Weight moving device in power transmission line split conductor operation
By designing a transmission line with adjustable bracket and pulley assembly, the heavy object moving device in the operation of the wire splitting wire is solved, the vibration and fracture problems caused by the ice dancing of the wire is solved, and the rapid movement and installation of the wire is realized, reducing the worker and labor intensity. It improves work efficiency and versatility and is suitable for ultra-ultra-high voltage transmission lines across the province.
Patent Information
- Application Number
- CN202411165399.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-11-15
AI Technical Summary
In the live defect removal task of ultra-high voltage AC-DC transmission lines above 330kV and above, the ice-covered wires cause vibration, aging and fracture. The existing technology requires at least two operators to cooperate to complete the movement and installation of the interphase spacing rods, and lack of The heavy objects commissioning mobile device using wires as rails results in long working time, high labor intensity and low efficiency.
A heavy object moving device in the power transmission line split conductor operation including an adjustable bracket, a pulley bracket, a brake assembly and a lead screw is designed. The conductor direction and multi-split conductor arrangement are realized through a horizontal dual pulley moving device and an adjustable bracket. Fast and safe movement of heavy objects and lift and descend through brake assembly and lead screw.
Shorten the time of shifting between phase-space rods, reduce workers, reduce labor intensity, improve work efficiency, realize universality and large-scale promotion potential throughout the province, improve economic benefits and safe power supply Assure.
Smart Images

Figure CN118970721A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of power transmission line tools, and in particular relates to a heavy object moving device in a power transmission line conductor splitting operation. Background Art
[0002] In the task of live fault elimination of 330kV and above ultra-high (extra) high voltage AC and DC transmission lines, the ice-covered dancing of overhead transmission line conductors has always been a thorny problem that seriously threatens the safe and stable operation of transmission lines. As time goes by, the conductors will vibrate under the action of breeze, and line equipment will age and break under long-term vibration operation. The conductor interphase spacer is an effective measure to prevent conductor dancing and shorten the phase spacing to cause discharge, but the long-term dancing of the conductor will cause the equalizing ring at the lower end of the interphase spacer to wear the conductor, causing the conductor to break. In recent years, severe weather has occurred frequently, and conductor wear and breakage have occurred from time to time, affecting the safe and stable operation of the line. At present, the treatment method for repairing the interphase spacer and equalizing ring worn conductors of the transmission line requires operators A new conductor spacer is installed at a position about 3 meters away from the worn part of the conductor, and then the operator moves the phase-to-phase spacer to the position of the new conductor spacer for installation, and then removes the old conductor spacer and uses pre-twisted wire to repair the conductor. In the previous operation method, at least two operators usually need to cooperate with each other to lift and move the phase-to-phase spacer, which is time-consuming and labor-intensive. In addition, the current domestic power transmission line split conductor moving heavy objects adopts the method of dropping the objects to the ground, moving the pulley position, and then lifting the objects to the working position. There is no heavy object lifting and moving device that uses the conductor as a track. Therefore, it is very necessary to provide a heavy object moving device for the transmission line split conductor operation that shortens the operation time, reduces labor intensity, improves work efficiency, and has good versatility. Summary of the invention
[0003] The purpose of the present invention is to overcome the shortcomings of the prior art and to provide a heavy object moving device for power transmission line conductor splitting operation, which can shorten the operation time, reduce labor intensity, improve work efficiency and has good versatility.
[0004] The objective of the present invention is achieved as follows: a device for moving heavy objects in a power transmission line splitting conductor operation comprises a walking aid, the walking aid comprises an adjustable bracket and a support frame, pulley brackets are arranged on both sides of the left and right sides of the adjustable bracket, mounting sleeves are arranged at the inner upper ends of the pulley brackets corresponding to the adjustable brackets, the mounting sleeves are movably connected to the corresponding adjustable brackets and fixed by first rivets; a connecting seat connected to the support frame is arranged below the pulley brackets; a baffle is arranged on the outer side of the pulley brackets, a pulley assembly located above the conductor is installed on the upper side between the pulley brackets and the baffles, and a brake assembly located below the conductor is installed on the lower side.
[0005] The adjustable bracket is a two-section bracket as a whole, including a first bracket rod and a second bracket rod with the same structure, symmetrically arranged and hollow, and the first bracket rod and the second bracket rod are movably connected via an adjustable connection and positioning assembly.
[0006] The adjustable connection and positioning assembly includes an adjustable rod, wherein the two ends of the adjustable rod are respectively a fixed end and a free end, and the fixed end of the adjustable rod is located inside the second bracket rod, and the free end is inserted into the first bracket rod, and the fixed end is fixedly connected to the second bracket rod by a group of fixing rivets, and a plurality of threaded through holes are arranged in sequence from left to right inside the free end, and a hole matching the threaded through hole is opened at one end of the first bracket rod and is connected to the free end by a positioning bolt.
[0007] The support frame is an “Ω”-shaped structure as a whole, and both ends of the support frame are hollow structures with threaded sleeves arranged inside. The threaded sleeves are installed inside the support frame through second rivets.
[0008] The second rivet is a ∅3 drilled rivet, and the first rivet is a ∅3 copper rivet.
[0009] A compression spring is arranged at the lower part of the pulley bracket, and the compression spring is installed inside the pulley bracket through a spring shaft arranged inside the compression spring. A push rod is arranged at the top of the pulley bracket.
[0010] The pulley assembly includes a group of nylon pulleys, which are installed on the upper side between the pulley bracket and the baffle through a pulley shaft. The nylon pulley is connected to the pulley shaft through a group of bearing gaskets, and one outer end of the pulley shaft is installed on the baffle through a baffle screw.
[0011] The brake assembly comprises a brake bracket, a side sliding sleeve seat is arranged on the upper outer side of the brake bracket, and a threaded base is arranged on the bottom. The brake bracket is slidably connected with the corresponding baffle through the side sliding sleeve seat.
[0012] A brake pad is installed on the upper surface of the brake bracket. The brake pad is connected to the brake bracket through a countersunk screw, and the countersunk screw adopts an M4×12 screw.
[0013] An adjusting bolt matched with the threaded base is arranged inside the threaded base, and one end of the adjusting bolt extending into the support frame is fastened by a top screw, and the top screw adopts an M4 drill top screw.
[0014] The beneficial effects of the present invention are as follows: the present invention is a device for moving heavy objects in the operation of splitting conductors of power transmission lines. During use, the present invention utilizes the conductor direction and the arrangement of multiple split conductors to design the pulley assembly as a horizontal double-pulley moving device. Using the present invention to move on the conductor to install the interphase spacer can shorten the time for shifting the interphase spacer, reduce the number of operators, reduce the intensity of manual labor, increase economic benefits, and improve work efficiency; the present invention can achieve the width adjustment according to the width of the sub-conductor through an adjustable bracket, and lock it after matching and adjusting through an adjusting bolt to ensure stable use, so that the present invention can be applied to the lifting and shifting of various split conductor heavy objects, and can be used in ultra-high voltage transmission lines throughout the province, with the possibility of large-scale promotion; in addition, the present invention is equipped with a lead screw to lift or lower heavy objects, solve practical problems in future operations, improve operation efficiency, reduce the intensity of labor, and improve economic benefits; the present invention has the advantages of shortening operation time, reducing labor intensity, improving work efficiency, and good versatility. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a front view of the present invention.
[0016] Figure 2 It is a top view of the present invention.
[0017] Figure 3 For the present invention Figure 1 A schematic diagram of the enlarged structure in the middle.
[0018] Figure 4 For the present invention Figure 1 Schematic diagram of part of the structure.
[0019] In the figure: 1, adjustable bracket 11, first bracket rod 12, second bracket rod 13, adjustable connection positioning assembly 31, adjustable rod 32, fixed end 33, free end 34, fixing rivet 35, threaded through hole 36, positioning bolt 2, support frame 21, threaded sleeve 22, second rivet 3, pulley bracket 4, mounting sleeve 5, first rivet 6, connecting seat 7, compression spring 8, spring shaft 9, push rod 10, baffle 200, pulley assembly 20, nylon pulley 30, pulley shaft 40, bearing gasket 50, baffle screw 300, brake assembly 60, brake bracket 61, side sliding sleeve seat 62, threaded base 70, brake pad 80, countersunk screw 90, adjusting bolt 100, top wire 400, wire. DETAILED DESCRIPTION
[0020] The present invention will be further described below in conjunction with the accompanying drawings. Example
[0021] like Figure 1-4As shown, a device for moving heavy objects in a power transmission line splitting conductor operation includes a walking aid, and the walking aid includes an adjustable bracket 1 and a support frame 2. Pulley brackets 3 are arranged on both sides of the adjustable bracket 1, and mounting sleeves 4 are arranged at the inner upper end of the pulley bracket 3 corresponding to the adjustable bracket 1. The mounting sleeves 4 are movably connected to the corresponding adjustable bracket 1 by plugging and fixed by a first rivet 5; a connecting seat 6 connected to the support frame 2 is arranged below the pulley bracket 3; a baffle 10 is arranged on the outer side of the pulley bracket 3, and a pulley assembly 200 located above the conductor 400 is installed on the upper side between the pulley bracket 3 and the baffle 10, and a brake assembly 300 located below the conductor 400 is installed on the lower side.
[0022] The adjustable bracket 1 is a two-section bracket as a whole, including a first bracket rod 11 and a second bracket rod 12 with the same structure, symmetrically arranged and hollow. The first bracket rod 11 and the second bracket rod 12 are movably connected via an adjustable connection and positioning assembly 13.
[0023] The adjustable connection positioning assembly 13 includes an adjustable rod 31, the two ends of the adjustable rod 31 are respectively a fixed end 32 and a free end 33, and the fixed end 32 of the adjustable rod 31 is located inside the second bracket rod 12, and the free end 33 is inserted into the first bracket rod 11, the fixed end 32 is fixedly connected to the second bracket rod 12 by a group of fixing rivets 34, and a plurality of threaded through holes 35 are arranged in sequence from left to right inside the free end 33, and one end of the first bracket rod 11 is provided with a hole matching the threaded through hole 35 and is connected to the free end 33 by a positioning bolt 36.
[0024] In this embodiment, the working principle of the adjustable bracket is as follows: since the adjustable bracket is a two-section structure, the first bracket rod and the second bracket rod are connected by an adjustable rod member, and the disconnection distance between the first bracket rod and the second bracket rod is adjusted by changing the length of the free end of the adjustable rod member extending into the first bracket rod, so that the spacing between the first bracket rod and the second bracket rod can be adjusted, thereby realizing that the width can be adjusted according to the width of the sub-conductor through the adjustable bracket. After adjusting the appropriate width, the adjusting bolt is inserted into the threaded through hole matching the hole opened at one end of the first bracket rod and locked to ensure stable and reliable use, so that the present invention can be applied to the lifting and shifting of various split conductor weights on ultra-high voltage transmission lines throughout the province, greatly improving the practicality, applicability and universal performance of the present invention, and has the possibility of large-scale promotion.
[0025] In this embodiment, after the present invention is promoted, it can greatly improve work efficiency, while achieving the goal of saving personnel and rapid operation, ensuring the personal safety of personnel, saving a large amount of direct economic costs such as manpower, money and materials, and at the same time, safe power supply guarantee also brings great economic benefits to the company's production and people's lives, and has great economic benefits and significant social benefits.
[0026] The present invention is a device for moving heavy objects in the operation of splitting conductors of power transmission lines. During use, the present invention utilizes the conductor direction and the arrangement of multiple split conductors to design the pulley assembly 200 as a horizontal double-pulley moving device. Using the present invention to move on the conductor to install the interphase spacer can shorten the time for shifting the interphase spacer, reduce the number of operators, reduce the intensity of manual labor, increase economic benefits, and improve work efficiency. The present invention can achieve the width adjustment according to the width of the sub-conductor through the adjustable bracket 1, and lock it after matching and adjusting through the adjusting bolt 90 to ensure stable use, so that the present invention can be applied to the lifting and shifting of various split conductor heavy objects, and can be used in ultra-high voltage transmission lines throughout the province, with the possibility of large-scale promotion. In addition, the present invention is equipped with a lead screw to lift or lower the heavy object, solve practical problems in future operations, improve operation efficiency, reduce the intensity of labor, and improve economic benefits. The present invention has the advantages of shortening operation time, reducing labor intensity, improving work efficiency, and good versatility. Example
[0027] like Figure 1-4 As shown, a device for moving heavy objects in a power transmission line splitting conductor operation includes a walking aid, and the walking aid includes an adjustable bracket 1 and a support frame 2. Pulley brackets 3 are arranged on both sides of the adjustable bracket 1, and mounting sleeves 4 are arranged at the inner upper end of the pulley bracket 3 corresponding to the adjustable bracket 1. The mounting sleeves 4 are movably connected to the corresponding adjustable bracket 1 by plugging and fixed by a first rivet 5; a connecting seat 6 connected to the support frame 2 is arranged below the pulley bracket 3; a baffle 10 is arranged on the outer side of the pulley bracket 3, and a pulley assembly 200 located above the conductor 400 is installed on the upper side between the pulley bracket 3 and the baffle 10, and a brake assembly 300 located below the conductor 400 is installed on the lower side.
[0028] The support frame 2 is an “Ω”-shaped structure as a whole. Both ends of the support frame 2 are hollow structures and threaded sleeves 21 are provided inside. The threaded sleeves 21 are installed inside the support frame 2 through second rivets 22 .
[0029] The second rivet 22 is a ∅3 drilled rivet, and the first rivet 5 is a ∅3 copper rivet.
[0030] A compression spring 7 is arranged at the lower part of the pulley bracket 3 . The compression spring 7 is installed inside the pulley bracket 3 via a spring shaft 8 arranged inside the compression spring 7 . A push rod 9 is arranged at the top of the pulley bracket 3 .
[0031] In the present embodiment, the working principle of the pulley bracket is as follows: the pulley bracket is connected to the first bracket rod through the installation sleeve and then fixed by the first rivet, the pulley bracket is connected to the support frame through the connecting seat, and the upper and lower spacing between the adjustable bracket and the support frame is adjusted by adjusting the length of the push rod extending into the interior of the pulley bracket, so as to adjust the spacing between the pulley assembly and the brake assembly. When the present invention moves on the conductor, the push rod is adjusted to increase the spacing between the pulley assembly and the brake assembly, so as to ensure that the heavy object (such as the phase spacing rod) can be quickly lifted and moved on the split conductor, which greatly saves the labor of personnel and shortens the operation time; when moving to the corresponding work place, it is only necessary to adjust the push rod so that the spacing between the pulley assembly and the brake assembly is reduced, and the brake assembly is used to closely contact the conductor between the pulley assembly and the brake assembly to achieve the brake locking effect, and the operator can realize the disassembly and installation of the phase spacing rod. Only one operator is needed to complete the disassembly, displacement and other tasks using the device of the present invention, while ensuring the safety and reliability of live working, increasing economic benefits and improving work efficiency.
[0032] In this embodiment, the device of the present invention can increase the practicality and applicability during use, greatly improve work efficiency, and ensure safe power supply, which brings great economic benefits to the company's production and has great economic benefits and significant social benefits.
[0033] The present invention is a device for moving heavy objects in the operation of splitting conductors of power transmission lines. During use, the present invention utilizes the conductor direction and the arrangement of multiple split conductors to design the pulley assembly 200 as a horizontal double-pulley moving device. Using the present invention to move on the conductor to install the interphase spacer can shorten the time for shifting the interphase spacer, reduce the number of operators, reduce the intensity of manual labor, increase economic benefits, and improve work efficiency. The present invention can achieve the width adjustment according to the width of the sub-conductor through the adjustable bracket 1, and lock it after matching and adjusting through the adjusting bolt 90 to ensure stable use, so that the present invention can be applied to the lifting and shifting of various split conductor heavy objects, and can be used in ultra-high voltage transmission lines throughout the province, with the possibility of large-scale promotion. In addition, the present invention is equipped with a lead screw to lift or lower the heavy object, solve practical problems in future operations, improve operation efficiency, reduce the intensity of labor, and improve economic benefits. The present invention has the advantages of shortening operation time, reducing labor intensity, improving work efficiency, and good versatility. Example
[0034] like Figure 1-4As shown, a device for moving heavy objects in a power transmission line splitting conductor operation includes a walking aid, and the walking aid includes an adjustable bracket 1 and a support frame 2. Pulley brackets 3 are arranged on both sides of the adjustable bracket 1, and mounting sleeves 4 are arranged at the inner upper end of the pulley bracket 3 corresponding to the adjustable bracket 1. The mounting sleeves 4 are movably connected to the corresponding adjustable bracket 1 by plugging and fixed by a first rivet 5; a connecting seat 6 connected to the support frame 2 is arranged below the pulley bracket 3; a baffle 10 is arranged on the outer side of the pulley bracket 3, and a pulley assembly 200 located above the conductor 400 is installed on the upper side between the pulley bracket 3 and the baffle 10, and a brake assembly 300 located below the conductor 400 is installed on the lower side.
[0035] The pulley assembly 200 includes a group of nylon pulleys 20, which are installed on the upper side between the pulley bracket 3 and the baffle 10 through a pulley shaft 30. The nylon pulley 20 is connected to the pulley shaft 30 through a group of bearing gaskets 40, and one outer end of the pulley shaft 30 is installed on the baffle 10 through a baffle screw 50.
[0036] In this embodiment, the working principle of the pulley assembly of the present invention is as follows: the present invention utilizes the direction of the conductor and the arrangement of multiple split conductors, and its pulley assembly adopts a set of horizontal double-pulley moving devices, which can achieve fast, reliable and smooth movement on the conductor, allowing operators to quickly lift and move heavy objects (such as interphase spacer bars) through the device of the present invention, shortening the time for shifting the interphase spacer bars and improving work efficiency; in addition, the pulley assembly adopts a nylon pulley, which does not damage the conductor while ensuring fast and reliable movement on the conductor, thereby reducing wear on the conductor.
[0037] The brake assembly 300 includes a brake bracket 60 , a side sliding sleeve seat 61 is arranged on the upper outer side of the brake bracket 60 , and a threaded base 62 is arranged on the bottom. The brake bracket 60 is slidably connected to the corresponding baffle 10 through the side sliding sleeve seat 61 .
[0038] In this embodiment, the brake assembly of the present invention is slidably connected to the corresponding baffle through a side sliding sleeve seat. When the pulley bracket adjusts the upper and lower spacing of the adjustable bracket and the support frame, it is convenient to cooperate with its adjustment process, so that the brake assembly can rise and fall smoothly, and realize the change of the brake assembly to the locking state (tight contact with the wire) and the separation state (not contacting the wire) of the wire.
[0039] A brake pad 70 is installed on the upper surface of the brake bracket 60 , and the brake pad 70 is connected to the brake bracket 60 via a countersunk screw 80 .
[0040] In this embodiment, the brake assembly of the present invention achieves a braking effect through a brake pad. While providing an effective braking effect, it also provides protection for the wires to a certain extent, avoids damage to the wires, and increases the service life of the wires.
[0041] An adjusting bolt 90 threadably matched with the threaded base 62 is disposed inside the threaded base 62 , and one end of the adjusting bolt 90 extending into the support frame 2 is fastened by a top screw 100 .
[0042] In this embodiment, the adjusting bolt of the present invention is threadably matched with the threaded base. By rotating the adjusting bolt, the threaded base can be driven to move on the adjusting bolt. When the distance between the first support rod and the second support rod is adjusted by the adjustable connection positioning assembly, it is convenient to cooperate with the adjustment process, so that the brake assembly and the baffle and other structures can be smoothly moved left and right, thereby realizing the overall adjustment of the present invention according to the sub-conductor width.
[0043] In this embodiment, the present invention has the following advantages: ① At present, there is no device for moving heavy objects in the split conductor operation of power transmission lines in China. The device of the present invention is proposed for the first time in China. It solves the problem of moving heavy objects in the split conductor operation of power transmission lines by dropping the objects on the ground, moving the pulley position, and then lifting and transferring the objects to the working position; ② The present invention is a moving device that can be installed on the conductor, and at the same time, a mechanical screw can be added and used to lift and lower heavy objects over short distances; ③ The device of the present invention can reduce one high-altitude operator and quickly move the position of heavy objects; ④ The present invention effectively improves the reliable operation of the line, reduces the intensity of manual labor, and will bring huge economic benefits and social effects to power companies.
[0044] The present invention is a device for moving heavy objects in the operation of splitting conductors of power transmission lines. During use, the present invention utilizes the conductor direction and the arrangement of multiple split conductors to design the pulley assembly 200 as a horizontal double-pulley moving device. Using the present invention to move on the conductor to install the interphase spacer can shorten the time for shifting the interphase spacer, reduce the number of operators, reduce the intensity of manual labor, increase economic benefits, and improve work efficiency. The present invention can achieve the width adjustment according to the width of the sub-conductor through the adjustable bracket 1, and lock it after matching and adjusting through the adjusting bolt 90 to ensure stable use, so that the present invention can be applied to the lifting and shifting of various split conductor heavy objects, and can be used in ultra-high voltage transmission lines throughout the province, with the possibility of large-scale promotion. In addition, the present invention is equipped with a lead screw to lift or lower the heavy object, solve practical problems in future operations, improve operation efficiency, reduce the intensity of labor, and improve economic benefits. The present invention has the advantages of shortening operation time, reducing labor intensity, improving work efficiency, and good versatility.
Claims
1. A device for moving heavy objects during the splitting of power transmission lines, which includes a walking aid, Features: The walking aid includes an adjustable bracket and a support frame, pulley brackets are arranged on the left and right sides of the adjustable bracket, and mounting sleeves are arranged at the inner upper ends of the pulley brackets corresponding to the adjustable brackets, and the mounting sleeves are movably connected with the corresponding adjustable brackets and fixed by first rivets; a connecting seat connected to the support frame is arranged under the pulley bracket; a baffle is arranged on the outer side of the pulley bracket, and a pulley assembly located above the wire is installed on the upper side between the pulley bracket and the baffle, and a brake assembly located below the wire is installed on the lower side.
2. The heavy object moving device in the power transmission line conductor splitting operation as claimed in claim 1, Features: The adjustable bracket is a two-section bracket as a whole, including a first bracket rod and a second bracket rod with the same structure, symmetrically arranged and hollow, and the first bracket rod and the second bracket rod are movably connected via an adjustable connection and positioning assembly.
3. The heavy object moving device in the power transmission line conductor splitting operation as claimed in claim 2, Features: The adjustable connection and positioning assembly includes an adjustable rod, wherein the two ends of the adjustable rod are respectively a fixed end and a free end, and the fixed end of the adjustable rod is located inside the second bracket rod, and the free end is inserted into the first bracket rod, and the fixed end is fixedly connected to the second bracket rod by a group of fixing rivets, and a plurality of threaded through holes are arranged in sequence from left to right inside the free end, and a hole matching the threaded through hole is opened at one end of the first bracket rod and is connected to the free end by a positioning bolt.
4. The heavy object moving device in the power transmission line conductor splitting operation as claimed in claim 3, Features: The support frame is an "Ω"-shaped structure as a whole, and both ends of the support frame are hollow structures with threaded sleeves arranged inside. The threaded sleeves are installed inside the support frame through second rivets.
5. The heavy object moving device in the power transmission line conductor splitting operation as claimed in claim 4, Features: The second rivet is a ∅3 drilled rivet, and the first rivet is a ∅3 copper rivet.
6. The heavy object moving device in the power transmission line conductor splitting operation as claimed in claim 4, Features: A compression spring is arranged at the lower part of the pulley bracket, and the compression spring is installed inside the pulley bracket through a spring shaft arranged inside the compression spring. A push rod is arranged at the top of the pulley bracket.
7. The heavy object moving device in the power transmission line conductor splitting operation as claimed in claim 6, Features: The pulley assembly includes a group of nylon pulleys, which are installed on the upper side between the pulley bracket and the baffle through a pulley shaft, and the nylon pulley is connected to the pulley shaft through a group of bearing gaskets, and one outer end of the pulley shaft is installed on the baffle through a baffle screw.
8. The heavy object moving device in the power transmission line conductor splitting operation as claimed in claim 7, Features: The brake assembly comprises a brake bracket, a side sliding sleeve seat is arranged on the upper outer side of the brake bracket, and a threaded base is arranged on the bottom. The brake bracket is slidably connected with the corresponding baffle through the side sliding sleeve seat.
9. The heavy object moving device in the power transmission line conductor splitting operation as claimed in claim 8, Features: A brake pad is installed on the upper surface of the brake bracket, and the brake pad is connected to the brake bracket through a countersunk screw.
10. The heavy object moving device in the power transmission line conductor splitting operation as claimed in claim 9, Features: An adjusting bolt which is threadably matched with the threaded base is arranged inside the threaded base, and one end of the adjusting bolt extending into the support frame is fastened by a top screw.