Flexible job shop energy-saving batch flow scheduling multi-objective optimization method considering processing preparation resources

By constructing a multi-objective optimization mathematical model in the flexible job shop and adopting the knowledge-driven batch method and improved multi-objective evolutionary algorithm, combined with the tooling post-adjustment strategy, the collaborative optimization problem of energy consumption, time and cost in the flexible job shop was solved and improved improve production efficiency and resource utilization.

CN118732622AActive Publication Date: 2024-10-01SHENYANG UNIVERSITY OF TECHNOLOGY
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202410763644.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-13
Publication Date
2024-10-01
Estimated Expiration
2044-06-13

AI Technical Summary

Technical Problem

It is difficult to collaboratively optimize energy consumption, completion time, and processing costs in a flexible job shop with existing technology, and the allocation of processing preparation resources is not properly optimized, resulting in high computational complexity and multiple local optimal solutions, affecting production efficiency and resource utilization. .

Method used

This paper proposes a multi-objective optimization method for energy-saving batch flow scheduling in flexible job shops considering processing preparation resources, including constructing a multi-objective optimization mathematical model, using knowledge-driven batch methods and improved multi-objective evolutionary algorithms for solution, and designing a multi-objective optimization method based on adjacent processes. Adjust the strategy after tooling to reduce the number of tooling and fixture switching times and energy consumption in processing preparation.

Benefits of technology

It achieves the comprehensive optimization of the total energy consumption of the workshop, workpiece completion time and total processing cost, improves machine tool utilization and production efficiency, and reduces the waiting time and processing preparation energy consumption of the production process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118732622A_ABST
    Figure CN118732622A_ABST
Patent Text Reader

Abstract

The invention relates to a flexible job shop energy-saving batch flow scheduling multi-objective optimization method considering processing preparation resources, and belongs to the technical field of shop scheduling. The method comprises the following steps: considering a flexible job shop energy-saving batch flow scheduling multi-objective optimization mathematical model of processing preparation resources; a model solving method based on a knowledge-driven batching method and an improved multi-objective evolutionary algorithm; and a tool post-adjustment strategy based on adjacent processes. According to the optimization method provided by the invention, the multi-objective optimization problem of flexible job shop energy-saving batch flow scheduling considering processing preparation resources can be efficiently solved, efficient collaborative optimization of workpiece batching, machine tool distribution, process sorting and tool distribution is realized, and a scheduling scheme with excellent completion time, total energy consumption and total processing cost is obtained.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a multi-objective optimization method for energy-saving batch flow scheduling of a flexible job shop taking processing preparation resources into consideration, and belongs to the technical field of shop scheduling. Background Art

[0002] Under fierce market competition, how to deliver orders efficiently, with high quality and low cost while saving energy, so as to improve core competitiveness is an important issue facing enterprises. Therefore, in addition to considering energy consumption targets, energy-saving batch flow scheduling in flexible workshops also needs to coordinate targets such as completion time and processing cost to achieve integrated optimization of economic indicators and green indicators. However, there is often a conflict between these two types of indicators in collaborative optimization. The reduction of total energy consumption in the workshop will cause the completion time of the workpiece to be extended, and it will also have an uncertain impact on the processing cost of the workpiece, which poses a challenge to the multi-objective collaborative optimization ability of the optimization method. In addition, while paying attention to machine tools and material constraints, workshop production also needs to consider processing preparation resource constraints such as tooling and fixtures. Processing preparation resources such as tooling and fixtures play a key role in the production line, ensuring the accurate positioning and stable fixation of the workpiece, which directly affects the smooth operation of the entire production line. At the same time, the allocation of processing preparation resources has an important impact on production efficiency and resource utilization. Reasonable arrangement and use of tooling and fixtures can greatly reduce equipment switching and preparation time and improve equipment utilization. Therefore, conducting research on multi-objective optimization methods for energy-saving batch flow scheduling in flexible job shops that take into account processing preparation resources, improving machine tool utilization, reducing the number of tooling and fixture switching, and reducing the waiting time of the production process and processing preparation energy consumption are the key to improving the overall production efficiency of the workshop and reducing total energy consumption and processing costs.

[0003] The energy-saving batch flow scheduling problem of a flexible job shop considering processing preparation resources involves multiple factors such as sub-problem coupling, goal conflict, and resource constraint integration, which leads to high computational complexity and many local optimal solutions. In this case, the matching result between the optimization method and the problem characteristics directly affects the quality of the scheduling solution. Therefore, when modeling the energy-saving batch flow scheduling problem of a flexible job shop considering processing preparation resources, the sub-problems of workpiece batching, process sequencing, machine tool and tooling allocation are comprehensively considered, and the economic indicators and green indicators, processing resources and processing preparation resources are coordinated and optimized; when solving the problem, attention is paid to the synergistic relationship between the problem characteristics, algorithm operations, and algorithm parameters, and the importance and applicable conditions of their impact on the algorithm performance are analyzed. This is the core of obtaining a better scheduling solution for the energy-saving batch flow scheduling problem of a flexible job shop considering processing preparation resources, which still needs to be systematically and deeply discussed and studied.

[0004] At present, the relevant research on the energy-saving batch flow scheduling problem of flexible job shops considering processing preparation resources is mainly carried out around traditional economic indicators, and has not explored the multi-objective collaborative optimization of energy consumption, completion time and processing cost and the characteristic mechanism of the coupling effect of multiple sub-problems of the energy-saving batch flow scheduling problem of flexible job shops with processing preparation resources; at the same time, most of the existing studies merge the processing preparation time into the workpiece processing time, which is easy to implement, but it leads to the inability to properly optimize the processing preparation resources. Based on the no free lunch theory, there is no algorithm that can be fully applied to two different optimization problems. Therefore, it is still necessary to study the optimization method of energy-saving batch flow scheduling of flexible job shops with processing preparation resources. By exploring the collaborative optimization mechanism between each sub-problem and studying the conflict relationship between different scheduling indicators, it is the key to design an efficient multi-objective collaborative optimization method to ensure the scientificity and effectiveness of its multi-objective decision-making. Summary of the invention

[0005] In view of the above-mentioned deficiencies and improvement needs of the prior art, the present invention proposes a multi-objective optimization method for energy-saving batch flow scheduling in a flexible job workshop taking into account processing preparation resources. The method aims to solve the problems that traditional optimization methods are difficult to apply and prone to premature convergence, and to achieve coordinated optimization of processing resources, processing preparation resources and transportation resources in energy-saving batch flow scheduling in a flexible job workshop taking into account processing preparation resources.

[0006] To solve the above technical problems, the present invention proposes a multi-objective optimization method for energy-saving batch flow scheduling in a flexible job shop considering processing preparation resources, comprising the following steps: S1. Constructing a multi-objective optimization mathematical model for energy-saving batch flow scheduling in a flexible job shop considering processing preparation resources; S2. Proposing a hybrid method of a knowledge-driven batching method and an improved multi-objective evolutionary algorithm to solve the model; S3. Designing a post-tooling adjustment strategy based on adjacent processes to reduce the number of tooling and fixture switching, shorten the completion time of the workpiece, and reduce processing preparation energy consumption.

[0007] According to the present invention, as a further preferred embodiment, in the step S1, the multi-objective optimization mathematical model for energy-saving batch flow scheduling of a flexible job shop considering processing preparation resources has the optimization objectives of minimizing the completion time, minimizing the total energy consumption and the total processing cost, and the calculation formula is:

[0008] F=min(TEC,T max ,TC)

[0009] Among them, F is the objective function, TEC, T max , TC are the total energy consumption, completion time and total processing cost of the workshop respectively.

[0010] In addition to meeting the basic constraints of flexible job shop batch flow scheduling, it is also necessary to meet the constraint that the same tool can only be used for processing in one process at the same time, which can be expressed as:

[0011]

[0012]

[0013] Among them, ST i,j,r Process Q ij Occupied tooling MT r The start time of RT g,h,r Process Q ij Occupied tooling MT r End time of is a decision variable, if process Q ij and subsequent process Q gh Both require the use of tooling MT r 1 when , otherwise 0; B is a sufficiently large real number; O i,j Q is the processable process ij Tooling MT r Collection; O g,h Q is the processable process gh Tooling MT r set; n' is the total number of workpieces after all workpieces are divided into batches; i, g are workpiece indexes; g, h are process indexes; r is tooling index; q i For workpiece J i The number of processes; q g For workpiece J g The number of processes.

[0014] On this basis, it is also necessary to satisfy the constraint that all tooling is available at the initial time of scheduling, which can be expressed as:

[0015]

[0016] Y i,j,k,r ∈{0,1},i∈[1,n'],j∈[1,q i ],k∈[1,m],r∈[1,N t ]

[0017] R r ∈{0,1},r∈[1,N t ]

[0018] Where k is the machine tool index; m is the number of machine tools; N t BT is the number of tooling; i,1,k For workpiece J i The first process is on the machine tool M k The start time of the previous processing; Y i,j,k,r is a decision variable, if the batch process Q ij In machine tool M k Use tooling MTr When it is 1, otherwise it is 0; R r is a decision variable, if tooling MT r The value is 1 if it is available at the initial scheduling time, otherwise it is 0.

[0019] According to the present invention, as further preferred, step S2 includes the following sub-steps:

[0020] A two-stage feedback optimization method is adopted to optimize the workpiece batching sub-problem using the knowledge-driven batching method framework, and the machine tool allocation, process sequencing, and tooling allocation sub-problems are optimized based on the proposed improved multi-objective evolutionary algorithm. That is, under the knowledge-driven flexible job shop batching method framework, based on the three-objective optimization characteristics of the model, an optimization strategy based on the moth flame operator is introduced to fully explore the three-dimensional solution space of the problem;

[0021] A co-evolution operator based on genetic operators and differential evolution operators is designed to promote information interaction among moth individuals.

[0022] According to the present invention, as further preferred, the post-tooling adjustment strategy based on adjacent processes in step S3 includes the following sub-steps:

[0023] Obtain current workpiece, machine tool and tooling status information;

[0024] Determine the first process to be started among the selected processes. If multiple processes start at the same time, one of them will be randomly selected.

[0025] Determine the process and the adjacent process on the selected machine tool Whether to select the same tooling for processing. If yes, then eliminate the process and return to step 2, otherwise go to the next step;

[0026] Judgment process Whether the tooling used can be used for the process Its process Is it available within the processing cycle? If yes, The tooling used Adjust to be consistent, update the tooling status information and go to the next step; otherwise, eliminate the process and return to step 2;

[0027] in, For machine tool M k The jth process of the previous processing, For machine tool M k The j-1th processing step.

[0028] End the algorithm.

[0029] The beneficial effects of the present invention are as follows: taking into account the total energy consumption of the workshop, the completion time of the workpiece and the total processing cost, a multi-objective optimization mathematical model for energy-saving batch flow scheduling of a flexible job shop considering processing preparation resources is constructed. A hybrid method of a knowledge-driven batch method and an improved multi-objective evolutionary algorithm is proposed to solve the model; under the framework of the knowledge-driven batch method, the three-dimensional solution space of the problem is fully explored based on the moth flame operator; the co-evolution operator is introduced to improve the diversity of the population, promote information interaction between populations, and improve the search speed and convergence effect of the algorithm. A post-tooling adjustment strategy based on adjacent processes is designed to reduce the number of tooling fixture switching, shorten the completion time of the workpiece, and reduce the processing preparation energy consumption. The optimal workpiece batch division, machine tool allocation, process sorting, and tooling allocation scheme for the total energy consumption, workpiece completion time, and total processing cost of the workshop are obtained. The combination of multi-resource constraint flexible production batch flow scheduling technology and intelligent optimization considering processing preparation resources is promoted, and a theoretical basis and practical support are provided for multi-variety variable batch production under the collaborative constraints of processing resources and processing preparation resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1(a) and 1(b) This is an example diagram of the energy-saving batch flow scheduling problem of a flexible job shop considering processing preparation resources in the present invention, wherein FIG1(a) is a scheduling scheme diagram before the workpieces are batched, and FIG1(b) is a scheduling scheme diagram after the workpieces are batched and optimized;

[0031] Figure 2 A model solving framework diagram of the hybrid method of the present invention based on the knowledge-driven batch method and the improved multi-objective evolutionary algorithm;

[0032] Figure 3 The optimized batch scheduling scheme process and machine tool allocation Gantt chart for the benchmark problem MK06 (Ave_B=20) of the present invention;

[0033] Figure 4 The Gantt chart of the batch scheduling scheme process and tooling allocation after optimization of the benchmark problem MK06 (Ave_B=20) of the present invention;

[0034] Figure 5(a) , 5(b) and 5(c) are box plots of the comparison results of IGD, GD and MS indicators for solving example problems using the knowledge-driven batch method and the improved multi-objective evolutionary algorithm and MOEA / D, NSGA-II, MOPSO, MOEA / PSL and LMOCSO according to an embodiment of the present invention, wherein FIG5(a) is a box plot of the comparison results of the IGD indicator, FIG5(b) is a box plot of the comparison results of the GD indicator, and FIG5(c) is a box plot of the comparison results of the MS indicator;

[0035] Figure 6A Gantt chart of the optimal solution scheduling scheme for solving example problems using the knowledge-driven batch method and improved multi-objective evolutionary algorithm according to an embodiment of the present invention;

[0036] Figure 7 This is a Gantt chart of the current scheduling plan of an enterprise according to an example of an embodiment of the present invention. DETAILED DESCRIPTION

[0037] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. However, it should be understood that the embodiments are used to explain the present invention but are not used to limit the present invention.

[0038] In order to make the present invention more clear, the method of the present invention is described below with a specific embodiment. Figure 1(a) and 1(b) As shown; the flexible job shop energy-saving batch flow scheduling optimization method provided by the embodiment of the present invention, the method steps are as follows Figure 2 As shown, the following steps are included:

[0039] S1. Multi-objective optimization mathematical model for energy-saving batch flow scheduling in flexible job shops considering processing preparation resources.

[0040] S2. Model solving method based on knowledge-driven batch method and improved multi-objective evolutionary algorithm.

[0041] S3. Post-tooling adjustment strategy based on adjacent processes.

[0042] S4. Numerical experiments.

[0043] S5. Example verification.

[0044] Furthermore, the multi-objective optimization mathematical model for energy-saving batch flow scheduling of flexible job shops considering processing preparation resources in step S1 is:

[0045] Objective function: F = min(TEC, T max ,TC)

[0046] Among them, F is the objective function, TEC, T max , TC are the total energy consumption, completion time and total processing cost of the workshop respectively.

[0047] On the basis of satisfying the basic constraints of batch flow scheduling in flexible job shops, the sub-batch workpieces after batching are approximately regarded as one workpiece; when the workpieces cannot be completely divided equally, the workpiece batch division constraint that the remaining workpieces are processed in the last batch, the preceding constraint that a workpiece can only be processed in the subsequent sequence after its previous sequence process is completed, the processing capacity constraint that the machine tool can only process one process at the same time, the processing number constraint that each process can only be processed once by any machine tool, and the availability of the machine tool at the initial scheduling time and the random arrival constraint of the workpiece.

[0048] In addition, the constraint that the same tooling can only be used for one process at the same time must be met, which can be expressed as:

[0049]

[0050]

[0051] Among them, ST i,j,r Process Q ij Occupied tooling MT r The start time of the

[0052] RT g,h,r Process Q ij Occupied tooling MT r The end time of .

[0053] is a decision variable, if process Q ij and subsequent process Q gh Both require the use of tooling MT r It takes 1 when it is, otherwise it takes 0.

[0054] B is a sufficiently large real number.

[0055] O i,j Q is the processable process ij Tooling MT r gather.

[0056] O g,h Q is the processable process gh Tooling MT r gather.

[0057] n' is the total number of workpieces after all workpieces are divided into batches.

[0058] i,g are artifact indices;

[0059] g,h are process indexes.

[0060] r is the tooling index.

[0061] q i For workpiece J i The number of processes.

[0062] q g For workpiece J g The number of processes.

[0063] On this basis, it is also necessary to satisfy the constraint that all tooling is available at the initial time of scheduling, which can be expressed as:

[0064]

[0065] Yi,j,k,r ∈{0,1},i∈[1,n'],j∈[1,q i ],k∈[1,m],r∈[1,N t ]

[0066] R r ∈{0,1},r∈[1,N t ]

[0067] Among them, k is the machine tool index.

[0068] m is the number of machine tools.

[0069] N t The number of tooling.

[0070] BT i,1,k For workpiece J i The first process is on the machine tool M k The start time of the processing.

[0071] Y i,j,k,r is a decision variable, if the batch process Q ij In machine tool M k Use tooling MT r It takes 1 when it is, otherwise it takes 0.

[0072] R r is a decision variable, if tooling MT r The value is 1 if it is available at the initial scheduling time, otherwise it is 0.

[0073] Furthermore, the specific implementation steps of the model solving method based on the knowledge-driven batch method and the improved multi-objective evolutionary algorithm in step S2 are:

[0074] A two-stage feedback optimization method is adopted to optimize the workpiece batching sub-problem using the knowledge-driven batching method framework, and the machine tool allocation, process sequencing, and tooling allocation sub-problems are optimized based on the proposed improved multi-objective evolutionary algorithm. That is:

[0075] The workpiece batches are divided based on the equal batching method and the variable minimum batch constraint.

[0076] The performance of the workpiece batch partitioning scheme is evaluated using the proposed improved multi-objective evolutionary algorithm.

[0077] The initial batch partitioning scheme is kept unchanged in each iteration, and the local solution space of the problem is searched based on the number of workpiece batches.

[0078] According to the different problem sizes under different batching schemes, the key parameters of the algorithm are dynamically and adaptively adjusted.

[0079] A three-vector encoding method and greedy active decoding method are adopted to realize the bidirectional mapping between the solution space and problem space of machine tool allocation, process sequencing and tooling allocation sub-problems.

[0080] A mutual conversion method between individual positions and encoding vectors is introduced to continuously process the energy-saving batch flow scheduling problem of flexible job shops considering processing preparation resources, providing a basis for its subsequent optimization.

[0081] According to the number of workpiece processes q i Generate the initial workpiece information sequence, and generate 1 to The continuous numbers of form the process number vector, and the continuous values ​​of individual positions are randomly generated in the range of [-α,α], α>0; secondly, the generated continuous values ​​are arranged in descending order according to the size, and the process number vector corresponding to the position information is adjusted at the same time; finally, the real process sorting information is formed through process permutation.

[0082] The position information is converted into machine tool and tooling allocation information. The conversion formula is:

[0083] Among them, m u Q corresponding to a process in the machine tool or tooling allocation ij The position vector, s u Can be used for process Q ij The number of machine tools or tooling used for processing.

[0084] The inverse function of the above formula is used to convert the continuous value of the position vector into the discrete value of the machine tool and tooling allocation plan.

[0085] The continuous value of the position vector is converted into a discrete value of the process sequencing scheme. The conversion formula is:

[0086]

[0087] in, is the real process sorting information vector, r u ∈r,

[0088] In the framework of knowledge-driven batch method, the following formula is used to initialize the moth individuals:

[0089] x u =LB+rand(0,1)×(UB-LB)

[0090] Among them, x u is the moth individual, UB and LB are the upper and lower bounds of the individual component value, which are 1 and -1 respectively.

[0091] Based on the moth flame operator, the three-dimensional solution space of the energy-saving batch flow scheduling problem in a flexible job shop considering processing preparation resources is fully explored.

[0092] The formula for moth search is: u = dis(x u ,f u )×e bt ×cos(2πt)+f u

[0093] Among them, dis(x u ,f u ) indicates moth x u With flames u The Euclidean distance between .

[0094] b is the defined spiral shape constant, which is taken as 0.01.

[0095] t is the path coefficient, and its value range is [-1,1].

[0096] Multiple co-evolution operators based on genetic operators and differential evolution operators promote information interaction among moth individuals. Genetic operators mainly include crossover and mutation. The crossover operation is expressed as:

[0097] w u =0.5×[(1+κ)×x u +(1-κ)×x v ]

[0098] w v =0.5×[(1+κ)×x u +(1-κ)×x v ]

[0099] The mutation operation is expressed as:

[0100]

[0101] The differential evolution operator includes differential mutation and crossover, where the crossover operation is consistent with the genetic operator crossover operation. There are three mutation operators, which are represented as follows:

[0102] DE / rand / 1:W u =x a +F×(x b -x c )

[0103] DE / rand / 2:W u =x a +F×(x b -x c )+F×(xd -x e )

[0104] DE / current-to-rand / 1:

[0105] Among them, W u , and They are different moth offspring individuals.

[0106] x v ,x a , x b , x c , x d and x e They are different moth parent individuals respectively.

[0107] K and F are scaling factors, which are taken as 0.5 here.

[0108] η is the distribution factor.

[0109] △ max is the maximum difference in the values ​​of the individual moth components.

[0110] The selection strategy based on IGD-NS (i.e., inverse generation distance considering non-contributing solutions) index is introduced to obtain the multi-objective non-dominated solution set of the energy-saving batch flow scheduling problem of the flexible job shop considering the processing preparation resources, so as to ensure the continuous optimization ability of the moth population; the calculation formula of IGD-NS index is:

[0111]

[0112] Among them, P' is the set of all non-contributing solutions, P is the set of non-dominated solutions, and P * For the reference set.

[0113] dis(x,y) represents the point y in the solution set P and the reference set P * The Euclidean distance between the points x in .

[0114] dis(x,y') represents the point y' in the solution set P' and the reference set P * The Euclidean distance between the points x in .

[0115] Among them, a non-contributing solution refers to a non-dominated solution that is not the nearest neighbor of any point in the reference set.

[0116] Furthermore, the specific implementation steps of the post-tooling adjustment strategy based on adjacent processes in step S3 are:

[0117] Step 1: Get the current workpiece, machine tool and tooling status information.

[0118] Step 2: Determine the first process to be started among the selected processes. If multiple processes start at the same time, randomly select one of them.

[0119] Step 3: Determine the process and the adjacent process on the selected machine tool Do you select the same tooling for processing? If yes, then eliminate the process and return to step 2, otherwise go to the next step.

[0120] Step 4: Determine the process Whether the tooling used can be used for the process Its process Is it available within the processing cycle? If yes, The tooling used Adjust to be consistent, update the tooling status information and go to the next step; otherwise, eliminate the process and return to step 2.

[0121] Step 5. End the algorithm.

[0122] in, For machine tool M k The jth process of the previous processing, For machine tool M k The j-1th processing step.

[0123] Furthermore, the step S4 includes the following sub-steps:

[0124] In order to verify the effectiveness of the energy-saving batch flow scheduling optimization method for flexible job shops proposed in this invention, the benchmark case 20×MK06 in the literature "Tian ZQ, Jiang XY, Liu WJ, et al. Knowledge-based lot-splitting optimization method for flexible job shops considering energy consumption [J]. IEEE Transactions on Automation Science and Engineering, early access, 2023." was selected for testing. The example contains 10 workpieces, 10 machine tools, the average number of processes for each workpiece is 15, and each process can be processed by an average of 3 machine tools. The average batch of workpieces is 20. The proposed knowledge-driven batching method and the improved multi-objective evolutionary algorithm hybrid method, MOEA / D, NSGA-II, MOPSO, MOEA / PSL and LMOCSO are used to solve the problem. The statistical results of 10 solutions are shown in Table 1. As can be seen from Table 1, for the average value, the proposed knowledge-driven batching method and the improved multi-objective evolutionary algorithm hybrid method are significantly better than the comparison algorithm. The Gantt chart of the optimized scheduling scheme is shown in the figure below. Figure 3 and 4 As shown in the figure, at this time, the batch division scheme of each workpiece is: [12, 10; 12, 17; 12, 8; 12, 9; 14, 19, 17, 10, 12, 12, 14], and the completion time, total energy consumption of the workshop and total processing cost of the workpiece are 4092.9h, 362053kW·h and 104635CNY respectively.

[0125] Table 1 Statistical results of the benchmark case 20×MK06 under different solution algorithms

[0126]

[0127] Furthermore, the example verification in step S5 comes from a production workshop of a machine tool manufacturing enterprise. A workshop of the enterprise has 16 processing equipment such as gantry machining centers, horizontal CNC machine tools, medium-sized CNC machine tools, small CNC machine tools, vertical machining centers, boring and milling machining centers, etc. The processing batches of a certain batch order are 10, 15 and 20 bed, column and slide parts respectively. The number of processes for each part is 22, 15 and 18 respectively, and there are 9 available toolings. The proposed knowledge-driven batch method and the improved multi-objective evolutionary algorithm hybrid method, MOEA / D, NSGA-II, MOPSO, MOEA / PSL and LMOCSO are used to solve the problem. The comparison results of each indicator after 10 solutions are as follows: Figure 5(a) , 5(b) and 5(c). Figure 5(a) , 5(b) As can be seen from Figure 5(c), the proposed knowledge-driven batch method and the improved multi-objective evolutionary algorithm hybrid method are significantly better than the comparison algorithms in all indicators. The Gantt charts of the scheduling schemes optimized by the proposed method and the current one of the enterprise are shown in Figure 5(c). Figure 6 and 7 As shown in the figure, the workpiece completion time, total energy consumption of the workshop and total processing cost of the company's current scheduling plan are 2778.23min, 4035.66kW·min and 60916.9CNY respectively; the workpiece completion time, total energy consumption of the workshop and total processing cost of the scheduling plan optimized based on the proposed method are 1872.3min, 3731.73kW·min and 58666.1CNY respectively. It can be seen that after optimization based on the proposed method, the workpiece completion time is shortened by 32.6%, the total energy consumption of the workshop is reduced by 7.5%, and the total processing cost is reduced by 3.7%.

[0128] The above embodiments are only for illustrating the technical concept and features of the present invention, and the purpose is to enable technicians in this field to understand the content of the present invention and implement it. It cannot be used to limit the protection scope of the present invention. All equivalent changes or modifications made according to the essence of the present invention belong to the protection scope of the present invention.

Claims

1. A multi-objective optimization method for energy-saving batch flow scheduling of flexible job shops considering processing preparation resources, characterized in that: The following steps are involved: S1. Multi-objective optimization mathematical model for energy-saving batch flow scheduling in flexible job shops considering processing preparation resources; S2, model solving method based on knowledge-driven batch method and improved multi-objective evolutionary algorithm; S3. Post-tooling adjustment strategy based on adjacent processes.

2. The multi-objective optimization method for energy-saving batch flow scheduling of flexible job shops considering processing preparation resources as claimed in claim 1 is characterized in that: The multi-objective optimization mathematical model of energy-saving batch flow scheduling in a flexible job shop considering processing preparation resources includes: The optimization goal of the model is to minimize the completion time, total energy consumption and total processing cost. The calculation formula is: F=min(TEC,T max ,TC) Among them, F is the objective function, TEC, T max , TC are the total energy consumption, completion time and total processing cost of the workshop respectively, In addition to meeting the basic constraints of flexible job shop batch flow scheduling, it is also necessary to meet the constraint that the same tool can only be used for processing in one process at the same time, which can be expressed as: Among them, ST i,j,r Process Q ij Occupied tooling MT r The start time of RT g,h,r Process Q ij Occupied tooling MT r End time of is a decision variable, if process Q ij and subsequent process Q gh Both require the use of tooling MT r 1 when , otherwise 0; B is a sufficiently large real number; O i,j The process Q ij Tooling MT r Collection; O g,h The process Q gh Tooling MT r set; n' is the total number of workpieces after all workpieces are divided into batches; i, g are workpiece indexes; g, h are process indexes; r is tooling index; q i For workpiece J i The number of processes; q g For workpiece J g The number of processes, On this basis, it is also necessary to satisfy the constraint that all tooling is available at the initial time of scheduling, which can be expressed as: Y i,j,k,r ∈{0,1},i∈[1,n'],j∈[1,q i ],k∈[1,m],r∈[1,N t ] R r ∈{0,1},r∈[1,N t ] Where k is the machine tool index; m is the number of machine tools; N t BT is the number of tooling; i,1,k For workpiece J i The first process is on the machine tool M k The start time of the previous processing; Y i,j,k,r is a decision variable, if the batch process Q ij In machine tool M k Use tooling MT r When it is 1, otherwise it is 0; R r is a decision variable, if tooling MT r The value is 1 if it is available at the initial scheduling time, otherwise it is 0.

3. The multi-objective optimization method for energy-saving batch flow scheduling of a flexible job shop considering processing preparation resources as described in claim 1 or 2, characterized in that: Model solving methods based on knowledge-driven batch method and improved multi-objective evolutionary algorithm include: A two-stage feedback optimization method is adopted, and the knowledge-driven batch method framework is used to optimize the workpiece batching sub-problem. The machine tool allocation, process sequencing, and tooling allocation sub-problems are optimized based on the proposed improved multi-objective evolutionary algorithm. That is, under the framework of the knowledge-driven batch method, the three-dimensional solution space of the energy-saving batch flow scheduling problem in a flexible job shop considering processing preparation resources is fully explored based on the moth flame operator, and a variety of co-evolution operators based on genetic operators and differential evolution operators promote information interaction between moth individuals.

4. The multi-objective optimization method for energy-saving batch flow scheduling of flexible job shops considering processing preparation resources as claimed in claim 3 is characterized in that: Post-tooling adjustment strategies based on adjacent processes include: Step 1. Obtain the current workpiece, machine tool and tooling status information; Step 2. Determine the first process to start processing among the selected processes. If multiple processes start at the same time, randomly select one of them. Step 3. Determine the process and the adjacent process on the selected machine tool Whether to select the same tooling for processing, if yes, then eliminate the process and return to step 2, otherwise go to the next step; Step 4. Determine the process Whether the tooling used can be used for the process Its process Is it available within the processing cycle? If yes, The tooling used Adjust to be consistent, update the tooling status information and go to the next step; otherwise, eliminate the process and return to step 2; Step 5. End the algorithm, in, For machine tool M k The jth process of the previous processing, For machine tool M k The j-1th processing step.

Citation Information

Patent Citations

  • Multi-variety small-batch multi-target flexible job shop energy consumption optimization scheduling method

    CN112882449A

  • Flexible flow shop combinatorial scheduling rule generation method considering batch processing

    CN113805545A

  • Flexible job shop batch scheduling optimization method and device and electronic equipment

    CN115292950A

  • Flexible job shop batch scheduling method based on multi-objective algorithm

    CN115936342A

  • Green reentrant workshop production scheduling method based on improved moth fire suppression algorithm

    CN116151589A