Seawall construction period flood control protection structure
By designing a flood protection structure during the seawall construction with a screw-mounted lifting mechanism for deflection lifting, the problem of insufficient flood control of the existing seawall slope protection structure is solved, and higher flood control needs and better practicality are achieved. sex.
Patent Information
- Application Number
- CN202421226822.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-31
- Publication Date
- 2025-02-14
- Estimated Expiration
- 2034-05-31
AI Technical Summary
The existing seawall slope protection structure is not practical in flood prevention and has a limited scope of flood prevention, making it difficult to meet higher flood prevention needs.
A flood protection structure during the construction period of seawall was designed, and a screw-mounted lifting mechanism was used for skewed lifting. Through the cooperation of components such as movable shafts, movable frames, flood control plates, etc., the flood control plates were realized on the basis of constant seawall height. Eccentric lift.
With the constant seawall height, the flood control mechanism is achieved to meet higher flood control needs through skewed lifting, and improve practicality and flood control effect.
Smart Images

Figure CN222477341U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of flood control mechanisms, in particular to a flood control protection structure during the construction period of a seawall. Background Art
[0002] Seawalls are embankments built along the coast to block tides and waves. Seawalls are important hydraulic structures in sea reclamation projects. As wave-proof structures, seawalls not only withstand the effects of waves, but also block tides. Structurally, seawalls consist of two parts: tide-proof and anti-seepage soil and wave-proof structures. Seawalls are generally not allowed to cross waves, and their top elevation requirements are relatively high. Although the inner slopes of seawalls are mostly earth slopes, they generally do not require face protection because there is no requirement for wave protection.
[0003] During the construction of seawalls, it is necessary to set up corresponding flood prevention organizations. There is currently a seawall slope protection ecological transformation structure with a Chinese patent publication number of CN109868789A, which changes the traditional hard and cold reinforced concrete structure on the outside of the seawall, greatly improving the ecological effect of the seawall; it does not reduce the original seawall's wave-breaking capacity and defense standards, and has no effect on the structural stability of the original seawall; it is easy to construct and has mature technology, and can be applied to the ecological transformation of the hard outer slope structure of ordinary seawalls.
[0004] However, the device is installed directly in contact with the seawall, so its flood control range is relatively limited and its practicality is insufficient. Utility Model Content
[0005] 1. Technical issues to be solved
[0006] In view of the shortcomings of the existing technology, the utility model provides a flood control mechanism that can be set up on the basis of a constant seawall height and perform corresponding oblique lifting through a screw-mounted lifting mechanism, thereby meeting higher flood control needs and improving practicality of a seawall construction period flood protection structure.
[0007] (II) Technical solution
[0008] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a flood protection structure during the construction period of a seawall, comprising a base, a constraint frame, a movable shaft, a movable frame, a flood control board, an articulated frame one, an articulated shaft one, a rotation constraint sleeve, a threaded rod, a twisting plate, an articulated frame two, an articulated shaft two and an internal threaded sleeve, wherein the front side of the top end of the base is connected to the bottom end of the constraint frame, the inner side of the constraint frame is movably connected to the outer side of the movable frame via the movable shaft, the rear end of the movable frame is connected to the front end of the flood control board, the middle part of the rear end of the flood control board is connected to the front side of the second articulated frame, the inner side of the second articulated frame is movably connected to the middle part of the outer side of the internal threaded sleeve via the second articulated shaft, the middle and rear side of the top end of the base is connected to the bottom end of the first articulated frame, the inner side of the first articulated frame is movably connected to the middle part of the outer side of the rotation constraint sleeve via the first articulated shaft, the inner wall of the rotation constraint sleeve is rotatably connected to the outer wall of the lower part of the threaded rod, the bottom end of the threaded rod is connected to the middle part of the top end of the twisting plate, and the upper outer wall of the twisting plate is threadedly connected to the inner wall of the internal threaded sleeve.
[0009] Preferably, a limiting plate is further included, and the top end of the threaded rod is connected to the middle part of the bottom end of the limiting plate.
[0010] Preferably, it further comprises a connecting frame, a spring and a clamping plate, wherein a rear side of the articulated frame is connected to the exterior of the front side of the connecting frame, and the middle of the front side of the connecting frame is connected to the rear side of the clamping plate via a spring.
[0011] Preferably, it also includes a sliding sleeve, a sliding rod and a pull tab, the inner side of the middle part of the connecting frame is connected to the outer side of the sliding sleeve, the inner wall of the sliding sleeve is slidably connected to the outer wall of the sliding rod, the rear end of the sliding rod is connected to the middle part of the front end of the pull tab, and the front end of the sliding rod is connected to the middle part of the rear end of the card plate.
[0012] Preferably, it also includes reinforcement beams, and the bottom end of the flood control board is connected to the top ends of multiple groups of reinforcement beams.
[0013] Preferably, it further comprises a slot rack, and the left and right sides of the top of the base are respectively connected to the bottom ends of a group of slot racks.
[0014] (III) Beneficial effects
[0015] Compared with the prior art, the utility model provides a flood protection structure for seawall construction period, which has the following beneficial effects:
[0016] The base is fixed at the river bank, and the threaded rod is rotated by twisting the twisting plate, and the threaded rod is constrained by the rotation constraint sleeve to rotate. The threaded rod and the internal threaded sleeve are screwed together to change the distance between the movable shaft and the twisting plate. The threaded rod is constrained by hinge shaft one to move in hinge frame one through the twisting plate, and the internal threaded sleeve is constrained by hinge shaft two to move in hinge frame two, so that the threaded rod is deflected accordingly. The flood control board is connected through the movable frame, and the movable shaft is constrained to rise and fall in the constraint frame, and is self-lockingly fixed at any angle within the range through the threaded rod and the rotation constraint sleeve. Under the condition that the height of the seawall is constant, a flood control mechanism with corresponding deflection and lifting can be set up through a screw-mounted lifting mechanism on this basis, so as to meet higher flood control needs and improve practicality. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is an axial view of the schematic diagram of the structure of the utility model;
[0018] Figure 2 For this utility model Figure 1 The top view of
[0019] Figure 3 For this utility model Figure 1 Right view of;
[0020] Figure 4 For this utility model Figure 1 Rear view of.
[0021] Markings in the attached drawings: 1. base; 2. constraint frame; 3. movable shaft; 4. movable frame; 5. flood control board; 6. hinged frame one; 7. hinged shaft one; 8. rotation constraint sleeve; 9. threaded rod; 10. screw plate; 11. hinged frame two; 12. hinged shaft two; 13. internal threaded sleeve; 14. limit plate; 15. connecting frame; 16. spring; 17. clamping plate; 18. sliding sleeve; 19. sliding rod; 20. pull tab; 21. reinforcement beam; 22. slot frame. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] Example
[0024] See also Figure 1-4 A flood protection structure during the construction period of a seawall comprises a base 1, a constraint frame 2, a movable shaft 3, a movable frame 4, a flood control board 5, an articulated frame 1 6, an articulated shaft 1 7, a rotation constraint sleeve 8, a threaded rod 9, a screw plate 10, an articulated frame 2 11, an articulated shaft 2 12 and an internal threaded sleeve 13. The front side of the top of the base 1 is connected to the bottom end of the constraint frame 2, the inner side of the constraint frame 2 is movably connected to the outer side of the movable frame 4 via the movable shaft 3, the rear end of the movable frame 4 is connected to the front end of the flood control board 5, the middle part of the rear end of the flood control board 5 is connected to the front side of the articulated frame 2 11, the inner side of the articulated frame 2 11 is movably connected to the middle part of the outer side of the internal threaded sleeve 13 via the articulated shaft 2 12, the middle and rear side of the top of the base 1 is connected to the bottom end of the articulated frame 1 6, the inner side of the articulated frame 1 6 is movably connected to the middle part of the outer side of the rotation constraint sleeve 8 via the articulated shaft 7, and the rotation constraint The inner wall of the sleeve 8 is rotatably connected to the outer wall of the lower part of the threaded rod 9, the bottom end of the threaded rod 9 is connected to the middle of the top of the screw plate 10, and the upper outer wall of the screw plate 10 is screwed to the inner wall of the internal threaded sleeve 13; the base 1 is placed and fixed at the river bank position, and the screw plate 10 is screwed to make the threaded rod 9 rotate under the constraint of the rotation constraint sleeve 8, and the threaded rod 9 and the internal threaded sleeve 13 are screwed together to change the spacing between the movable shaft 3 and the screw plate 10, and the screw plate 10 is constrained by the hinge shaft 1 7 to move in the hinge frame 1 6, and the internal threaded sleeve 13 is constrained by the hinge shaft 2 12 to move in the hinge frame 2 11, so that the threaded rod 9 is correspondingly deflected, and the flood control board 5 is connected through the movable frame 4, and is movably constrained to rise and fall in the constraint frame 2 by the movable shaft 3, and is self-lockingly fixed at any angle within the range through the threaded rod 9 and the rotation constraint sleeve 8 threads.
[0025] It also includes a limiting piece 14, and the top of the threaded rod 9 is connected to the middle of the bottom end of the limiting piece 14; the upper side of the threaded rod 9 can be limited by the limiting piece 14 to prevent the internal threaded sleeve 13 from sliding upward outside the threaded rod 9, thereby improving reliability.
[0026] It also includes a connecting frame 15, a spring 16 and a clamping plate 17. The rear side of the articulated frame 16 is connected to the outside of the front side of the connecting frame 15, and the middle part of the front side of the connecting frame 15 is connected to the rear side of the clamping plate 17 via the spring 16. Under the connection action of the connecting frame 15, the elastic action of the spring 16 can make the clamping plate 17 act forward on the outside of the screw disk 10 to tighten it, thereby preventing the screw disk 10 from moving and improving stability.
[0027] It also includes a sliding sleeve 18, a sliding rod 19 and a pull tab 20. The inner side of the middle part of the connecting frame 15 is connected to the outer side of the sliding sleeve 18, the inner wall of the sliding sleeve 18 is slidably connected to the outer wall of the sliding rod 19, the rear end of the sliding rod 19 is connected to the middle part of the front end of the pull tab 20, and the front end of the sliding rod 19 is connected to the middle part of the rear end of the clamping plate 17; by holding the pull tab 20 backwards, the sliding rod 19 can be slid backward under the constraint of the sliding sleeve 18, so that the clamping plate 17 can be separated from the screw plate 10, which is convenient for screwing and adjustment.
[0028] It also includes reinforcement beams 21, and the bottom end of the flood control board 5 is connected to the top of multiple groups of reinforcement beams 21; the flood control board 5 can be auxiliary reinforced through the reinforcement beams 21 to increase the impact resistance, avoid easy deformation, breakage and damage, and improve stability.
[0029] It also includes a slot rack 22, and the left and right sides of the top of the base 1 are respectively connected to the bottom ends of a group of slot racks 22; a fork can be inserted through the slot rack 22, so that the device can be easily picked up and placed, thereby improving convenience.
[0030] In summary, when a flood protection structure during the construction period of a seawall is used, a forklift is inserted into the slot frame 22 to fix the base 1 at the riverbank position, and by holding the pull tab 20 backward, the slide rod 19 can be slid backward under the constraint of the sliding sleeve 18, so that the clamping plate 17 is separated from the screw disk 10, and the screw disk 10 is screwed to make the threaded rod 9 rotate under the constraint of the rotation constraint sleeve 8, and the threaded rod 9 is screwed with the internal threaded sleeve 13 to change the distance between the movable shaft 3 and the screw disk 10, and is limited by the upper side of the limit plate 14, and the screw disk 10 is constrained by the hinge shaft 7 to move in the hinge frame 6, and the internal threaded sleeve 1 3 is constrained to move in the articulated frame 11 through the hinged shaft 12, so that the threaded rod 9 is deflected accordingly, and the flood control board 5 is connected through the movable frame 4, and is constrained to rise and fall in the constraint frame 2 by the movable shaft 3, and is fixed by the threaded self-locking of the threaded rod 9 and the rotation constraint sleeve 8 at any angle within the range. Under the connection action of the connecting frame 15, the elastic action of the spring 16 can make the clamping plate 17 act forward on the outer side of the screw plate 10 to tighten it and prevent the screw plate 10 from moving. In addition, the flood control board 5 can be auxiliary reinforced through the reinforcement beam 21 to increase the impact resistance, avoid easy deformation, fracture and damage, and improve stability.
[0031] This flood control board 5 is a well-known device purchased directly from the market by technicians in this field. Here we just use it without making any improvements to its structure and function, so we will not go into details here.
[0032] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A flood protection structure for seawall construction period, characterized in that: The invention comprises a base (1), a restraining frame (2), a movable shaft (3), a movable frame (4), a flood control board (5), an articulated frame (6), an articulated shaft (7), a rotation restraining sleeve (8), a threaded rod (9), a screw plate (10), an articulated frame (11), an articulated shaft (12) and an internal threaded sleeve (13), wherein the front side of the top end of the base (1) is connected to the bottom end of the restraining frame (2), the inner side of the restraining frame (2) is movably connected to the outer side of the movable frame (4) via the movable shaft (3), the rear end of the movable frame (4) is connected to the front end of the flood control board (5), and the middle part of the rear end of the flood control board (5) is connected to the front end of the flood control board (5). The base (1) is connected to the front side of the second articulated frame (11); the inner side of the second articulated frame (11) is movably connected to the middle part of the outer side of the internal threaded sleeve (13) via the second articulated shaft (12); the middle and rear side of the top end of the base (1) is connected to the bottom end of the first articulated frame (6); the inner side of the first articulated frame (6) is movably connected to the middle part of the outer side of the rotation constraint sleeve (8) via the first articulated shaft (7); the inner wall of the rotation constraint sleeve (8) is rotatably connected to the lower outer wall of the threaded rod (9); the lower end of the threaded rod (9) is connected to the middle part of the top end of the screwing plate (10); the upper outer wall of the screwing plate (10) is threadedly connected to the inner wall of the internal threaded sleeve (13).
2. A flood protection structure for seawall construction period according to claim 1, characterized in that: It also includes a limiting plate (14), and the top end of the threaded rod (9) is connected to the middle part of the bottom end of the limiting plate (14).
3. A flood protection structure for seawall construction period according to claim 1, characterized in that: It also includes a connecting frame (15), a spring (16) and a clamping plate (17), wherein the rear side of the hinged frame (6) is connected to the outside of the front side of the connecting frame (15), and the middle part of the front side of the connecting frame (15) is connected to the rear side of the clamping plate (17) via the spring (16).
4. A flood protection structure for seawall construction period according to claim 3, characterized in that: It also includes a sliding sleeve (18), a sliding rod (19) and a pull tab (20), wherein the inner side of the middle part of the connecting frame (15) is connected to the outer side of the sliding sleeve (18), the inner wall of the sliding sleeve (18) is slidably connected to the outer wall of the sliding rod (19), the rear end of the sliding rod (19) is connected to the middle part of the front end of the pull tab (20), and the front end of the sliding rod (19) is connected to the middle part of the rear end of the clamping plate (17).
5. The flood protection structure for seawall construction period according to claim 1, characterized in that: It also includes reinforcement beams (21), and the bottom end of the flood control board (5) is connected to the top ends of multiple groups of reinforcement beams (21).
6. The flood protection structure for seawall construction period according to claim 1, characterized in that: It also comprises a slot frame (22), and the left and right sides of the top end of the base (1) are respectively connected to the bottom ends of a group of slot frames (22).
Citation Information
Patent Citations
Seawall protection slope ecological reconstruction structure
CN109868789A