Structural joint template

By using structural joint formwork, including skeleton, inner formwork and outer formwork, combined with the gap generated by the shrinkage of the concrete itself, the formwork is removed, and the high cost, low quality and safety problems of joint fill and sectional construction in the prior art are solved, and the effects of reducing costs, saving construction period and improving safety are achieved.

CN222649450UActive Publication Date: 2025-03-21XINJIANG BEIXIN ROAD & BRIDGE GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420818855.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-17
Publication Date
2025-03-21
Estimated Expiration
2034-04-17

AI Technical Summary

Technical Problem

In the prior art, foam boards and extruded polystyrene boards are used for joint filling or segmented construction, and there are problems such as high production cost, poor quality effect, affecting construction period and low safety.

Method used

A structural seam template is provided, including a skeleton, an inner form and an outer form. Through the cooperation of the skeleton and the inner form, a caulking structure is formed, and the form is taken out through the gap generated by the shrinkage of the concrete itself, thereby realizing the forming of the structural seam.

Benefits of technology

This formwork can reduce production costs, save construction period, improve structural joint molding quality, and improve construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222649450U_ABST
    Figure CN222649450U_ABST
Patent Text Reader

Abstract

The embodiment of the utility model provides a structural joint formwork, and relates to the technical field of building construction. The structural joint formwork comprises a framework, a first inner formwork, a second inner formwork, a first outer formwork and a second outer formwork, the first inner formwork is arranged on one side of the framework, the second inner formwork is oppositely arranged on the other side of the framework, and the first outer formwork is arranged on the side, away from the framework, of the first inner formwork at intervals to form a first concrete pouring space; the second outer formworks are arranged on the sides, away from the framework, of the second inner formworks at intervals to form a second concrete pouring space. According to the structural joint formwork, the production cost can be reduced, the construction period is shortened, the structural joint forming quality is improved, and the construction safety is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building construction, in particular to a structural joint template. Background Art

[0002] The main body of a building is usually a reinforced concrete structure. According to the specifications and requirements of structural settlement, floor area, apartment distribution, lighting, thermal expansion and contraction, etc., structural joints ranging from 100mm to 300mm are usually designed in the construction plan. To ensure the formation of the structural joints, foam boards, extruded polystyrene boards are usually used for filling the joints in the prior art, or a segmented construction method is adopted.

[0003] However, the method of using foam boards and extruded polystyrene boards for filling or segmented construction has problems such as high production cost, poor quality, affected construction period and low safety. Utility Model Content

[0004] The utility model aims to provide a structural joint template, which can reduce production costs, save construction period, improve structural joint forming quality, and has high construction safety.

[0005] The embodiment of the utility model is achieved as follows:

[0006] In a first aspect, the utility model provides a structural seam template, comprising:

[0007] skeleton;

[0008] A first inner template, wherein the first inner template is arranged on one side of the frame;

[0009] A second inner template, the second inner template is arranged opposite to the other side of the frame;

[0010] a first outer formwork, the first outer formwork being spaced apart from a side of the first inner formwork away from the frame to form a first concrete pouring space; and

[0011] The second outer formwork is spaced apart from a side of the second inner formwork away from the frame to form a second concrete pouring space.

[0012] In an optional embodiment, the skeleton includes a first support frame, a second support frame and a plurality of inner support bars, the first support frame and the second support frame are arranged at intervals, the plurality of inner support bars are arranged at intervals, and each of the inner support bars is connected to the first support frame and the second support frame at the same time;

[0013] The first inner template is arranged on a side of the first support frame away from the second support frame, and the second inner template is arranged on a side of the second support frame away from the first support frame.

[0014] In an optional embodiment, the first support frame includes a plurality of first horizontal bars and a plurality of first vertical bars, and the second support frame includes a plurality of second horizontal bars and a plurality of second vertical bars, the plurality of first horizontal bars and the plurality of second horizontal bars are arranged at intervals along the first direction and correspond one to one, and the plurality of first vertical bars and the plurality of second vertical bars are arranged at intervals along the first direction and correspond one to one;

[0015] The plurality of first vertical bars and the plurality of second vertical bars are arranged at intervals along the second direction, the plurality of first horizontal bars and the plurality of second horizontal bars are arranged at intervals along the third direction, one end of each of the inner support bars is connected to the first horizontal bar and the first vertical bar at the same time, and the other end is connected to the second horizontal bar and the second vertical bar at the same time;

[0016] The first direction, the second direction and the third direction are perpendicular to each other.

[0017] In an optional embodiment, the top of the skeleton is higher than the top surface of the first outer template and the second outer template;

[0018] The top of the first inner template is higher than the top surfaces of the first outer template and the second outer template;

[0019] The top end of the second inner template is higher than the top surfaces of the first outer template and the second outer template.

[0020] In an optional embodiment, the structural seam formwork further includes a connecting piece, and the first inner formwork and the second inner formwork are both connected to the frame via the connecting piece.

[0021] In an optional embodiment, the structural seam formwork further includes a lifting ring, and the lifting ring is simultaneously connected to the first inner formwork, the second inner formwork and the frame.

[0022] In an optional embodiment, the structural seam template also includes a third inner template, a fourth inner template, a top template and a bottom template, and the first inner template, the third inner template, the second inner template and the fourth inner template are sequentially arranged around the frame; the top template is arranged on the top surface of the frame, and the bottom template is arranged on the bottom surface of the frame.

[0023] In an optional embodiment, the structural seam template further includes a screw, a first nut, a second nut, a first buckle, a second buckle, a first fixing tube and a second fixing tube, and the screw is used to sequentially penetrate the first outer template, the first inner template, the frame, the second inner template and the second outer template;

[0024] The first buckle is sleeved on the screw rod and located on a side of the first outer template away from the first inner template. The first fixing tube is arranged between the first buckle and the first outer template. The first nut is sleeved on the screw rod and located on a side of the first buckle away from the first fixing tube, so as to fix the first buckle and the first fixing tube to the first outer template.

[0025] The second clip is sleeved on the screw rod and located on the side of the second outer template away from the second inner template. The second fixing tube is arranged between the second clip and the second outer template. The second nut is sleeved on the screw rod and located on the side of the second clip away from the second fixing tube, so as to fix the second clip and the second fixing tube to the second outer template.

[0026] In an optional embodiment, the structural seam formwork also includes a first fixing plate and a second fixing plate, the first fixing plate is arranged between the first outer formwork and the first fixing tube, and the second fixing plate is arranged between the second outer formwork and the second fixing tube; the screw rod is used to sequentially penetrate the first fixing plate, the first outer formwork, the first inner formwork, the frame, the second inner formwork, the second outer formwork and the second fixing plate.

[0027] In an optional embodiment, the structural seam formwork further includes a pipe sleeve, which is sleeved on the screw rod and is used to sequentially penetrate the first outer formwork, the first inner formwork, the frame, the second inner formwork and the second outer formwork.

[0028] The beneficial effects of the embodiments of the utility model include:

[0029] The structural joint template includes a frame, a first inner template, a second inner template, a first outer template and a second outer template. The first inner template is arranged on one side of the frame, and the second inner template is arranged on the other side of the frame. The first outer template is arranged at a distance from the first inner template on the side away from the frame to form a first concrete pouring space, and the second outer template is arranged at a distance from the second inner template on the side away from the frame to form a second concrete pouring space. By pouring concrete into the first concrete pouring space and the second concrete pouring space, after the pouring is completed, the structural joint template can be taken out by relying on the gap generated by the shrinkage of the concrete itself, so that the gap between the two concretes is the formed structural joint.

[0030] That is to say, the skeleton can play a supporting role in the process of pouring concrete, and cooperate with the first inner formwork and the second inner formwork to form a filling structure. Compared with the existing method of using foam boards and extruded polystyrene boards for filling, it can save material costs; at the same time, through the cooperation of the first inner formwork and the first outer formwork, and the cooperation of the second inner formwork and the second outer formwork, the structural joints formed by pouring concrete have good appearance quality and avoid the quality risks of slag inclusions in the main structure; and the use of this structural joint formwork can enable parallel construction on the same floor. Compared with the segmented construction method, it can save implementation time. At the same time, there is no edge operation, which avoids the risk of falling from height and improves construction safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] In order to more clearly illustrate the technical solutions of the embodiments of the utility model, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.

[0032] Figure 1 A schematic diagram of the structure of the structural seam template provided by the embodiment of the utility model;

[0033] Figure 2 A schematic diagram of the structure of a skeleton provided in an embodiment of the utility model;

[0034] Figure 3 A cross-sectional view of a structural seam template provided by an embodiment of the utility model in a first direction;

[0035] Figure 4 A cross-sectional view of the structural seam template provided in the embodiment of the utility model in the second direction.

[0036] Icons: 100-structural joint formwork; 10-skeleton; 11-first support frame; 111-first horizontal bar; 112-first vertical bar; 12-second support frame; 121-second horizontal bar; 122-second vertical bar; 13-inner support bar; 21-first inner formwork; 22-second inner formwork; 23-third inner formwork; 24-fourth inner formwork; 25-top formwork; 26-bottom formwork; 31-first outer formwork; 32-second outer formwork; 41-first concrete pouring space; 42-second concrete pouring space; 51-connector; 52-lifting ring; 61-screw; 62-first nut; 63-second nut; 64-first buckle; 65-second buckle; 66-first fixing pipe; 67-second fixing pipe; 68-pipe sleeve; 71-first fixing plate; 72-second fixing plate; 200-concrete; 300-structural joint. DETAILED DESCRIPTION

[0037] In order to make the purpose, technical scheme and advantages of the embodiments of the utility model clearer, the technical scheme in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Generally, the components of the embodiments of the utility model described and shown in the drawings here can be arranged and designed in various different configurations.

[0038] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the present invention to be protected, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0039] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0040] In the description of the present utility model, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate the orientation or position relationship based on the orientation or position relationship shown in the accompanying drawings, or the orientation or position relationship in which the utility model product is usually placed when in use, which is only for the convenience of describing the utility model and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0041] In addition, the terms "horizontal", "vertical" and the like do not mean that the components are required to be absolutely horizontal or suspended, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0042] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0043] As described in the background technology, to ensure the formation of structural joints, foam boards and extruded polystyrene boards are usually used for caulking in the prior art, or a segmented construction method is used. However, the inventors have found that the method of using foam boards and extruded polystyrene boards for caulking has the following disadvantages: the purchase cost of using all foam boards and extruded polystyrene boards for caulking is high; when pouring concrete into the mold, the foam boards and extruded polystyrene boards are easily damaged by impact, causing the boards to be sandwiched in the cast-in-place concrete, reducing the strength of the main structure concrete; workers are prone to uneven material feeding on both sides during the concrete pouring process, resulting in a large difference in the deadweight of the concrete on both sides, and the boards are squeezed, resulting in the concrete structure on the other side without a protective layer, etc. The segmented construction method has the following disadvantages: the use of segmented flow construction affects the construction period; the risk of falling from a height is greater when constructing near the edge; if edge protection is used, the cost will increase, etc.

[0044] That is, the method of using foam boards and extruded polystyrene boards for filling or segmented construction has technical problems such as high production cost, poor quality, impact on construction period and low safety.

[0045] Based on this, please refer to Figure 1-Figure 4 The embodiment of the utility model provides a structural seam template 100, which can effectively improve the above-mentioned technical problems, that is, it can reduce production costs, save construction time, improve the quality of structural seam forming, and has high construction safety.

[0046] It should be noted that the first direction in the following content is Figure 1-Figure 4 The X direction is shown in Figure 1-Figure 4 The Y direction is shown in the figure, and the third direction is Figure 1-Figure 4 The structural seam template 100 will be described in detail below.

[0047] Please refer to Figure 1 , Figure 1 The structural diagram of the structural seam template 100 provided in this embodiment is combined with Figure 1The structural joint template 100 includes a frame 10, a first inner template 21, a second inner template 22, a first outer template 31 and a second outer template 32. The first inner template 21 is arranged on one side of the frame 10, and the second inner template 22 is relatively arranged on the other side of the frame 10. The first outer template 31 is arranged at intervals on the side of the first inner template 21 away from the frame 10 to form a first concrete pouring space 41, and the second outer template 32 is arranged at intervals on the side of the second inner template 22 away from the frame 10 to form a second concrete pouring space 42. By pouring concrete 200 into the first concrete pouring space 41 and the second concrete pouring space 42, after the pouring is completed, the structural joint template 100 can be taken out by relying on the gap generated by the shrinkage of the concrete 200 itself, so that the gap between the two concretes 200 is the formed structural joint 300.

[0048] That is to say, the skeleton 10 can play a supporting role in the process of pouring concrete, and cooperate with the first inner formwork 21 and the second inner formwork 22 to form a filling structure. Compared with the existing method of using foam boards and extruded polystyrene boards for filling, it can save material costs; at the same time, through the cooperation of the first inner formwork 21 and the first outer formwork 31, and the cooperation of the second inner formwork 22 and the second outer formwork 32, the structural joint 300 formed by pouring concrete has good appearance molding quality and avoids the quality risk of slag inclusion in the main structure; and the use of the structural joint formwork 100 can be carried out in parallel on the same floor. Compared with the segmented construction method, it can save implementation time. At the same time, there is no edge operation, which avoids the risk of falling from height and improves construction safety.

[0049] It should be noted that, in order to better separate the structural joint formwork 100 from the cast concrete 200 , an isolation agent may be applied to the first inner formwork 21 , the second inner formwork 22 , the first outer formwork 31 and the second outer formwork 32 .

[0050] Specifically, please refer to Figure 2 , Figure 2 The schematic diagram of the structure of the skeleton 10 provided in this embodiment, combined with Figure 1 and Figure 2The skeleton 10 includes a first support frame 11, a second support frame 12 and a plurality of inner support bars 13. The first support frame 11 and the second support frame 12 are arranged at intervals, and the plurality of inner support bars 13 are arranged at intervals. Each inner support bar 13 is connected to the first support frame 11 and the second support frame 12 at the same time. The first inner template 21 is arranged on the side of the first support frame 11 away from the second support frame 12, and the second inner template 22 is arranged on the side of the second support frame 12 away from the first support frame 11. In other words, the first inner template 21 is fixed on the outer side of the first support frame 11, and the second inner template 22 is fixed on the outer side of the second support frame 12, and then the first support frame 11 and the second support frame 12 are firmly connected by the plurality of inner support bars 13, thereby forming a high-strength caulking structure.

[0051] Further, in the present embodiment, the first support frame 11 includes a plurality of first horizontal bars 111 and a plurality of first vertical bars 112, the second support frame 12 includes a plurality of second horizontal bars 121 and a plurality of second vertical bars 122, the plurality of first horizontal bars 111 and the plurality of second horizontal bars 121 are arranged at intervals and correspond one to one along the first direction, the plurality of first vertical bars 112 and the plurality of second vertical bars 122 are arranged at intervals and correspond one to one along the first direction; the plurality of first vertical bars 112 and the plurality of second vertical bars 122 are arranged at intervals along the second direction, the plurality of first horizontal bars 111 and the plurality of second horizontal bars 121 are arranged at intervals along the third direction, one end of each inner support bar 13 is connected to the first horizontal bar 111 and the first vertical bar 112 at the same time, and the other end is connected to the second horizontal bar 121 and the second vertical bar 122 at the same time; wherein the first direction, the second direction and the third direction are perpendicular to each other.

[0052] like Figure 2 As shown, in this embodiment, through the mutual connection and cooperation of multiple first vertical bars 112, multiple second vertical bars 122, multiple first horizontal bars 111, multiple second horizontal bars 121 and multiple inner support bars 13, a structure in which multiple small rectangular brackets are arranged in a matrix can be formed. Compared with filling the seams entirely with foam boards or extruded polystyrene boards, production costs are saved, and the internal structures of the skeleton 10 interact with each other, have higher strength, and can form a structural seam 300 of better quality.

[0053] In order to better connect the first inner template 21, the second inner template 22 and the frame 10, please refer to Figure 3 and Figure 4 , Figure 3 A cross-sectional view of the structural seam template 100 provided in this embodiment in a first direction, Figure 4 The cross-sectional view of the structural seam template 100 provided in this embodiment in the second direction, combined with Figure 3 and Figure 4The structural seam template 100 also includes a connecting piece 51 , and the first inner template 21 and the second inner template 22 are both connected to the frame 10 via the connecting piece 51 .

[0054] It should be noted that, in the present embodiment, the connecting member 51 is a screw, and the first inner template 21, the second inner template 22 can be directly connected to the skeleton 10 by hitting the screw with a hammer; in other embodiments, the connecting member 51 can also be a connecting structure such as a bolt; of course, the first inner template 21, the second inner template 22 can also be bonded to the skeleton 10 by gluing.

[0055] Furthermore, in order to prevent materials from falling into the skeleton 10 during the pouring of concrete, and also to further improve the quality of structural seam forming, the structural seam formwork 100 also includes a third inner formwork 23, a fourth inner formwork 24, a top formwork 25 and a bottom formwork 26. The first inner formwork 21, the third inner formwork 23, the second inner formwork 22 and the fourth inner formwork 24 are sequentially arranged around the skeleton 10; the top formwork 25 is arranged on the top surface of the skeleton 10, and the bottom formwork 26 is arranged on the bottom surface of the skeleton 10.

[0056] It is easy to understand that in this embodiment, the first inner template 21, the second inner template 22, the third inner template 23, the fourth inner template 24, the top template 25 and the bottom template 26 are all connected to the frame 10 by screws.

[0057] Please combine Figure 1 and Figure 3 During the installation of the structural seam formwork 100 and the pouring of the concrete 200, in order to facilitate the staff to check the elevation, in this embodiment, the top height of the skeleton 10 is higher than the top surfaces of the first outer formwork 31 and the second outer formwork 32; the top height of the first inner formwork 21 is higher than the top surfaces of the first outer formwork 31 and the second outer formwork 32; the top height of the second inner formwork 22 is higher than the top surfaces of the first outer formwork 31 and the second outer formwork 32.

[0058] After the first inner template 21, the second inner template 22, the third inner template 23, the fourth inner template 24, the top template 25 and the bottom template 26 are connected to the frame 10 to form a caulking structure, in order to facilitate transportation and installation, please continue to combine Figure 1 and Figure 3 In this embodiment, the structural seam template 100 further includes a lifting ring 52, which is simultaneously connected to the first inner template 21, the second inner template 22 and the frame 10. A tower crane or other equipment may be used to connect to the lifting ring 52 to perform auxiliary lifting and transportation operations.

[0059] Please continue to combine Figure 1In order to facilitate the overall fixation of the skeleton 10, the first inner template 21, the second inner template 22, the first outer template 31 and the second outer template 32, and facilitate the subsequent concrete pouring, in this embodiment, the structural joint template 100 also includes a screw 61, a first nut 62, a second nut 63, a first buckle 64, a second buckle 65, a first fixing tube 66 and a second fixing tube 67, and the screw 61 is used to be sequentially penetrated through the first outer template 31, the first inner template 21, the skeleton 10, the second inner template 22 and the second outer template 32; that is, the two ends of the screw 61 extend from the first outer template 31 and the second outer template 32 respectively.

[0060] The first clip 64 is sleeved on the screw rod 61 and is located on the side of the first outer template 31 away from the first inner template 21. The first fixing tube 66 is arranged between the first clip 64 and the first outer template 31. The first nut 62 is sleeved on the screw rod 61 and is located on the side of the first clip 64 away from the first fixing tube 66, so as to fix the first clip 64 and the first fixing tube 66 to the first outer template 31; similarly, the second clip 65 is sleeved on the screw rod 61 and is located on the side of the second outer template 32 away from the second inner template 22. The second fixing tube 67 is arranged between the second clip 65 and the second outer template 32. The second nut 63 is sleeved on the screw rod 61 and is located on the side of the second clip 65 away from the second fixing tube 67, so as to fix the second clip 65 and the second fixing tube 67 to the second outer template 32.

[0061] It should be noted that, combined with Figure 1 and Figure 2 The first fixing tube 66 and the second fixing tube 67 both extend along the second direction. Through the cooperation between the first buckle 64 and the first nut 62, and the cooperation between the second buckle 65 and the second nut 63, the first fixing tube 66 can better fix the first outer template 31, and the second fixing tube 67 can better fix the second outer template 32.

[0062] Furthermore, in the process of actually installing the structural seam template 100, since the surfaces of the first outer template 31 and the second outer template 32 are relatively smooth, in order to improve the stability of the first fixing tube 66 and the second fixing tube 67, the structural seam template 100 further includes a first fixing plate 71 and a second fixing plate 72, wherein the first fixing plate 71 is arranged between the first outer template 31 and the first fixing tube 66, and the second fixing plate 72 is arranged between the second outer template 32 and the second fixing tube 67; the screw 61 is used to sequentially penetrate the first fixing plate 71, the first outer template 31, the first inner template 21, the frame 10, the second inner template 22, the second outer template 32 and the second fixing plate 72. Through this arrangement, it is also possible to avoid damage to the first outer template 31 and the second outer template 32 by the first buckle 64, the second buckle 65, the first fixing tube 66 and the second fixing tube 67 during the installation process.

[0063] In addition, in order to facilitate installation and protect the screw 61, in this embodiment, the structural seam template 100 also includes a pipe sleeve 68, which is sleeved on the screw 61 and is used to be sequentially passed through the first outer template 31, the first inner template 21, the frame 10, the second inner template 22 and the second outer template 32.

[0064] It should be noted that, in this embodiment, the frame 10, the first inner template 21, the second inner template 22, the third inner template 23, the fourth inner template 24, the top template 25, the bottom template 26, the first outer template 31, the second outer template 32, the first fixing plate 71 and the second fixing plate 72 are all made of wood beams, which can be easily assembled to form the structural joint template 100 and disassembled after pouring. Of course, in other embodiments, the above structure can also be made of other materials such as plastic.

[0065] Through the above description, this embodiment also provides a method for preparing a structural seam template 100, and the preparation method specifically includes:

[0066] Step S10: Use wooden beams to make a skeleton 10, the height of the skeleton 10 is: the height of the concrete 200 + 200mm, the width of the skeleton 10 is: the width of the structural joint 300 - 15mm*2 (15mm is the thickness of the first inner formwork 21 and the second inner formwork 22); the length of the skeleton 10 is: the length of the structural joint 300 - 15mm*2 (15mm is the thickness of the third inner formwork 23 and the fourth inner formwork 24); the spacing between the multiple first vertical bars 112, the second vertical bars 122, the first horizontal bars 111 and the second horizontal bars 121 is 250mm, and the spacing between the multiple inner support bars 13 is 500mm.

[0067] Step S20: Connect the first inner template 21, the second inner template 22, the third inner template 23, the fourth inner template 24, the top template 25 and the bottom template 26 to the four sides, the top surface and the bottom surface of the frame 10 by screws to form a caulking structure.

[0068] Step S30 : applying a release agent on the surfaces of the first inner template 21 , the second inner template 22 , the third inner template 23 , the fourth inner template 24 , the top template 25 and the bottom template 26 .

[0069] Step S40: Connect the lifting ring 52 to the first inner formwork 21, the second inner formwork 22 and the frame 10, and connect the lifting ring 52 to the tower crane to transport the caulking structure to a designated location.

[0070] Step S50: Assemble the first fixing plate 71 and the first outer formwork 31 , and separate them from the first inner formwork 21 to form a first concrete pouring space 41 ; assemble the second fixing plate 72 and the second outer formwork 32 , and separate them from the second inner formwork 22 to form a second concrete pouring space 42 .

[0071] Step S60: Drill holes in the first fixed plate 71, the first outer template 31, the first inner template 21, the second inner template 22, the second outer template 32 and the second fixed plate 72, and pass the pipe sleeve 68 through the drilled holes in sequence through the first fixed plate 71, the first outer template 31, the first inner template 21, the frame 10, the second inner template 22, the second outer template 32 and the second fixed plate 72.

[0072] Step S70: insert the screw 61 into the sleeve 68, and then install the first nut 62, the second nut 63, the first clip 64 and the second clip 65 with the screw 61, so that the first fixing tube 66 and the second fixing tube 67 are fixed on the first fixing plate 71 and the second fixing plate 72 respectively.

[0073] Step S80: pouring concrete 200 into the first concrete pouring space 41 and the second concrete pouring space 42 , and after the pouring is completed, taking out the structural joint template 100 by relying on the gap created by the shrinkage of the concrete 200 itself.

[0074] It should be noted that the assembly and drilling operations of the skeleton 10 only need to be performed once and do not need to be repeated subsequently, which can improve work efficiency; in addition, after taking out the structural seam template 100 each time, it is necessary to clean the surfaces of the first inner template 21, the second inner template 22, the third inner template 23, the fourth inner template 24, the top template 25, the bottom template 26, the first outer template 31 and the second outer template 32 in time, and apply an isolation agent before use.

[0075] In summary, the embodiment of the utility model provides a structural seam template 100, which includes a skeleton 10, a first inner template 21, a second inner template 22, a first outer template 31 and a second outer template 32. The first inner template 21 is arranged on one side of the skeleton 10, and the second inner template 22 is relatively arranged on the other side of the skeleton 10. The first outer template 31 is arranged at intervals on the side of the first inner template 21 away from the skeleton 10 to form a first concrete pouring space 41, and the second outer template 32 is arranged at intervals on the side of the second inner template 22 away from the skeleton 10 to form a second concrete pouring space 42. By pouring concrete 200 into the first concrete pouring space 41 and the second concrete pouring space 42, after the pouring is completed, the structural seam template 100 can be taken out by relying on the gap generated by the shrinkage of the concrete 200 itself, so that the gap between the two concretes 200 is the formed structural seam 300.

[0076] That is to say, the skeleton 10 can play a supporting role in the process of pouring concrete, and cooperate with the first inner formwork 21 and the second inner formwork 22 to form a filling structure. Compared with the existing method of using foam boards and extruded polystyrene boards for filling, it can save material costs; at the same time, through the cooperation of the first inner formwork 21 and the first outer formwork 31, and the cooperation of the second inner formwork 22 and the second outer formwork 32, the structural joint 300 formed by pouring concrete has good appearance molding quality and avoids the quality risk of slag inclusion in the main structure; and the use of the structural joint formwork 100 can be carried out in parallel on the same floor. Compared with the segmented construction method, it can save implementation time. At the same time, there is no edge operation, which avoids the risk of falling from height and improves construction safety.

[0077] Therefore, the structural joint template 100 has the advantages of reducing production costs, saving construction period, improving the molding quality of the structural joint 300, and having high construction safety.

[0078] The above description is only a specific embodiment of the utility model and is not intended to limit the utility model. For those skilled in the art, the utility model may have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A structural seam template, characterized in that: include: Skeleton (10); A first inner template (21), the first inner template (21) being arranged on one side of the frame (10); A second inner template (22), the second inner template (22) being arranged relatively on the other side of the frame (10); a first outer formwork (31), the first outer formwork (31) being spaced apart from a side of the first inner formwork (21) away from the frame (10) to form a first concrete pouring space (41); and A second outer formwork (32), the second outer formwork (32) being spaced apart from a side of the second inner formwork (22) away from the frame (10) to form a second concrete pouring space (42); Wherein, the top height of the skeleton (10) is higher than the top surfaces of the first outer template (31) and the second outer template (32); the top height of the first inner template (21) is higher than the top surfaces of the first outer template (31) and the second outer template (32); the top height of the second inner template (22) is higher than the top surfaces of the first outer template (31) and the second outer template (32).

2. The structural seam template according to claim 1, characterized in that: The skeleton (10) comprises a first support frame (11), a second support frame (12) and a plurality of inner support bars (13); the first support frame (11) and the second support frame (12) are arranged at intervals, the plurality of inner support bars (13) are arranged at intervals, and each of the inner support bars (13) is connected to the first support frame (11) and the second support frame (12) at the same time; The first inner template (21) is arranged on a side of the first support frame (11) away from the second support frame (12), and the second inner template (22) is arranged on a side of the second support frame (12) away from the first support frame (11).

3. The structural seam template according to claim 2, characterized in that: The first support frame (11) comprises a plurality of first horizontal bars (111) and a plurality of first vertical bars (112); the second support frame (12) comprises a plurality of second horizontal bars (121) and a plurality of second vertical bars (122); the plurality of first horizontal bars (111) and the plurality of second horizontal bars (121) are arranged at intervals along a first direction and correspond one to one; the plurality of first vertical bars (112) and the plurality of second vertical bars (122) are arranged at intervals along the first direction and correspond one to one; The plurality of first vertical bars (112) and the plurality of second vertical bars (122) are arranged at intervals along the second direction, the plurality of first horizontal bars (111) and the plurality of second horizontal bars (121) are arranged at intervals along the third direction, one end of each of the inner support bars (13) is connected to both the first horizontal bar (111) and the first vertical bar (112), and the other end is connected to both the second horizontal bar (121) and the second vertical bar (122); The first direction, the second direction and the third direction are perpendicular to each other.

4. The structural seam template according to claim 1, characterized in that: The structural seam template (100) further comprises a connecting piece (51), and the first inner template (21) and the second inner template (22) are both connected to the frame (10) via the connecting piece (51).

5. The structural seam template according to claim 1, characterized in that: The structural seam formwork (100) further comprises a lifting ring (52), wherein the lifting ring (52) is simultaneously connected to the first inner formwork (21), the second inner formwork (22) and the frame (10).

6. The structural seam template according to claim 1, characterized in that: The structural seam template (100) further comprises a third inner template (23), a fourth inner template (24), a top template (25) and a bottom template (26); the first inner template (21), the third inner template (23), the second inner template (22) and the fourth inner template (24) are sequentially arranged around the frame (10); the top template (25) is arranged on the top surface of the frame (10), and the bottom template (26) is arranged on the bottom surface of the frame (10).

7. The structural seam formwork according to claim 1, characterized in that: The structural seam template (100) further comprises a screw (61), a first nut (62), a second nut (63), a first buckle (64), a second buckle (65), a first fixing tube (66) and a second fixing tube (67), wherein the screw (61) is used to be sequentially inserted into the first outer template (31), the first inner template (21), the frame (10), the second inner template (22) and the second outer template (32); The first buckle (64) is sleeved on the screw rod (61) and is located on a side of the first outer template (31) away from the first inner template (21); the first fixing tube (66) is arranged between the first buckle (64) and the first outer template (31); the first nut (62) is sleeved on the screw rod (61) and is located on a side of the first buckle (64) away from the first fixing tube (66), so as to fix the first buckle (64) and the first fixing tube (66) to the first outer template (31); The second buckle (65) is sleeved on the screw rod (61) and is located on a side of the second outer template (32) away from the second inner template (22); the second fixing tube (67) is arranged between the second buckle (65) and the second outer template (32); the second nut (63) is sleeved on the screw rod (61) and is located on a side of the second buckle (65) away from the second fixing tube (67) for fixing the second buckle (65) and the second fixing tube (67) to the second outer template (32).

8. The structural seam formwork according to claim 7, characterized in that: The structural seam template (100) further comprises a first fixing plate (71) and a second fixing plate (72), wherein the first fixing plate (71) is arranged between the first outer template (31) and the first fixing tube (66), and the second fixing plate (72) is arranged between the second outer template (32) and the second fixing tube (67); the screw rod (61) is used to sequentially penetrate the first fixing plate (71), the first outer template (31), the first inner template (21), the frame (10), the second inner template (22), the second outer template (32) and the second fixing plate (72).

9. The structural seam formwork according to claim 7, characterized in that: The structural seam template (100) further comprises a pipe sleeve (68), wherein the pipe sleeve (68) is sleeved on the screw rod (61) and is used to be sequentially passed through the first outer template (31), the first inner template (21), the frame (10), the second inner template (22) and the second outer template (32).