Method for replacing temporary supporting plate strip on periphery of basement in foundation pit engineering
By using fluid solidified soil to replace temporary support strips and anchor cable support in foundation pit projects, the high cost and waterproofing problems in foundation pit projects are solved, efficient waterproofing and simple construction of the basement are achieved, and long-term waterproofing performance of the basement is ensured. .
Patent Information
- Application Number
- CN202411457987.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-18
- Publication Date
- 2024-11-29
AI Technical Summary
Conventional support structures in existing foundation pit projects lead to high project cost, waste of resources, poor basement waterproofing, complex and difficult construction, especially in the case of high groundwater levels, it is difficult to effectively solve the problem of basement leakage.
Flow-state solidified soil technology is used to replace temporary support plate belts, combined with anchor cable support, realize the water and soil pressure transmission of the foundation pit enclosure structure, and use fluid-state solidified soil for waterproofing and backfilling of the basement outdoors during construction to ensure that the backfill is compact and Waterproof effect.
Effectively save engineering costs, enhance the waterproofing effect of the basement, simplify the construction process, ensure the waterproof performance of the basement during the use stage, and avoid leakage problems.
Smart Images

Figure CN119041449A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of underground space development, and in particular relates to a measure for replacing temporary replacement of support strips around basements in the development of underground spaces with high groundwater levels, which helps to save engineering costs and can enhance the waterproofing effect of basements during normal use. Background Art
[0002] With the rapid development of urban underground space, foundation pit engineering has been widely used as one of the most commonly used means of underground space development. In the construction foundation pit engineering with deep excavation depth and sequential construction method, considering the requirements of deformation control, the most commonly used is the support system of pile row + internal support, and its construction technology is relatively mature. Pile rows are used as the foundation pit retaining structure to withstand the unbalanced earth pressure and water pressure inside and outside the pit. During the layered excavation of the foundation pit, the water and soil pressure on the outside is transmitted to the pile row, and then to the internal support. As the underground structure construction proceeds, the original support needs to be removed layer by layer from bottom to top. In order to ensure the stability of the foundation pit project, the water and soil pressure on the foundation pit retaining structure needs to be safely and orderly transferred to the basement structure through the replacement support structure. This link is called "foundation pit replacement support". Conventional replacement support includes two forms: bottom plate replacement support and middle floor plate replacement support. Bottom plate replacement support means full casting of the bottom plate. The middle floor refers to the floor slabs of each floor in the basement. The middle floor slab is generally a concrete slab of a certain thickness. The concrete slab is set in the pit fertilizer trough between the foundation pit retaining structure and the basement middle floor to play a force transmission role. The slab should be opened at intervals as a channel for construction workers to remove the basement exterior wall formwork and waterproofing work, and also as a channel for dense backfilling between the foundation pit retaining structure and the basement exterior wall in the future.
[0003] Conventional foundation pit replacement structures usually have the following problems: (1) The project cost is high. In the foundation pit project implemented by the conventional sequential method, temporary replacement support strips need to be set up around the elevation of each floor of the basement, and the replacement support strips will be left in the soil as waste in the permanent stage, resulting in a waste of resources. (2) Due to the existence of the replacement support components, the basement external waterproofing will be interrupted at the replacement support location, resulting in the inability to form a complete external waterproofing on the outside of the basement, which in turn leads to water leakage in the basement during the permanent use stage. (3) The replacement of the middle floor slab usually uses the interval opening as the backfill channel for the fertilizer trough of the foundation pit, but this method usually causes the fertilizer trough around the foundation pit to be unable to be backfilled densely, becoming a cavity where groundwater gathers, which is also prone to basement leakage. (4) The construction is complicated. In addition to increasing the construction process of the replacement support structure, after the basement is completed, the construction personnel also need to enter and exit the interval opening position of the middle floor slab replacement support to remove the basement external wall formwork and carry out waterproofing construction. The construction is difficult and affects the construction quality of the building's external waterproofing.
[0004] Fluidized soil solidification technology is to mix a certain amount of chemical soil solidifier with the soil. The special solidifier will undergo a series of physical and chemical reactions with the soil, thereby improving the structural strength of the soil and improving the engineering performance of the soil. Because this method has the advantages of fast consolidation speed, good impermeability, simple construction, and low construction noise. At present, some foundation pit projects have also begun to use fluidized soil as the backfill material for the fertilizer trough of the foundation pit. However, in the current foundation pit engineering applications, it is usually only considered that fluidized soil can ensure the quality of fertilizer trough backfill and the advantages of convenient construction, and its material properties have not been fully explored.
[0005] At present, the research on the implementation of foundation pit engineering by sequential construction method, especially the technical means to improve the current conventional foundation pit replacement support technology and enhance the waterproof effect of basement in the permanent use stage, is still immature. Summary of the invention
[0006] The present invention provides a method for replacing temporary support plate strips around basements in foundation pit projects, which is particularly suitable for the development of multi-layer underground spaces with high groundwater levels and great depths. The construction method combines fluidized soil solidification technology to replace temporary support strips around basements, thereby saving project costs and enhancing the waterproofing effect of basements during normal use.
[0007] The construction steps of the present invention are: Step 1: First, construct the foundation pit retaining structure. Excavate the foundation pit to the bottom elevation of each temporary support in turn, construct each temporary support, and then excavate the foundation pit to the basement basement elevation, construct the foundation bottom plate and the replacement support around the bottom plate, and the replacement support around the bottom plate is plain concrete.
[0008] Step 2: After the foundation slab and the surrounding replacement supports of the slab have reached the designed strength, remove the lowest temporary support, construct the structural floor slab and basement wall of the basement, and then construct the external waterproofing of the basement; when the external waterproofing of the basement is completed, fill the fluidized solidified soil in the foundation pit fertilizer trough outside the basement.
[0009] Step 3: After the fluidized solidified soil on the lower layer reaches the designed strength, remove the temporary support of the previous layer, construct the structural floor slab of the upper layer of the basement, the basement walls and the basement exterior waterproofing; then fill the fluidized solidified soil in the foundation pit fertilizer trough outside the basement.
[0010] Step 4: Repeat step 3 to complete the entire structure of the basement.
[0011] Based on the above technical features: fluidized solidified soil is used instead of plain concrete for the replacement of the support around the bottom plate.
[0012] Based on the above technical features: temporary support uses anchor cables.
[0013] The concept of the above technical solution is as follows: the conventional sequential foundation pit project needs to transfer the water and soil pressure on the foundation pit retaining structure to the basement structure through a temporary replacement support plate. Due to the existence of the temporary replacement support plate, the basement external waterproofing will be interrupted at the replacement support location, resulting in the inability to form a complete external waterproofing on the outside of the basement. In addition, the replacement support of the middle floor slab usually uses the interval opening as the backfill channel of the foundation pit fertilizer trough, but this method usually causes the fertilizer trough around the foundation pit to be unable to be backfilled densely, becoming a cavity where groundwater gathers, and is also not conducive to the removal of the exterior wall formwork and waterproofing construction. The present invention makes full use of the advantages of high strength, fast consolidation speed, and good impermeability of fluidized solidified soil. With the removal of the foundation pit support and the backbuilding of the basement, the basement external waterproofing is constructed in time and the fertilizer trough is backfilled with fluidized solidified soil. The strength of fluidized solidified soil is relatively high, which can reach 2MPa in actual engineering; at the same time, the backfill height of each step is the height of a basement floor, so after replacing the conventional replacement support plate belt around the foundation pit, the safety of the foundation pit can also be ensured. In addition, the fluidized solidified soil has a fast solidification speed, and the strength can reach 0.3-0.5MPa in 3 days, which can meet the construction needs and does not affect the construction period. Moreover, the fluidized solidified soil is close to liquid before solidification, which can fully ensure the backfill is dense. After solidification, it has good anti-seepage performance and can be used as a waterproof measure, further ensuring that there will be no leakage problems in the basement during the permanent use stage.
[0014] The present invention uses liquid solidified soil to replace temporary support strips in foundation pit engineering, which can effectively save engineering costs. At the same time, the waterproof roll can be continuously penetrated, and the fluid solidified soil itself has impermeability, which can effectively avoid leakage problems in the basement, and plays an important role in underground space construction projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the conventional sequential method of foundation pit excavation, temporary support and foundation bottom plate construction in step one of the present invention.
[0016] Figure 2 It is a construction schematic diagram of step 2 in the present invention.
[0017] Figure 3 It is a construction schematic diagram of step three in the present invention.
[0018] Figure 4 It is a schematic diagram of completing the entire basement structure and external waterproofing in the final state of step four in the present invention.
[0019] The numbers in the figure are as follows: foundation pit retaining structure 1; temporary support 2; foundation slab 3; replacement support around the slab 4; structural floor slab 5; basement wall 6; basement external waterproofing 7; fluidized solidified soil 8. DETAILED DESCRIPTION
[0020] The specific embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings. These embodiments are only used to illustrate the present invention, but not to limit the present invention.
[0021] In the description of the present invention, it should be noted that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0022] The present invention provides a method for replacing temporary support plates around basements in foundation pit projects. In the development of multi-layer underground spaces with high groundwater levels and great depths, the construction method combines fluidized solidified soil technology to replace temporary support plates around basements, thereby saving project costs and enhancing the waterproofing effect of basements during normal use. The specific description is as follows in conjunction with the accompanying drawings.
[0023] Step 1: If Figure 1 As shown, firstly, the foundation pit retaining structure 1 is constructed, the foundation pit is excavated to the bottom elevation of each support in turn, and each temporary support 2 is constructed, and the temporary support 2 can be anchored. Then, the foundation pit is excavated to the basement base elevation, and the foundation bottom plate 3 and the bottom plate peripheral replacement support 4 are constructed. The bottom plate peripheral replacement support 4 can be made of conventional plain concrete, and when the bottom plate replacement support is subjected to less force, fluidized solidified soil can also be used.
[0024] Step 2: If Figure 2 As shown, after the foundation slab 3 and the replacement brace 4 around the slab reach the designed strength, the last temporary support 2 is removed, and the structural floor slab 5 and the basement wall 6 of the basement are constructed, and then the basement external waterproofing 7 is constructed. When the basement external waterproofing 7 is completed, the fluidized solidified soil 8 is filled in the foundation pit fertilizer trough outside the basement.
[0025] Step 3: If Figure 3 As shown, after the fluidized solidified soil 8 at the lower layer reaches the designed strength, the upper temporary support 2 is removed, and the structural floor slab 5 of the upper layer of the basement, the basement wall 6, and the basement external waterproofing 7 are constructed, and then the fluidized solidified soil 8 is filled in the foundation pit fertilizer trough outside the basement.
[0026] Step 4: If Figure 4 As shown, repeat step three to complete the entire basement structure.
[0027] In summary, the present invention gives full play to the advantages of high strength, fast consolidation speed, and good impermeability of fluidized solidified soil, and uses fluidized solidified soil to replace the temporary replacement support strips set around the basement at the locations of conventional floor slabs. This technical measure has the following outstanding advantages: (1) It saves a large number of temporary replacement support strip structures in conventional foundation pit projects, saving project costs; (2) It is convenient to construct, avoiding the conventional cumbersome replacement support strip construction, and at the same time, the working environment during the construction of the basement external waterproofing is also significantly improved, making it easier to ensure the construction quality of the building's external waterproofing; (3) The conventional foundation pit basement external waterproofing needs to be disconnected at the replacement support strip position. The technical measures of the present invention can ensure the continuity of the basement external waterproofing, and the waterproofing membrane is not easily damaged; (4) The fluidized solidified soil can ensure dense filling and has good impermeability, so it is also conducive to ensuring the reliability of the basement waterproofing during normal use.
[0028] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. A method for replacing temporary support strips around basements in foundation pit projects: Step 1: First, construct the foundation pit retaining structure (1), excavate the foundation pit in sequence to the bottom elevation of each temporary support (2), construct each temporary support (2), and then excavate the foundation pit to the basement base elevation, construct the foundation bottom plate (3) and the bottom plate peripheral replacement support (4), and the bottom plate peripheral replacement support (4) is plain concrete; Step 2: After the foundation slab (3) and the replacement support (4) around the slab have reached the designed strength, the temporary support (2) at the bottom is removed, and the structural floor slab (5) and the basement wall (6) of the basement are constructed, and then the basement external waterproofing (7) is constructed; when the construction of the basement external waterproofing (7) is completed, the fluidized solidified soil (8) is filled in the foundation pit fertilizer trough outside the basement; Step 3: After the fluidized solidified soil (8) at the lower layer reaches the designed strength, the temporary support (2) of the previous layer is removed, and the structural floor (5) of the upper layer of the basement, the basement wall (6) and the basement external waterproofing (7) are constructed; and then the fluidized solidified soil (8) is filled in the foundation pit fertilizer trough outside the basement; Step 4: Repeat step 3 to complete the entire structure of the basement.
2. A method for replacing temporary support strips around basements in foundation pit engineering according to claim 1, Features: The bottom plate peripheral support replacement (4) uses the fluidized solidified soil to replace the plain concrete.
3. A method for replacing temporary support strips around basements in foundation pit engineering according to claim 1: Features: The temporary support (2) adopts anchor cables.