Connection limiter for the transition section between concrete column and concrete filled steel tube column
A technology of concrete-filled steel tube columns and concrete columns, which is applied in construction and building construction, can solve problems such as difficult quality control and difficult operation, and achieve the effects of saving costs and reducing the amount of measures used
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
specific Embodiment approach
[0017] The preferred embodiment of the connection limiter for the transition section between the concrete column and the concrete-filled steel tube column of the present invention is:
[0018] The connection limiter is set between the lower concrete column and the upper concrete-filled steel tube column, and includes a ring plate, and ribs and studs are arranged inside the ring plate. The positions, sizes, and The thickness and direction are consistent with the position, size, thickness and direction of the ribs and studs inside the steel tube concrete column, and are used to limit the reinforcement of the concrete column.
[0019] The outer diameter of the steel bar limiter is consistent with the outer diameters of the concrete column and the steel tube concrete column.
[0020] The ring plate has a height of 50mm to 150mm and a thickness of 8mm to 12mm.
[0021] The connection limiter for the transitional section between the concrete column and the steel pipe concrete colum...
specific Embodiment
[0026] The basic composition of the connection limiter used for the transition section between the concrete column and the steel tube concrete column:
[0027] like Figure 5a , Figure 5b , Figure 5c As shown, the connection limiter used for the transition section between concrete columns and CFST columns is mainly composed of three parts: ring plates, rib plates and studs.
[0028] 1) Rib and stud design:
[0029] The position, size, thickness and direction of the ribs and studs should be consistent with the upper steel pipe column, so as to play the role of steel bar limit. The height and thickness of the ribs should be appropriate. In this example, the height of the ribs is 50mm, and the thickness is 10mm. .
[0030] 2) Ring plate design:
[0031] In order to avoid the situation that the concrete column formwork cannot be closed after the steel bar stopper is installed, the outer diameter of the steel bar stopper should be consistent with the outer diameter of the co...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com