 to contract. When the first damping rod 402 contracts, the rubber block 408 squeezes the bottom of the toolbox body 1, causing the rubber block 408 to be squeezed and deformed. Because the side of the rubber block 408 Circular holes 409 are evenly opened through the surface, thereby increasing the deformation degree of the rubber block 408, thereby playing a certain degree of buffering effect, and then through the squeezing effect of the second damping rod 404 and the second spring 405, the connecting plate 406 can be well restricted inside the rectangular frame 401. When the connecting plate 406 is slid into the interior of the rectangular frame 401, the sponge block 407 is slid into the interior of the rectangular frame 401, and then the repair instruments and tools inside the rectangular frame 401 are squeezed by the sponge block 407, thereby well preventing the repair instruments and tools from moving inside the rectangular frame 401, thereby preventing the repair instruments from bumping into the interior of the rectangular frame 401 and being damaged. When the bottom of the toolbox body 1 is collided, the second damping rod 404 and the second spring 405 5 shrinks, which can play a buffering role to a certain extent, and can prevent the emergency repair equipment from being damaged due to vibration to a certain extent. When using the fixing mechanism 5, when performing emergency repairs on the top of the electric pole, manually control the support rod 503 to rotate on the surface of the rotating rod 502, so that the support rod 503 is away from the tool box body 1, and then the blocking plate 508 is inserted into the inside of the U-shaped plate 501, and the blocking plate 508 is pulled away from one end of the U-shaped plate 501 by the third spring 509 (that is, the end of the blocking plate 508 away from the U-shaped plate 501 is closer to the U-shaped plate 501), so that the blocking plate 508 is well restricted in the inside of the U-shaped plate 501, and then the blocking plate 508 is set on the surface of the support rod 503, and then the first semicircular plate 504 is sleeved on the surface of the top of the electric pole, and then the second semicircular plate 505 is sleeved on the surface of the top of the electric pole, and the threaded rod 506 is threadedly inserted through the second semicircular plate 505 and the first semicircular plate 504 in sequence, and then the nut 507 is threadedly sleeved on one end of the threaded rod 506 close to the first semicircular plate 504, so that the first semicircular plate 504 and the second semicircular plate 505 are well fixed together, and then the tool box body 1 is set on the surface of the top of the electric pole through the circle formed by the first semicircular plate 504 and the second semicircular plate 505, so that it is very convenient for repair personnel to take tools. When the fixing mechanism 5 is not in use, the support rod 503 is manually controlled to rotate relative to the rotating rod 502, so that the support rod 503 is close to the bottom of the tool box body 1.Then, the locking plate 508 is inserted into the interior of the U-shaped plate 501, and the third spring 509 pulls the locking plate 508 away from one end of the U-shaped plate 501, thereby well restricting the locking plate 508 inside the U-shaped plate 501, and then setting the locking plate 508 on the surface of the support rod 503, so that the support rod 503 can be well fixed on the surface of the rotating rod 502, and then the fixing mechanism 5 can be well stored at the bottom of the tool box body 1.
Claims
1. A tool box for power emergency repair, comprising a tool box body (1), characterized in that: A connecting cover (2) is arranged on the top of the toolbox body (1), a handle (3) is arranged on the top of the connecting cover (2), a buffer mechanism (4) is arranged inside the toolbox body (1), a fixing mechanism (5) is arranged on the inner bottom of the toolbox body (1), the buffer mechanism (4) comprises a rectangular frame (401), the rectangular frame (401) is arranged inside the toolbox body (1), a first damping rod (402) is fixedly connected to the inner bottom of the toolbox body (1), an end of the first damping rod (402) away from the toolbox body (1) is fixedly connected to the outer bottom of the rectangular frame (401), and a first spring (403) is sleeved on the outer periphery of the first damping rod (402).
2. The power repair tool box according to claim 1, characterized in that: A second damping rod (404) is fixedly connected to the inner side of the connection cover (2); an end of the second damping rod (404) away from the connection cover (2) is fixedly connected to a connection plate (406); a second spring (405) is sleeved on the outer periphery of the second damping rod (404); and the connection plate (406) is sleeved relative to the inner wall of the rectangular frame (401).
3. The power repair tool box according to claim 2, characterized in that: One end of the connecting plate (406) away from the second damping rod (404) is evenly and fixedly connected to a sponge block (407).
4. The power repair tool box according to claim 1, characterized in that: A rubber block (408) is fixedly connected to the outer bottom of the rectangular frame (401), and round holes (409) are evenly penetrated through one side of the rubber block (408).
5. The power repair tool box according to claim 1, characterized in that: The fixing mechanism (5) comprises a U-shaped plate (501), the inner wall of the U-shaped plate (501) being fixedly connected to a rotating rod (502), a support rod (503) being rotatably sleeved on the surface of the rotating rod (502), an end of the support rod (503) away from the U-shaped plate (501) being fixedly connected to a first semicircular plate (504), and an end of the first semicircular plate (504) away from the support rod (503) being provided with a second semicircular plate (505).
6. The power repair tool box according to claim 5, characterized in that: A threaded rod (506) is threadedly inserted through one side of the second semicircular plate (505), and the threaded rod (506) is threadedly inserted through one side of the first semicircular plate (504). A nut (507) is threadedly sleeved on one end of the threaded rod (506) close to the first semicircular plate (504).
7. The power repair tool box according to claim 5, characterized in that: A locking plate (508) is slidably inserted on one side of the U-shaped plate (501), and the locking plate (508) has two positions, one of which is arranged on the surface of the support rod (503) to limit the rotation of the support rod (503), and the other position of the locking plate (508) is free from the restricted rotation of the support rod (503).
8. The power repair tool box according to claim 7, characterized in that: One end of the locking plate (508) away from the U-shaped plate (501) is fixedly connected to the first end of the third spring (509), and the second end of the third spring (509) is fixedly connected to one side of the U-shaped plate (501).