Engineering actual measurement method and system, terminal and storage medium
Obtaining images through drones and identifying defects or errors in building materials and buildings using preset models, the problem of material quality in engineering construction is solved, the quality of the project is improved, and the risk of equipment damage is reduced through self-charging of drones.
Patent Information
- Application Number
- CN202411078303.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2024-11-22
AI Technical Summary
During the construction process, material stacking is susceptible to external environment and causes defects, which in turn reduces the quality of the material and affects the quality of the project.
The drone control method is used to obtain images of building materials and buildings, and the defect or error location of materials and buildings are identified through preset detection routes and defect identification models, and the staff are notified to make rectifications through warning devices.
Effectively identify and screen out defective materials and building errors, improve the quality of project construction, reduce the situation where the material quality does not meet the standards, and reduce the risk of equipment damage through self-charging of drones.
Smart Images

Figure CN119000686A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of engineering detection, and in particular to an engineering actual measurement method, system, terminal and storage medium. Background Art
[0002] Actual measurement of engineering projects refers to the on-site measurement method of quantifiable allowable deviations of engineering quality using measuring instruments and tools during the construction process of a building project.
[0003] In the prior art, materials used in engineering construction are generally piled together first, and materials are taken when used. Deviations in engineering construction are generally detected by tools such as rulers, levels, and laser scanners, so that deviations can be corrected in time when they occur, thereby improving the quality of engineering construction.
[0004] When materials are stacked, they are easily affected by the external environment, which may cause defects in the materials and reduce the quality of the materials, which in turn leads to the quality of the projects built with the materials not meeting the standards. Summary of the invention
[0005] In order to improve the quality of engineering construction and reduce the situation where material quality does not meet the standards, the present invention provides an engineering actual measurement method, system, terminal and storage medium.
[0006] In a first aspect, the present invention provides an engineering actual measurement method, which adopts the following technical solution:
[0007] An engineering actual measurement method, comprising:
[0008] Obtaining a stacking image of stacked building materials;
[0009] Matching the inspection route from the preset inspection route planning model according to the stacked image;
[0010] Controlling a preset drone to fly along a detection route according to a preset drone control method, and controlling a camera device preset on the drone to acquire a building material image of the building material;
[0011] Determine whether the building materials have defects based on the building material image using a preset defect recognition model;
[0012] When there are defects in the building materials, the defect location is determined from the preset location determination model based on the building material image;
[0013] The preset defect warning device is controlled according to the defect position to warn the staff.
[0014] By adopting the above technical solution, by observing the appearance of the material, it is possible to identify whether the material has defects, and alert the staff when defects exist, so that the defective materials can be screened out, thereby reducing the situation of material quality not meeting the standards and improving the quality of engineering construction.
[0015] Optionally, also include:
[0016] Obtain construction images of engineering buildings;
[0017] Matching the measurement route from the preset inspection route planning model according to the construction image;
[0018] Control the preset UAV to fly along the measurement route according to the preset UAV control method, and control the camera device preset on the UAV to obtain the building image of the engineering building;
[0019] Matching the construction error value from a preset error recognition model according to the building image and the preset three-dimensional construction information;
[0020] When the construction error value exceeds the preset construction error range, the error position is determined from a preset position determination model according to the building image;
[0021] The preset error warning device is controlled according to the error position to warn the staff.
[0022] By adopting the above technical solution, the degree of error in the construction project can be identified by observing the appearance of the building, and the staff can be warned when the error is too large, so that the error can be corrected in time, thereby improving the quality of the construction project.
[0023] Optionally, the drone control method includes:
[0024] Get the drone power of the drone;
[0025] When the drone battery falls into a preset low battery range, the drone position of the drone is obtained;
[0026] Matching a charging route from a preset flight route planning model based on the drone's location and the preset charging location;
[0027] Control the preset drone to fly to the charging location for charging according to the charging route.
[0028] By adopting the above technical solution, when the battery of the drone is low, the drone is controlled to go to the charging location for charging on its own, thereby reducing the situation where the drone runs out of power during use and causes it to fall, thereby causing damage to the equipment or injury to personnel.
[0029] Optionally, the drone control method further includes:
[0030] When the drone reaches the charging position, the construction position is determined from the preset position determination model according to the construction image;
[0031] According to the construction position and the charging position, a measurement angle for making a camera device preset on the drone face the construction position is calculated from a preset camera angle model, and a camera direction of the camera device is obtained;
[0032] Match the drone turning angle from the preset drone turning angle calculation model according to the camera orientation and measurement angle;
[0033] Control the preset drone rotation according to the drone rotation angle to make the drone face the construction location;
[0034] Matching the camera angle from a preset camera angle calculation model according to the camera orientation and the measurement angle;
[0035] The camera device preset on the drone is controlled to rotate according to the camera angle so that the camera device faces the construction location.
[0036] By adopting the above technical solution, when the drone is charging, the camera on the drone is pointed towards the construction site, so that the error degree of the engineering construction can be measured while charging, thereby improving the continuity of drone detection, so that errors can be detected in time when they occur.
[0037] Optionally, the drone control method further includes:
[0038] When the power level of the drone falls into a preset low power range, the observation position is matched from a preset observation position matching model according to the construction image, and the device position of the charging device is obtained;
[0039] According to the observation position and the device position, the adjustment direction and the adjustment distance of the charging device moving to the observation position are matched from a preset position adjustment model;
[0040] Controlling the moving device preset on the charging device to move to the observation position according to the adjustment direction and the adjustment distance;
[0041] Matching the lift distance from a preset lift distance identification model according to the observation position and the device position;
[0042] The lifting device preset on the charging device is controlled according to the lifting distance to lift the charging device to the observation position.
[0043] By adopting the above technical solution, when the drone needs to be charged, an observation position that is convenient for observing the building is matched according to the image of the building, and the charging device is transported to the observation position through the moving device and the lifting device.
[0044] Optionally, the drone control method further includes:
[0045] When the battery level of the drone falls into a preset low battery range, an observation image of the observation location is obtained;
[0046] According to the observation image, a preset UAV parking space recognition model is used to determine whether there is space for UAV parking at the observation location;
[0047] When there is no space for the drone to park at the observation position, the camera position is matched from a preset camera position matching model according to the observation image;
[0048] Matching the camera angle from a preset camera angle model according to the camera position and the construction position;
[0049] According to the camera angle and camera position, the preset independent camera is fixed at the camera position through the preset camera fixing device, and the drone is controlled to go to the preset charging position for charging.
[0050] By adopting the above technical solution, when the observation position is not suitable for the drone to park and charge, an independent camera with an independent power supply can be fixed at the shooting position by the drone to replace the drone to inspect the engineering building.
[0051] Optionally, the drone control method further includes:
[0052] When the drone battery level falls into a preset low battery range, the drone usage time is matched from a preset usage time judgment model according to the drone battery level;
[0053] Match the flight time from the preset flight time judgment model according to the charging route and the preset UAV flight speed;
[0054] The difference between the usage time and the flight time is calculated and defined as the camera time;
[0055] Matching the construction time required for completing the current construction part from a preset construction time judgment model according to the construction image and the construction three-dimensional information;
[0056] Calculate the difference between the shooting time and the construction time and define it as the surplus time;
[0057] When the surplus time falls within the preset stay time range, the preset UAV is controlled to continue acquiring building images.
[0058] By adopting the above technical solution, when the battery of the drone is low, the time the drone can still inspect the engineering building is determined according to the battery level of the drone, and the time required to complete the building is estimated based on the image. When the remaining battery of the drone is sufficient to support the drone to detect the completion of the building, the drone is controlled to continue the inspection, thereby improving the continuity of the drone inspection.
[0059] In the second aspect, the present application provides an engineering measurement system, which adopts the following technical solutions:
[0060] An engineering actual measurement system, comprising:
[0061] The acquisition module is used to acquire stacking images, building material images, construction images, drone power, drone position, camera orientation, device position, and observation images;
[0062] A memory for storing a program of a control method of any one of the engineering actual measurement methods;
[0063] The program in the processor memory can be loaded and executed by the processor to implement any control method of an engineering actual measurement method.
[0064] In a third aspect, the present application provides a computer storage medium capable of storing corresponding programs, which is convenient for implementing an engineering actual measurement method, and adopts the following technical solution:
[0065] A computer-readable storage medium stores a computer program that can be loaded by a processor and execute any engineering measurement method.
[0066] In a fourth aspect, the present application provides an intelligent terminal, which adopts the following technical solution:
[0067] An intelligent terminal comprises a memory and a processor, wherein the memory stores a computer program which can be loaded by the processor and execute any engineering actual measurement method.
[0068] By adopting the above technical solution, by observing the appearance of the material, it is possible to identify whether the material has defects, and alert the staff when defects exist, so that the defective materials can be screened out, thereby reducing the situation of material quality not meeting the standards and improving the quality of engineering construction.
[0069] In summary, the present application includes at least one of the following beneficial technical effects:
[0070] 1. By observing the appearance of the material, it can be identified whether the material has defects, and the staff can be alerted when there are defects, so that the defective materials can be screened out, thereby reducing the situation of substandard material quality and improving the quality of engineering construction;
[0071] 2. By observing the appearance of the building, the error degree of the project construction can be identified, and the staff can be warned when the error is too large, so that the error can be corrected in time, thereby improving the quality of the project construction;
[0072] 3. When the drone battery is low, control the drone to go to the charging location to charge by itself, thereby reducing the possibility of the drone running out of power and falling during use, which may cause damage to the equipment or injury to personnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0073] Figure 1 It is a process of engineering actual measurement method. Figure 1 .
[0074] Figure 2 It is a process of engineering actual measurement method. Figure 2 .
[0075] Figure 3 This is the process of drone control method Figure 1 .
[0076] Figure 4 This is the process of drone control method Figure 2 .
[0077] Figure 5 This is the process of drone control method Figure 3 .
[0078] Figure 6 This is the process of drone control method Figure 4 .
[0079] Figure 7 This is the process of drone control method Figure 5 .
[0080] Figure 8 It is a module diagram of an engineering measurement system. DETAILED DESCRIPTION
[0081] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the following Figure 1-8 It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0082] Reference Figure 1 The present application embodiment discloses an engineering measurement method, comprising the following steps:
[0083] Step 100: Acquire a stacking image of stacked building materials.
[0084] The stacking image refers to a picture of a material stacking location, which shows the positional relationship of materials in the material stacking location. The stacking image can be obtained through a camera. The method for obtaining the stacking image is selected by the staff according to actual conditions and will not be elaborated here.
[0085] Step 101: Matching a detection route from a preset detection route planning model according to the stacked image.
[0086] The detection route planning model refers to a neural network model obtained through sample training in advance. The detection route planning model can match the image of the material stacking with a flight route that enables the drone to detect objects in all directions in the image. The detection route is the result obtained by the detection route planning model from matching the stacking image.
[0087] Step 102: controlling a preset drone to fly along a detection route according to a preset drone control method, and controlling a camera device preset on the drone to acquire a building material image of the building material.
[0088] Building material images refer to pictures of building materials, which are used to show the appearance of building materials. Camera devices refer to equipment used to obtain building material images. Camera devices are set on drones. The control method of the camera device is selected by the staff according to actual conditions, which will not be elaborated here.
[0089] Step 103: judging whether the building material has defects from a preset defect recognition model according to the building material image.
[0090] Defects refer to defects on the appearance of building materials that damage the quality of building materials. The defect recognition model refers to a neural network model obtained through sample training in advance. The defect recognition model can determine whether there are defects in the image.
[0091] Step 104: When there are defects in the building materials, the defect position is determined from a preset position determination model according to the building material image.
[0092] Defects in building materials indicate that the quality of the building materials is low, which may lead to a decrease in the quality of the buildings built with the building materials. The position judgment model refers to a neural network model obtained through sample training in advance. The position judgment model can identify the location of the image from the image. The defect position is the result obtained by the position judgment model from the building material image.
[0093] Step 105: Control a preset defect warning device to warn the staff according to the defect position.
[0094] The defect warning device refers to a device that warns the staff through flashing lights, beeps, etc. The defect warning device warns the staff and sends the defect location to the staff, so that the staff can replace the defective building materials in time. The defect warning device and its use method are selected by the staff according to the actual situation and will not be described in detail here.
[0095] Reference Figure 2 , an engineering actual measurement method also includes the following steps:
[0096] Step 106: Acquire a construction image of the engineering building.
[0097] The construction image refers to a picture of a construction site in progress. The positional relationship of the construction site is displayed through the construction image. The construction image can be obtained through a camera. The method for obtaining the construction image is selected by the staff according to the actual situation and will not be elaborated here.
[0098] Step 107: Matching a measurement route from a preset detection route planning model according to the construction image.
[0099] The measurement route is the UAV flight route identified by the detection route planning model from the construction image, which enables the UAV to detect all directions of the construction site.
[0100] Step 108: Control the preset drone to fly along the measurement route according to the preset drone control method, and control the camera device preset on the drone to obtain the building image of the engineering building.
[0101] Architectural images refer to pictures of the construction site from all directions. Architectural images are used to show the dimensions of the completed building parts.
[0102] Step 109: Matching the construction error value from the preset error recognition model according to the building image and the preset three-dimensional construction information.
[0103] The construction three-dimensional information refers to the three-dimensional information of the building to be constructed. The construction three-dimensional information is input by the staff according to the actual situation and will not be described in detail here. The error recognition model refers to a neural network model obtained through sample training in advance. The error recognition model can be used to calculate the error value between the building in the picture and the building in the three-dimensional information. The construction error value refers to the error value between the size of the building in the building image and the building in the construction three-dimensional information calculated by the error recognition model.
[0104] Step 110: When the construction error value exceeds a preset construction error range, the error position is determined from a preset position determination model according to the building image.
[0105] The construction error range refers to the range of construction error values that are allowed to exist. The construction error range is set by the staff according to the actual situation and will not be elaborated here. If the construction error value exceeds the construction error range, it means that the size error between the completed building and the expected building is large and needs to be corrected.
[0106] Step 111: Control a preset error warning device to warn the staff according to the error position.
[0107] The error warning device refers to a device that warns the staff by flashing light, beeping, etc. The error warning device warns the staff and sends the error position to the staff so that the staff can correct the error in time. The error warning device and its use method are selected by the staff according to the actual situation and will not be described in detail here.
[0108] Reference Figure 3 , the UAV control method includes the following steps:
[0109] Step 200: Obtain the drone power level of the drone.
[0110] The drone power refers to the real-time remaining power of the drone. The drone power can be obtained through a power detection device installed on the drone. The method for obtaining the drone power is set by the staff according to the actual situation and will not be elaborated here.
[0111] Step 201: When the power of the drone falls into a preset low power range, the drone position of the drone is obtained.
[0112] The low battery range refers to the range of power in which the drone has low power. The low battery range is set by the staff according to the actual situation and will not be described here. When the drone falls into the low battery range, it means that the drone has low power and needs to be charged.
[0113] The drone position refers to the coordinate position of the drone. The drone position can be obtained through a positioning device installed on the drone. The method for obtaining the drone position is set by the staff according to the actual situation and will not be elaborated here.
[0114] Step 202: Match a charging route from a preset flight route planning model according to the drone position and the preset charging position.
[0115] The flight route planning model refers to a neural network model obtained through sample training in advance. The flight route planning model can plan the flight route of the drone from one coordinate to another. The charging position refers to the coordinate position of a fixed charging device for charging the drone. The charging device generally uses the direction of wireless charging to charge the drone. The charging device is selected by the staff according to the actual situation and will not be described here. The charging route is the flight route of the drone from the drone position to the charging position planned by the flight route planning model.
[0116] Step 203: Control the preset UAV to fly to the charging location for charging according to the charging route.
[0117] Control the drone to go to the charging location for charging.
[0118] Reference Figure 4 , the UAV control method also includes the following steps:
[0119] Step 204: When the drone arrives at the charging position, the construction position is determined from a preset position determination model according to the construction image.
[0120] The drone arriving at the charging position indicates that the drone is in the charging state. The construction position is the coordinate position of the engineering construction identified by the position judgment model from the construction image.
[0121] Step 205: Calculate the measurement angle for making the camera device preset on the drone face the construction position from the preset camera angle model according to the construction position and the charging position, and obtain the camera direction of the camera device.
[0122] The camera angle model refers to a neural network model obtained through sample training in advance. The camera angle model can calculate the angle of the camera when it faces from one coordinate to another. The measured angle is the angle of the camera from the charging position to the construction position calculated by the camera angle model. The camera orientation refers to the orientation of the camera device on the drone. The camera orientation can be obtained by obtaining a picture of the camera device through the camera, and then the camera orientation can be identified from the picture. The method for obtaining the camera orientation is selected by the staff according to the actual situation, and will not be elaborated here.
[0123] Step 206: Match the drone turning angle from a preset drone turning angle calculation model according to the camera orientation and the measurement angle.
[0124] The drone turning angle calculation model refers to a neural network model obtained through sample training in advance. The drone turning angle calculation model can calculate the angle required to turn the drone toward the construction location, wherein the side of the drone with the camera device is defined as the front, and the direction of the front of the drone is defined as the direction of the drone. The drone turning angle is the turning angle result calculated by the drone turning angle calculation model.
[0125] Step 207: Control the preset rotation of the drone according to the rotation angle of the drone so that the drone faces the construction location.
[0126] The drone is controlled to face the construction location, and the camera device on the drone is directed toward the construction location by rotating the drone in the horizontal direction.
[0127] Step 208: Match the camera angle from a preset camera angle calculation model according to the camera orientation and the measurement angle.
[0128] The camera angle calculation model refers to a neural network model obtained through sample training in advance. The camera angle calculation model can calculate the angle that the camera device needs to rotate to align with the construction position. The camera angle is the result calculated by the camera angle calculation model.
[0129] Step 209: Control the camera device preset on the drone to rotate according to the camera angle so that the camera device faces the construction location.
[0130] The camera device is adjusted in a vertical direction by rotating itself, so that the camera device is aligned with the construction position, and the error degree of the engineering construction is detected by the camera device while charging.
[0131] Reference Figure 5 , the UAV control method also includes the following steps:
[0132] Step 300: When the power level of the drone falls into a preset low power range, the observation position is matched from a preset observation position matching model according to the construction image, and the device position of the charging device is obtained.
[0133] The observation position matching model refers to a neural network model obtained through sample training in advance. The observation position matching model can match the position of the construction site of the complete observation project according to the position relationship shown on the construction image. The observation position is the result obtained by matching the observation position matching model. The device position refers to the coordinate position of the non-fixed charging device. The device position can be obtained by the positioning device set on the charging device. The method for obtaining the device position is selected by the staff according to the actual situation and will not be elaborated here.
[0134] Step 301: Matching the adjustment direction and adjustment distance of the charging device to the observation position from a preset position adjustment model according to the observation position and the device position.
[0135] The position adjustment model refers to a neural network model obtained through sample training in advance. The position adjustment model can match the direction and distance required to move the charging device from the device position to the projection position of the observation position, where the projection position of the observation position refers to the coordinate position obtained by vertically projecting the observation position on the ground. The adjustment direction and adjustment distance are the results obtained by matching the position adjustment model.
[0136] Step 302: Control the mobile device preset on the charging device to move to the observation position according to the adjustment direction and the adjustment distance.
[0137] The mobile device refers to a device used to carry the charging device so as to adjust the position of the charging device on the ground. The mobile device and its use method are selected by the staff according to actual conditions and will not be elaborated here.
[0138] Step 303: Match the lifting distance from a preset lifting distance recognition model according to the observation position and the device position.
[0139] The lift distance recognition model refers to a neural network model obtained through sample training in advance. The lift distance recognition model can match the distance required to be lifted from the projection position of the observation position to the observation position. The lift distance is the result obtained by matching the lift distance recognition model.
[0140] Step 304: Control a lifting device preset on the charging device to lift the charging device to an observation position according to the lifting distance.
[0141] The lifting device refers to a device used to lift the charging device to the observation position so that the drone can be charged at the observation position. The charging device can also be lifted by building a high platform. The lifting device and its use method are selected by the staff according to actual conditions and will not be elaborated here.
[0142] The charging device is moved to the observation position through the cooperation of the lifting device and the moving device, so that the UAV can better observe the error of the construction position while charging.
[0143] Reference Figure 6 , the UAV control method also includes the following steps:
[0144] Step 305: When the battery level of the drone falls into a preset low battery range, an observation image of the observation location is acquired.
[0145] The observation image refers to a picture of the observation location. The observation image can be obtained through a camera device installed on a drone. The method for obtaining the observation image is selected by the staff according to the actual situation and will not be elaborated here.
[0146] Step 306: Determine whether there is space for parking the drone at the observation location based on the observation image from a preset drone parking space recognition model.
[0147] The drone parking space recognition model refers to a neural network model obtained through sample training in advance. The drone parking space recognition model can recognize whether there is space in the picture for the drone to park and charge.
[0148] Step 307: When there is no space for the drone to park at the observation position, the camera position is matched from a preset camera position matching model according to the observation image.
[0149] If there is no space for the drone to park at the observation location, it means that the drone cannot be charged at the observation location. The camera position matching model refers to a neural network model obtained through sample training in advance. The camera position matching model can match the location for the independent camera to be installed from the observation image. The independent camera refers to a camera that is equipped with an independent power supply and can be set up separately on the drone.
[0150] Step 308: Match the camera angle from a preset camera angle model according to the camera position and the construction position.
[0151] The camera angle is the angle of the camera matched by the camera angle model when it is aligned from the camera position to the construction position.
[0152] Step 309: Fix the preset independent camera at the shooting position through the preset camera fixing device according to the shooting angle and the shooting position, and control the drone to go to the preset charging position for charging.
[0153] The camera fixing device refers to a device used to fix the independent camera at the shooting position. The camera fixing device can adopt a structure that is easy to disassemble and assemble, such as a suction cup. The camera fixing device and its use method are selected by the staff according to the actual situation and are not described in detail here. The independent camera is fixed at the shooting position by the camera fixing device, so that the error degree of the construction position can be continuously observed through the independent camera while the drone flies to the charging position for charging.
[0154] Reference Figure 7 , the UAV control method also includes the following steps:
[0155] Step 400: When the power level of the drone falls into a preset low power range, the usage time of the drone is matched from a preset usage time judgment model according to the power level of the drone.
[0156] The usage time judgment model refers to a neural network model obtained through sample training in advance. The usage time judgment model can judge the remaining working time of the drone based on the remaining power of the drone. The usage time is the result obtained by matching the usage time judgment model.
[0157] Step 401: Match the flight time from a preset flight time judgment model according to the charging route and the preset UAV flight speed.
[0158] The flight speed of a drone refers to the average speed of a drone's normal flight. The flight speed of a drone is selected by the staff based on the actual situation and will not be elaborated here. The flight time judgment model refers to a neural network model obtained through sample training in advance. The flight time judgment model can match the flight route of the drone with the flight speed of the drone to obtain the time required for the drone to fly along the flight route. The flight time is the time required for the drone to fly to the charging location for charging at the flight speed of the drone according to the charging route, as obtained by matching the flight time judgment model.
[0159] Step 402: Calculate the difference between the use time and the flight time, and define it as the shooting time.
[0160] The shooting time refers to the time during which the UAV can actually detect the error range of the construction site. The shooting time can be obtained by calculating the difference between the use time and the flight time.
[0161] Step 403: Match the construction time required for completing the current construction part from a preset construction time judgment model according to the construction image and the construction 3D information.
[0162] The construction time judgment model refers to a neural network model obtained through sample training in advance. The construction time judgment model can match the length of time required to complete the construction of the building according to the construction status of the building in the picture and the estimated construction status of the current part in the three-dimensional information. During the construction of the project, the entire building will be divided into small parts for partial construction. The division status is recorded in the three-dimensional construction information. The estimated construction status of the current part can be obtained through the three-dimensional information. The construction time is the result obtained by matching the construction time judgment model.
[0163] Step 404: Calculate the difference between the shooting time and the construction time, and define it as the surplus time.
[0164] The surplus time refers to the remaining time after the shooting time exceeds the construction time. The surplus time can be obtained by calculating the difference between the shooting time and the construction time.
[0165] Step 405: When the surplus time falls within the preset stay time range, the preset UAV is controlled to continue acquiring the building image.
[0166] The temporary stay time range refers to the range of spare time that the drone is allowed to stay temporarily. The temporary stay time range is selected by the staff according to the actual situation and will not be described in detail here. If the spare time falls within the temporary stay time range, it means that the drone's power is sufficient to support the drone's work until the current part of the building is completed. At this time, it can be temporarily stopped and continued to charge after the current part of the project is completed.
[0167] Based on the same inventive concept, an embodiment of the present invention provides an engineering actual measurement system, including:
[0168] An acquisition module 500 is used to acquire a stacking image, a building material image, a construction image, a drone power level, a drone position, a camera orientation, a device position, and an observation image;
[0169] A memory 501 is used to store a program of a control method of any one of the engineering actual measurement methods;
[0170] Processor 502, the program in the memory can be loaded and executed by the processor and realize any one of the control methods of engineering actual measurement method
[0171] Those skilled in the art can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional modules is used as an example. In actual applications, the above-mentioned functions can be assigned to different functional modules as needed, that is, the internal structure of the device is divided into different functional modules to complete all or part of the functions described above. The specific working process of the system, device and unit described above can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.
[0172] An embodiment of the present invention provides a computer-readable storage medium storing a computer program that can be loaded by a processor and execute an engineering actual measurement method.
[0173] Computer storage media include, for example, various media that can store program codes, such as USB flash drives, mobile hard disks, read-only memories (ROM), random access memories (RAM), magnetic disks or optical disks.
[0174] Based on the same inventive concept, an embodiment of the present invention provides an intelligent terminal, including a memory and a processor, wherein the memory stores a computer program that can be loaded by the processor and execute an engineering actual measurement method.
[0175] Those skilled in the art can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional modules is used as an example. In actual applications, the above-mentioned functions can be assigned to different functional modules as needed, that is, the internal structure of the device is divided into different functional modules to complete all or part of the functions described above. The specific working process of the system, device and unit described above can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.
[0176] The above is only a preferred embodiment of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, some improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.
Claims
1. A method for actual measurement of engineering, characterized in that: include: Obtaining a stacking image of the stacked building materials; Matching the inspection route from the preset inspection route planning model according to the stacked image; Controlling a preset drone to fly along a detection route according to a preset drone control method, and controlling a camera device preset on the drone to acquire a building material image of the building material; Determine whether the building materials have defects based on the building material image using a preset defect recognition model; When there are defects in the building materials, the defect location is determined from the preset location determination model based on the building material image; The preset defect warning device is controlled according to the defect position to warn the staff.
2. The engineering actual measurement method according to claim 1 is characterized in that: Also includes: Obtain construction images of engineering buildings; Matching the measurement route from the preset inspection route planning model according to the construction image; Control the preset UAV to fly along the measurement route according to the preset UAV control method, and control the camera device preset on the UAV to obtain the building image of the engineering building; Matching the construction error value from a preset error recognition model according to the building image and the preset construction three-dimensional information; When the construction error value exceeds the preset construction error range, the error position is determined from a preset position determination model according to the building image; According to the error position, the preset error warning device is controlled to warn the staff.
3. The engineering actual measurement method according to claim 2 is characterized in that: The drone control method comprises: Get the drone power of the drone; When the drone battery falls into a preset low battery range, the drone position of the drone is obtained; Matching a charging route from a preset flight route planning model based on the drone's location and the preset charging location; Control the preset drone to fly to the charging location for charging according to the charging route.
4. The engineering actual measurement method according to claim 3 is characterized in that: The drone control method further includes: When the drone reaches the charging position, the construction position is determined from the preset position determination model according to the construction image; According to the construction position and the charging position, a measurement angle for making a camera device preset on the drone face the construction position is calculated from a preset camera angle model, and a camera direction of the camera device is obtained; Match the drone turning angle from the preset drone turning angle calculation model according to the camera orientation and measurement angle; Control the preset drone rotation according to the drone rotation angle to make the drone face the construction location; Matching the camera angle from a preset camera angle calculation model according to the camera orientation and the measurement angle; The camera device preset on the drone is controlled to rotate according to the camera angle so that the camera device faces the construction location.
5. The engineering actual measurement method according to claim 3 is characterized in that: The drone control method further includes: When the power level of the drone falls into a preset low power range, the observation position is matched from a preset observation position matching model according to the construction image, and the device position of the charging device is obtained; According to the observation position and the device position, the adjustment direction and the adjustment distance of the charging device moving to the observation position are matched from a preset position adjustment model; Controlling the moving device preset on the charging device to move to the observation position according to the adjustment direction and the adjustment distance; Matching the lift distance from a preset lift distance identification model according to the observation position and the device position; The lifting device preset on the charging device is controlled according to the lifting distance to lift the charging device to the observation position.
6. The engineering actual measurement method according to claim 5 is characterized in that: The drone control method further includes: When the battery level of the drone falls into a preset low battery range, an observation image of the observation location is obtained; According to the observation image, a preset UAV parking space recognition model is used to determine whether there is space for UAV parking at the observation location; When there is no space for the drone to park at the observation position, the camera position is matched from a preset camera position matching model according to the observation image; Matching the camera angle from a preset camera angle model according to the camera position and the construction position; According to the camera angle and camera position, the preset independent camera is fixed at the camera position through the preset camera fixing device, and the drone is controlled to go to the preset charging position for charging.
7. The engineering actual measurement method according to claim 3 is characterized in that: The drone control method further includes: When the drone battery level falls into a preset low battery range, the drone usage time is matched from a preset usage time judgment model according to the drone battery level; Match the flight time from the preset flight time judgment model according to the charging route and the preset UAV flight speed; The difference between the usage time and the flight time is calculated and defined as the camera time; Matching the construction time required for completing the current construction part from a preset construction time judgment model according to the construction image and the construction three-dimensional information; Calculate the difference between the shooting time and the construction time and define it as the surplus time; When the surplus time falls within the preset stay time range, the preset UAV is controlled to continue acquiring building images.
8. An engineering measurement system, characterized in that: include: The acquisition module is used to acquire stacking images, building material images, construction images, drone power, drone position, camera orientation, device position, and observation images; A memory for storing a program of a control method of an engineering actual measurement method according to any one of claims 1 to 7; The program in the memory can be loaded and executed by the processor to implement a control method for an engineering actual measurement method as claimed in any one of claims 1 to 7.
9. A computer-readable storage medium, characterized in that: The computer program is stored which can be loaded by a processor and execute the engineering measurement method according to any one of claims 1 to 7.
10. An intelligent terminal, characterized in that: The method comprises a memory and a processor, wherein the memory stores a computer program that can be loaded by the processor and executes any one of the engineering measurement methods as claimed in claims 1 to 7.