Compaction method
By establishing linear approximations for compaction levels using different heavy machinery, the method ensures efficient and accurate compaction of embankments, even with multiple machines, reducing completion time.
Patent Information
- Application Number
- JP2021168176
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2021-10-13
- Publication Date
- 2024-11-28
- Estimated Expiration
- 2041-10-13
AI Technical Summary
Existing compaction methods do not effectively manage compaction using multiple types of heavy machinery, leading to inefficiencies and incomplete compaction in embankment construction.
A method that determines compaction levels for different types of heavy machinery by establishing linear approximations between the number of compactions and compaction degrees or surface settlement, allowing for the use of multiple machines to achieve appropriate compaction levels.
Enables efficient compaction of embankment areas using multiple types of heavy machinery, ensuring accurate compaction levels and reducing the time required for completion.
Smart Images

Figure 0007591482000001 
Figure 0007591482000002 
Figure 0007591482000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a compaction method. [Background technology]
[0002] Conventionally, when compacting embankment materials, a method of managing the number of compaction times using a Global Navigation Satellite System (GNSS) to ensure that the number of compaction times determined through test construction is reached over the entire area of the embankment construction range has been known (see, for example, Non-Patent Document 1, etc.).
[0003] In this management method, a distribution map of compaction times is displayed on the monitor of a PC (Personal Computer) installed on the machine (heavy machinery) used in the test construction. Then, the worker operates the heavy machinery while checking the displayed distribution map of compaction times, and compacts until all of the management blocks in the construction area are colored in a color that indicates that they have been compacted the specified number of times. [Prior art documents] [Non-patent literature]
[0004] [Non-Patent Document 1] "Guidelines for Compaction Management of Embankments Using TS and GNSS" Ministry of Land, Infrastructure, Transport and Tourism, March 2020 Summary of the Invention [Problem to be solved by the invention]
[0005] However, the technique of the above-mentioned Non-Patent Document 1 does not assume the use of multiple types of machines (heavy machinery) when compacting one embankment construction area.
[0006] Therefore, an object of the present invention is to provide a compaction method that can use multiple types of heavy machinery to compact the compacted area to an appropriate state. [Means for solving the problem]
[0007] A first compaction method according to the present invention includes determining a first linear approximation between the number of compaction operations and the degree of compaction by a first heavy machine in a test area having the same soil type as a predetermined compaction area, and determining a second linear approximation between the number of compaction operations and the degree of compaction by a second heavy machine of a different type from the first heavy machine in the test area; When the correlation coefficient of the first linear approximation and the correlation coefficient of the second linear approximation are within a reference range, it is determined that compaction using a plurality of types of heavy machines using the first heavy machine and the second heavy machine is possible, A first compaction level of the first heavy machine is determined according to a correlation coefficient of the first linear approximation, and a second compaction level of the second heavy machine is determined according to a correlation coefficient of the second linear approximation. Then, the first heavy machine and the second heavy machine compact the predetermined compaction area. This is the method.
[0008] A second compaction method according to the present invention includes determining a first linear approximation between the number of compaction operations of a first heavy machine and the amount of surface settlement due to compaction in a test area having the same soil type as a predetermined compaction area, and determining a second linear approximation between the number of compaction operations of a second heavy machine of a type different from the first heavy machine in the test area and the amount of surface settlement due to compaction, When the correlation coefficient of the first linear approximation and the correlation coefficient of the second linear approximation are within a reference range, it is determined that compaction using a plurality of types of heavy machines using the first heavy machine and the second heavy machine is possible, A first compaction level of the first heavy machine is determined according to a correlation coefficient of the first linear approximation, and a second compaction level of the second heavy machine is determined according to a correlation coefficient of the second linear approximation. Then, the first heavy machine and the second heavy machine compact the predetermined compaction area. This is the method. Effect of the Invention
[0009] According to the present invention, multiple types of heavy machinery can be used to compact the compacted area to an appropriate condition. [Brief description of the drawings]
[0010] [Figure 1] FIG. 1 is a diagram showing the configuration of a compaction management system. [Diagram 2] FIG. 2 is a diagram illustrating a hardware configuration of a management device and an on-board device for heavy machinery. [Diagram 3] FIG. 2 is a functional block diagram of a management device and an on-board device for heavy machinery. [Figure 4] FIG. 13 is a diagram showing a compaction position table. [Diagram 5]5(a) and 5(b) are diagrams showing a bulldozer A, FIGS. 5(c) and 5(d) are diagrams showing a vibrating roller A, and FIGS. 5(e) and 5(f) are diagrams showing a scraper A. [Figure 6] FIG. 13 is a diagram showing a compaction level table. [Figure 7] 7(a) to 7(c) are graphs showing an example of the results of the test construction. [Figure 8] 13 is a flowchart showing a process of a management device. [Figure 9] FIG. 1 shows an example screen. [Figure 10] FIG. 2 shows an example screen. [Figure 11] 1 is a graph showing an example of the results of a test application of rock mass material. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0011] The following provides a detailed description of a compaction management system according to one embodiment.
[0012] FIG. 1 shows a schematic configuration of a compaction management system 100 according to an embodiment. As shown in FIG. 1, the compaction management system 100 includes a management device 10 and a plurality of heavy machinery vehicle-mounted devices (in FIG. 1, a bulldozer vehicle-mounted device 70, a vibrating roller vehicle-mounted device 72, and a scraper vehicle-mounted device 74). The management device 10 and the heavy machinery vehicle-mounted devices 70, 72, and 74 are connected to each other via a network 80 such as the Internet. The management device 10 is, for example, an information processing device such as a PC (Personal Computer) used at a site where embankment construction is performed. The heavy machinery vehicle-mounted devices 70, 72, and 74 are devices mounted on heavy machinery (such as a bulldozer, a vibrating roller, and a scraper). A bulldozer is a construction machine mainly used for plowing soil and sand, filling soil, and leveling the ground, a vibrating roller is a construction machine used for compacting the embankment, and a scraper is a construction machine used for scraping and transporting soil.
[0013] FIG. 2 shows the hardware configuration of the management device 10 and the on-board device for heavy machinery. As shown in FIG. 2, the management device 10 includes a CPU (Central Processing Unit) 90, a ROM (Read Only Memory) 92, a RAM (Random Access Memory) 94, a storage unit (such as a HDD (Hard Disk Drive) or an SSD (Solid State Drive)) 96, a communication unit 97, a display unit 93, an input unit 95, and a drive for a portable storage medium 99. The display unit 93 is a liquid crystal display or the like, and the input unit 95 is a keyboard, a mouse, a touch panel, or the like. These components of the management device 10 are connected to a bus 98. In the management device 10, the CPU 90 executes a program stored in the ROM 92 or the storage unit 96, or a program read by the drive for a portable storage medium 99 from the portable storage medium 91, thereby realizing the functions of the components shown in FIG. 3. The functions of the units in Fig. 3 may be implemented by an integrated circuit such as an Application Specific Integrated Circuit (ASIC) or a Field Programmable Gate Array (FPGA), etc. Details of the units in Fig. 3 will be described later.
[0014] The bulldozer vehicle-mounted device 70 includes a CPU 190, a ROM 192, a RAM 194, a storage unit (HDD, SSD, etc.) 196, a communication unit 197, a GNSS device 189, a display unit 193, and an input unit 195. The GNSS device 189 is a device for detecting the position information (three-dimensional coordinates) of the bulldozer. These components of the bulldozer vehicle-mounted device 70 are connected to a bus 198. In the bulldozer vehicle-mounted device 70, the CPU 190 executes a program stored in the ROM 192 or the storage unit 196, thereby realizing the functions of the components shown in FIG. 3. The hardware configurations of the vibratory roller vehicle-mounted device 72 and the scraper vehicle-mounted device 74 are also similar to that of the bulldozer vehicle-mounted device 70.
[0015] FIG. 3 shows a functional block diagram of the management device 10, the vehicle-mounted device 70 for the bulldozer, the vehicle-mounted device 72 for the vibratory roller, and the vehicle-mounted device 74 for the scraper.
[0016] The management device 10 functions as an input information acquisition unit 20, a travel trajectory acquisition unit 22, a compaction level update unit 24, and a screen generation / output unit 26 by the CPU 90 executing a program.
[0017] The input information acquisition unit 20 acquires information input by the worker via the input unit 195 of any of the heavy machine on-board devices 70 , 72 , 74 .
[0018] The travel trajectory acquisition unit 22 acquires the position information (three-dimensional coordinates) of each heavy equipment on-board device 70, 72, 74, and acquires the travel trajectory of each heavy equipment based on the position information. The travel trajectory acquisition unit 22 uses the compaction position table 30 when acquiring the travel trajectory. Here, the compaction position table 30 is a table that stores information required to identify the location (range) where each heavy equipment performed compaction from the position information of each heavy equipment. Specifically, in the compaction position table 30, as shown in FIG. 4, information on offsets (front-back, left-right, height) and rolling width is managed in association with the type of heavy equipment.
[0019] FIG. 5(a) shows the bulldozer A as viewed from the rear, and FIG. 5(b) shows the bulldozer A as viewed from above. A GNSS device 189 is provided in the driver's seat of the bulldozer A. Here, the position of the GNSS device 189 does not coincide with the position of the caterpillar track of the bulldozer A. Therefore, in the compaction position table 30, the position error (offset) between the center position of the GNSS device 189 and the compaction location (the rear end of the caterpillar track) is managed, and information on the compaction range (the width of the caterpillar track) is also managed. In the case of the bulldozer A in FIG. 5(a) and FIG. 5(b), since there are two compaction locations, information on the two compaction ranges (width H1a) is stored in the compaction position table 30.
[0020] FIG. 5(c) shows the vibrating roller A as viewed from the side, and FIG. 5(d) shows the vibrating roller A as viewed from above. A GNSS device 189 is provided in the driver's seat of the vibrating roller A. In this case, too, the position of the GNSS device 189 does not coincide with the compaction location of the vibrating roller A (the ground contact position of the roller). Therefore, in the compaction position table 30, the position error (offset) between the GNSS device 189 and the center position of the ground contact position of the roller is managed, and information on the width of the roller (compaction range) is also managed. The GNSS device 189 may be provided in a place other than the bulldozer A or the driver's seat of the vibrating roller A. For example, in the case of the bulldozer A, the GNSS device 189 may be provided in the blade or the like.
[0021] FIG. 5(e) shows the scraper A as viewed from the side, and FIG. 5(f) shows the rear wheels and the GNSS device 189 as viewed from the rear. The GNSS device 189 is provided on a part of the scraper A. In this case, the position of the GNSS device 189 does not coincide with the compaction point of the scraper A (the ground contact position of the rear wheels). Therefore, in the compaction position table 30, the position error (offset) between the GNSS device 189 and the center of the ground contact position of each rear wheel is managed, and information on the width (compacted range) of each rear wheel is also managed. In the case of FIG. 5(e) and FIG. 5(f), since there are four compaction ranges, information on the four compaction ranges (width H3a) is stored in the compaction position table 30. The installation position of the GNSS device 189 on the scraper A may be changed as appropriate.
[0022] Returning to FIG. 3, the compaction level update unit 24 divides the embankment construction range into a number of blocks (square divided areas) (see FIG. 9 and FIG. 10), and updates the compaction level of each block, which has been compacted by a heavy machine running over it, based on the compaction level table 32. Here, the compaction level table 32 is a table for storing data obtained by a test construction carried out in advance, and manages data such as that shown in FIG. 6. The compaction level table 32 will be described in detail later, but the compaction level update unit 24 updates the compaction level of each block by adding the compaction level of the heavy machine that performed the compaction, stored in the compaction level table 32, to the compaction level of the block corresponding to the position where each heavy machine performed the compaction. In this embodiment, the compaction level of each block refers to the ratio of the current compaction level to the target compaction level of each block. The degree of compaction is a value that indicates the degree of compaction at the time of filling, assuming that the soil (or roadbed material) is the same as the sample used in the test. The dry density is calculated from a field density test using an RI meter, and this value is expressed as a percentage of the maximum dry density obtained in a laboratory compaction test (JIS A 1210A / B method or JIS A 1210C / D / E method).
[0023] The screen generation / output unit 26 generates a screen displaying the compaction level of each block updated by the compaction level update unit 24, and transmits (outputs) it to the display processing unit 42 of each heavy machinery vehicle-mounted device 70, 72, 74. In other words, the screen generation / output unit 26 transmits the generated screen to the heavy machinery vehicle-mounted devices 70, 72, 74, thereby causing the display units 193 of the heavy machinery vehicle-mounted devices 70, 72, 74 to display the generated screen.
[0024] The bulldozer vehicle-mounted device 70, the vibratory roller vehicle-mounted device 72, and the scraper vehicle-mounted device 74 function as a position information acquisition unit 40, a display processing unit 42, and an input processing unit 44 by the CPU 190 executing a program.
[0025] The position information acquisition unit 40 acquires position information (three-dimensional coordinates) from the GNSS device 189 and transmits it to the traveling locus acquisition unit 22 of the management device 10.
[0026] The display processing unit 42 acquires the screen generated by the screen generation and output unit 26 of the management device 10 , and displays it on the display unit 193 .
[0027] The input processing unit 44 acquires information input by the worker via the input unit 195 and transmits it to the input information acquisition unit 20 of the management device 10 .
[0028] (Regarding the processing of the management device 10) Next, the processing of the management device 10 will be described in detail with reference to the flowchart of FIG. 8 and other drawings as appropriate. Note that, as a prerequisite for starting the processing of FIG. 8, the worker performs a test construction (rolling test) for the compaction of the embankment using each heavy machine traveling on the site in order to determine the construction specifications (compaction level by one compaction for each type of heavy machine, over-compaction level for each type of heavy machine). This test construction is performed under the same conditions (soil quality and spreading thickness) as those for the actual compaction. At this time, the setting of the yard (test area) where the test construction is performed is set to an appropriate width and length, taking into consideration the test method, the soil quality of the embankment material, the dimensions of the machine used for compaction, etc. Note that, depending on the conditions such as the soil quality and weather at the site, over-compaction does not occur, so it is not necessary to determine the over-compaction level.
[0029] In the test construction, workers operated each heavy machine and repeatedly traveled over a set yard to obtain the relationship between the number of compaction passes and the degree of compaction (see Figures 7(a) to 7(c)).
[0030] Here, the number of compaction times at which a predetermined (target) degree of compaction can be stably obtained is defined as the prescribed number of compaction times n. For example, if the predetermined degree of compaction is a control standard value (e.g., 92%), the number of compaction times at which the degree of compaction exceeds the control standard value and further compaction results in almost no change in the degree of compaction is defined as the prescribed number of compaction times n.
[0031] In addition, when an approximately linear relationship is observed between the number of compaction times from 0 to the specified number of compaction times n and the compaction degree, the compaction level for the compaction degree at the specified number of compaction times n is set to 1.0. An approximately linear relationship is observed between the number of compaction times and the compaction degree when, for example, the correlation coefficient in the linear approximation is within a reference range (0.85 to 1.0, preferably 0.9 to 1.0). In this case, the compaction level after one compaction by each heavy machine can be calculated using the following formula (1). Compaction level after one compaction = 1.0 / n …(1)
[0032] 7(a) to 7(c) show the results of a test construction carried out at the Kitaibaraki MS (Mega Solar) Work Site of Japan Land Development Co., Ltd., as an example of the results of the test construction.
[0033] Figure 7(a) is a graph showing the relationship between the number of compaction passes and the degree of compaction when a test construction was carried out using a vibrating roller (a 10-ton vibrating roller (non-vibrating)) after the embankment material, which is clayey soil (soil), was spread and leveled in the test area. From this graph in Figure 7(a), it can be seen that the specified number of compaction passes, n, at which the degree of compaction stabilizes beyond the control standard value, is 4 passes. Furthermore, the approximation line (y=2.21x+86.4) between the number of compaction passes from 0 to the specified number of compaction passes n and the degree of compaction has a correlation coefficient R of 0.9261, and an approximately linear relationship is recognized. Therefore, the compaction level after one compaction pass can be calculated as 1.0 / 4=0.25.
[0034] Figure 7(b) is a graph showing the relationship between the number of compaction passes and the degree of compaction when a test construction was carried out using a vibrating roller (a 10-ton vibrating roller (strong vibration)) after the embankment material, which is gravelly soil, was spread and leveled in the test area. From this graph in Figure 7(b), it can be seen that the specified number of compaction passes, n, at which the degree of compaction stabilizes beyond the control standard value, is 4 passes. Furthermore, the approximation line (y = 3.12x + 87.7) between the number of compaction passes from 0 to the specified number of compaction passes n and the degree of compaction has a correlation coefficient R of 0.9712, and an approximately linear relationship is recognized. Therefore, the compaction level after one compaction pass can be calculated as 1.0 / 4 = 0.25.
[0035] Figure 7(c) is a graph showing the relationship between the number of compaction attempts and the degree of compaction when embankment material, which is gravelly soil, was spread and leveled in the test area and then test construction was performed using a scraper. From the graph in Figure 7(c), it can be seen that the specified number of compaction attempts n, at which the degree of compaction exceeds the control standard value and stabilizes, is 4. In addition, the approximation line (y=4.29x+86.0) between the number of compaction attempts from 0 to the specified number of compaction attempts n and the degree of compaction has a correlation coefficient R of 0.9554, and an approximately linear relationship is recognized. Therefore, the compaction level after one compaction attempt can be calculated as 1.0 / 4=0.25.
[0036] The specified number of compaction times n at which the degree of compaction stabilizes beyond the control standard value may be determined by the worker, or may be determined using machine learning. In the latter case, a graph showing the relationship between the number of compaction times in the past and the degree of compaction, and the specified number of compaction times n determined by the worker from the graph are input as learning data to the information processing device, and machine learning is performed, making it possible to automatically determine the specified number of compaction times n from the newly obtained graph.
[0037] As described above, in this embodiment, a linear approximation (first linear approximation, second linear approximation, ...) between the number of compactions and the degree of compaction is obtained for each type of heavy machinery (first heavy machinery, second heavy machinery, ...) in a test area set under the same conditions as during actual compaction, and the compaction level of each heavy machinery is determined according to the correlation coefficient of the linear approximation. This makes it possible to accurately determine the compaction level of each heavy machinery. Note that, for heavy machinery whose correlation coefficient of linear approximation is not included in the reference range, it may be determined that the heavy machinery is not suitable for the process of FIG. 8 (compaction using multiple types of heavy machinery) and may not be used for compaction. Note that, in this embodiment, the range in which the linear approximation is obtained is the range in which the degree of compaction increases approximately linearly with an increase in the number of compactions from the start of compaction of the test area by the heavy machinery (the range until the degree of compaction becomes stable). This makes it possible to perform linear approximation in a range in which the correlation coefficient is likely to be included in the reference range, and the compaction level of each heavy machinery can be accurately obtained.
[0038] In addition, in the test construction, the number of compaction operations (number of over-compactions m) required by each heavy machine until over-compaction occurred is obtained. Then, the over-compaction level is calculated from the number of over-compactions m using the following formula (2). Over-compaction level = Compaction level by one compaction × m … (2)
[0039] For example, in the case of bulldozer A shown in Figure 6, the number of compactions n was 10, so the compaction level for one compaction is 1.0 / 10 = 0.10. Also, the number of over-compactions m for bulldozer A was 14, so the over-compaction level is 0.10 x 14 = 1.4.
[0040] When the process of FIG. 8 is started, first, in step S12, the input information acquisition unit 20 waits until the worker inputs the embankment construction range, etc., via the input unit 195 of the heavy equipment vehicle-mounted device 70, 72, 74 or the input unit 95 of the management device 10. For example, the worker inputs the outer periphery line of the area to be compacted (compaction area) as the embankment construction range, with a map displayed on the display unit 93 of the management device 10. The worker also inputs the type of heavy equipment currently used at the site (type of heavy equipment that may travel in the embankment construction range). The heavy equipment input by the worker becomes the monitoring target of the management device 10 in the subsequent process. Also, at this stage, the compaction level update unit 24 refers to the compaction level table 32 (FIG. 6) and sets the smallest value of the over-compaction levels of the heavy equipment input by the worker as the over-compaction level of the embankment construction range. For example, when a bulldozer A, a vibrating roller A, and a scraper A are input, the smallest value (1.3) among the over-compaction levels of these heavy machines becomes the over-compaction level of the embankment construction area. If the information of the heavy machine input by the user is not included in the compaction level table 32, a notice may be given that test construction of the heavy machine is necessary.
[0041] When there is an input from the worker in step S12, the process proceeds to step S14, where the input information acquisition unit 20 waits until the leveling thickness of the embankment construction area reaches a predetermined value. Here, the predetermined value is a value similar to the leveling thickness when the test construction was performed. In step S14, the input information acquisition unit 20 may wait until the worker inputs via the input unit 95 of the management device 10 or the input unit 195 of the bulldozer vehicle-mounted device 70 that the leveling thickness has reached the predetermined value, or may monitor the positions and operations of the scraper and bulldozer after step S12 and estimate that the leveling thickness of the embankment construction area has reached the predetermined value using machine learning or the like.
[0042] If the determination in step S14 is positive, the process proceeds to step S16, where the travel trajectory acquisition unit 22 starts compaction management of the embankment construction range. That is, if the heavy equipment travels through the embankment construction range thereafter, the compaction level within the embankment construction range is updated. At this stage, the screen generation / output unit 26 generates a screen as shown in FIG. 9 and outputs it to the display processing unit 42 of each of the heavy equipment vehicle-mounted devices 70, 72, and 74. As a result, the screen of FIG. 9 is displayed on the display unit 193 of each of the heavy equipment vehicle-mounted devices 70, 72, and 74. The screen of FIG. 9 is a screen in which the embankment construction range is divided into many blocks and the compaction level of each block is displayed in a different color, but at this stage, the compaction level of all blocks is 0.
[0043] Next, in step S18, the travel trajectory acquisition unit 22 acquires the travel trajectory of each heavy machine. Specifically, the travel trajectory acquisition unit 22 acquires information such as position information (three-dimensional coordinates) and time transmitted from the position information acquisition unit 40 of each heavy machine on-board device 70, 72, 74.
[0044] Next, in step S19, the travel trajectory acquisition unit 22 identifies the compacted location. Specifically, the travel trajectory acquisition unit 22 identifies the compacted location (block) from the acquired position information of the heavy machine (GNSS device 189) based on the information stored in the compaction position table 30.
[0045] Next, in step S20, the compaction level update unit 24 judges whether the embankment construction range has been compacted. If the judgment in step S20 is negative, the process returns to step S18, but if the judgment is positive, the process proceeds to step S22.
[0046] When the process proceeds to step S22, the compaction level update unit 24 updates the compaction level of the area (block) compacted by each heavy machine with the compaction level from one compaction corresponding to the heavy machine that performed the compaction. For example, if a block with compaction level = 0 is compacted by bulldozer A (compaction level from one compaction = 0.1), the compaction level of that block is updated to 0 + 0.1 = 0.1. Also, for example, if a block with compaction level = 0.5 is compacted by vibrating roller A (compaction level from one compaction = 0.17), the compaction level of that block is updated to 0.5 + 0.17 = 0.67. In this embodiment, the compaction level can reflect not only the compaction by heavy machinery (e.g., vibrating roller) traveling in the embankment construction area for compaction, but also the compaction by heavy machinery passing through the embankment construction area (e.g., scrapers and dump trucks passing through the embankment construction area to carry soil to another location). This allows the compaction level of each block to be managed with high accuracy. In addition, in this embodiment, whether or not compaction is progressing is expressed by the integrated value of the compaction level by one compaction of each heavy machinery that compacted each block, so that it is possible to manage compaction using multiple types of heavy machinery, unlike when it is expressed by the number of compactions by the same heavy machinery. In addition, management is possible even if multiple types of heavy machinery are run simultaneously in one embankment construction area. Therefore, the time required for compaction can be shortened by parallel work by multiple heavy machinery. In addition, heavy machinery that is not scheduled to be used at the site can be diverted to compaction, so that the heavy machinery can be used efficiently.
[0047] Next, in step S23, the screen generating / outputting unit 26 updates the screen with the updated compaction level and outputs the updated screen to the display processing unit 42 of each heavy machine vehicle-mounted device 70, 72, 74. As a result, the screen displayed on the display unit 193 of each heavy machine vehicle-mounted device 70, 72, 74 is updated. FIG. 10 shows an example of a screen during compaction. Since the position of the heavy machine is also displayed on the screen of FIG. 10, the worker can easily confirm where the heavy machine he is driving is in the embankment construction range and what range should be compacted next. In addition, since the worker can easily confirm the places where over-compaction is likely to occur, the worker can avoid traveling through such places. Note that the screen generating / outputting unit 26 may output a warning from the screen or voice when the heavy machine is approaching a place where over-compaction is likely to occur.
[0048] Next, in step S24, the compaction level update unit 24 judges whether the compaction level of the entire embankment construction range is equal to or greater than a predetermined value (e.g., 1.0). If the judgment in step S24 is negative, the process returns to step S18, and the above-mentioned processes from step S18 to step S24 are repeatedly executed. On the other hand, if the judgment in step S24 is positive, the process proceeds to step S26.
[0049] When the process proceeds to step S26, the screen generation / output unit 26 generates a screen for notifying the completion of compaction, and outputs the generated screen to the display processing unit 42 of each of the heavy machinery vehicle-mounted devices 70, 72, 74. As a result, a screen notifying the completion of compaction is displayed on the display unit 193 of each of the heavy machinery vehicle-mounted devices 70, 72, 74. By checking the screen notifying the completion of compaction, the worker can move on to compaction work for the next embankment construction area.
[0050] With the above, the entire process in FIG. 8 is completed.
[0051] As described above in detail, according to this embodiment, the travel trajectory acquisition unit 22 acquires the travel trajectory for each heavy machine and identifies the compaction location. Then, when the heavy machine travels through the embankment construction area (S20: Yes), the compaction level update unit 24 updates the compaction level based on the compaction level table 32 that manages the compaction level for each heavy machine in one compaction. As a result, even when multiple types of heavy machines travel through the embankment construction area, it becomes possible to appropriately determine whether compaction has been completed for each part (block) of the embankment construction area. Therefore, the embankment construction area can be compacted to an appropriate compaction level using multiple types of heavy machines. In addition, since multiple types of heavy machines can be used, heavy machines present at the site (for example, heavy machines that are not originally used for compaction) can be effectively used. Furthermore, since multiple heavy machines (regardless of whether they are the same type or different types) can be simultaneously run through one embankment construction area, the time required for compaction can be shortened.
[0052] In addition, in this embodiment, the screen generation / output unit 26 displays the compaction level for each of the many blocks into which the embankment construction area is divided, so that the worker operating the heavy machinery can check in detail which areas of the embankment construction area he or she should and should not drive on.
[0053] In addition, in this embodiment, blocks that are likely to be over-compacted are displayed in an identifiable manner among a large number of blocks on a screen such as Figure 10, so that a worker operating heavy machinery can drive while avoiding areas that are over-compacted.
[0054] In this embodiment, the compaction level of each heavy machine after one compaction is determined in a test construction, so that the compaction level of each compaction can be set to an appropriate value by performing the test construction under the same conditions as the actual compaction conditions. In this test construction, a linear approximation between the number of compactions and the degree of compaction is obtained for each type of heavy machine in a test area under the same conditions as the actual compaction, and the compaction level of each heavy machine is determined according to the correlation coefficient of the linear approximation. This allows the compaction level of each heavy machine to be obtained with high accuracy.
[0055] In the above embodiment, the case where the compaction level of the embankment construction range is updated and displayed on the screen according to the travel trajectory of the heavy machine has been described, but the present invention is not limited to this, and the compaction level of the area adjacent to the embankment construction range (adjacent area) may also be updated and displayed on the screen. For example, if the area adjacent to the embankment construction range is an area where compaction has been completed, there is a risk of over-compacting if the heavy machine travels further, so by managing the compaction level of the adjacent area where compaction has been completed even after compaction and displaying it on the screen, the worker can travel while avoiding areas that are likely to be over-compacted.
[0056] In the above embodiment, not only the heavy machinery vehicle-mounted devices 70, 72, 74 but also the management device 10 may have a GNSS device. In this case, the position information of the heavy machinery vehicle-mounted devices 70, 72, 74 may be corrected based on the position information obtained from the GNSS device of the management device 10. The device that acquires the position information of the heavy machinery vehicle-mounted devices 70, 72, 74 does not have to be the GNSS device 189. For example, the positional relationship between the heavy machinery vehicle-mounted devices 70, 72, 74 and the management device 10 may be grasped using Wi-Fi or the like, and the positions of the heavy machinery vehicle-mounted devices 70, 72, 74 may be detected from the positional relationship and the positional information (three-dimensional coordinates) obtained from the GNSS device of the management device 10.
[0057] In the above embodiment, the case where the worker operates the heavy machinery while checking the display unit 193 has been described, but the present invention is not limited to this, and at least a part of the heavy machinery may be automatically controlled based on the compaction level of each block in the embankment construction area. Depending on the soil quality of the embankment material, the compaction level may be managed by physical properties such as the degree of saturation and air void ratio of the embankment material in addition to the degree of compaction.
[0058] (Modification) In the above embodiment, an example is described in which the embankment material is a soil whose quality can be controlled by the degree of compaction. However, there are also cases in which the embankment material is a soil whose quality cannot be controlled by the degree of compaction, such as a rock mass material.
[0059] The following describes a compaction method when rock mass materials are used as embankment materials.
[0060] In the case of rock mass materials that cannot be controlled by the degree of compaction, test construction is carried out for each type of heavy machinery in a test area with the same soil quality as the actual compaction site, and the relationship between the number of compaction times and the amount of surface settlement due to compaction is obtained. For example, a graph showing the relationship between the number of compaction times and the amount of surface settlement as shown in Figure 11 can be obtained. Here, as described in the above Non-Patent Document 1 ("Guidelines for Compaction Management of Embankments Using TS / GNSS", Ministry of Land, Infrastructure, Transport and Tourism, March 2020, p. 25), in the case of rock mass materials, the prescribed number of compaction times n is generally set to the number of compaction times corresponding to the inflection point of the amount of surface settlement (near the point where the amount of settlement converges).
[0061] Therefore, in this modified example, the relationship between the number of compaction times and the amount of surface subsidence from the start of compaction to the number of compaction times (prescribed number of compaction times n) corresponding to the inflection point of the amount of surface subsidence is linearly approximated. Then, when an approximately linear relationship is recognized between the number of compaction times from 0 to the prescribed number of compaction times n and the amount of surface subsidence, that is, when the correlation coefficient of the linear approximation is within a reference range (0.85 to 1.0, preferably 0.9 to 1.0), the compaction level for the compaction degree at the prescribed number of compaction times n is set to 1.0. In this case, the compaction level after one compaction of each heavy machine can be obtained using the above formula (1) (compaction level after one compaction = 1.0 / n).
[0062] For example, in the graph of Figure 11, the number of compactions (prescribed number of compactions n) corresponding to the inflection point is 8. In addition, the approximation line (y = 0.535x) between the number of compactions from 0 to 8 and the amount of surface settlement has a correlation coefficient R of 0.9973, and an approximate linear relationship is recognized. Therefore, the compaction level after one compaction is calculated as 1.0 / 8 = 0.125.
[0063] In this way, in this modified example, a linear approximation (first linear approximation, second linear approximation, ...) between the number of compactions and the amount of surface settlement due to compaction is obtained for each type of heavy machinery (first heavy machinery, second heavy machinery, ...) in a test area set under the same conditions as in actual compaction, and the compaction level by one compaction of each heavy machinery is obtained according to the correlation coefficient of the linear approximation. As a result, even for embankment materials with soil quality (such as rock mass materials) that cannot be managed by the degree of compaction, the compaction level by one compaction of each heavy machinery can be obtained with high accuracy. Therefore, even in the case of rock mass materials, the same processing as in FIG. 8 (compaction using multiple types of heavy machinery) can be performed using the compaction level by one compaction of each heavy machinery. In addition, in the case of rock mass materials, over-compaction does not occur, so the over-compaction level is not managed.
[0064] Incidentally, the inflection points of the graph in Fig. 11 may be determined by an operator or may be determined using machine learning. In the latter case, a past graph and the inflection points determined by the operator from the graph are input as learning data to an information processing device, and machine learning is performed, thereby making it possible to automatically determine the inflection points from a newly obtained graph.
[0065] In this embodiment and this modified example, the predetermined value (the spreading and leveling thickness in this construction) in step S14 in FIG. 8 is set as follows. (a) Measure the thickness of the layer to be laid in the test construction in advance. (b) Measure the finished thickness calculated from the amount of surface settlement at the specified compaction cycle n. (c) The thickness of the paving (predetermined value) for this construction is determined using the following formula (3). Thickness of the paving for this project = Specified finished thickness x (test construction even thickness / test construction finished thickness) …(3) The specified finished thickness is, for example, 30 cm or less for embankment construction and road body embankment construction, and 20 cm or less for roadbed embankment construction.
[0066] The above-described embodiment is a preferred example of the present invention, but the present invention is not limited to this embodiment and can be modified in various ways without departing from the scope of the present invention. [Explanation of symbols]
[0067] 10 Management device 22 Driving trajectory acquisition unit 24 Compaction level update section 26 Screen generation / output section
Claims
1. A first linear approximation is obtained between the number of compaction operations of the first heavy machine and the degree of compaction in a test area having the same soil quality as the predetermined compaction area; A second linear approximation is obtained between the number of compactions and the degree of compaction of a second heavy machine of a type different from the first heavy machine in the test area; When the correlation coefficient of the first linear approximation and the correlation coefficient of the second linear approximation are within a reference range, it is determined that compaction using a plurality of types of heavy equipment using the first heavy equipment and the second heavy equipment is possible, and a first compaction level of the first heavy equipment is determined in accordance with the correlation coefficient of the first linear approximation, and a second compaction level of the second heavy equipment is determined in accordance with the correlation coefficient of the second linear approximation; A compaction method for compacting the specified compaction area using the first heavy machine and the second heavy machine.
2. A compaction method as described in claim 1, in which it is determined that compaction of the specified compaction area will not be performed for the first heavy equipment whose correlation coefficient of the first linear approximation is not included in the standard range or the second heavy equipment whose correlation coefficient of the second linear approximation is not included in the standard range.
3. Acquiring a first travel trajectory of the first heavy machine and a second travel trajectory of the second heavy machine; A compaction method as described in claim 1 or claim 2, wherein when the first heavy machine and the second heavy machine travel through the specified compaction area, the first compaction level and the second compaction level, which is different from the first compaction level, are added to update the compaction level of the specified compaction area.
4. The first travel trajectory is acquired based on information regarding a compaction position of the first heavy machine and information regarding a compaction width of the first heavy machine, The compaction method according to claim 3 , wherein the second travel trajectory is acquired based on information relating to a compaction position of the second heavy machine and information relating to a compaction width of the second heavy machine.
5. A compaction method described in any one of claims 1 to 4, wherein when the first heavy machine and the second heavy machine travel through the specified compaction area, the first compaction level and the second compaction level are added together to update the compaction level of the specified compaction area.
6. The range in which the first linear approximation is calculated is a range in which the degree of compaction increases approximately linearly with an increase in the number of compactions from the start of compaction of the test area by the first heavy machine, A compaction method as described in any one of claims 1 to 4, wherein the range in which the second linear approximation is calculated is a range in which the degree of compaction increases approximately linearly with an increase in the number of compactions from the start of compaction of the test area by the second heavy equipment.
7. The first compaction level is the reciprocal of the number of compactions in the range in which the first linear approximation is obtained, The compaction method according to claim 6 , wherein the second compaction level is the reciprocal of the number of compactions in the range in which the second linear approximation is determined.
8. The method according to any one of claims 1 to 7, wherein the test area has been paved and leveled.
9. 9. The compaction method according to claim 1, wherein the reference range of the correlation coefficient of the first linear approximation and the correlation coefficient of the second linear approximation is 0.85 or more and 1.0 or less.
10. A compaction method described in any one of claims 1 to 9, wherein the number of compactions is set based on the amount of surface subsidence.
11. A first linear approximation is obtained between the number of compactions by the first heavy machine and the amount of surface settlement due to compaction in a test area having the same soil quality as the specified compaction area; A second linear approximation is obtained between the number of compactions by a second heavy machine of a type different from the first heavy machine in the test area and the amount of surface settlement due to compaction; When the correlation coefficient of the first linear approximation and the correlation coefficient of the second linear approximation are within a reference range, it is determined that compaction using a plurality of types of heavy equipment using the first heavy equipment and the second heavy equipment is possible, and a first compaction level of the first heavy equipment is determined in accordance with the correlation coefficient of the first linear approximation, and a second compaction level of the second heavy equipment is determined in accordance with the correlation coefficient of the second linear approximation; A compaction method for compacting the specified compaction area using the first heavy machine and the second heavy machine.
12. A compaction method as described in claim 11, in which it is determined that no compaction will be performed on the specified compaction area for the first heavy equipment whose correlation coefficient of the first linear approximation is not included in the reference range or for the second heavy equipment whose correlation coefficient of the second linear approximation is not included in the reference range.
13. The first linear approximation is obtained based on the number of compactions of the first heavy machine and an inflection point of the amount of surface subsidence due to the compaction, The compaction method according to claim 11 or 12, wherein the second linear approximation is determined based on the number of compactions by the second heavy machine and an inflection point of the amount of surface subsidence due to the compaction.
14. The first compaction level is the reciprocal of the number of compactions corresponding to the inflection point at which the first linear approximation is obtained, The compaction method according to claim 13, wherein the second compaction level is the reciprocal of the number of compactions corresponding to the inflection point at which the second linear approximation is obtained.
Citation Information
Patent Citations
Highway subgrade compaction quality rapid detection method based on dynamic rebound modulus
CN111236199A
Vibration controller for vibration roller and compaction construction method
JP2008050859A
Rolling compaction machine
JP2020007704A
Movable measuring device of water content, and rolling compaction method
JP2020007730A