Incremental launching construction method for large-span steel box girder bridge crossing riverway

By using intelligent overhead pushing systems and efficient step overhead pushing equipment in the construction of large-span bridges across the river, the construction accuracy and safety issues are solved, and efficient and safe installation of steel box girders is achieved, reducing construction costs and river channels are carried out. The impact of navigation.

CN119041315APending Publication Date: 2024-11-29CHINA RAILWAY 14TH BUREAU GRP 1ST ENG CO LTD +1
View PDF 0 Cites 9 Cited by

Patent Information

Application Number
CN202411418661.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-12
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In the construction of large-span bridges across rivers, the existing technology has problems such as long construction cycles, large impact on river navigation, high construction costs and increased construction difficulties under complex geological and hydrological conditions, especially in ensuring construction safety and efficiency There are challenges in the aspects.

Method used

The over-pushing construction method of steel box girder bridges across the river is adopted, including the installation of efficient step-by-pushing equipment in the intelligent overpushing system after the temporary support is erected, and the position of the steel box girder is monitored through multi-stage overpushing control and intelligent monitoring system. Offset ensures the installation accuracy within 10mm, and uses efficient step-by-step pushing equipment and intelligent monitoring system for precise positioning and adjustment.

Benefits of technology

It significantly improves the installation accuracy of steel box girders, reduces the cost of post-adjustment caused by installation errors, ensures the stability and safety of construction, improves construction quality and efficiency, and reduces the impact on river navigation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041315A_ABST
    Figure CN119041315A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of bridge construction, and discloses a river-crossing large-span steel box girder bridge incremental launching construction method which comprises the following steps: step 1, before hoisting a steel box girder, erecting a temporary bracket near a pier stud; 2, after the temporary support is erected, the steel box girder is hoisted; 3, pushing the steel box girder by adopting efficient walking type pushing equipment, monitoring whether the elevation of the girder deck, the middle line of the bridge and the longitudinal position of the steel box girder deviate or not by utilizing an intelligent monitoring system, and modifying if the deviation occurs; 4, after the steel box girders are pushed to the corresponding positions, the steel box girders are fixed in a butt joint mode; according to the method, through the multi-stage pushing control technology and the self-adaptive temporary supporting system, the mounting precision of the steel box girder is remarkably improved, and the later adjustment cost caused by mounting errors is reduced; the safety risk of river channel crossing incremental launching construction is effectively reduced, and the problems existing in the prior art are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridge construction, and in particular relates to a method for jacking construction of a large-span steel box girder bridge across a river. Background Art

[0002] In the field of bridge construction, the construction of long-span bridges across rivers often faces a series of challenges, such as complex construction environment, difficult underwater operations, and high construction safety risks. Traditional construction methods, such as cast-in-place method and prefabricated assembly method, have problems such as long construction period, great impact on river navigation, and high construction cost when crossing wider rivers. Especially in environments with complex geological conditions and harsh hydrological conditions, the construction difficulty and cost increase exponentially. Therefore, seeking a construction method that can effectively solve the above problems has become a research hotspot in the field of bridge construction.

[0003] In recent years, with the continuous development of material science and construction technology, steel box girders, as an important type of bridge structure, have been widely used in bridge construction due to their advantages such as light weight, high strength and fast construction speed. Especially in the construction of bridges across large spans and complex terrains, steel box girders have become the preferred structural form due to their unique advantages. However, how to efficiently and safely complete the construction of large-span steel box girders in the complex environment of crossing rivers is still a technical problem that needs to be solved urgently. As an advanced bridge construction technology, top-pushing construction has been widely used in bridge construction because of its advantages such as reducing the impact on navigation under the bridge, reducing construction costs and improving construction efficiency. Especially in the construction of large-span bridges across natural obstacles such as rivers and valleys, top-pushing construction technology shows its unique advantages. However, the existing top-pushing construction methods still have some technical difficulties in the construction of bridges across large spans and complex hydrological conditions, such as the selection of top-pushing equipment, the control of the top-pushing process, and the stability of the bridge structure. These all need to be studied and optimized in depth to meet the construction needs under different working conditions.

[0004] Therefore, researching and developing a new method for jacking construction of large-span steel box girder bridges across rivers has important theoretical significance and practical application value for improving bridge construction efficiency, reducing construction costs, and ensuring construction safety. Summary of the invention

[0005] 1. Technical issues to be solved

[0006] In view of the shortcomings of the prior art, the present invention provides a method for jacking construction of a large-span steel box girder bridge across a river, which is capable of controlling the installation accuracy of the large-span steel box girder bridge within 10mm, thereby effectively reducing the safety risks of jacking construction across the river and solving the problems existing in the prior art.

[0007] (II) Technical solution

[0008] In order to achieve the above-mentioned purpose of facilitating the jacking construction of a large-span steel box girder bridge across a river and ensuring the installation accuracy of the large-span steel box girder bridge, the present invention provides the following technical solutions:

[0009] A method for jacking construction of a large-span steel box girder bridge across a river, comprising:

[0010] Step 1: Before hoisting the steel box girder, set up temporary supports on both sides of the pier column near the river bank;

[0011] Step 2: After the temporary support is erected, install the efficient walking jacking equipment in the intelligent jacking system on the temporary support and piers. After the installation is completed, hoist the steel box girder;

[0012] Step 3: Push the steel box girder and use the intelligent monitoring system in the intelligent pushing system to monitor whether the beam deck elevation, bridge centerline and longitudinal position of the steel box girder are offset. If offset occurs, make modifications;

[0013] Step 4: After the steel box girder is pushed up to meet the design requirements, the steel box girder is dropped;

[0014] Step 5: After the steel box girder is dropped to the designed position, butt-join and fix the steel box girder.

[0015] As a preferred embodiment of the present invention, the distance between two adjacent temporary supports is the same as the distance between two adjacent piers; each lateral column steel pipe of the temporary support and the distribution beam on the top of the steel pipe are correspondingly arranged on the left and right sides of the steel box beam.

[0016] As a preferred embodiment of the present invention, the process of hoisting the steel box girder in step 2 includes:

[0017] Step 2.1: Arrange the crane between the temporary support and the pier;

[0018] Step 2.2: Use a crane to lift the steel box girder, or a truck to lift the steel box girder. Move the boom to move the steel box girder to a position 0.2m above the height of the beam adjustment support at the top of the temporary support, and adjust the horizontal and vertical positions of the steel box girder.

[0019] Step 2.3: Move the steel box girder toward the high-efficiency walking jacking equipment in the intelligent jacking system, adjust the position of the steel box girder according to the longitudinal and transverse axes, and after the longitudinal and transverse alignment of the steel box girder with the positioning lines, place the steel box girder on the beam drop adjustment support.

[0020] As a preferred embodiment of the present invention, when hoisting the steel box girder, the deviation between the steel box girder and the positioning line is within 5 mm in the longitudinal direction of the bridge and within 5 mm in the transverse direction of the bridge.

[0021] As a preferred embodiment of the present invention, the high-efficiency walking-type jacking equipment includes a vertical jacking cylinder, a lateral adjustment cylinder, a base, a longitudinal jacking cylinder, a first sliding base and a second sliding base; the base is arranged on the upper end platform of the temporary support and the pier; the first sliding base is slidably arranged on the upper side of the sliding rod on the base, and is connected to the lateral adjustment cylinder; the second sliding base is slidably arranged on the first sliding base, and is connected to the longitudinal jacking cylinder; the vertical jacking cylinder is arranged on the second sliding base, and a connecting steel plate is arranged at the end of the piston rod of the vertical jacking cylinder for use in conjunction with the perforated steel plate arranged on the lower side of the steel box girder.

[0022] As a preferred embodiment of the present invention, the beam-dropping adjustment support is symmetrically arranged on the upper end platform of the temporary bracket and the pier column outside the high-efficiency walking-type jacking equipment.

[0023] As a preferred embodiment of the present invention, the intelligent monitoring system in the intelligent jacking system includes a monitoring prism, a radar ranging sensor, an ultra-wide-angle camera, an electronic total station and a computer; the monitoring prism is symmetrically arranged at the four corners of the front end of the steel box girder, the radar ranging sensor is arranged on both sides of the front end of the steel box girder, the ultra-wide-angle camera is arranged at the front end center of the steel box girder, and the electronic total station is arranged on one side of the steel box girder for monitoring the deflection of the steel box girder; and the monitoring prism, radar ranging sensor, ultra-wide-angle camera and electronic total station are all connected to the computer.

[0024] As a preferred embodiment of the present invention, the process of jacking the steel box girder in step 3 and step 4 includes:

[0025] Step 4.1: First, conduct a trial push, keep the steel box girder lifted by about 10cm, and hold the load for no less than 30 minutes to check the actual state of the push process;

[0026] Step 4.2: After the trial jacking, the formal jacking is carried out. First, the vertical jacking cylinder is opened, and the vertical jacking cylinder is used to support the steel box girder to separate from the beam drop adjustment support, and the steel box girder is lifted;

[0027] Step 4.3: Then start the longitudinal push cylinder to move the steel box girder and the upper first sliding base forward as a whole to the beam drop adjustment support position. At the same time, use the longitudinal push cylinder to push the second sliding base for deviation correction until the horizontal push cylinder completes a stroke. Repeat the above operation continuously to make the steel box girder reach the specified beam drop position.

[0028] As a preferred embodiment of the present invention, the process of dropping the steel box girder in step 4 includes:

[0029] Step 4.4: After the steel box girder is dropped onto the pier, the position of the steel box girder is fine-tuned using the efficient walking jacking device on the pier according to the readings of the intelligent monitoring system so that its position meets the design requirements. After the adjustment is completed, the steel box girder is lifted up again using the efficient walking jacking device on the temporary support;

[0030] Step 4.5: Finally, open the jacking cylinder and lower the steel box girder to the designed elevation by alternately supporting and disassembling the lower support system of the jack and the tray of the beam adjustment support.

[0031] As a preferred embodiment of the present invention, when the steel box girders are butt-jointed and fixed in step 5, segmented bolted joints are installed, and channel steels are used to connect the top plate interfaces of adjacent steel box girders.

[0032] (III) Beneficial effects

[0033] Compared with the prior art, the present invention provides a method for jacking construction of a large-span steel box girder bridge across a river, which has the following beneficial effects:

[0034] 1. This construction method uses multi-level jacking control technology and efficient walking jacking equipment to carry out jacking construction on the steel box girder, and monitors the offset of the steel box girder and corrects it during the positioning process, which significantly improves the installation accuracy of the steel box girder and reduces the cost of adjusting the position of the steel box girder later due to installation errors.

[0035] 2. This method combines multiple factors such as the bridge span, the weight of the steel box girder, the hydrological conditions of the river during the construction process, selects and designs high-capacity, high-precision jacking equipment, and optimizes the structure of the jacking equipment to ensure the stability and safety of the steel box girder during the jacking process, thereby improving the construction quality and box girder installation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 It is a schematic diagram of the initial jacking process of the large-span steel box girder bridge across the river of the present invention;

[0037] Figure 2 It is a schematic diagram of the large-span steel box girder bridge across the river after the jacking is completed according to the present invention;

[0038] Figure 3 It is a schematic diagram of a large-span steel box girder bridge across a river after the beam is dropped according to the present invention;

[0039] Figure 4 It is a schematic diagram of the structure of the temporary support of the present invention;

[0040] Figure 5 It is a structural schematic diagram of the efficient walking type pushing device of the present invention;

[0041] Figure 6It is a front view of the tray of the present invention;

[0042] Figure 7 A top view of the tray of the present invention;

[0043] Figure 8 This is a front view of adjacent trays after being connected according to the present invention;

[0044] Fig. 9 A bottom view of the steel box girder of the present invention;

[0045] Fig.10 It is a structural schematic diagram of the perforated steel plate of the present invention;

[0046] Fig.11 This is a layout diagram of the intelligent monitoring system of the present invention;

[0047] Fig.12 It is a flow chart of the butt jointing of the steel box girder of the present invention;

[0048] Fig.13 The present invention is a process flow chart of the method for jacking construction of a large-span steel box girder bridge across a river.

[0049] In the figure: 1. vertical lifting cylinder; 2. steel box beam; 21. web; 22. partition; 23. rib; 24. bottom bolt; 25. prism; 26. distance sensor; 27. ultra-wide-angle camera; 3. beam adjustment support; 31. tray; 32. flange; 33. connecting bolt; 4. longitudinal jacking cylinder; 5. base; 6. temporary support; 61. column steel pipe; 62. diagonal brace; 63. distribution beam; 64. base; 65. support steel pipe; 66. cross brace; 7. perforated steel plate; 8. lower support system of jack; 9. pier column; 10. longitudinal jacking cylinder; 11. first sliding base; 12. second sliding base; 13. slide rod. DETAILED DESCRIPTION

[0050] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0051] Example 1: Please refer to Figure 1-Figure 13 , the present invention provides a technical solution:

[0052] A method for jacking construction of a large-span steel box girder bridge across a river, comprising:

[0053] The steel box girder 2 of a certain project uses a steel-concrete composite box girder with a main span of 60+90+60m. The steel box girder 2 is pushed to the top of pier 9 and dropped. Nearly one-third of the main span of the steel-concrete composite box girder bridge is in the river. Take a push cycle as an example:

[0054] Step 1. Set up temporary supports 6 on both sides of the pier 9 near the river bank.

[0055] like Figure 1 , Figure 2 , Figure 3 and Figure 4 As shown, temporary brackets 6 are set up on both sides of the pier 9 near the river bank, and the distance between two adjacent temporary brackets 6 is the same as the distance between two adjacent piers 9. In the temporary brackets 6, each horizontal column steel pipe 61 and the top distribution beam 63 of the steel pipe are correspondingly arranged on the left and right sides of the steel box beam 2; each group of temporary brackets 6 is composed of 4 column steel pipes 61 of φ325×8mm.

[0056] During installation, two groups of temporary supports 6 on the short mileage side are arranged with a width of 3m in the longitudinal direction and 2.4m in the transverse direction, and the base 64 adopts a 4000×3500×800mm concrete foundation; one group on the long mileage side is arranged with a width of 1.5m in the longitudinal direction and 2.4m in the transverse direction as a pile foundation; an HW300×300 steel is placed side by side in the transverse direction at the upper end of the column steel pipe 61 as a distribution beam 63, and a φ325×8mm steel pipe is used as a supporting steel pipe 65 at the intersection of the web 21 and the partition 22 of the steel box beam 2 on the distribution beam 63 to adjust the elevation of the steel box beam 2.

[0057] The horizontal brace 66 between the column steel pipes 61 is made of 3m 20 channel steel, the diagonal brace 62 is made of ∠100×10 angle steel, and the steel material used for the temporary support 6 is Q235B.

[0058] Among them, after the temporary support 6 is erected, during the hoisting and pushing process of the steel box girder 2, a BX120-50AA resistance strain gauge is pasted on the temporary support 6 at 0.2m from the bottom, and the Donghua DH5922 dynamic data acquisition instrument is used to collect data to monitor the stress and strain of the temporary support 6 in real time, and compare it with the allowable stress of the temporary support 6 to monitor the bearing capacity and stress changes of the temporary support 6.

[0059] Step 2: Install the high-efficiency walking jacking equipment in the intelligent jacking system on the temporary support 6 and the pier 9, and after the installation of the high-efficiency walking jacking equipment is completed, hoist the steel box girder 2

[0060] Step 2.1: Use a 300t crane to hoist the steel box girder 2, use a car crane to lift the steel box girder 2, slowly move the boom, move the steel box girder 2 to a height of about 0.2m above the beam adjustment support 3 of the temporary support 6 at the top of the temporary support 6, adjust the transverse and longitudinal positions of the steel box girder 2, move the steel box girder 2 toward the high-efficiency walking-type jacking equipment, adjust the position of the steel box girder 2 according to the longitudinal and transverse axes, and after the steel box girder 2 is aligned with the positioning line in the longitudinal and transverse directions, slowly put the steel box girder 2 on the beam adjustment support 3, and when dropping the steel box girder 2, ensure that the deviation between the box girder 2 and the positioning line is controlled within: 5mm in the longitudinal bridge direction and 5mm in the transverse bridge direction;

[0061] Among them, the high-efficiency walking-type pushing equipment mainly includes a vertical lifting cylinder 1, a transverse adjustment cylinder 4, a base 5, a longitudinal pushing cylinder 10, a first sliding base 11 and a second sliding base 12. The base 5 is fixedly installed on the upper platform of the temporary bracket 6. The first sliding base 11 is slidably installed above the sliding rod 13 on the base 5 and is connected to the transverse adjustment cylinder 4. The transverse adjustment cylinder 4 is installed on the outside of the base 5. The first sliding base 11 is driven to slide left and right on the base 5 by the transverse adjustment cylinder 4. The second sliding base 12 is slidably installed on the first sliding base 11 and is connected to the longitudinal pushing cylinder 10. The longitudinal pushing cylinder 10 pushes the second sliding base 12 to slide on the first sliding base 11. The vertical lifting cylinder 1 is fixedly installed on the second sliding base 12, and a connecting steel plate is provided at the end of the piston rod of the vertical lifting cylinder 1 to cooperate with the steel box girder to support the steel box girder. Specifically, when in use, the hydraulic drive of the oil valve is controlled by computer intelligent frequency conversion (the vertical jacking cylinder 1, the lateral adjustment cylinder 4 and the longitudinal jacking cylinder 10 are all hydraulic cylinders) to achieve various combinations and sequences of actions to meet the construction requirements for jacking and correction of the steel box girder 2. The jacking tonnage of the vertical jacking cylinder 1 is: 200 tons, double-acting, displacement sensor (measuring displacement); the jacking tonnage of the lateral adjustment cylinder 4 is: 100 tons, double-acting (hydraulic self-locking), displacement sensor (measuring displacement); the jacking tonnage of the longitudinal jacking cylinder 10 (correction jack) is: 50 tons, double-acting, displacement sensor.

[0062] Step 3: After the box girder 2 is hoisted on the temporary support 6, the steel box girder 2 is pushed, and the intelligent monitoring system in the intelligent pushing system is used to monitor whether the beam bridge deck elevation, bridge centerline offset and longitudinal position of the steel box girder 2 are offset, and if offset occurs, it is modified; after the box girder 2 is hoisted in place, the bridge surface elevation is continuously measured by trigonometric height measurement method; and then the monitoring prism 25, the radar ranging sensor 26, and the ultra-wide-angle camera 27 are used to accurately measure the bridge centerline offset and longitudinal position of the steel box girder 2;

[0063] During installation, four monitoring prisms 25 are symmetrically arranged at the four corners of the front end of the steel box beam 2 ( Fig.10The deflection is calculated by monitoring the elevation of both ends and the middle of the bridge using an electronic total station throughout the entire process. Before and during each jacking construction, the surveying personnel shall use the trigonometric height measurement method to observe the elevation changes of the measuring points and compare them with the calculated values.

[0064] At the same time, GUL15 mine-use intrinsically safe radar distance measuring sensors 26 ( Fig.11 E, F) and connect to the computer, install AHD ultra-wide-angle camera 27 (CA-309) at the top center of the front end of steel box girder 2 ( Fig.11 (G) is connected to a computer to remotely observe whether the center line of the bridge is offset and the longitudinal position changes. If the measurement results meet the design requirements, the steel box girder 2 is pushed and dropped to prepare for the installation of the next section of the steel box girder 2. If there is a deviation in the center line of the entire beam section, the pushing construction should be suspended, and the deviation of the steel box girder 2 should be corrected using the efficient walking pushing equipment through step 4.

[0065] Step 4: After the steel box girder is pushed up to meet the design requirements, the steel box girder 2 is dropped.

[0066] Use the vertical lifting cylinder 1 to lift the steel box girder 2 slightly away from the beam drop adjustment support 3 (which is symmetrically arranged at four positions on the upper platform of the temporary support 6 and the pier 9 to support the lower side of the steel box girder 2), and fine-tune the steel box girder 2 under the monitoring of the measuring instrument (specifically achieved by the lateral adjustment cylinder 4 and the longitudinal jacking cylinder 10) until the installation position meets the design requirements;

[0067] Adjust the height of the beam adjustment support 3 so that it is close to the bottom of the steel box girder 2. The jack is lowered to transfer the force to the beam adjustment support 3, thus completing the precise positioning of the steel box girder 2.

[0068] The process of adjusting the position of the steel box girder 2 by pushing and pushing includes: installing the base 5, the first sliding base 11 and the second sliding base 12, arranging the vertical lifting cylinder 1 of the walking-type pushing on the second sliding base 12, and arranging the longitudinal pushing cylinder 4 and the base 5 on the supporting steel pipe 65 composed of five 32 I-beams at the top of each temporary support 6. The elevation is adjusted by using the beam adjustment support 3. The structure of the beam adjustment support 3 is as shown in FIG. Figure 5 , Figure 6 and Figure 7 As shown, a vertical lifting cylinder 1 for walking-type pushing is arranged on each set of temporary supports 6 and piers 9;

[0069] Step 4.1: First, conduct a trial push, keep the steel box girder 2 lifted by about 10 cm, and hold the load for no less than 30 minutes to check the actual state of the push process;

[0070] Step 4.2: After the trial jacking, the formal jacking is carried out. First, the vertical jacking cylinder 1 is opened, and the vertical jacking cylinder 1 of the walking jacking is used to support the steel box girder 2 to separate from the beam drop adjustment support 3, and the steel box girder 2 is lifted;

[0071] Step 4.3: Then start the longitudinal push cylinder 4 to move the steel box girder 2 and the upper first sliding base 11 forward as a whole to the beam drop adjustment support position, and at the same time use the longitudinal push cylinder 10 to push the second sliding base 12 to correct the deviation until the horizontal push cylinder completes a stroke, and repeat the above operation continuously, so that the steel box girder 2 reaches the specified beam drop position;

[0072] Step 4.4: After the steel box girder 2 is dropped onto the pier 9, the position of the steel box girder 2 is fine-tuned by using the efficient walking-type jacking equipment on the pier 9 so that its position meets the use requirements. After the adjustment is completed, the steel box girder 2 is lifted up again by using the efficient walking-type jacking equipment on the temporary support 6, and the efficient walking-type jacking equipment on the pier 9 is removed;

[0073] Step 4.5: Finally, the lifting cylinder 1 on the temporary support 6 is opened, and the steel box girder 2 is dropped to the designed elevation through the cylinder lower support system 8 and the tray 31 of the beam drop adjustment support 3, and the beam drop operation is completed, so that the steel box girder 2 is seated on the pier 9, and the beam drop process of the steel box girder 2 is completed;

[0074] In the beam dropping process of step 4.5, when completing an adjustment process, first remove a section of the jack lower support system 8, then lift the jack, remove a section of the pallet 31 and then return the jack to make the steel box beam 2 fall on the next section of the pallet 31; repeat this step until the steel box beam falls to the design elevation;

[0075] Among them, during the process of jacking, fine-tuning and beam dropping, the placement position of the vertical jacking cylinder 1 must be straight with the jacking line of the steel box beam 2. During the jacking process, it is necessary to prevent the top supporting structure of the temporary pier from being emptied and causing stress concentration, which will cause the beam body of the steel box beam 2 to be damaged;

[0076] Step 5: Butt-joint fixing of steel box girder 2

[0077] After the steel box girder is pushed to the designed position, the steel box girder is lowered to the designed elevation by alternately supporting and disassembling the lower part of the jack and the pallet. High-strength bolts are used to connect the steel box girders. The installation process is as follows: Fig.10 shown.

[0078] Install the segmented bolted joints, use 10 channel steel to connect the top plate interfaces of the adjacent steel box girders 2, and arrange the crane between the temporary support 6 and the pier 9. The maximum boom length is 30.5m, the lifting radius is 10m, and the rated maximum lifting capacity is 79t.

[0079] Through the above construction technology and monitoring method described in this embodiment, the installation accuracy of the steel-concrete composite box girder bridge during the top-pushing construction is within 10mm, the maximum stress of the temporary support and the maximum stress of the bottom of the steel box girder are 45MPa and 69MPa respectively, the maximum offset of the temporary support is 2‰, and the cantilever deflection of the steel box girder is within 10mm. The safety and stability of the structural system are effectively guaranteed to meet the construction requirements.

[0080] Preferably, Fig.10 As shown, a perforated steel plate 7 is welded and installed at the bottom of the steel box girder 2. The perforated steel plate 7 is provided with holes with a diameter of 40 mm and a thickness of 3 cm, which are used in conjunction with the bottom bolts 24 of the steel box girder 2. This can not only protect the bottom bolts of the steel box girder 2, but also prevent local pressure damage to the bottom of the steel box girder 2 during the jacking process.

[0081] Preferably, Figure 5 , Figure 6 and Figure 7 As shown, the beam-dropping adjustment support 3 includes a plurality of trays 31, the trays 31 are flange parts, and flange plates 32 are provided on the upper and lower sides of the trays 31, and screw holes are provided on the flange plates 32 for use with connecting bolts 33. When in use, the connecting bolts 33 are used to connect two adjacent trays 31 to form a beam-dropping adjustment support 3 that can play a stable supporting role, and the beam-dropping adjustment support 3 is used to support the steel box girder 2.

[0082] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.

[0083] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A method for jacking construction of a large-span steel box girder bridge across a river, characterized in that: include: Step 1: Before hoisting the steel box girder (2), temporary supports (6) are set up on both sides of the pier (9) on the side close to the river bank; Step 2: After the temporary support (6) is erected, a high-efficiency walking-type jacking device is installed on the temporary support (6) and the pier (9). After the installation is completed, the steel box girder (2) is hoisted; Step 3: Use an efficient walking-type pushing device to push the steel box girder (2), and use an intelligent monitoring system to monitor whether the beam deck elevation, bridge centerline and longitudinal position of the steel box girder (2) are offset, and make corrections if offset occurs; Step 4: After the steel box girder is pushed up to meet the design requirements, the steel box girder (2) is dropped; Step 5: After the steel box girder (2) is dropped to the designed position, the steel box girder (2) is butt-jointed and fixed.

2. The method for jacking construction of a large-span steel box girder bridge across a river as claimed in claim 1, characterized in that: The distance between two adjacent temporary supports (6) is the same as the distance between two adjacent piers (9); each horizontal column steel pipe (61) of the temporary support (6) and the distribution beam (63) on the top of the steel pipe are correspondingly arranged on the left and right sides of the steel box beam (2).

3. The method for jacking construction of a large-span steel box girder bridge across a river as claimed in claim 1, characterized in that: The process of hoisting the steel box girder (2) described in step 2 includes: Step 2.1: Arrange the crane between the temporary support (6) and the pier (9); Step 2.2: Use a crane to lift the steel box girder (2), use a truck crane to lift the steel box girder (2), move the boom to move the steel box girder (2) to a position 0.2 m above the height of the beam adjustment support (3) at the top of the temporary support (6), and adjust the horizontal and vertical positions of the steel box girder (2); Step 2.3: Move the steel box girder (2) toward the high-efficiency walking-type jacking equipment, adjust the position of the steel box girder (2) according to the longitudinal and transverse axes, and after the steel box girder (2) is aligned with the positioning lines longitudinally and transversely, place the steel box girder (2) on the beam drop adjustment support (3).

4. The method for jacking construction of a large-span steel box girder bridge across a river as claimed in claim 3, characterized in that: When the steel box girder (2) is hoisted, the deviation between the steel box girder (2) and the positioning line is within 5 mm in the longitudinal direction of the bridge and within 5 mm in the transverse direction of the bridge.

5. The method for jacking construction of a large-span steel box girder bridge across a river as claimed in claim 1, characterized in that: The high-efficiency walking-type jacking equipment comprises a vertical jacking cylinder (1), a transverse adjustment cylinder (4), a base (5), a longitudinal jacking cylinder (10), a first sliding base (11) and a second sliding base (12); the base (5) is arranged on the upper end platform of the temporary support (6) and the pier (9); the first sliding base (11) is slidably arranged on the upper side of the sliding rod (13) on the base (5) and is connected to the transverse adjustment cylinder (4); the second sliding base (12) is slidably arranged on the first sliding base (11) and is connected to the longitudinal jacking cylinder (10); the vertical jacking cylinder (1) is arranged on the second sliding base (12), and a connecting steel plate is arranged at the end of the piston rod of the vertical jacking cylinder (1) for use in conjunction with a perforated steel plate (7) arranged on the lower side of the steel box girder (2).

6. The method for jacking construction of a large-span steel box girder bridge across a river as claimed in claim 3, characterized in that: The beam drop adjustment support (3) is symmetrically arranged on the upper end platform of the temporary support (6) and the pier column (9) outside the high-efficiency walking type jacking equipment.

7. The method for jacking construction of a large-span steel box girder bridge across a river as claimed in claim 3, characterized in that: The intelligent monitoring system comprises a monitoring prism (25), a radar ranging sensor (26), an ultra-wide angle camera (27), an electronic total station and a computer; the monitoring prism (25) is symmetrically arranged at the four corners of the front end of the steel box girder (2), the radar ranging sensor (26) is arranged at both sides of the front end of the steel box girder (2), the ultra-wide angle camera (27) is arranged at the center of the front end of the steel box girder (2), and the electronic total station is arranged on one side of the steel box girder (2) for monitoring the deflection of the steel box girder (2); and the monitoring prism (25), the radar ranging sensor (26), the ultra-wide angle camera (27) and the electronic total station are all connected to the computer.

8. The method for jacking construction of a large-span steel box girder bridge across a river as claimed in claim 3, characterized in that: The process of pushing the steel box girder (2) in step 3 and step 4 includes: Step 4.1: First, conduct a trial push, keep the steel box girder (2) lifted by about 10 cm, and hold the load for no less than 30 minutes to check the actual state of the push process; Step 4.2: After the trial jacking, the formal jacking is carried out. First, the vertical jacking cylinder (1) is opened, and the vertical jacking cylinder (1) is used to support the steel box girder (2) to separate from the beam drop adjustment support (3), and the steel box girder (2) is lifted; Step 4.3: Then start the longitudinal push cylinder (4) to move the steel box girder (2) and the upper first sliding base (11) forward as a whole to the position of the beam drop adjustment support (3). At the same time, use the longitudinal push cylinder (10) to push the second sliding base (12) to correct the deviation until the horizontal push cylinder completes a stroke. Repeat the above operation continuously to make the steel box girder (2) reach the specified beam drop position.

9. The method for jacking construction of a large-span steel box girder bridge across a river as claimed in claim 4, characterized in that: The process of dropping the steel box girder (2) in step 4 includes: Step 4.4: After the steel box girder (2) is dropped onto the pier (9), the position of the steel box girder (2) is fine-tuned using the efficient walking jacking device on the pier (9) according to the readings of the intelligent monitoring system, so that its position meets the design requirements. After the adjustment is completed, the steel box girder (2) is lifted up again using the efficient walking jacking device on the temporary support (6); Step 4.5: Finally, the lifting cylinder (1) is opened, and the steel box girder (2) is lowered to the designed elevation by alternately supporting and disassembling the lower support system (8) of the jack and the tray (31) of the beam adjustment support (3).

10. The method for jacking construction of a large-span steel box girder bridge across a river as claimed in claim 1, characterized in that: When the steel box beam (2) is butt-jointed and fixed in step 5, the segmented bolted butt joint is installed, and the top plate joints of the adjacent steel box beams (2) are connected using channel steel.

Citation Information

Cited By

  • Incremental launching construction method for bridge with small curvature radius

    CN116556225A

  • Construction method of large-span large-section steel box girder

    CN119640693A

  • Cross-channel steel box girder hoisting, assembling and hoisting device and construction technology thereof

    CN120139094A

  • Offset real-time measuring device based on arched girder collaborative pushing and using method thereof

    CN120800287A

  • Real-time measurement device for offset based on arch beam cooperative jacking and method of using the same

    CN120800287B