A construction method for positioning and installing an extra-long screw

By dividing the structure of upper and lower screws and positioning tooling for two levels of positioning and installation, the problems of low construction efficiency and insufficient accuracy of traditional ultra-long screw positioning and installation are solved, and efficient and accurate screw positioning and installation are achieved, reducing costs and construction cycle.

CN116025171BActive Publication Date: 2024-11-15CHINA RAILWAY NO 5 ENGINEERING GROUP CO LTD +4
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211731724.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-30
Publication Date
2024-11-15
Estimated Expiration
2042-12-30

AI Technical Summary

Technical Problem

The traditional ultra-long screw positioning and installation has a long construction cycle and is inconvenient to operate, making it difficult to ensure positioning accuracy, and the construction efficiency is low and the cost is high, so it cannot be suitable for positioning and installation of ultra-long screws.

Method used

Using an ultra-long screw structure divided into upper and lower screws, two-stage positioning and installation are carried out through positioning tooling, including measurement and staking, interface agent treatment, tooling fixing and grouting pouring, and precise adjustment is made using measuring instruments to ensure the positioning accuracy and construction of the screw efficiency.

Benefits of technology

It improves the positioning accuracy and construction efficiency of the ultra-long screw, saves labor and material costs, shortens the construction cycle, and ensures the overall quality of the slide rail test line.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116025171B_ABST
    Figure CN116025171B_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for positioning and installing an extra-long screw. The extra-long screw is grouting and fixed in a square sleeve. The extra-long screw includes an upper screw, a connector and a lower screw which are threadedly connected in sequence. A steel plate is worn on the upper screw. The construction method includes the following steps: S1: measuring and setting out the control points of the grouting material range, manually marking the lines, roughening all the concrete surfaces within the grouting range, and cleaning them; S2: cleaning the wall of the square sleeve, and brushing the interface agent on the concrete surface within the grouting range; S3: placing the extra-long screw in the square sleeve and fixing it with a tool; S4: adjusting the tool elevation, flatness, and the elevation of the steel plate, and fine-tuning the position of the upper screw one by one with a measuring instrument; S5: fixing the steel plate and grouting. The invention has the characteristics of accurate positioning, safety and reliability, simple operation, high construction efficiency, etc., and can ensure the overall quality of the high-speed slide rail test line.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a construction method for positioning and installing an extra-long screw. Background Art

[0002] The large aircraft ground dynamics test platform is the first test platform in the relevant field in China. It is of great significance and far-reaching impact. After completion, it will test various aircraft tires, wheel brakes, landing gear systems, high-speed dynamic characteristics on different pavement surfaces and large sideslip angle dynamic characteristics on real runways, collect basic data, break the foreign monopoly on key technical basic data, and fill a gap in China.

[0003] The slide rail test line is the main structure of the test platform (an extra-long and large concrete structure), which involves the pre-buried installation of a large number of extra-long screws. The screw installation accuracy is related to the success of subsequent processes and the success of the high-speed slide rail test line. It is the core control indicator of the entire test line. The traditional screw positioning and installation construction period is long, the operation is inconvenient, and a large number of operators are required to cooperate in the construction. The cost is high, it is not suitable for the positioning and installation of extra-long screws, the positioning accuracy cannot be guaranteed, and the construction efficiency is low. Summary of the invention

[0004] The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a construction method for positioning and installing an ultra-long screw with precise positioning.

[0005] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0006] A construction method for positioning and installing an extra-long screw, wherein the extra-long screw is grouted and fixed in a square sleeve, the extra-long screw comprises an upper screw, a connector and a lower screw which are threadedly connected in sequence, a steel plate is passed through the upper screw, and the construction method comprises the following steps:

[0007] S1: Measure and mark the control points of the grouting material range, manually draw lines, roughen the concrete surface within the grouting range, and clean it.

[0008] S2: Clean the wall of the other sleeve and brush the interface agent on the concrete surface within the grouting range.

[0009] S3: Place the extra-long screw into the square sleeve and fix it using a positioning tool;

[0010] S4: Adjust the height, flatness and height of the tooling, and the height of the steel plate, and use measuring instruments to fine-tune the position of the upper screw rods one by one.

[0011] S5: Fix the steel plate and carry out grouting.

[0012] As a further improvement of the above technical solution:

[0013] In step S2, the interface agent is set as cement slurry with a water-cement ratio of 1:0.45.

[0014] In step S3, the positioning tool includes a bracket and a positioning steel plate, and the positioning steel plate is provided with screw holes.

[0015] In step S3, the upper screw rod passes through the screw rod hole on the positioning steel plate and is fixed with a nut.

[0016] In step S4, a CPIII Leica total station is used to check the flatness of the steel plate and the position of the upper screw, and an electronic level is used to check the verticality of the upper screw.

[0017] In step S5, the steel plates are fixed by welding with steel bars.

[0018] Compared with the prior art, the advantages of the present invention are:

[0019] The construction method for positioning and installing an extra-long screw of the present invention divides the extra-long screw into an upper screw and a lower screw connected by connector threads, which is very convenient for later maintenance and replacement; a positioning tool is used to fix the extra-long screw, and a measuring instrument is used to perform two-stage positioning, that is, the positioning tool is first positioned as a whole, and then each extra-long screw is accurately positioned one by one, thereby ensuring the positioning accuracy of the extra-long screw; the positioning tool has a simple structure and is easy to operate, and is not affected by the track gauge. A single set of positioning tool can position and install multiple groups of extra-long screws at one time, and multiple sets of the positioning tool can be used in combination to simultaneously position and install a large number of extra-long screws, thereby improving construction efficiency; a large amount of labor and material costs are saved, the construction period is short, and the smooth implementation of subsequent key processes is ensured, thereby ensuring the overall quality of the slide rail test line. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a schematic diagram of the super-long screw structure in the present invention.

[0021] Figure 2 It is a schematic diagram of the tooling structure in the present invention.

[0022] The symbols in the figure represent:

[0023] 1. Extra-long screw; 11. Upper screw; 12. Connector; 13. Lower screw; 14. Steel plate; 2. Tooling; 21. Bracket; 22. Positioning steel plate. DETAILED DESCRIPTION

[0024] The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

[0025] like Figure 1 and Figure 2As shown, the construction method for positioning and installing the extra-long screw in this embodiment is that the extra-long screw 1 is grouted and fixed in the square sleeve. The extra-long screw 1 includes an upper screw 11, a connector 12 and a lower screw 13 which are threadedly connected in sequence. A steel plate 14 is passed through the upper screw 11. The construction method includes the following steps:

[0026] S1: Measure and mark the control points of the grouting material range, manually draw lines, roughen the concrete surface within the grouting range, and clean it.

[0027] S2: Clean the wall of the other sleeve and brush the interface agent on the concrete surface within the grouting range.

[0028] S3: Place the extra-long screw 1 into the square sleeve and fix it with the tooling 2.

[0029] S4: Adjust the elevation and flatness of the tooling 2 and the elevation of the steel plate 14, and use a measuring instrument to fine-tune the position of the upper screw 11 one by one.

[0030] S5: Fix the steel plate 14 and perform grouting.

[0031] The method divides the extra-long screw 1 into an upper screw and a lower screw that are threadedly connected by a connector 12, which is very convenient for later maintenance and replacement; the extra-long screw 1 is fixed by a positioning tool 2, and a measuring instrument is used for two-stage positioning, that is, the positioning tool 2 is first positioned as a whole, and then each extra-long screw 1 is accurately positioned one by one, thereby ensuring the positioning accuracy of the extra-long screw. A single set of positioning tooling can be used to position and install multiple groups of extra-long screws at one time, thereby improving construction efficiency and saving labor and material costs.

[0032] In this embodiment, in step S2, the interface agent is set as cement slurry with a water-cement ratio of 1:0.45. Applying the interface agent is beneficial to the bonding of new and old concrete.

[0033] In this embodiment, in step S3, the tool 2 includes a bracket 21 and a positioning steel plate 22, and a screw hole is provided on the positioning steel plate 22. In this structure, the bracket 21 is 6m long, the positioning steel plate 22 is 5.99m long, the positioning steel plate 22 is welded on the bracket 21, the bracket 21 is made of 40×4mm square steel pipe, the positioning steel plate 22 is a 6mm thick Q235 material steel plate, and the positioning steel plate 22 is provided with a screw hole that is consistent with the vertical and horizontal spacing of the upper screw 11. The tool 2 can complete the positioning and fixing of multiple groups of super-long screws 1 at one time, and the tool 2 can set up steel plates, connect and fix them through the screw hole bolts, and multiple sets can be used together, which improves the construction efficiency, shortens the construction period, and saves labor costs.

[0034] In this embodiment, in step S3, the upper screw 11 passes through the screw hole on the positioning steel plate 22 and is fixed with a nut. In this embodiment, the upper screw 11 and the lower screw 13 are connected with the connector 12 and then assembled with the steel plate 14 and placed in the square sleeve. The upper screw 11 passes through the screw hole and is fixed and suspended on the positioning steel plate 22 with a nut. The operation is convenient and fast, and the construction efficiency is high.

[0035] In this embodiment, in step S4, the CPIII Leica total station is used to check the flatness of the steel plate 14 and the position of the upper screw 11, and the electronic level is used to check the verticality of the upper screw 11. In this embodiment, a support screw is also provided on the tooling 2 as a fixed support. The balance and center line of the tooling 2 are determined by adjusting the axis and elevation of the tooling 2. First, the tooling elevation is adjusted to determine the flatness of the tooling: the CPIII instrument measures the elevation of the top surface of the tooling, and adjusts the upper and lower adjustment rods on the tooling according to the data elevation, and further adjusts and determines the flatness of the tooling; adjust the axis: through the CPIII instrument, the tooling axis is adjusted to be consistent with the axis of the screw assembly, which meets the design. The adjustment is made through the left and right adjustment screws on the tooling; after the flatness and centerline of the tooling are adjusted into place, the tooling is fixed by the left and right supports to prevent changes; after the flatness and centerline of the tooling 2 are determined, the elevation of the steel plate 14 is measured and adjusted to reach the designed elevation. After the steel plate 14 is adjusted into place, the CPIII Leica total station is used to fine-tune the position of each upper screw 11 one by one to ensure that the plane position of all upper screws 11 meets the tolerance requirements, and then a review is carried out to ensure the accurate positioning of the extra-long screw 1.

[0036] In this embodiment, in step S5, the steel plate 14 is fixed by welding with steel bars. Rebars are planted on the side of the steel plate 14, and the steel plate 14 is fixed by welding with steel bars to prevent the steel plate 14 from being disturbed during the grouting process, thereby affecting the positioning accuracy of the super-long screw 1.

[0037] In this embodiment, when using a measuring instrument for measurement, try to avoid high temperature weather, and choose to measure at night or in a shade shed. After the position of the upper screw 11 is adjusted, pour the grouting material as soon as possible to avoid people walking on the tooling 2 affecting the positioning accuracy. The steel plate 14 and the steel bar can be spot welded. During the grouting process, the grouting speed is controlled, the grouting pressure cannot be too large, and the grouting material flows in evenly.

[0038] Although the present invention has been disclosed as above with preferred embodiments, it is not intended to limit the present invention. Any technician familiar with the art can make many possible changes and modifications to the technical solution of the present invention by using the technical content disclosed above without departing from the scope of the technical solution of the present invention, or modify it into an equivalent embodiment of equivalent changes. Therefore, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention should fall within the scope of protection of the technical solution of the present invention.

Claims

1. A construction method for positioning and installing an extra-long screw, wherein the extra-long screw (1) is grouted and fixed in a square sleeve, characterized in that: The super-long screw (1) comprises an upper screw (11), a connector (12) and a lower screw (13) which are threadedly connected in sequence, a steel plate (14) is passed through the upper screw (11), and the construction method comprises the following steps: S1: Measure and set out the control points of the grouting material range, manually draw lines, roughen all the concrete surfaces within the grouting range, and clean them; S2: Clean the wall of the other sleeve and apply interface agent on the concrete surface within the grouting range; S3: placing the extra-long screw (1) into the square sleeve and fixing it with a positioning tool (2), wherein the positioning tool (2) comprises a bracket (21) and a positioning steel plate (22), wherein the positioning steel plate (22) is provided with a screw hole, and the upper screw (11) passes through the screw hole on the positioning steel plate (22) and is fixed with a nut; S4: adjusting the elevation, flatness, centerline of the positioning tool (2), and the elevation of the steel plate (14), using a measuring instrument to fine-tune the position of each upper screw (11), using a CPIII Leica total station to check the flatness of the steel plate (14) and the position of the upper screw (11), and using an electronic level to check the verticality of the upper screw (11); after the flatness and centerline of the tool are adjusted to the right position, the tool is fixed by the left and right supports; after the flatness and centerline of the tool (2) are determined, the elevation of the steel plate (14) is measured and adjusted to reach the designed elevation; after the steel plate (14) is adjusted to the right position, the position of each upper screw (11) is fine-tune one by one using a CPIII Leica total station; S5: Fix the steel plate (14) and perform grouting. The steel plate (14) is fixed by welding with steel bars.

2. The construction method for positioning and installing an extra-long screw according to claim 1, characterized in that: In step S2, the interface agent is set to cement slurry with a water-cement ratio of 1:0.45.