Auxiliary conveying device for concrete pouring of pump truck
By designing an auxiliary conveying device for concrete pouring of pump trucks including spherical joint parts, double-headed universal pipes and spherical pipes, the problem of frequent adjustment of position of traditional pump trucks in complex construction sites is solved, and the flexibility of concrete conveying is achieved and efficient.
Patent Information
- Application Number
- CN202421219620.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-30
- Publication Date
- 2025-02-14
- Estimated Expiration
- 2034-05-30
AI Technical Summary
When laying out complex construction sites, traditional pump trucks need to frequently adjust their positions or use additional auxiliary equipment, resulting in unstable concrete conveying and inefficient construction.
An auxiliary conveying device for concrete pouring of pump trucks is designed, including pump truck output pipe and flexible conveying pipe. Through the combination of spherical joints, double-headed universal pipes and spherical pipes, flexible adjustment and quick connection of the conveying pipes are achieved.
The device can flexibly adjust the conveying direction, reduce the number of pump truck position and angle adjustments, improve concrete pouring efficiency and construction flexibility, and ensure the stability and efficiency of the conveying process.
Smart Images

Figure CN222478176U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building construction, in particular to an auxiliary conveying device for pouring concrete on a pump truck. Background Art
[0002] In modern construction, pump trucks are important equipment for pouring concrete in high-rise and complex structures. However, when faced with complex construction site layouts, traditional pump trucks often need to frequently adjust their positions or use additional auxiliary equipment to ensure that concrete can be accurately and smoothly delivered to the pouring point, which not only increases the difficulty of the operation but also affects the construction efficiency. Therefore, it is particularly important to develop an auxiliary conveying device with a simple structure, easy connection, and the ability to effectively extend the conveying distance and flexibly adjust the conveying direction. Utility Model Content
[0003] The utility model aims to provide an auxiliary conveying device for concrete pouring by a pump truck, which improves the concrete pouring efficiency and flexibility of the pump truck, simplifies the structure and ensures flexible and stable concrete conveying, thus solving the problems in the prior art.
[0004] In order to achieve the above purpose, the utility model provides the following technical solutions:
[0005] An auxiliary conveying device for pouring concrete on a pump truck comprises an output pipe of the pump truck and a flexible conveying pipe. The port of the output pipe of the pump truck is connected to the flexible conveying pipe through an auxiliary adjusting component. The auxiliary adjusting component comprises a double-headed directional tube and a spherical joint component. There are two spherical joint components, which are respectively located at the two ends of the double-headed universal tube. The two ends of the double-headed universal tube are connected with spherical tubes, which are located in the spherical joint components. One of the spherical joint components is connected to the output pipe of the pump truck through a first flange, and the other spherical joint component is connected to the flexible conveying pipe through a second flange.
[0006] Preferably, the spherical joint component includes a first hemispherical component and a second hemispherical component, and the outer edge portions of the contact surfaces of the first hemispherical component and the second hemispherical component are each provided with a third flange, and the first hemispherical component and the second hemispherical component are spliced together through the third flange, and the interiors of the first hemispherical component and the second hemispherical component form a cavity for the spherical tube to slide.
[0007] Preferably, a first opening is opened in the axial direction of the first hemispherical member, and a second opening is opened in the axial direction of the second hemispherical member. The diameter of the second opening is larger than that of the first opening, and the spherical tube passes through the second opening.
[0008] Preferably, the outer wall of the spherical tube fits with the first hemispherical part and the second hemispherical part.
[0009] Preferably, a third opening is provided at one end of the spherical tube facing the pump truck outlet pipe / flexible delivery pipe, and the caliber of the third opening is not less than the caliber of the second opening.
[0010] Preferably, the spherical tube, the first hemispherical component and the second hemispherical component located on both sides of the double-headed universal tube are symmetrically distributed.
[0011] Preferably, the outside of the first flange, the second flange and the third flange is provided with a quick locking ring, which consists of two semi-annular parts, one corresponding end of the semi-annular parts is pivoted, and the other end of the semi-annular parts is provided with an internal thread block, and locking bolts pass through the two internal thread blocks.
[0012] Preferably, a ring groove is provided inside the quick locking ring, two opposite side walls of the ring groove gradually narrow from the center to the periphery, and a sealing rubber ring is provided on the bottom surface of the ring groove.
[0013] Compared with the prior art, the beneficial effects of the utility model are as follows:
[0014] 1. The utility model uses the design of spherical joints, double-headed universal tubes and spherical tubes to assist the flexible delivery pipe in flexibly adjusting the delivery direction. It is no longer limited by the position and angle of the pump truck output pipe, can better adapt to complex construction site conditions, and reduce the number of re-movement and positioning of the pump truck.
[0015] 2. The utility model is provided with a quick locking ring to realize a quick and convenient connection between the pump truck output pipe, the flexible delivery pipe, the first hemispherical part and the second hemispherical part. There is no need to install multiple bolts on the first flange, the second flange and the third flange for connection, thereby greatly reducing the time required for the installation, adjustment and disassembly process, while ensuring stability and flexibility during the delivery process, and effectively improving the efficiency of concrete pouring.
[0016] 3. The utility model has a simple structure, is easy to install and operate, and significantly improves the flexibility and efficiency of concrete pouring by the pump truck. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is the axonometric drawing of the overall structure of the utility model;
[0018] Figure 2 It is a partial structural connection diagram of the utility model;
[0019] Figure 3 It is a longitudinal cross-sectional view of a part of the structure of the utility model;
[0020] Figure 4 This is an axonometric view of the quick locking ring of the utility model;
[0021] Figure 5 It is a longitudinal sectional view of the quick locking ring of the utility model.
[0022] In the figure: 1, pump truck output pipe; 11, first flange; 2, flexible delivery pipe; 21, second flange; 3, double-headed universal tube; 31, spherical tube; 311, third port; 4, spherical joint; 41, first hemispherical part; 411, first port; 42, second hemispherical part; 421, second port; 43, third flange; 5, quick locking ring; 51, internal thread block; 52, locking bolt; 53, ring groove; 54, sealing rubber ring. DETAILED DESCRIPTION
[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
[0024] In order to solve the problem in the prior art that the flexible delivery pipe is easily restricted by the position and angle of the pump truck output pipe, forcing the pump truck to frequently adjust its position and angle, resulting in low construction efficiency, the following technical solution is provided. Please refer to Figure 1-5 ;
[0025] An auxiliary conveying device for pouring concrete on a pump truck comprises a pump truck output pipe 1 and a flexible conveying pipe 2. The port of the pump truck output pipe 1 is connected to the flexible conveying pipe 2 through an auxiliary adjusting member. The auxiliary adjusting member comprises a double-headed universal tube 3 and a spherical joint 4. Two spherical joints 4 are provided and are respectively located at the two ends of the double-headed universal tube 3. The two ends of the double-headed universal tube 3 are connected with a spherical tube 31. The spherical tube 31 is located in the spherical joint 4. The double-headed universal tube 3 can form a certain rotation angle with the spherical joint 4 through the spherical tube 31. One of the spherical joints 4 is connected to the pump truck output pipe 1 through a first flange 11, and the other spherical joint 4 is connected to the flexible conveying pipe 2 through a second flange 21.
[0026] The spherical joint 4 includes a first hemispherical part 41 and a second hemispherical part 42. The outer edges of the contact surfaces of the first hemispherical part 41 and the second hemispherical part 42 are respectively provided with a third flange 43. The first hemispherical part 41 and the second hemispherical part 42 are spliced by the third flange 43. The first hemispherical part 41 and the second hemispherical part 42 form a cavity for the spherical tube 31 to slide inside. The spherical tube 31 and the cavity are both standard spheres. Therefore, the spherical tube 31 can rotate freely in the cavity within a certain range, so that the two sides of the double-headed universal tube 3 form a certain rotation angle with the pump truck output pipe 1 and the flexible conveying pipe 2 respectively, thereby assisting the flexible conveying pipe 2 to flexibly adjust the conveying direction and no longer be limited by the position and angle of the pump truck output pipe 1. The outer wall of the spherical tube 31 is closely fitted with the first hemispherical part 41 and the second hemispherical part 42 to prevent concrete from entering the gap between the spherical tube 31 and the first hemispherical part 41 and the second hemispherical part 42.
[0027] A first opening 411 is provided in the axial direction of the first hemispherical member 41, and a second opening 421 is provided in the axial direction of the second hemispherical member 42. The diameter of the second opening 421 is larger than that of the first opening 411. The spherical tube 31 runs through the second opening 421. The diameter of the second opening 421 and the diameter of the double-headed universal tube 3 determine the rotation amplitude of the spherical tube 31 in the cavity. A third opening 311 is provided at one end of the spherical tube 31 facing the pump truck output pipe 1 / flexible delivery pipe 2. The diameter of the third opening 311 is not smaller than that of the second opening 421. The first opening 411 is always kept within the rotation coverage range of the third opening 311, so that concrete can smoothly enter the third opening 311 from the first opening 411. The spherical tube 31, the first hemispherical member 41 and the second hemispherical member 42 on both sides of the double-headed universal tube 3 are symmetrically distributed.
[0028] Concrete is output from the pump truck output pipe 1, enters the first spherical joint 4 through the first opening 411, enters the first spherical tube 31 through the third opening 311 in the spherical joint 4, then flows into the double-headed universal tube 3, and then enters the second spherical joint 4 through the next spherical tube 31, and finally enters the flexible conveying pipe 2.
[0029] The first flange 11, the second flange 21 and the third flange 43 are provided with a quick locking ring 5 on the outside. The quick locking ring 5 is composed of two semi-circular parts, one corresponding end of which is pivotally connected, and the other end of the semi-circular parts is provided with an internal thread block 51, and locking bolts 52 penetrate the two internal thread blocks 51. The quick locking ring 5 is provided with an annular groove 53 inside, and the two opposite side walls of the annular groove 53 gradually narrow from the center to the periphery, and a sealing rubber ring 54 is provided on the bottom surface of the annular groove 53. The sizes of the first flange 11, the second flange 21 and the two third flanges 43 may be different in actual situations, so the size of the quick locking ring 5 is adjusted according to actual situations, but the connection method is the same. Here, the third flange 43 is taken as an example. When connecting, the quick locking ring 5 is opened and the annular groove 53 is aligned with the two spliced third flanges 43, then the semi-circular parts are merged, the locking bolts 52 are inserted into the two internal thread blocks 51 and tightened with nuts, and the third flange 43 gradually penetrates into the annular groove 53 and keeps moving closer in the gradually narrowing side wall of the annular groove 53 until it fits tightly, so that the first hemispherical parts 41 and the second hemispherical parts 42 on both sides of the third flange 43 are firmly connected, and the sealing rubber ring 54 further seals the gap between the third flange 43 to prevent moisture in the concrete from seeping out.
[0030] Working principle: The spherical tube 31 can rotate freely to a certain extent in the circular cavity formed by the first hemispherical part 41 and the second hemispherical part 42. Therefore, the double-headed universal tube 3 can form a flexible rotation angle with the pump truck output pipe 1 and the flexible delivery pipe 2 connected to the first hemispherical parts 41 on both sides thereof, thereby assisting the flexible delivery pipe 2 to flexibly adjust the delivery direction.
[0031] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0032] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An auxiliary conveying device for pouring concrete on a pump truck, comprising a pump truck output pipe (1) and a flexible conveying pipe (2), characterized in that: The port of the pump truck output pipe (1) is connected to the flexible delivery pipe (2) through an auxiliary adjustment component. The auxiliary adjustment component comprises a double-headed universal tube (3) and a spherical joint component (4). Two spherical joint components (4) are provided and are respectively located at the two ends of the double-headed universal tube (3). The two ends of the double-headed universal tube (3) are connected to a spherical tube (31). The spherical tube (31) is located in the spherical joint component (4). One of the spherical joint components (4) is connected to the pump truck output pipe (1) through a first flange (11), and the other spherical joint component (4) is connected to the flexible delivery pipe (2) through a second flange (21).
2. The auxiliary conveying device for pouring concrete on a pump truck according to claim 1, characterized in that: The spherical joint component (4) comprises a first hemispherical component (41) and a second hemispherical component (42). The outer edges of the contact surfaces of the first hemispherical component (41) and the second hemispherical component (42) are each provided with a third flange (43). The first hemispherical component (41) and the second hemispherical component (42) are spliced together via the third flange (43). The first hemispherical component (41) and the second hemispherical component (42) form a cavity inside for the spherical tube (31) to slide.
3. The auxiliary conveying device for pouring concrete on a pump truck according to claim 2, characterized in that: The first hemispherical component (41) is provided with a first opening (411) in the axial direction, and the second hemispherical component (42) is provided with a second opening (421) in the axial direction. The diameter of the second opening (421) is larger than that of the first opening (411), and the spherical tube (31) passes through the second opening (421).
4. The auxiliary conveying device for pouring concrete on a pump truck according to claim 3, characterized in that: The outer wall of the spherical tube (31) fits the first hemispherical part (41) and the second hemispherical part (42).
5. The auxiliary conveying device for concrete pouring of a pump truck according to claim 4, characterized in that: The spherical tube (31) is provided with a third opening (311) at one end facing the pump truck output pipe (1) / flexible delivery pipe (2), and the caliber of the third opening (311) is not less than the caliber of the second opening (421).
6. The auxiliary conveying device for pouring concrete on a pump truck according to claim 5, characterized in that: The spherical tube (31), the first hemispherical component (41) and the second hemispherical component (42) located on both sides of the double-headed universal tube (3) are symmetrically distributed.
7. The auxiliary conveying device for pouring concrete on a pump truck according to claim 6, characterized in that: A quick locking ring (5) is provided on the outside of the first flange (11), the second flange (21) and the third flange (43), and the quick locking ring (5) is composed of two semi-annular parts, one corresponding end of the semi-annular parts is pivotally connected, and the other end of the semi-annular parts is provided with an internal thread block (51), and locking bolts (52) pass through the two internal thread blocks (51).
8. The auxiliary conveying device for pouring concrete on a pump truck according to claim 7, characterized in that: The quick locking ring (5) is provided with an annular groove (53) inside, and two opposite side walls of the annular groove (53) gradually narrow from the center to the periphery, and a sealing rubber ring (54) is provided on the bottom surface of the annular groove (53).