High-efficiency dredging device for water conservancy construction

By setting up a filter cover and a scraper arm in the water conservancy construction dredging device, the problem of large particles and impurities in the silt blocking the sewage pipe is solved, and the continuous and efficient progress of the dredging operation and the improvement of the effect is achieved.

CN222477585UActive Publication Date: 2025-02-14THE FIRST ENG OF CHINA RAILWAY 16TH CONSTR BUREAU GROUP
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202421224783.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-31
Publication Date
2025-02-14
Estimated Expiration
2034-05-31

AI Technical Summary

Technical Problem

The existing water conservancy construction dredging equipment lacks a filter structure, which causes large particles of impurities in the sludge to easily block the sewage pipe, thereby hindering the smooth progress of the dredging operation.

Method used

A high-efficiency water conservancy construction silting device was designed, and a filter cover and a scraper arm were installed. The filter cover was used to filter large particles of impurities in the silt, and the scraper arm was used to open the gathering of the bottom of the filter cover. Large particle impurities prevent them from blocking the filter cover.

Benefits of technology

By setting up a filter cover and a scraping arm, large particles and impurities can be effectively prevented from entering the sewage pipe, avoid blockage, ensure the continuous and efficient operation of dredging operations, and improve the dredging effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222477585U_ABST
    Figure CN222477585U_ABST
Patent Text Reader

Abstract

The utility model discloses a high-efficiency dredging device for water conservancy construction, and relates to the technical field of water conservancy construction. The device comprises a desilting frame, a transverse plate is slidably connected to the interior of the desilting frame, a driving box is fixedly connected to the top of the transverse plate, a second motor is fixedly installed on the top of the inner side of the driving box, a driving gear is fixedly connected to the rotating end of the second motor in a sleeved mode, and rotating shafts are symmetrically and rotationally connected to the portions, on the two sides of the driving gear, in the driving box through bearings. By arranging the filter cover, large-particle impurities in sludge can be filtered before the sludge is sucked into the sludge suction pipe, the large-particle impurities are prevented from entering the sludge suction pipe to cause blockage, and the rotating shaft is fixedly sleeved with the impurity stirring and scraping arm, so that the rotating shaft can drive the stirring rod to stir the sludge and can drive the impurity stirring and scraping arm to rotate while stirring the sludge; large-particle impurities filtered out from the bottom of the filter cover are pushed aside to prevent the large-particle impurities from blocking the dirt inlet end face of the filter cover, so that continuous and efficient dredging operation can be guaranteed, and the dredging effect is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of water conservancy construction, and particularly relates to a high-efficiency water conservancy construction silt removal device. Background Art

[0002] River dredging generally refers to the management of rivers. Through mechanical equipment, the silt deposited on the riverbed is blown and stirred into turbid water, which flows away with the river water, thereby playing a role in dredging. After searching, the patent with application number 202321597912.2 discloses a highly efficient water conservancy construction dredging device, in which a stirring mechanism is arranged on the top of the frame, and the stirring mechanism includes a return box, and a driving motor is fixedly installed on the inner wall of the return box, and one end of the output shaft of the driving motor is fixedly connected to a first stirring rod, and the output shaft of the driving motor is fixedly connected to a first gear, and a rotating shaft is arranged on both sides of the first gear, and one end of the output shaft of the rotating shaft is fixedly connected to a second stirring shaft, and the outer surface of the rotating shaft is fixedly connected to a second gear.

[0003] However, during actual use, the applicant found that the dredging device lacked a filtering structure for sludge. During the dredging process, the sludge was directly sucked into the sewage pipe by the sewage pump. During this process, large particles of impurities would exist in the sludge. These impurities could easily get stuck in the sewage pipe, thereby hindering the smooth progress of the dredging operation. In view of this, we proposed a high-efficiency dredging device for water conservancy construction. Utility Model Content

[0004] In order to solve the above technical problems, the utility model is realized by the following technical solutions:

[0005] The utility model is a highly efficient silting device for water conservancy construction, comprising a silting frame, wherein a horizontal plate is slidably connected inside the silting frame, a driving box is fixedly connected to the top of the horizontal plate, a second motor is fixedly installed on the top of the inner side of the driving box, a driving gear is sleeved and fixed to the rotating end of the second motor, a rotating shaft is symmetrically rotatably connected to the driving box on both sides of the driving gear through a bearing, a driven gear is sleeved and fixed to the upper end of the rotating shaft, the driving gear is meshed and connected with the driven gear, the lower end of the rotating shaft movably penetrates the horizontal plate, and stirring rods are evenly arranged on the peripheral side walls of the lower part of the rotating shaft, scraping arms are sleeved and fixed on the two rotating shafts, and a A threaded sleeve, a first motor is fixedly installed on the top of the dredging frame, a screw is fixedly connected to the rotating end of the first motor, and the lower end of the screw is threaded into the threaded sleeve, a sewage pump is fixedly installed at the top of the dredging frame near the first motor, a filter cover is fixedly connected at the center position of the bottom of the cross plate, the top of the scraper arm is fitted with the bottom of the filter cover, the sewage suction end of the sewage pump is connected with the interior of the filter cover through a sewage pipe, a sewage discharge branch pipe is arranged on the sewage pipe near the sewage pump, a mounting bracket is arranged on one side of the dredging frame, a ship side slot is opened on the mounting bracket, and a locking bolt is screwed on the top thread of the mounting bracket.

[0006] Preferably, a control switch is fixedly mounted on the top of the mounting support, the control switch is electrically connected to an external power source via a wire, and the first motor, the sewage pump and the second motor are electrically connected to the control switch via wires, respectively.

[0007] Preferably, two locking bolts are provided on the top of the mounting support.

[0008] Preferably, both sides of the transverse plate slide along guide grooves provided on the inner side walls of the dredging frame respectively.

[0009] The utility model has the following beneficial effects:

[0010] The utility model discloses a high-efficiency dredging device for water conservancy construction. Through the filter cover set up, large impurities in the sludge can be filtered before the sludge is sucked into the sewage suction pipe to prevent the large impurities from entering the interior of the sewage suction pipe and causing blockage. By sleeve-fitting a scraper arm on the rotating shaft, the rotating shaft drives the stirring rod to stir the sludge and at the same time, can drive the scraper arm to rotate, so as to push away the large impurities filtered out by the bottom of the filter cover to prevent the large impurities from blocking the sewage inlet end face of the filter cover, thereby ensuring continuous and efficient dredging operation and improving the dredging effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for describing the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0012] Figure 1 This is a schematic diagram of the top view of a high-efficiency hydraulic construction dredging device according to the utility model;

[0013] Figure 2 This is a schematic diagram of the structure of a high-efficiency hydraulic construction desilting device according to the utility model when viewed from above;

[0014] Figure 3 The utility model is a schematic diagram of the internal structure of a driving box in a high-efficiency water conservancy construction silt removal device.

[0015] In the accompanying drawings, the components represented by the reference numerals are listed as follows:

[0016] 1. Dredging frame; 2. Mounting support; 21. Side slot; 3. Locking bolt; 4. Control switch; 5. First motor; 6. Sewage pump; 7. Screw; 8. Drive box; 81. Threaded sleeve; 82. Second motor; 83. Driving gear; 84. Driven gear; 9. Sewage pipe; 91. Sewage branch pipe; 10. Cross plate; 11. Filter cover; 12. Rotating shaft; 121. Agitator rod; 13. Debris scraper arm. DETAILED DESCRIPTION

[0017] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0018] See also Figure 1-3 As shown, the utility model provides a technical solution:

[0019] Embodiment 1: A highly efficient silting device for water conservancy construction, comprising a silting frame 1, wherein a horizontal plate 10 is slidably connected inside the silting frame 1, and both sides of the horizontal plate 10 slide along the guide slide grooves provided on the inner side wall of the silting frame 1, respectively, and a driving box 8 is fixedly connected to the top of the horizontal plate 10, and a second motor 82 is fixedly installed on the top of the inner side of the driving box 8, and a driving gear 83 is sleeved and fixed to the rotating end of the second motor 82, and a rotating shaft 12 is symmetrically rotatably connected to the driving box 8 on both sides of the driving gear 83 through bearings, and a driven gear 84 is sleeved and fixed to the upper end of the rotating shaft 12, and the driving gear 83 is meshed and connected with the driven gear 84, and the lower end of the rotating shaft 12 movably passes through the horizontal plate 10, and stirring rods 121 are evenly arranged on the peripheral side wall of the lower part of the rotating shaft 12. A threaded sleeve 81 is fixedly provided on the top of the driving box 8, a first motor 5 is fixedly provided on the top of the dredging frame 1, a screw 7 is fixedly connected to the rotating end of the first motor 5, and the lower end of the screw 7 is threaded into the threaded sleeve 81, a sewage pump 6 is fixedly provided at the top of the dredging frame 1 near the first motor 5, a filter cover 11 is fixedly connected at the center position of the bottom of the horizontal plate 10, the sewage suction end of the sewage pump 6 is connected with the interior of the filter cover 11 through the sewage pipe 9, and the sludge sucked into the sewage pipe 9 can be filtered through the filter cover 11 to prevent large particles of impurities from being sucked into the sewage pipe 9 and blocking the interior of the sewage pipe 9, a sewage discharge branch pipe 91 is provided on the sewage pipe 9 near the sewage pump 6, and one side of the dredging frame 1 A mounting support 2 is provided, on which a side-of-the-ship slot 21 is provided, a locking bolt 3 is screwed on the top thread of the mounting support 2, two locking bolts 3 are provided on the top of the mounting support 2, a control switch 4 is fixedly installed on the top of the mounting support 2, the control switch 4 is electrically connected to an external power supply through a wire, a first motor 5, a sewage pump 6 and a second motor 82 are electrically connected to the control switch 4 through wires respectively, when dredging in water conservancy construction, the side of the ship can be stuck in the side-of-the-ship slot 21, and the locking bolt 3 is rotated with a hexagonal wrench, the locking bolt 3 is screwed into the threaded hole provided on the side of the ship, the dredging device is installed and fixed on the side of the ship, then the device is connected to the power supply on the ship, and the second motor 82 is driven to rotate through the control switch 4 The rotation of the second motor 82 can drive the driving gear 83 to rotate, and the rotation of the driving gear 83 can drive the driven gear 84 to rotate together with the rotating shaft 12. The rotation of the rotating shaft 12 can drive the stirring rod 121 to rotate, so as to stir the sludge. By driving the first motor 5 to rotate and drive the screw 7 to rotate, the threaded sleeve 81 and the screw 7 can be cooperated to drive the drive box 8 to move downward together with the rotating shaft 12, so as to stir the sludge of different depths. In this process, the sewage pump 6 is driven to rotate, and the rotation of the sewage pump 6 can pass through the sewage pipe 9, and the stirred sludge is filtered through the filter cover 11, and the large particles of impurities in the sludge are removed, so that the sludge is transported to the sewage branch pipe 91 for discharge, so as to realize the dredging operation of water conservancy construction.

[0020] Embodiment 2: The difference between this embodiment and embodiment 1 lies in that, scraper arms 13 are sleeved and fixed on both rotating shafts 12, and the top of the scraper arms 13 fits with the bottom of the filter cover 11. During the rotation of the rotating shaft 12, the scraper arms 13 can be driven to rotate, and the large particles of impurities gathered at the bottom of the filter cover 11 can be pushed away from the bottom of the filter cover 11 by the rotation of the scraper arms 13, so as to prevent the large particles of impurities from blocking the sewage inlet end face of the filter cover 11, thereby ensuring continuous and efficient dredging operations.

[0021] Working principle: When in use, during dredging of water conservancy construction, the side of the boat can be stuck in the side of the boat slot 21, and the locking bolt 3 can be rotated with a hexagonal wrench, and the locking bolt 3 can be screwed into the threaded hole on the side of the boat to fix the dredging device on the side of the boat. Then the device is connected to the power supply on the boat, and the second motor 82 is driven to rotate through the control switch 4. The rotation of the second motor 82 can drive the driving gear 83 to rotate, and the rotation of the driving gear 83 can drive the driven gear 84 to rotate together with the rotating shaft 12. The rotation of the rotating shaft 12 can drive the stirring rod 121 to rotate, so as to stir the sludge. By driving the first motor 5 to rotate, the screw 7 can be driven to rotate, and the threaded sleeve 81 can cooperate with the screw 7. The driving box 8 is driven to move downward together with the rotating shaft 12, so that the sludge at different depths can be stirred. In this process, the sewage pump 6 is driven to rotate. The rotation of the sewage pump 6 can pass through the sewage pipe 9, and the stirred sludge is filtered through the filter cover 11, and the large particles of impurities in the sludge are removed, so that the sludge is transported to the sewage branch pipe 91 for discharge, so as to realize the dredging operation of the water conservancy construction. During the rotation of the rotating shaft 12, the scraper arm 13 can be driven to rotate, and the large particles of impurities gathered at the bottom of the filter cover 11 can be pushed away from the bottom of the filter cover 11 by the rotation of the scraper arm 13, so as to prevent the large particles of impurities from blocking the sewage inlet end face of the filter cover 11, thereby ensuring continuous and efficient dredging operations.

[0022] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0023] The above are only preferred embodiments of the present invention and do not limit the present invention. Any modification to the technical solutions described in the aforementioned embodiments and any equivalent replacement of some of the technical features therein are within the protection scope of the present invention.

Claims

1. A high-efficiency dredging device for water conservancy construction, comprising a dredging frame (1), characterized in that: The dredging frame (1) is slidably connected to a transverse plate (10) inside, and a driving box (8) is fixedly connected to the top of the transverse plate (10). A second motor (82) is fixedly installed on the top of the inner side of the driving box (8). A driving gear (83) is sleeved and fixed to the rotating end of the second motor (82). A rotating shaft (12) is symmetrically rotatably connected to the driving box (8) on both sides of the driving gear (83) through bearings. A driven gear (84) is sleeved and fixed to the upper end of the rotating shaft (12). The driving gear (83) is meshed and connected with the driven gear (84). The lower end of the rotating shaft (12) movably passes through the transverse plate (10), and stirring rods (121) are evenly arranged on the peripheral side wall of the lower part of the rotating shaft (12). A debris scraping arm (13) is sleeved and fixed to the two rotating shafts (12). A threaded sleeve (81) is fixedly arranged on the top of the driving box (8). The dredging frame (1) A first motor (5) is fixedly installed on the top of the desilting frame (1), a screw rod (7) is fixedly connected to the rotating end of the first motor (5), the lower end of the screw rod (7) is threadedly screwed into a threaded sleeve (81), a sewage pump (6) is fixedly installed at a position near the first motor (5) on the top of the desilting frame (1), a filter cover (11) is fixedly connected at the center position of the bottom of the transverse plate (10), the top of the scraper arm (13) is in contact with the bottom of the filter cover (11), the sewage suction end of the sewage pump (6) is connected to the inside of the filter cover (11) through a sewage suction pipe (9), a sewage discharge branch pipe (91) is arranged on the sewage suction pipe (9) near the sewage pump (6), a mounting support (2) is arranged on one side of the desilting frame (1), a ship side slot (21) is provided on the mounting support (2), and a locking bolt (3) is threadedly screwed on the top of the mounting support (2).

2. A high-efficiency water conservancy construction dredging device according to claim 1, characterized in that: A control switch (4) is fixedly mounted on the top of the mounting support (2); the control switch (4) is electrically connected to an external power source via a wire; and the first motor (5), the sewage pump (6) and the second motor (82) are electrically connected to the control switch (4) via wires, respectively.

3. A high-efficiency water conservancy construction dredging device according to claim 1, characterized in that: Two locking bolts (3) are provided on the top of the mounting support (2).

4. The high-efficiency water conservancy construction dredging device according to claim 1 is characterized in that: Both sides of the transverse plate (10) slide along guide grooves provided on the inner side wall of the silt removal frame (1).

Citation Information

Patent Citations

  • High-efficiency dredging device for water conservancy construction

    CN220225514U