Splicing type building template for constructional engineering
By designing spliced building formwork and using composite support mechanisms and connection mechanisms, the existing formwork has been solved, and a more efficient construction process has been achieved.
Patent Information
- Application Number
- CN202421214822.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-30
- Publication Date
- 2025-02-25
- Estimated Expiration
- 2034-05-30
AI Technical Summary
When used, existing building formwork has poor support and single fixing method, which leads to inconvenient disassembly and affects construction efficiency.
A spliced building formwork was designed, and the support mechanism was composed of a combination of fixed plate, support plate, threaded rod, support rod and thread sleeve. The horizontal plate was connected by locking bolts to increase the support of the formwork, and the main body was facilitated by connecting the mechanism. Connection and removal of templates and secondary templates.
It improves the support of building formwork, simplifies the fixing and dismantling process of formwork, and improves construction efficiency.
Smart Images

Figure CN222525843U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of building templates, in particular to a spliced building template for construction engineering. Background Art
[0002] Building formwork is a temporary structure, which is made according to the design requirements to shape the concrete structure and components according to the specified position and geometric size, maintain its correct position, and bear the weight of the building formwork and the load acting on it. The purpose of formwork engineering is to ensure the quality and construction safety of concrete engineering, speed up the construction progress and reduce engineering costs.
[0003] The existing building formwork is generally fixed with bolts when in use, which has poor support for the building formwork and a single fixing method. After the formwork is poured, it is extremely inconvenient to disassemble, resulting in low construction efficiency for workers. Therefore, we propose a spliced building formwork for construction engineering. Utility Model Content
[0004] In view of the problems in the prior art, the utility model provides a spliced building template for construction engineering.
[0005] The technical solution adopted by the utility model to solve its technical problems is a spliced building formwork for construction engineering, comprising a main formwork and a transverse plate, a support mechanism is installed at the plate wall of the transverse plate, and the support mechanism is composed of a fixed plate, a support plate, a threaded rod, a support rod and a threaded sleeve combination, a group of symmetrical fixed plates are welded at the plate wall of the transverse plate, a group of fixed plates are plugged with threaded rods between the plate walls, two groups of symmetrical threaded sleeves are threadedly connected at the rod walls of the threaded rods, and the fixed plates are located between the threaded sleeves, a support rod is welded at the rod wall of the threaded rod, and a support plate is welded to the other end of the support rod.
[0006] By adopting the above technical scheme, when supporting the building formwork, since the horizontal plates are connected by locking bolts, the horizontal plates are attached to the board wall of the main formwork, and then the locking bolts are screwed to tighten the locking bolts. Since a supporting mechanism is installed at the board wall of the horizontal plate, the supporting mechanism is composed of a fixed plate, a supporting plate, a threaded rod, a support rod and a threaded sleeve. After the personnel pass the threaded rod through the fixed plate, they screw the threaded sleeve to squeeze the two sides of the fixed plate to fix the threaded rod. Since a support rod is welded at the rod wall of the threaded rod, and a support plate is welded at the other end of the support rod, the support plate supports the ground, thereby supporting the main formwork and increasing the supportability of the building formwork.
[0007] Specifically, it also includes a connecting mechanism, and the connecting mechanism is installed on the board wall of the main template.
[0008] By adopting the above technical solution, the main template and the auxiliary template can be conveniently connected through the connecting mechanism.
[0009] Specifically, the connecting mechanism is composed of a combination of a secondary template, a vertical plate, a card plate and a card slot. A group of symmetrical card slots are opened on the board wall of the main template, a group of symmetrical vertical plates are fixedly installed on the board wall of the secondary template, a group of card plates are welded on the board wall of the vertical plates, and the card slots are plug-connected with the card plates.
[0010] By adopting the above technical scheme, when the main template and the auxiliary template are connected, since a connecting mechanism is installed on the board wall of the main template, the connecting mechanism is composed of a combination of an auxiliary template, a vertical plate, a card plate and a card slot, a group of symmetrical card slots are opened on the board wall of the main template, a group of symmetrical vertical plates are fixedly installed on the board wall of the vertical plate, and the card plate is welded on the board wall of the vertical plate, so that after the personnel insert the card plate into the card slot, the main template and the auxiliary template can be plugged and connected, which is convenient for the personnel to disassemble later.
[0011] Specifically, the plate walls of the transverse plate are connected by a group of symmetrical locking bolts.
[0012] By adopting the above technical solution, the cross plates can be conveniently connected by screwing the locking bolts.
[0013] Specifically, the main template and the cross plate are attached to each other.
[0014] By adopting the above technical solution, the cross plate is fixed by squeezing the main template through the cross plate.
[0015] Beneficial effects of the utility model:
[0016] (1) The utility model discloses a spliced building formwork for construction engineering. When supporting the building formwork, the horizontal plates are connected by locking bolts, so that the horizontal plates are attached to the plate wall of the main formwork, and then the locking bolts are screwed to tighten the locking bolts. Since a support mechanism is installed at the plate wall of the horizontal plate, the support mechanism is composed of a fixed plate, a support plate, a threaded rod, a support rod and a threaded sleeve. After the personnel pass the threaded rod through the fixed plate, they screw the threaded sleeve to squeeze the two sides of the fixed plate to fix the threaded rod. Since the support rod is welded to the rod wall of the threaded rod, and the other end of the support rod is welded to the support plate, the support plate supports the ground, thereby supporting the main formwork and increasing the supportability of the building formwork.
[0017] (2) The utility model discloses a spliced building formwork for construction projects. When the main formwork and the auxiliary formwork are connected, a connecting mechanism is installed on the board wall of the main formwork. The connecting mechanism is composed of an auxiliary formwork, a vertical plate, a clamping plate and a clamping groove. A group of symmetrical clamping grooves are opened on the board wall of the main formwork. A group of symmetrical vertical plates are fixedly installed on the board wall of the vertical plate. The clamping plate is welded on the board wall of the vertical plate. After the personnel insert the clamping plate into the clamping groove, the main formwork and the auxiliary formwork can be plugged and connected, which is convenient for the personnel to disassemble later. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The utility model is further described below in conjunction with the accompanying drawings and embodiments.
[0019] Figure 1 It is the main figure of the utility model;
[0020] Figure 2 This is a schematic diagram of the support mechanism structure of the utility model;
[0021] Figure 3 This is a schematic diagram of the connection mechanism structure of the utility model;
[0022] In the figure: 1. main template; 2. locking bolt; 3. horizontal plate; 4. supporting mechanism; 401. fixing plate; 402. supporting plate; 403. threaded rod; 404. supporting rod; 405. threaded sleeve; 5. connecting mechanism; 501. auxiliary template; 502. vertical plate; 503. clamping plate; 504. clamping slot. DETAILED DESCRIPTION
[0023] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.
[0024] As an embodiment of the present utility model, Figure 1 , Figure 2 and Figure 3 As shown, a spliced building formwork for construction engineering described in the utility model includes a main formwork 1 and a transverse plate 3, a support mechanism 4 is installed at the plate wall of the transverse plate 3, and the support mechanism 4 is composed of a fixed plate 401, a support plate 402, a threaded rod 403, a support rod 404 and a threaded sleeve 405. A group of symmetrical fixed plates 401 are welded at the plate wall of the transverse plate 3, a group of fixed plates 401 are plugged and connected between the plate walls, two groups of symmetrical threaded sleeves 405 are threadedly connected at the rod walls of the threaded rods 403, and the fixed plates 401 are located between the threaded sleeves 405, support rods 404 are welded at the rod walls of the threaded rods 403, and the other end of the support rod 404 is welded to a support plate 402.
[0025] When in use, since the cross plates 3 are connected by locking bolts 2, after the cross plates 3 are attached to the board wall of the main formwork 1, the locking bolts 2 are screwed to tighten the locking bolts 2. Since a supporting mechanism 4 is installed at the board wall of the cross plate 3, the supporting mechanism 4 is composed of a fixed plate 401, a support plate 402, a threaded rod 403, a support rod 404 and a threaded sleeve 405. After the personnel pass the threaded rod 403 through the fixed plate 401, they screw the threaded sleeve 405 to make the threaded sleeve 405 squeeze the two sides of the fixed plate 401 to fix the threaded rod 403. Since the support rod 404 is welded to the rod wall of the threaded rod 403, and the other end of the support rod 404 is welded to the support plate 402, the support plate 402 supports the ground, thereby supporting the main formwork 1 and increasing the supportability of the building formwork.
[0026] like Figure 1 As shown, it also includes a connecting mechanism 5, and the connecting mechanism 5 is installed on the board wall of the main template 1.
[0027] When in use, the main template 1 and the auxiliary template 501 are conveniently connected through the connecting mechanism 5.
[0028] like Figure 1 and Figure 3 As shown, the connecting mechanism 5 is composed of a secondary template 501, a vertical plate 502, a clamping plate 503 and a clamping slot 504. A group of symmetrical clamping slots 504 are opened on the board wall of the main template 1, a group of symmetrical vertical plates 502 are fixedly installed on the board wall of the secondary template 501, a group of clamping plates 503 are welded on the board wall of the vertical plates 502, and the clamping slots 504 are plug-connected with the clamping plates 503.
[0029] When in use, since a connecting mechanism 5 is installed on the board wall of the main template 1, the connecting mechanism 5 is composed of a sub-template 501, a vertical plate 502, a card plate 503 and a card slot 504. A group of symmetrical card slots 504 are opened on the board wall of the main template 1, and a group of symmetrical vertical plates 502 are fixedly installed on the board wall of the vertical plate 502. The card plate 503 is welded on the board wall of the vertical plate 502. After the personnel inserts the card plate 503 into the card slot 504, the main template 1 and the sub-template 501 are plugged and connected, which is convenient for the personnel to disassemble later.
[0030] like Figure 1 As shown, the plate walls of the transverse plate 3 are connected by a group of symmetrical locking bolts 2.
[0031] When in use, the cross plates 3 can be conveniently connected by screwing the locking bolts 2 .
[0032] like Figure 1 As shown, the main template 1 and the cross plate 3 are attached to each other.
[0033] When in use, the cross plate 3 is fixed by squeezing the main template 1 through the cross plate 3 .
[0034] When the utility model is in use, when supporting the building formwork, since the horizontal plates 3 are connected by the locking bolts 2, the horizontal plates 3 are attached to the plate wall of the main formwork 1, and the locking bolts 2 are screwed to tighten the locking bolts 2. Since the plate wall of the horizontal plate 3 is equipped with a supporting mechanism 4, the supporting mechanism 4 is composed of a fixed plate 401, a supporting plate 402, a threaded rod 403, a supporting rod 404 and a threaded sleeve 405. After the personnel pass the threaded rod 403 through the fixed plate 401, they screw the threaded sleeve 405 so that the threaded sleeve 405 squeezes the two sides of the fixed plate 401 to fix the threaded rod 403. Since the support rod 404 is welded at the rod wall of the threaded rod 403, the other end of the support rod 404 is welded with a supporting rod 404. The support plate 402 supports the ground, thereby supporting the main template 1 and increasing the support of the building template. When the main template 1 is connected to the auxiliary template 501, since the connecting mechanism 5 is installed on the board wall of the main template 1, the connecting mechanism 5 is composed of the auxiliary template 501, the vertical plate 502, the clamping plate 503 and the clamping groove 504. A group of symmetrical clamping grooves 504 are opened on the board wall of the main template 1, and a group of symmetrical vertical plates 502 are fixedly installed on the board wall of the vertical plate 502. The clamping plate 503 is welded on the board wall of the vertical plate 502, so that after the personnel insert the clamping plate 503 into the clamping groove 504, the main template 1 and the auxiliary template 501 are plugged and connected, which is convenient for personnel to disassemble later.
[0035] The above shows and describes the basic principles, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions in the specification are only to illustrate the principles of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the protection required by the utility model. The scope of protection required by the utility model is defined by the attached claims and their equivalents.
Claims
1. A spliced building formwork for construction engineering, characterized in that: The invention comprises a main template (1) and a transverse plate (3), wherein a support mechanism (4) is installed at the plate wall of the transverse plate (3), wherein the support mechanism (4) is composed of a fixed plate (401), a support plate (402), a threaded rod (403), a support rod (404) and a threaded sleeve (405), wherein a group of symmetrical fixed plates (401) are welded at the plate wall of the transverse plate (3), a threaded rod (403) is plugged and connected between the plate walls of a group of fixed plates (401), two groups of symmetrical threaded sleeves (405) are threadedly connected at the rod walls of the threaded rods (403), and the fixed plate (401) is located between the threaded sleeves (405), a support rod (404) is welded at the rod wall of the threaded rod (403), and the other end of the support rod (404) is welded to the support plate (402).
2. The spliced building template for construction engineering according to claim 1 is characterized by: It also comprises a connecting mechanism (5), and the connecting mechanism (5) is installed on the board wall of the main template (1).
3. The spliced building template for construction engineering according to claim 2 is characterized by: The connecting mechanism (5) is composed of a secondary template (501), a vertical plate (502), a clamping plate (503) and a clamping slot (504). A group of symmetrical clamping slots (504) are provided on the plate wall of the main template (1). A group of symmetrical vertical plates (502) are fixedly installed on the plate wall of the secondary template (501). A clamping plate (503) is welded on the plate wall of a group of the vertical plates (502). The clamping slots (504) are plug-connected to the clamping plates (503).
4. The spliced building formwork for construction engineering according to claim 1, characterized in that: The plate walls of the transverse plate (3) are connected via a group of symmetrical locking bolts (2).
5. The spliced building formwork for construction engineering according to claim 1, characterized in that: The main template (1) and the transverse plate (3) are attached to each other.