Building facade cleaning structure

By designing a building facade cleaning structure including suspension mechanism and connection mechanism, the risks and structural damage problems of manual suspension cleaning in the prior art are solved, and efficient cleaning effect with easy installation and safe use is achieved.

CN222525820UActive Publication Date: 2025-02-25CHINA CONSTR SECOND BUREAU DECORATION ENG CO
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420101951.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-16
Publication Date
2025-02-25
Estimated Expiration
2034-01-16

AI Technical Summary

Technical Problem

Existing building facade cleaning methods require manual hanging ropes, which pose risks and may require damage to the existing structure of the building, affecting the service life.

Method used

A building facade cleaning structure is designed, including building roof and vertical plates arranged horizontally, with a hanging mechanism and a connecting mechanism inside. The suspension mechanism is composed of vertical rods, cross rods, oblique braces and suspended ropes, and the connecting mechanism is pre-buried. It is composed of parts, connecting rods and fixing seats, and locking pins and safety ropes are used to improve the stability and safety of the structure.

Benefits of technology

The structure does not require additional counterweights. It is connected by the building body and the suspension mechanism, which is easy to install and safe to use, avoiding the risk of destroying the building structure and improving cleaning efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222525820U_ABST
    Figure CN222525820U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building curtain walls, and discloses a building facade cleaning structure which comprises a transversely-arranged building top plate and a building vertical plate arranged on the top of the outer side of the building top plate. Hanging mechanisms are arranged on the inner side of the building vertical plate at intervals, connecting mechanisms are arranged between the hanging mechanisms and the building vertical plate, each hanging mechanism comprises a vertical rod, a transverse rod connected to the vertical rod and extending to the outer side of the building vertical plate and an inclined strut connected between the vertical rod and the transverse rod, and a lifting rope is arranged in the length direction of the transverse rod. The lifting rope extends to the bottom of the transverse rod, a plurality of first mounting holes are vertically formed in the vertical rod at intervals, the outer surface of the vertical rod is sleeved with a plurality of sleeves, and locking pins are arranged between the vertical rod and the sleeves and used for limiting relative displacement between the sleeves and the vertical rod.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building curtain walls, in particular to a building facade cleaning structure. Background Art

[0002] At present, when cleaning the facade of a building, it is mostly necessary to manually clean the facade layer by layer through the suspension of a hanging rope, and the hanging rope requires a hanging mechanism to be implemented. The general practice is to set a hanging mechanism on the top floor of the building and add a counterweight on the inside of the hanging mechanism. This method has certain risks. In order to fix the hanging mechanism, it may be necessary to destroy the existing structure of the building, affecting the service life of the building. Therefore, it has certain limitations. Therefore, the utility model is born. Utility Model Content

[0003] The present application provides a building facade cleaning structure to solve the problems in the background technology.

[0004] To solve the above technical problems, the present application provides a building facade cleaning structure, comprising: a horizontally arranged building top plate and a building vertical plate arranged on the top of the outer side of the building top plate; a hanging mechanism is arranged at the inner side intervals of the building vertical plate, a connecting mechanism is arranged between the hanging mechanism and the building vertical plate, the hanging mechanism comprises a vertical rod, a horizontal rod connected to the vertical rod and extending to the outer side of the building vertical plate, and a diagonal brace connected between the vertical rod and the horizontal rod, a hanging rope is arranged in the length direction of the horizontal rod, the hanging rope extends to the bottom of the horizontal rod, a plurality of first mounting holes are arranged at vertical intervals on the vertical rod, a plurality of sleeves are arranged on the outer surface of the vertical rod, a locking pin is arranged between the vertical rod and the sleeve, and the locking pin is used to limit the relative displacement between the sleeve and the vertical rod.

[0005] In some embodiments of the present application, the connecting mechanism includes a first embedded part, a second embedded part and a third embedded part, which are arranged in sequence from top to bottom in the vertical plate of the building, a first connecting rod is arranged between the first embedded part and the vertical rod, a vertical support is arranged at one end of the first connecting rod away from the first embedded part, a fourth embedded part is arranged in the vertical support, two ends of the fourth embedded part are respectively connected to the first connecting rod and the sleeve, a second connecting rod is arranged between the second embedded part and the vertical rod, the second connecting rod is connected to the sleeve, a fixed seat is arranged at one end of the third embedded part close to the vertical rod, a safety rope is arranged on the fixed seat, and the safety rope is connected to the vertical rod.

[0006] In some embodiments of the present application, an outer frame is provided on the outer side of the first connecting rod, and the outer frame includes a plurality of transverse square tubes, vertical square tubes provided between the transverse square tubes, and galvanized steel plates provided on the outer surfaces of the transverse square tubes and the vertical square tubes, and a plurality of longitudinal square tubes are provided between adjacent outer frames, and an aluminum plate is provided on the outer side of the galvanized steel plate, and the aluminum plate and the longitudinal steel tubes are fixedly connected by angle codes.

[0007] In some embodiments of the present application, a U-shaped connecting piece is provided at one end of the first embedded part away from the first connecting rod, and the U-shaped connecting piece is fixedly connected to the vertical square tube by a bolt group.

[0008] In some embodiments of the present application, thermal insulation panels are provided on the outer sides of the building vertical panels and on the bottom of the aluminum panels.

[0009] In some embodiments of the present application, the thickness of the galvanized steel plate is 1.5 mm, and the thickness of the aluminum plate is 3 mm.

[0010] Compared with the prior art, the utility model has the following characteristics and beneficial effects:

[0011] The utility model provides a hanging mechanism and a hanging rope, which makes it convenient for workers to clean the exterior facade of a building. The connecting mechanism is provided to connect the hanging mechanism and the building body to improve the safety of the hanging mechanism. The sleeve and the locking pin are provided to respectively connect the vertical rod to the first connecting rod and the second connecting rod. The fixing seat and the safety rope are provided to improve the safety of the hanging mechanism. The first embedded part, the second embedded part and the third embedded part are provided to improve the stability between the connecting mechanism and the building body. The diagonal brace is provided to improve the stability of the hanging mechanism's own structure. The utility model does not need an additional counterweight, utilizes the building body and the hanging mechanism for connection, is easy to install, safe to use, and can produce better results when promoted and used. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a side view schematic diagram of the overall structure of an embodiment of the utility model.

[0013] In the figure, 100, building roof; 200, building vertical board; 300, hanging mechanism; 310, vertical rod; 320, horizontal rod; 330, diagonal brace; 340, hanging rope; 350, sleeve; 360, locking pin; 400, connecting mechanism; 410, first embedded part; 420, second embedded part; 430, third embedded part; 440, first connecting rod; 450, vertical support; 460, fourth embedded part; 470, second connecting rod; 480, fixing seat; 490, safety rope; 500, outer frame; 510, horizontal square tube; 520, vertical square tube; 530, galvanized steel plate; 540, longitudinal square tube; 550, aluminum single plate; 600, U-shaped connecting piece; 700, thermal insulation decorative panel. DETAILED DESCRIPTION

[0014] The following is a further detailed description of the specific implementation of the present invention in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0015] In the description of the present application, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0016] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, unless otherwise specified, "plurality" means two or more.

[0017] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0018] like Figure 1 As shown, according to some embodiments of the present application, a building facade cleaning structure includes: a building top plate 100 arranged horizontally and a building vertical plate 200 arranged on the top of the outer side of the building top plate 100; a hanging mechanism 300 is arranged at intervals on the inner side of the building vertical plate 200, and a connecting mechanism 400 is arranged between the hanging mechanism 300 and the building vertical plate 200, and the hanging mechanism 300 includes a vertical rod 310, a horizontal rod connected to the vertical rod 310 and extending to the outer side of the building vertical plate 200. 320, and a diagonal brace 330 connected between the vertical rod 310 and the horizontal rod 320, a suspension rope 340 is provided in the length direction of the horizontal rod 320, and the suspension rope 340 extends to the bottom of the horizontal rod 320, a plurality of first mounting holes are vertically spaced apart on the vertical rod 310, a plurality of sleeves 350 are sleeved on the outer surface of the vertical rod 310, and a locking pin 360 is provided between the vertical rod 310 and the sleeve 350, and the locking pin 360 is used to limit the relative displacement between the sleeve 350 and the vertical rod 310.

[0019] According to some embodiments of the present application, the connecting mechanism 400 includes a first embedded part 410, a second embedded part 420 and a third embedded part 430 which are sequentially arranged from top to bottom in the building vertical plate 200, a first connecting rod 440 is arranged between the first embedded part 410 and the vertical rod 310, a vertical support 450 is arranged at one end of the first connecting rod 440 away from the first embedded part 410, a fourth embedded part 460 is arranged in the vertical support 450, two ends of the fourth embedded part 460 are respectively connected to the first connecting rod 440 and the sleeve 350, a second connecting rod 470 is arranged between the second embedded part 420 and the vertical rod 310, the second connecting rod 470 is connected to the sleeve 350, and a fixing seat 480 is arranged at one end of the third embedded part 430 close to the vertical rod 310, a safety rope 490 is arranged on the fixing seat 480, and the safety rope 490 is connected to the vertical rod 310.

[0020] According to some embodiments of the present application, an outer frame 500 is disposed on the outer side of the first connecting rod 440, and the outer frame 500 includes a plurality of transverse square tubes 510, vertical square tubes 520 disposed between the transverse square tubes, and galvanized steel plates 530 disposed on the outer surfaces of the transverse square tubes 510 and the vertical square tubes 520, a plurality of longitudinal square tubes 540 are disposed between adjacent outer frames 500, and an aluminum single plate 550 is disposed on the outer side of the galvanized steel plate 530, and the aluminum single plate 550 and the longitudinal steel tubes are fixedly connected by angle codes.

[0021] According to some embodiments of the present application, a U-shaped connector 600 is provided at one end of the first embedded part 410 away from the first connecting rod 440 , and the U-shaped connector 600 is fixedly connected to the vertical square tube 520 via a bolt group.

[0022] According to some embodiments of the present application, a thermal insulation decorative panel 700 is provided on the outer side of the building vertical panel 200 and the bottom of the aluminum single panel 550 .

[0023] According to some embodiments of the present application, the thickness of the galvanized steel plate 530 is 1.5 mm, and the thickness of the aluminum single plate 550 is 3 mm.

[0024] In summary, the utility model relates to the technical field of building curtain walls, and discloses a building facade cleaning structure, comprising: a horizontally arranged building top plate and a building vertical plate arranged on the top of the outer side of the building top plate; a hanging mechanism is arranged at the inner side intervals of the building vertical plate, a connecting mechanism is arranged between the hanging mechanism and the building vertical plate, the hanging mechanism comprises a vertical rod, a horizontal rod connected to the vertical rod and extending to the outer side of the building vertical plate, and a diagonal brace connected between the vertical rod and the horizontal rod, a hanging rope is arranged in the length direction of the horizontal rod, the hanging rope extends to the bottom of the horizontal rod, a plurality of first mounting holes are arranged at vertical intervals on the vertical rod, a plurality of sleeves are arranged on the outer surface of the vertical rod, a locking pin is arranged between the vertical rod and the sleeve, and the locking pin is used to limit the relative displacement between the sleeve and the vertical rod.

[0025] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principle of the present invention. These improvements and substitutions should also be regarded as the protection scope of the present invention.

Claims

1. A building facade cleaning structure, comprising: A building top plate (100) arranged horizontally and a building vertical plate (200) arranged on the top of the outer side of the building top plate (100); characterized in that a suspension mechanism (300) is arranged at intervals on the inner side of the building vertical plate (200), a connecting mechanism (400) is arranged between the suspension mechanism (300) and the building vertical plate (200), and the suspension mechanism (300) includes a vertical rod (310), a horizontal rod (320) connected to the vertical rod (310) and extending to the outer side of the building vertical plate (200), and a connecting mechanism (400) connected to the vertical rod (310) and the building vertical plate (200). A diagonal brace (330) is provided between the cross bars (320), a suspension rope (340) is provided in the length direction of the cross bar (320), and the suspension rope (340) extends to the bottom of the cross bar (320), a plurality of first mounting holes are vertically spaced apart on the vertical bar (310), a plurality of sleeves (350) are sleeved on the outer surface of the vertical bar (310), a locking pin (360) is provided between the vertical bar (310) and the sleeve (350), and the locking pin (360) is used to limit the relative displacement between the sleeve (350) and the vertical bar (310).

2. A building facade cleaning structure according to claim 1, characterized in that: The connecting mechanism (400) comprises a first embedded part (410), a second embedded part (420) and a third embedded part (430) which are sequentially arranged from top to bottom in the vertical plate (200) of the building, a first connecting rod (440) is arranged between the first embedded part (410) and the vertical rod (310), a vertical support (450) is arranged at one end of the first connecting rod (440) away from the first embedded part (410), a fourth embedded part (460) is arranged in the vertical support (450), and the fourth embedded part (460) is arranged in the vertical support (450). The two ends of the embedded part (460) are respectively connected to the first connecting rod (440) and the sleeve (350); a second connecting rod (470) is arranged between the second embedded part (420) and the vertical rod (310); the second connecting rod (470) is connected to the sleeve (350); a fixing seat (480) is arranged at one end of the third embedded part (430) close to the vertical rod (310); a safety rope (490) is arranged on the fixing seat (480); and the safety rope (490) is connected to the vertical rod (310).

3. A building facade cleaning structure according to claim 2, characterized in that: An outer frame (500) is arranged on the outer side of the first connecting rod (440), and the outer frame (500) includes a plurality of transverse square tubes (510), vertical square tubes (520) arranged between the transverse square tubes, and galvanized steel plates (530) arranged on the outer surfaces of the transverse square tubes (510) and the vertical square tubes (520). A plurality of longitudinal square tubes (540) are arranged between adjacent outer frames (500), and an aluminum single plate (550) is arranged on the outer side of the galvanized steel plate (530), and the aluminum single plate (550) and the longitudinal steel tube are fixedly connected by angle brackets.

4. A building facade cleaning structure according to claim 2, characterized in that: A U-shaped connecting piece (600) is provided at one end of the first embedded part (410) away from the first connecting rod (440), and the U-shaped connecting piece (600) is fixedly connected to the vertical square tube (520) via a bolt group.

5. A building facade cleaning structure according to claim 1, characterized in that: A thermal insulation decorative plate (700) is provided on the outer side of the building vertical plate (200) and the bottom of the aluminum single plate (550).