Flow control device and pouring system
By using flow control devices in the casting construction of vertical shafts, the risks of clogged pipes and fall accidents are solved, and the concrete flow rate and flow rate are effectively controlled, which improves the safety of the pipelines in the wellbore.
Patent Information
- Application Number
- CN202421404458.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-19
- Publication Date
- 2025-02-25
- Estimated Expiration
- 2034-06-19
AI Technical Summary
During the development of mineral resources in deep underground, the risk of ash pipe blocking and falling accidents is high due to the rapid decentralization speed of concrete and the low collapse during vertical shaft casting construction.
Design a flow control device, including a dust funnel and a flow controller, with at least two shunt plates in the flow controller, and the shunt plate is distributed along the radial and circumferential direction of the dust funnel, through the positioning plate and the quick connection short tube Achieve stable installation and connection.
The flow rate and flow rate of concrete are effectively controlled through the flow control device, reducing the chance of pipe blocking, reducing the friction of the ash pipe, and improving the safety of the pipelines in the wellbore.
Smart Images

Figure CN222526297U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of vertical shaft pouring, in particular to a flow control device and a pouring system. Background Art
[0002] In the process of developing deep underground mineral resources, shaft engineering is the throat engineering of mines. During the pouring and construction of shafts, the ash pipes may be blocked or fall due to operation, equipment and facilities, which will bring many economic and safety problems to the project. When the concrete is lowered from the surface too fast and the slump is too low, the friction between the concrete and the pipe wall will be too large. If you are not careful, the ash pipes will be blocked and the concrete impact will cause the ash pipes to fall.
[0003] In order to avoid blockage in the ash chute, the traditional method is to install a chute under the mixer and connect it directly to the ash chute. The flow rate and velocity of concrete cannot be effectively controlled, and it is easy to be mixed with large pieces or debris, which can easily cause pipe blockage and concrete segregation. Pipe blockage can easily cause impact on the pipeline, resulting in the risk of pipeline falling and causing serious safety accidents. Utility Model Content
[0004] The technical problem to be solved by the utility model is how to reduce the probability of pipe blockage during the use of the ash chute.
[0005] The utility model provides a technical solution to the above-mentioned technical problem as follows: a flow control device, comprising an ash hopper and a flow controller, wherein the flow controller is installed in the ash hopper, and the flow controller comprises at least two diverter plates, wherein the diverter plates are arranged along the radial direction of the ash hopper, and at least two of the diverter plates are distributed at intervals along the circumference of the ash hopper, and at least two of the diverter plates are fixed to each other at one end facing the center of the ash hopper.
[0006] The beneficial effect of the utility model is that after the flow controller is placed in the ash hopper and the position is adjusted, it controls the concrete flow, reduces the concrete flow rate, guides the flowing concrete, and reduces the friction of aggregate on the pipeline. The flow controller is fully used to control the concrete flow rate and flow rate, which not only ensures the continuity of concrete lowering, but also reduces the probability of pipe blockage, reduces the risk of pipe blockage of the ash hopper connected below the ash hopper to a certain extent, and ensures the safety of the pipeline in the wellbore.
[0007] On the basis of the above technical solution, the present invention can also be improved as follows.
[0008] Furthermore, the flow controller also includes a positioning plate, the lower end of which is fixedly connected to the diverter plate, and the upper end of which is in contact with the ash hopper.
[0009] The beneficial effect of adopting the above further solution is that the diverter plate is positioned and installed in the ash hopper through the positioning plate.
[0010] Furthermore, the upper end of the positioning plate has a positioning inclined surface, and the positioning inclined surface abuts against the conical surface in the ash hopper.
[0011] The beneficial effect of adopting the above further solution is that the positioning plate abuts against the conical surface in the ash hopper through the positioning inclined surface, and the flow controller can be installed and positioned simply by placing the flow controller in the ash hopper.
[0012] Furthermore, there are at least two positioning plates, and the positioning plates are arranged in one-to-one correspondence with the diverter plates and are fixedly connected.
[0013] The beneficial effect of adopting the above further solution is that at least two positioning plates are provided, and the flow controller has high stability during installation.
[0014] Furthermore, the flow control device also includes a quick-connect short pipe, the upper end of which is detachably connected to the lower end of the ash hopper.
[0015] The beneficial effect of adopting the above further solution is: a 15mm long quick-connect short pipe with a quick connector is reserved above the sealing plate, and the ash funnel is connected and fixed firmly by the quick connector. The ash funnel is easy to assemble and maintain and replace.
[0016] Furthermore, the upper end of the flow controller is in contact with the ash hopper, and the diverter plate is located in the quick-connect short tube.
[0017] The utility model also provides a pouring system, comprising the flow control device.
[0018] The beneficial effects are: using the ash pipe to control the flow rate and velocity of concrete, reduce the probability of concrete blocking the pipe, and reduce the impact on the pipeline causing safety problems such as pipeline falling.
[0019] Furthermore, the pouring system also includes an ash storage bucket, the lower end of the ash storage bucket is provided with an ash storage bucket outlet, and the ash storage bucket outlet is located above the ash sliding funnel.
[0020] Furthermore, the pouring system also includes a connecting pipe and a gate valve, one end of the connecting pipe is connected to and communicated with the ash storage bucket outlet, the other end of the connecting pipe is located above the ash hopper, and the gate valve is arranged at one end of the connecting pipe.
[0021] The beneficial effect of adopting the above further scheme is: using an ash storage bucket to store ash, and using a gate valve on the connecting pipe to control the flow rate of concrete.
[0022] Furthermore, the side wall of the connecting pipe has a transparent observation window.
[0023] The beneficial effect of adopting the above further solution is that the flow of materials in the connecting pipe can be checked through the observation window, and the concrete flow can be adjusted in time through the gate valve.
[0024] The beneficial effects of the utility model are:
[0025] 1) Concrete pouring process is the most important part of shaft construction. The use of ash chute can greatly reduce energy consumption, save costs and speed up construction progress. The use of flow controller can greatly reduce the probability of pipe blockage during the use of ash chute, thus ensuring the safety of ash chute.
[0026] 2) During the process of lowering concrete from the wellhead, the ash storage bucket and the gate valve can better ensure the uniform speed and amount of concrete lowering.
[0027] 3) Placing a flow controller in the ash hopper can effectively control the concrete flow rate, so that the concrete is lowered at a uniform speed and volume. The flow controller also has a guiding function, reducing the friction of concrete on the pipe wall and reducing the wear of the pipeline. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a front perspective view of the flow control device of the utility model;
[0029] Figure 2 It is a top view of the flow control device of the utility model;
[0030] Figure 3 It is a schematic diagram of the pouring system of the utility model;
[0031] Figure 4 This is a schematic diagram of the installation position of the plug valve of the utility model.
[0032] In the accompanying drawings, the components represented by the reference numerals are listed as follows:
[0033] 100, flow control device; 101, ash funnel; 102, flow controller; 121, diverter plate; 122, positioning plate; 103, quick-connect short pipe;
[0034] 200. Ash storage barrel; 300. Connecting pipe; 400. Gate valve. DETAILED DESCRIPTION
[0035] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0036] like Figure 1-Figure 4As shown, this embodiment provides a flow control device, the flow control device 100 includes an ash hopper 101 and a flow controller 102, the flow controller 102 is installed in the ash hopper 101, the flow controller 102 includes at least two diverter plates 121, the diverter plates 121 are arranged along the radial direction of the ash hopper 101, at least two of the diverter plates 121 are distributed at intervals along the circumference of the ash hopper 101, and at least two of the diverter plates 121 are fixed to each other at one end facing the center of the ash hopper 101.
[0037] The flow controller 102 is placed in the ash funnel 101, and after the position is adjusted, it controls the concrete flow, reduces the concrete flow rate, guides the flowing concrete, and reduces the friction of aggregate on the pipeline. The flow controller 102 is fully used to control the concrete flow rate and flow rate, which not only ensures the continuity of concrete lowering, but also reduces the probability of pipe blockage, and to a certain extent reduces the risk of pipe blockage of the ash pipe connected below the ash funnel 101, ensuring the safety of the pipeline in the wellbore.
[0038] The number of the diverter plates 121 can be set as desired, and the multiple diverter plates 121 are evenly distributed or evenly distributed along the circumference. Figure 1 and Figure 2 As shown, there are four diverter plates 121, and the four diverter plates 121 are fixed in a cross shape.
[0039] On the basis of any of the above solutions, the flow controller 102 further includes a positioning plate 122 , the lower end of the positioning plate 122 is fixedly connected to the diverter plate 121 , and the upper end of the positioning plate 122 abuts against the ash hopper 101 .
[0040] The diverter plate 121 is positioned and installed in the ash hopper 101 through the positioning plate 122 .
[0041] Alternatively, the positioning plate 122 is welded or clamped to the ash hopper 101 .
[0042] On the basis of any of the above solutions, the upper end of the positioning plate 122 has a positioning inclined surface, and the positioning inclined surface abuts against the conical surface in the ash hopper 101 .
[0043] The positioning plate 122 abuts against the conical surface in the ash hopper 101 through the positioning inclined surface. The flow controller 102 can be installed and positioned by simply placing the flow controller 102 in the ash hopper 101 .
[0044] Specifically, Figure 1 As shown, the upper end of the positioning plate 122 is a triangle, the lower end is a rectangle, and the hypotenuse of the triangle is a positioning slope.
[0045] On the basis of any of the above solutions, there are at least two positioning plates 122 , and the positioning plates 122 are arranged in one-to-one correspondence with the diverter plates 121 and are fixedly connected.
[0046] At least two positioning plates 122 are provided, so that the flow controller 102 has high stability during installation.
[0047] In one specific example, Figure 1 As shown, there are four positioning plates 122 .
[0048] On the basis of any of the above solutions, the flow control device further comprises a quick-connect short pipe 103 , the upper end of which is detachably connected to the lower end of the ash hopper 101 .
[0049] A 15 mm long quick-connect short pipe 103 with a quick connector is reserved above the sealing plate, and the ash funnel 101 is connected and fixed firmly by the quick connector. The ash funnel 101 is easy and quick to assemble and easy to maintain and replace.
[0050] On the basis of any of the above solutions, the upper end of the flow controller 102 is in contact with the ash hopper 101 , and the diverter plate 121 is located in the quick-connect short pipe 103 .
[0051] Specifically, the lower end of the quick-connect short pipe 103 is connected to the ash sluice pipe.
[0052] Specifically, the maximum diameter of the flow controller 102 should be smaller than the inner diameter of the quick-connect short tube 103 to ensure that the flow controller 102 can be moved at any time.
[0053] Specifically, the working principle of the flow controller 102 is: by dividing the space inside the quick-connect short pipe 103 and fixing the ash outlet capacity, it plays a role in controlling the concrete flow and maintaining the stability of the flow rate and flow velocity; and in the process of concrete lowering, it also plays a guiding role, reducing the scouring of the concrete on the ash chute pipe orifice, reducing the rebound of aggregates in the pipe, and reducing the wear of the pipeline.
[0054] This embodiment also provides a casting system, including the flow control device.
[0055] Use ash pipes to control the flow rate and velocity of concrete, reduce the probability of concrete blocking the pipe, and reduce safety issues such as pipe falling caused by impact on the pipeline.
[0056] On the basis of the above solution, the pouring system further includes an ash storage bucket 200 , the lower end of the ash storage bucket 200 is provided with an ash storage bucket outlet, and the ash storage bucket outlet is located above the ash sliding funnel 101 .
[0057] On the basis of the above scheme, the pouring system also includes a connecting pipe 300 and a gate valve 400, one end of the connecting pipe 300 is connected and communicated with the ash storage bucket outlet, the other end of the connecting pipe 300 is located above the ash hopper 101, and the gate valve 400 is arranged at one end of the connecting pipe 300.
[0058] The ash storage bucket 200 is used to store ash, and the flow rate of concrete is controlled by the gate valve 400 on the connecting pipe 300. After a certain amount of concrete is stored in the ash storage bucket 200, the gate valve 400 is opened and closed to discharge and control the flow rate of concrete.
[0059] On the basis of the above solution, the side wall of the connecting pipe 300 has a transparent observation window.
[0060] The flow of materials in the connection pipe 300 can be checked through the observation window, and the flow of concrete can be adjusted in time through the gate valve 400.
[0061] In the description of the present invention, it should be noted that the terms "axial", "radial", "circumferential", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0062] In the description of the present invention, "plurality" means at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0063] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being "above", "above" or "above" a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being "below", "below" or "below" a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0064] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.
[0065] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0066] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A flow control device, characterized in that: The flow control device (100) comprises an ash hopper (101) and a flow controller (102), wherein the flow controller (102) is installed in the ash hopper (101), and the flow controller (102) comprises at least two diverter plates (121), wherein the diverter plates (121) are arranged along the radial direction of the ash hopper (101), and at least two of the diverter plates (121) are distributed at intervals along the circumference of the ash hopper (101), and at least two of the diverter plates (121) are fixed to each other at one end facing the center of the ash hopper (101).
2. A flow control device according to claim 1, characterized in that: The flow controller (102) further comprises a positioning plate (122), the lower end of the positioning plate (122) being fixedly connected to the diverter plate (121), and the upper end of the positioning plate (122) being in contact with the ash hopper (101).
3. A flow control device according to claim 2, characterized in that: The upper end of the positioning plate (122) has a positioning inclined surface, and the positioning inclined surface abuts against the conical surface inside the ash sliding funnel (101).
4. A flow control device according to claim 2, characterized in that: There are at least two positioning plates (122), and the positioning plates (122) and the diverter plates (121) are arranged in a one-to-one correspondence and fixedly connected.
5. A flow control device according to any one of claims 1 to 4, characterized in that: It also comprises a quick-connect short pipe (103), the upper end of which is detachably connected to the lower end of the ash hopper (101).
6. A flow control device according to claim 5, characterized in that: The upper end of the flow controller (102) is in contact with the ash hopper (101), and the diverter plate (121) is located in the quick-connect short pipe (103).
7. A casting system, characterized in that: Comprising a flow control device as described in any one of claims 1-6.
8. A pouring system according to claim 7, characterized in that: It also includes an ash storage bucket (200), the lower end of the ash storage bucket (200) is provided with an ash storage bucket outlet, and the ash storage bucket outlet is located above the ash sliding funnel (101).
9. A pouring system according to claim 8, characterized in that: It also includes a connecting pipe (300) and a gate valve (400), one end of the connecting pipe (300) is connected to and communicates with the outlet of the ash storage bucket, the other end of the connecting pipe (300) is located above the ash hopper (101), and the gate valve (400) is arranged at one end of the connecting pipe (300).