Building template scaffold fastener

By designing a building formwork scaffolding fastener that includes fastening components and adjustment components, the adjustment and fixing of the crossing angle of the steel pipe is achieved, solving the problem that existing fasteners cannot adapt to crossing steel pipes without the ninety-degree angle.

CN222595498UActive Publication Date: 2025-03-11TIANJIN HANDING BUILDING DECORATION ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421279294.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-06
Publication Date
2025-03-11
Estimated Expiration
2034-06-06

AI Technical Summary

Technical Problem

The existing building formwork scaffolding fasteners can only be effectively fixed when the crossing angle of the steel pipe is 90 degrees, and cannot adapt to the situation where the crossing angle of the steel pipe is not 90 degrees.

Method used

A fastener is designed including a fastening assembly and an adjustment assembly, the fastening assembly includes a fixing buckle and a movable buckle. The adjustment assembly realizes adjustment and fixing of the angle between the steel pipes through a combination of the first and second adjustment discs, bolts and nuts.

Benefits of technology

By adjusting the angle in the fastener, the crossing angle of the steel pipe can be effectively fixed to the situation where the crossing angle of the steel pipe is not 90 degrees, which solves the problem that the existing fasteners cannot adapt to the crossing steel pipes that are not 90 degrees angle.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222595498U_ABST
    Figure CN222595498U_ABST
Patent Text Reader

Abstract

The utility model discloses a building template scaffold fastener which comprises fastening assemblies, an adjusting assembly is arranged between the fastening assemblies, the fastening assemblies comprise fixing buckles, the adjusting assembly comprises a first adjusting disc and a second adjusting disc, a first fixing hole is formed in the first adjusting disc, and a second fixing hole is formed in the second adjusting disc. A first fixing hole is formed in the first adjusting disc, a second fixing hole is formed in the second adjusting disc, and a first bolt and a second bolt are connected between the first fixing hole and the second fixing hole in a threaded mode. According to the building formwork scaffold fastener, the angle between the first adjusting disc and the second adjusting disc is adjusted, the first fixing holes and the second fixing holes are aligned again after angle adjustment, and the first fixing holes and the second fixing holes are fixed again through the first bolts and the second bolts after alignment, so that angle adjustment and fixation of the two fastening assemblies can be achieved; therefore, the problem that when the crossing angle between the steel pipes is not 90 degrees, the steel pipes are inconvenient to fix through fasteners is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of scaffold fasteners, in particular to a building template scaffold fastener. Background Art

[0002] Building formwork scaffolding is an indispensable and important tool in building construction. They not only provide convenience for construction, but also ensure the quality and safety of construction. In the application of building formwork scaffolding, we need to pay attention to the details of its design, installation and use to ensure its full play.

[0003] External scaffolding of buildings is generally composed of multiple steel pipes, which are connected by fasteners. The intersection of two steel pipes is generally fixed by fasteners perpendicular to each other on both sides. Although this fixing method can effectively fix the intersection of steel pipes, it can only cross two steel pipes vertically. When the intersection angle between the steel pipes is not ninety degrees, it is not convenient to fix them by this fastener.

[0004] Therefore, the utility model provides a building formwork scaffolding fastener to solve the above problems. Utility Model Content

[0005] In view of the deficiencies in the prior art, the utility model provides a building formwork scaffolding fastener to solve the above problems.

[0006] To achieve the above objectives, the utility model is implemented through the following technical solutions: a building formwork scaffolding fastener, including a fastening component, an adjustment component is arranged between the fastening components, the fastening component includes a fixing buckle, the adjustment component includes a first adjusting disk and a second adjusting disk, the first adjusting disk and the second adjusting disk are respectively fixedly installed on the opposite sides of the two fixing buckles, a first fixing hole is opened inside the first adjusting disk, a second fixing hole is opened inside the second adjusting disk, and a first bolt and a second bolt are screwed between the first fixing hole and the second fixing hole.

[0007] Preferably, the first adjusting disk and the second adjusting disk fit each other, and the positions of the first fixing holes and the second fixing holes correspond one to one.

[0008] By adopting the above technical solution, the angle between the two fasteners can be adjusted by aligning the first and second fixing holes at different positions.

[0009] Preferably: the first bolt is screwed from the inside of the first fixing hole to the inside of the second fixing hole, the second bolt is screwed from the inside of the second fixing hole to the inside of the first fixing hole, and the first bolt and the second bolt are both located on both sides of the corresponding fixing buckle.

[0010] By adopting the above technical solution, the first and second adjusting disks are fixed by the first and second bolts.

[0011] Preferably, the first adjusting disk and the second adjusting disk are respectively welded to corresponding fixing buckles.

[0012] By adopting the above technical solution, the welding method makes the installation more firm.

[0013] Preferably, the fastening assembly further comprises a movable buckle, the bottom of the movable buckle is rotatably connected to the bottom of the fixed buckle, and the groove positions of the fixed buckle and the movable buckle correspond to each other.

[0014] The above technical solution is adopted to fasten the steel pipe to the outside through the fixed buckle and the movable buckle.

[0015] Preferably: an adjustment groove is provided at the top of the fixing buckle, a movable rod is rotatably connected inside the adjustment groove, a threaded column is fixedly installed on the end face of the movable rod, a slot is provided at the top of the movable buckle, the threaded column is inserted into the slot, a nut is screwed on the outer side of the threaded column, and the nut is located on the outside of the movable buckle.

[0016] By adopting the above technical solution, the fixed buckle and the movable buckle are fixed by nuts and threaded columns.

[0017] Beneficial Effects

[0018] The utility model provides a building formwork scaffolding fastener. Compared with the prior art, it has the following beneficial effects:

[0019] 1. The building formwork scaffolding fastener can adjust the angle between the first adjusting disk and the second adjusting disk, realign the first fixing hole with the second fixing hole after the angle adjustment, and re-fix the two fastening components by the first bolt and the second bolt after the alignment, thereby solving the problem that it is inconvenient to fix the steel pipes by the fasteners when the crossing angle between the steel pipes is not ninety degrees.

[0020] 2. The building formwork scaffolding fastener is achieved by separating the movable buckle from the fixed buckle, and then buckling the fixed buckle and the movable buckle on both sides of the steel pipe respectively. Then, the threaded column is re-inserted into the slot through the movable rod, and the nut is tightened to fix the fixed buckle and the movable buckle on the outside of the steel pipe, and the cross steel pipe is fixed by the fixed buckle and movable buckle on both sides. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the implementation scheme of the utility model or the technical scheme in the prior art, the drawings required for use in the implementation scheme or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some implementation schemes of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0022] Figure 1 It is a three-dimensional diagram of the external structure of the utility model;

[0023] Figure 2 This is a three-dimensional diagram of the disassembled structure of the adjustment component of the utility model;

[0024] Figure 3 It is a stereogram of the overall structure of the adjustment component of the utility model;

[0025] Figure 4 It is an overall stereogram of the utility model after the angle is adjusted;

[0026] Figure 5 It is a three-dimensional diagram of the fastening assembly structure of the utility model.

[0027] In the figure: 1. fastening assembly; 11. fixing buckle; 12. movable buckle; 13. adjustment slot; 14. clamping slot; 15. movable rod; 16. threaded column; 17. nut; 2. adjustment assembly; 21. first adjustment disk; 22. second adjustment disk; 23. first fixing hole; 24. second fixing hole; 25. first bolt; 26. second bolt. DETAILED DESCRIPTION

[0028] It should be noted that in the description of the embodiments of the present application, the terms "front, rear", "left, right", "up, down", etc. indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present application. The terms "install", "connect", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to specific circumstances.

[0029] The present application is further described in detail below through drawings and examples.

[0030] Reference Figures 1 to 5The embodiment of the present application provides a building formwork scaffolding fastener, including a fastening component 1, an adjusting component 2 is arranged between the fastening components 1, the fastening component 1 includes a fixing buckle 11, the adjusting component 2 includes a first adjusting disk 21 and a second adjusting disk 22, the first adjusting disk 21 and the second adjusting disk 22 are respectively fixedly installed on the opposite sides of the two fixing buckles 11, a first fixing hole 23 is opened inside the first adjusting disk 21, a second fixing hole 24 is opened inside the second adjusting disk 22, and a first bolt 25 and a second bolt 26 are screwed between the first fixing hole 23 and the second fixing hole 24.

[0031] The first adjustment disk 21 and the second adjustment disk 22 fit each other, and the first fixing hole 23 and the second fixing hole 24 correspond to each other. The first bolt 25 is screwed from the inside of the first fixing hole 23 to the inside of the second fixing hole 24, and the second bolt 26 is screwed from the inside of the second fixing hole 24 to the inside of the first fixing hole 23. The first bolt 25 and the second bolt 26 are both located on both sides of the corresponding fixing buckle 11. The first adjustment disk 21 and the second adjustment disk 22 are respectively welded to the corresponding fixing buckle 11.

[0032] In this embodiment, two steel pipes are vertically fixed by fastening components 1 that are perpendicular to each other on both sides. When the fixing angle between the steel pipes needs to be adjusted, the first bolt 25 and the second bolt 26 are released. After release, the fixation between the first adjustment disk 21 and the second adjustment disk 22 can be released, so that the angle between the first adjustment disk 21 and the second adjustment disk 22 can be adjusted. After the angle is adjusted, the first fixing hole 23 is realigned with the second fixing hole 24. After alignment, they are re-fixed by the first bolt 25 and the second bolt 26. The angle adjustment and fixation of the two fastening components 1 can be achieved, thereby solving the problem that when the crossing angle between the steel pipes is not ninety degrees, it is inconvenient to fix them by fasteners.

[0033] Reference Figures 1 to 5 In one aspect of the present embodiment, the fastening assembly 1 further includes a movable buckle 12, the bottom of the movable buckle 12 is rotatably connected to the bottom of the fixed buckle 11, and the groove positions of the fixed buckle 11 and the movable buckle 12 correspond to each other.

[0034] An adjustment slot 13 is provided at the top of the fixed buckle 11, and a movable rod 15 is rotatably connected inside the adjustment slot 13. A threaded column 16 is fixedly installed on the end face of the movable rod 15. A slot 14 is provided at the top of the movable buckle 12, and the threaded column 16 is inserted into the slot 14. A nut 17 is screwed on the outer side of the threaded column 16, and the nut 17 is located on the outside of the movable buckle 12.

[0035] In this embodiment, when the fastener fixes the steel pipe, the nut 17 is moved outward from the threaded column 16 to release the fixation between the threaded column 16 and the movable buckle 12, and the movable buckle 12 is separated from the fixed buckle 11. After separation, the fixed buckle 11 and the movable buckle 12 are respectively buckled on both sides of the steel pipe, and then the threaded column 16 is re-inserted into the slot 14 through the movable rod 15, and the nut 17 is tightened, so that the fixed buckle 11 and the movable buckle 12 are fixed to the outside of the steel pipe, and the cross steel pipes are fixed by the fixed buckle 11 and the movable buckle 12 on both sides.

[0036] Working principle: The two steel pipes are vertically fixed by the fastening components 1 perpendicular to each other on both sides. When the fixed angle between the steel pipes needs to be adjusted, the first bolt 25 and the second bolt 26 are released, and the fixation between the first adjustment disk 21 and the second adjustment disk 22 can be released after the release, so that the angle between the first adjustment disk 21 and the second adjustment disk 22 can be adjusted. After the angle is adjusted, the first fixing hole 23 and the second fixing hole 24 are realigned, and after alignment, the first bolt 25 and the second bolt 26 are used to re-fix, so that the angle of the two fastening components 1 can be adjusted and fixed, thereby solving the problem of the steel pipes being fixed at the same time. When the crossing angle is not ninety degrees, it is inconvenient to fix it with fasteners; when the steel pipe is fixed with fasteners, the nut 17 is moved outward from the threaded column 16 to release the fixation between the threaded column 16 and the movable buckle 12, and the movable buckle 12 is separated from the fixed buckle 11. After separation, the fixed buckle 11 and the movable buckle 12 are respectively buckled on both sides of the steel pipe, and then the threaded column 16 is re-inserted into the slot 14 through the movable rod 15, and the nut 17 is tightened, so that the fixed buckle 11 and the movable buckle 12 are fixed to the outside of the steel pipe, and the cross steel pipes are fixed by the fixed buckle 11 and the movable buckle 12 on both sides.

[0037] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0038] Although the embodiments of the present application have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the appended claims and their equivalents.

Claims

1. A building formwork scaffolding fastener, comprising a fastening assembly (1), characterized in that: An adjustment component (2) is arranged between the fastening components (1), the fastening component (1) comprises a fixing buckle (11), and the adjustment component (2) comprises a first adjustment disk (21) and a second adjustment disk (22), the first adjustment disk (21) and the second adjustment disk (22) are respectively fixedly mounted on opposite sides of the two fixing buckles (11), a first fixing hole (23) is provided inside the first adjustment disk (21), a second fixing hole (24) is provided inside the second adjustment disk (22), and a first bolt (25) and a second bolt (26) are screwed between the first fixing hole (23) and the second fixing hole (24).

2. A building formwork scaffolding fastener according to claim 1, characterized in that: The first adjustment disk (21) and the second adjustment disk (22) fit each other, and the first fixing hole (23) and the second fixing hole (24) correspond in position to each other.

3. A building formwork scaffolding fastener according to claim 1, characterized in that: The first bolt (25) is screwed from the inside of the first fixing hole (23) to the inside of the second fixing hole (24), and the second bolt (26) is screwed from the inside of the second fixing hole (24) to the inside of the first fixing hole (23), and the first bolt (25) and the second bolt (26) are both located on both sides of the corresponding fixing buckle (11).

4. A building formwork scaffolding fastener according to claim 1, characterized in that: The first adjustment disk (21) and the second adjustment disk (22) are respectively welded to the corresponding fixing buckles (11).

5. A building formwork scaffolding fastener according to claim 1, characterized in that: The fastening assembly (1) further comprises a movable buckle (12), the bottom of which is rotatably connected to the bottom of the fixed buckle (11), and the groove positions of the fixed buckle (11) and the movable buckle (12) correspond to each other.

6. A building formwork scaffolding fastener according to claim 5, characterized in that: The top of the fixing buckle (11) is provided with an adjustment groove (13), the inside of the adjustment groove (13) is rotatably connected with a movable rod (15), the end surface of the movable rod (15) is fixedly mounted with a threaded column (16), the top of the movable buckle (12) is provided with a clamping groove (14), the threaded column (16) is inserted into the inside of the clamping groove (14), the outer side of the threaded column (16) is screwed with a nut (17), and the nut (17) is located outside the movable buckle (12).