Embedded pipe for concrete conveying of basement constructional column
By pre-embedding pipe sections and chute sections in the basement roof slab and fixing them with pipe clamps to form a concrete conveying chute, the problem of low concrete conveying efficiency in the basement was solved, achieving fast and stable concrete conveying and high-quality pouring results.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-04-28
- Publication Date
- 2026-04-07
AI Technical Summary
In the construction of the secondary structure of the basement, the low efficiency of concrete delivery leads to high labor costs, reduced concrete strength, and difficulty in ensuring the quality of pouring.
A pre-embedded pipeline system is adopted, including pipe opening sections and chute sections. These sections are fixed to the structural columns with pipe clamps to form a concrete conveying chute. The use of pipelines to form a concrete conveying chute shortens the conveying time and improves stability.
It improves concrete delivery efficiency, reduces labor costs, ensures concrete quality, reduces construction difficulty, and achieves fast and stable concrete delivery.
Smart Images

Figure CN224092991U_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The utility model belongs to the technical field of building construction, more particularly to a pre -buried pipe for basement structural column concrete delivery. BACKGROUND
[0002] During the construction of the basement secondary structure to the structural column pouring, the concrete needs to be used in many construction sites, which requires a large amount of concrete to be delivered to different places underground. In underground construction projects, the basement area is large, and the number of entrances is limited and fixed. If a bucket truck is used to transport concrete, the transportation capacity is small, and a large number of manual labor is required, which greatly increases the labor cost. At the same time, the waiting time is long, and the long waiting time of the concrete will lead to a decrease in concrete strength, slump and fluidity, increase the difficulty of on-site construction, and cannot guarantee the pouring quality. SUMMARY
[0003] To solve the problems in the prior art, the utility model provides a pre -buried pipe for basement structural column concrete delivery.
[0004] The utility model solves its technical scheme as follows: a pre -buried pipe for basement structural column concrete delivery, comprising: a pipe section, hollow inside; a chute section, hollow inside, fixedly installed below the pipe section and configured with the pipe section to form a channel for the flow of concrete, the bottom contour line of the pipe section falls on the top contour line of the chute section; pipe clamp, set on the outside of the chute section.
[0005] Further, the chute section is a hollow conical pipe with a gradually decreasing diameter from top to bottom.
[0006] Further, the pipe clamp is tangent to the outer wall of the chute section.
[0007] Further, there are at least two tangent points between the pipe clamp and the outer wall of the chute section.
[0008] Further, a plurality of pipe clamps are equally distributed outside the chute section.
[0009] Further, the pipe clamp is a U-shaped frame with a right angle.
[0010] Further, the pipe section is fixedly installed on the basement roof; the two ends of the pipe clamp are fixedly installed on the primary structural column.
[0011] Further, the top connection of the chute section is designed to be bent upward to form a buckle, the buckle is designed as a petal, and the pipe section is designed as a petal-shaped butt joint block.
[0012] Usage: before use, the pre-embedded pipe is installed near the primary structure column, and the pipe mouth section is embedded when the concrete of the basement roof is poured, the size meeting the design requirements is selected according to the actual needs, the pipe section is fixed below the pipe mouth section and connected to the basement during the secondary structure construction, and the pipe section is surrounded and fixed on the primary structure column by the pipe clamp combined with the screw, so that the pipe section is stable; the exposed pipe mouth section can be packaged with concrete and painted with warning color to avoid being damaged, and the overall structure is stable. After the overall installation of the pre-embedded pipe is completed, the pipe mouth section and the pipe section form a concrete conveying chute from the ground to the ground. When the concrete is needed during the secondary structure construction, the pipe joint is bent and connected to the pipe mouth section, and the concrete can be quickly conveyed from the concrete conveying chute to the basement, so that the concrete conveying time is shortened, the concrete pouring quality can be improved, and the labor required is less.
[0013] Compared with the prior art, the beneficial effects of the utility model are that: the pipeline forms a concrete conveying chute, the concrete is quickly conveyed to the basement, the concrete conveying time is shortened, and the labor cost is also reduced; the pipe mouth section is embedded in the basement roof, the pipe section is fixed on the structure column by the pipe clamp and the screw, the pipe section is stable, can be repeatedly used, and can be quickly conveyed, the problem that the required amount is large and the single transportation amount of the bucket car is small is solved, the concrete conveying time is obviously shortened, the construction is fast and simple, the concrete on-site waiting time is reduced, the concrete pouring quality is improved, and the construction difficulty is reduced. The top connection of the pipe section is designed to be upwardly bent and petal-shaped notched, is hung and connected first and then fastened by bolts, is convenient to install, and is stable in structure. BRIEF DESCRIPTION OF DRAWINGS
[0014] Figure 1 is a structural schematic view of the utility model;
[0015] Figure 2 is an installation schematic view of the utility model;
[0016] Figure 3 is a profile view of the butt joint equal-diameter setting in embodiment 2;
[0017] Figure 4 is a profile view of the butt joint flared setting in embodiment 2;
[0018] Figure 5 is a pipe mouth section structure schematic view of the hanging type fixation.
[0019] In the drawing:
[0020] 1, pipe mouth section, 2, pipe section, 3, pipe clamp, 4, primary structure column, 5, garage roof, 101, butt joint block, 201, buckle plate. DETAILED DESCRIPTION
[0021] In order to facilitate the understanding of the present application, the present application will be described in more detail below in conjunction with the drawings and specific embodiments. However, the present application can be implemented in many different forms, and is not limited to the embodiments described in the specification. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosed content of the present application more thorough and comprehensive.
[0022] Embodiment 1: in combination Figures 1-2 It is understood that a pre-embedded pipe for basement construction column concrete conveying includes: a pipe mouth section 1, which is internally hollow; a chute pipe section 2, which is internally hollow, is fixedly installed below the pipe mouth section 1 and is structured with the pipe mouth section 1 to form a channel for concrete flow, the bottom inner contour line of the pipe mouth section 1 falls on the top inner contour line of the chute pipe section 2; a pipe clamp 3 is arranged outside the chute pipe section 2.
[0023] Usage instruction: installation before use, the pre-embedded pipe is installed close to the primary structure column 4, when the basement roof concrete is poured, the pipe mouth section 1 is pre-embedded, and the size meeting the design requirements is selected according to the actual needs. For example, the pipe mouth section 1 is pre-embedded on the garage roof 5. In the secondary structure construction, the chute pipe section 2 is fixedly connected below the pipe mouth section 1 to the basement, and the pipe clamp 3 is used in combination with the screw nail to surround and fix it on the primary structure column 4, so that the chute pipe section 2 is stable; the exposed pipe mouth section 1 can be wrapped with concrete and painted with warning color to avoid being damaged, and the overall structure is stable. After the overall installation of the pre-embedded pipe is completed, the pipe mouth section 1 and the chute pipe section 2 form a concrete conveying chute from the ground to the ground. When concrete is needed in the secondary structure construction, a bend joint is used to extend to the pipe mouth section 1, and concrete can be quickly conveyed from the concrete conveying chute to the basement, which shortens the concrete conveying time and improves the concrete pouring quality; less labor is required.
[0024] After the construction is completed, the chute pipe section 2 is cut off, and the pipe mouth section 1 is backfilled.
[0025] Embodiment 2: on the basis of the structure of embodiment 1, in this embodiment, the pipe mouth section 1 is a hollow circular pipe, which can be made of PVC material; the chute pipe section 2 is a hollow conical pipe with the pipe diameter gradually decreasing from top to bottom; and the maximum pipe diameter of the chute pipe section 2 is not less than the bottom pipe diameter of the pipe mouth section 1, so that there is no material blocking step, ensuring smooth concrete conveying.
[0026] For the maximum pipe diameter of the chute pipe section 2 being equal to the bottom pipe diameter of the pipe mouth section 1, the bottom of the pipe mouth section 1 and the top of the chute pipe section 2 are respectively provided with flanges corresponding in size and bolt hole position, and are fastened and connected by fastening bolts, the pipe mouth section 1 and the chute pipe section 2 are seamlessly and smoothly connected, and refer to Figure 3 It is understood.
[0027] For the maximum pipe diameter of the chute section 2 is greater than the bottom pipe diameter of the pipe section 1, the bottom of the pipe section 1 and the top of the chute section 2 are respectively provided with flanges, and are connected by expanding and connecting through fastening bolts, and the inner contour line of the bottom of the pipe section 1 falls on the inner contour line of the top of the chute section 2, as shown in Figure 4 It is understood that the top connecting part of the chute section 2 is designed to be bent upwards to form a buckling plate 201, and the flanges on the pipe section 1 are designed to be petal-shaped butt blocks 101, and gaps are formed between adjacent butt blocks 101, as shown in Figure 5 The buckling plate 201 is also designed to be petal-shaped, and during installation, the buckling plate 201 is first embedded into the gaps between the butt blocks 101, and then is rotated to be hung on the butt blocks 101, and then is fastened by using fastening bolts, so that the installation is more convenient and the structure is stable. The present application mainly forms a concrete chute, and the expanding and connecting butt blocks are not contacted by concrete, that is, the chute section 2 is not a force-bearing part.
[0028] In one embodiment, the pipe clamp 3 is tangent to the outer wall of the chute section 2, and there are at least two tangent points. The pipe clamp 3 plays a role in fixing the chute section 2.
[0029] In one embodiment, a plurality of pipe clamps 3 are equidistantly distributed on the outer wall of the chute section 2. Multiple fixing points make the chute section 2 stable and safe to use.
[0030] In one embodiment, the pipe clamp 3 is a U-shaped frame with a right angle. The chute section 2 is formed to be outwardly expanded and protected, and the structure is more durable.
[0031] In some embodiments, the pipe section 1 and the chute section 2 can have a circular or square cross section, and can be variable-diameter or constant-diameter. The pipe section 1 can also be a galvanized pipe. The pipe clamp 3 can be a steel wire rope, which binds the chute section 2 and is fixed at the end of the structural column 4.
[0032] The present application uses a pipeline to form a concrete conveying chute, so that the concrete can be quickly conveyed to the basement, and the concrete conveying time is shortened, and the labor cost is also reduced. The pipe section 1 is pre-buried on the top plate of the basement, and the chute section 2 is fixed on the structural column by using pipe clamps and screws, so that it is stable and can be repeatedly used for quick conveying, solving the problem of large demand and small single transportation capacity of the bucket car, obviously shortening the concrete conveying time, and facilitating the construction, reducing the concrete waiting time on site, improving the concrete pouring quality, and reducing the construction difficulty.
[0033] The technical features of the above embodiments can be combined in any way. For the sake of brevity, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
Claims
1. An embedded pipe for conveying concrete for basement structural columns, characterized in that, include: The pipe section (1) is hollow inside; The chute section (2) is hollow inside and is fixedly installed below the pipe opening section (1) to form a channel for concrete flow with the pipe opening section (1). The bottom inner contour line of the pipe opening section (1) falls on the top inner contour line of the chute section (2). Pipe clamp (3) is installed on the outside of the chute section (2).
2. The embedded pipe for conveying concrete for basement structural columns according to claim 1, characterized in that, The chute section (2) is a hollow conical tube with a diameter that decreases from top to bottom.
3. The embedded pipe for conveying concrete for basement structural columns according to claim 2, characterized in that, The pipe clamp (3) is tangent to the outer wall of the chute section (2).
4. The embedded pipe for conveying concrete for basement structural columns according to claim 3, characterized in that, There are at least two tangent points between the pipe clamp (3) and the outer wall of the chute section (2).
5. The embedded pipe for conveying concrete for basement structural columns according to claim 1, characterized in that, Multiple pipe clamps (3) are equidistantly distributed outside the chute section (2).
6. The embedded pipe for conveying concrete for basement structural columns according to claim 1, characterized in that, The pipe clamp (3) is a U-shaped frame with right angles.
7. The embedded pipe for conveying concrete for basement structural columns according to any one of claims 1-6, characterized in that, The pipe section (1) is fixedly installed on the basement roof slab; the two ends of the pipe clamp (3) are respectively fixed on the primary structural column.
8. The embedded pipe for conveying concrete for basement structural columns according to claim 7, characterized in that, The top connection of the chute section (2) is bent upward to form a buckle plate (201), the buckle plate (201) is designed with petals, and the pipe opening section (1) is designed with a petal-shaped docking block (101).