Fabricated deep foundation pit foundation template system and mounting method thereof
Through the modularly designed prefabricated deep foundation pit foundation formwork system, the problem that traditional construction methods are difficult to meet the requirements of deep foundation pits in super high-rise buildings is solved, and the foundation pit slope stability and forming quality are improved, reducing construction risks and Cost, suitable for large-scale construction projects.
Patent Information
- Application Number
- CN202411454002.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-17
- Publication Date
- 2024-11-29
AI Technical Summary
Traditional masonry materials and construction methods are difficult to meet the requirements of deep foundation pit foundation forming in projects such as super high-rise buildings, large public buildings and bridge projects, resulting in insufficient slope support, instability of formwork, and uneven concrete pouring, increasing construction safety risks. And affects the quality and durability of the project.
Adopt a modular prefabricated deep foundation pit foundation formwork system, including columns, retaining plate units, foundation cushion layer and edge columns. By optimizing design and structural components, the stability of foundation pit slopes is improved, the quality of foundation molding is ensured, and the reasonable layout is adopted. The combination design of columns, retaining plates and edge columns, pole grooves and horizontal tie ribs ensures uniform distribution of concrete and structural stability.
Through modular design, the construction quality problems are reduced, the slope collapse risk is reduced, construction efficiency and safety are improved, and the accuracy and consistency of deep foundation pit foundations are achieved. It is suitable for foundation projects of different sizes and shapes, reducing the site Construction time and labor costs.
Smart Images

Figure CN119041480A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of building construction, and relates to construction measures and corresponding construction methods related to foundation, excavation, filling, etc., and specifically to an assembled deep foundation pit formwork system and an installation method. Background Art
[0002] At present, during the construction of building projects, foundation projects usually use masonry materials to build brick formwork to meet the molding requirements of the foundation project and ensure that the structure reaches the designed strength, seismic resistance and other technical performances. In general construction projects, most foundation projects use raft foundations, and the foundation thickness is usually between 500 mm and 1000 mm. Conventional masonry materials such as brick formwork or concrete can meet the construction requirements. This method is simple to construct and low in cost, so it has been widely used in small and medium-sized construction projects.
[0003] However, for projects such as super high-rise buildings, large public buildings and bridge projects, the foundation depth is usually more than 1000 mm, and traditional masonry materials and construction methods are difficult to meet the requirements in these scenarios. The use of conventional materials may lead to insufficient support of the excavated slope, which in turn causes the slope to collapse. In addition, the quality of foundation molding is also difficult to guarantee. Common problems include formwork instability and uneven concrete pouring. These problems not only increase the safety risks of construction, but may also cause the foundation strength to fail to meet the design standards, thus affecting the overall quality and durability of the project. Summary of the invention
[0004] In order to overcome the defects of the prior art, the present invention provides an assembled deep foundation pit formwork system and an installation method thereof, which improves the stability of the foundation pit slope during the construction process and ensures the molding quality and construction safety of the foundation by optimizing the design and structural components.
[0005] To achieve the above object, the technical solution of the present invention is as follows:
[0006] A prefabricated deep foundation pit formwork system, the formwork system comprises columns, retaining plate units, foundation cushion layers and edge columns; the columns are made of concrete; the retaining plate units comprise retaining plates, upright bar grooves, horizontal reserved holes and horizontal tie bars; the retaining plates are made of autoclaved aerated concrete plates, the overall vertical section is a right-angled trapezoid, the hypotenuse faces the soil, and the right-angled side faces the foundation; the upright bar grooves are arranged at the edges of both sides of the retaining plates, the cross section is rectangular, and the horizontal reserved holes are arranged in the retaining plates, the cross section is circular, and the horizontal reserved holes are extended in the horizontal direction of the retaining plates; the horizontal tie bars are made of hot-rolled ribbed steel bars, the diameter of which is smaller than the diameter of the horizontal reserved holes, so as to facilitate installation and concrete pouring; the foundation cushion layer is made of concrete, and the outer edge is flush with the outer lower edge of the retaining plate; the edge columns are made of concrete, and are arranged at the four corners of the formwork system to constrain the formwork system and enhance the overall stability.
[0007] Preferably, the pole groove includes a first pole groove at a non-corner location and a second pole groove at a corner location, the column is formed by pouring concrete in the first pole groove at a non-corner location, and the edge column is formed by pouring concrete in the second pole groove at a corner location.
[0008] Preferably, the columns and edge columns are made of concrete with a large slump and a small aggregate particle size.
[0009] Preferably, the diameter of the horizontal reserved hole is 16 mm, and the diameter of the horizontal tie bar is 14 mm.
[0010] Preferably, the size range of the foundation cushion layer is 100 mm outside the foundation edge and its thickness is 100 mm.
[0011] Preferably, the length of the horizontal tie bars exceeds the range of the retaining plate and is anchored into the surrounding soil to improve the tie effect.
[0012] Preferably, the column groove runs through the edge of the retaining board to provide a flow channel for concrete pouring to ensure the connection strength between the column and the edge column and the retaining board unit.
[0013] Preferably, the retaining plates of the retaining plate unit are enclosed in a rectangle, and the retaining plates are arranged at staggered heights of the horizontal reserved holes on the four sides of the rectangle.
[0014] The present invention also discloses an installation method based on the above-mentioned assembled deep foundation pit formwork system, and the installation method comprises the following steps:
[0015] S1, cleaning the foundation trench: using a combination of mechanical excavation and manual cleaning to ensure that the soil around the foundation trench is not disturbed and the ground is flat;
[0016] S2, foundation cushion construction: pour foundation cushion concrete in the cleaned foundation trench, and carry out subsequent construction after initial setting;
[0017] S3, installation of retaining wall unit: align the outer edge of the retaining wall with the outer edge of the foundation cushion;
[0018] S4, installation of horizontal tie bars: install horizontal tie bars through horizontal reserved holes, and anchor the tie bars into the surrounding soil to improve the tie efficiency;
[0019] S5, column construction: pour concrete in the first column groove, and the concrete flows through the gap between the horizontal reserved hole and the horizontal tie bar, filling the pores to enhance the tie strength and ensure the molding quality of the column;
[0020] S6, edge column construction, pouring concrete in the second column groove, the concrete flows through the gap between the horizontal reserved holes and the horizontal tie bars to ensure the stability of the four corners of the formwork system.
[0021] Preferably, during the construction of the columns and edge columns, a vibration tool is used to vibrate and compact the concrete when pouring the concrete.
[0022] The beneficial effects of the present invention are:
[0023] The present invention adopts a modular assembled deep foundation template system. Through standardized modular design, the quality standard of deep foundation construction is clarified. Each component such as columns, retaining plate units and edge columns adopts prefabricated standardized design, so that each step in the construction process has clear standards and specifications. This design greatly reduces the construction quality problems caused by non-standard processes in traditional foundation construction, and ensures the accuracy and consistency of deep foundation formation. At the same time, the template system can effectively support the slope during the excavation of the foundation pit through the rational layout of columns, retaining plates and edge columns, and prevent the collapse of the foundation pit slope. The combined design of the uprights and horizontal tie bars ensures the uniform distribution of concrete during the template pouring process, avoiding the phenomenon of structural deformation or uneven shrinkage. This stable structural design greatly reduces the risk of slope collapse commonly seen in traditional construction and reduces the occurrence of safety accidents. In addition, through the design of modular components, mass production and rapid installation are achieved. The standardized connection method between the components not only facilitates transportation, assembly and disassembly, but also improves the working efficiency of the construction site. The traditional deep foundation construction method often requires a large number of on-site processes, and the modular design of the present invention enables the components to be mass-produced in the factory, reducing the time and labor costs of on-site construction, thereby speeding up the construction progress. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1It is a schematic diagram of the overall structure of the assembled deep foundation formwork system according to an embodiment of the present invention.
[0025] Figure 2 This is a schematic diagram of the disassembly of a single retaining plate unit of the assembled deep foundation formwork system of an embodiment of the present invention.
[0026] Figure 3 This is a schematic diagram of the installation of a single retaining plate unit of the assembled deep foundation formwork system of an embodiment of the present invention.
[0027] Figure 4 The present invention is a flowchart of the installation method of the assembled deep foundation formwork system according to an embodiment of the present invention.
[0028] Explanation of the main component symbols: 1-column; 2-retaining board unit; 21-retaining board; 22-pole groove; 23-horizontal reserved hole; 24-horizontal tie bar; 3-foundation cushion layer; 4-edge column. DETAILED DESCRIPTION
[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0030] In the following, the terms "first" and "second" are used for descriptive purposes only and are not to be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the embodiments of the present disclosure, unless otherwise specified, "multiple" means two or more. In addition, the use of "based on" or "according to" means openness and inclusiveness, because the process, steps, calculations or other actions "based on" or "according to" one or more of the conditions or values may be based on additional conditions or values beyond the described values in practice.
[0031] See also Figure 1-3, this embodiment discloses an assembled deep foundation formwork system, the formwork system includes a column 1, a retaining plate unit 2, a foundation cushion 3 and an edge column 4. The material of the column 1 is concrete, which ensures that the column 1 has sufficient strength and stability when subjected to lateral soil pressure. The retaining plate unit 2 includes a retaining plate 21, a column groove 22, a horizontal reserved hole 23 and a horizontal tie bar 24. The material of the retaining plate 21 is an autoclaved aerated concrete plate, and the overall vertical cross-section is a right-angled trapezoid, with the hypotenuse facing the soil and the right-angled side facing the foundation. This design can enhance the ability of the retaining plate 21 to resist lateral soil pressure, while avoiding deformation of the concrete foundation. The column groove 22 is opened on the two side edges of the retaining plate 21, and the cross-section is rectangular and long. The long column groove 22 enables the column 1 to form a stable connection structure with the retaining plate 21, ensuring the overall stability of the formwork system during construction. The horizontal reserved hole 23 is arranged in the retaining plate 21, and has a circular cross section, extending in the horizontal direction of the retaining plate 21. The horizontal reserved hole 23 is used to install the horizontal tie bar 24. The horizontal tie bar 24 is made of hot-rolled ribbed steel bars, and its diameter is smaller than the diameter of the horizontal reserved hole 23. This not only ensures that the tie bar 24 can pass through the reserved hole 23 smoothly, but also provides a certain gap when pouring concrete, so that the concrete can be completely filled, thereby enhancing the overall strength of the structure. The material of the foundation cushion 3 is also concrete, and the outer edge is flush with the outer lower edge of the retaining plate 21. This arrangement can ensure that the foundation cushion 3 and the retaining plate 21 together form a complete and continuous foundation support structure, enhance the support effect of the foundation pit, and prevent the soil from sliding or collapsing. The material of the edge column 4 is concrete, and it is arranged at the four corners of the formwork system. Its function is to provide additional constraints and support for the entire formwork system, and avoid structural instability caused by stress concentration at the corners.
[0032] Furthermore, the column groove 22 includes a first column groove at a non-corner location and a second column groove at a corner location. The column 1 is formed by pouring concrete in the first column groove 22 at a non-corner location. This forming method ensures the stability of the column 1 at a non-corner location and can effectively bear vertical and horizontal loads. The edge column 4 is formed by pouring concrete in the second column groove 22 at a corner. Since the stress distribution at the corner is more complex, the design of the second column groove 22 can better constrain the edge column 4, so that it maintains structural stability when bearing corner stress. Both the column 1 and the edge column 4 use concrete with a large slump and a small aggregate particle size. This choice of concrete ensures good fluidity during the pouring process, and at the same time can achieve a more uniform and dense structure after forming, thereby improving the strength and durability of the entire foundation formwork system. The diameter of the horizontal tie bar 24 is slightly smaller than the diameter of the horizontal reserved hole 23. Specifically, the diameter of the horizontal reserved hole 23 can be designed to be 16 mm, and the diameter of the horizontal tie bar 24 is 14 mm. This ensures that the tie bar 24 can be smoothly inserted into the reserved hole 23, while also providing sufficient clearance for concrete pouring to ensure that the concrete can fully wrap the tie bar 24 and form a stable structural connection. The size range of the foundation cushion 3 is 100 mm outside the foundation edge, and its thickness is 100 mm, which ensures that the foundation cushion 3 can form a complete foundation structure when connected to the retaining plate 21, and provides sufficient support and bearing capacity to prevent the foundation slope from becoming unstable.
[0033] Furthermore, the length of the horizontal tie bars 24 exceeds the range of the retaining board 21 and is anchored into the surrounding soil, which effectively enhances the fixing effect of the tie bars 24 on the retaining board 21, especially when the foundation slope is subjected to a large lateral pressure, which can significantly improve the tie strength of the overall structure and prevent the retaining board 21 from shifting during construction. The column groove 22 runs through the edge of the retaining board 21, providing a flow channel for concrete pouring, ensuring that the column 1 and the edge column 4 form a complete concrete structure when connected to the retaining board 21, thereby greatly enhancing the connection strength between the column 1, the edge column 4 and the retaining board unit 2, and ensuring that the overall structure has sufficient stability when subjected to force.
[0034] In this embodiment, the retaining plates 21 of the retaining plate unit 2 are enclosed in a rectangle to form a complete support structure, so that the entire formwork system can adapt to the needs of foundation projects of different sizes and shapes. At the same time, the retaining plates 21 are arranged at staggered heights at the horizontal reserved holes 23 on the four sides of the rectangle. This design can effectively avoid interference between the horizontal tie bars 24 at the intersection, especially at the edge columns 4, ensuring that the tie bars 24 can be installed smoothly and give full play to their tie effect, further enhancing the stability of the structure.
[0035] In some embodiments, the retaining plate unit 2 can be adjusted accordingly according to the difference in the actual thickness of the foundation, such as changing the height of the retaining plate 21 and other measures. Such a design ensures that the formwork system can flexibly adapt to foundation projects of different thicknesses. Whether it is a thicker or thinner foundation structure, it can provide sufficient support and stability by adjusting the height of the retaining plate unit 2, further improving the applicability of the formwork system. At the same time, according to the difference in the actual length and width of the foundation, the number of retaining plate units 2 and the size of the column 1 can be adjusted. Specifically, in a longer or wider foundation structure, the number of retaining plate units 2 is increased, and the size of the column 1 is appropriately increased according to the force requirements. Such adjustments enable the formwork system to show good adaptability in foundation projects of different sizes, which not only ensures the stability of the construction, but also improves the efficiency of the formwork, ensuring its wide application in different scenarios.
[0036] See also Figure 4 The present invention also discloses an installation method based on the above-mentioned assembled deep foundation pit formwork system, and the installation method comprises the following steps:
[0037] S1, cleaning the foundation pit: use a combination of large-scale mechanical excavation and manual cleaning to ensure that the soil around the foundation pit is not disturbed and the ground is flat.
[0038] In this step, efficiency is improved through mechanical excavation, while manual cleaning can ensure that the soil is not overly disturbed, ensuring the flatness of the ground and laying a stable foundation for subsequent construction.
[0039] S2, foundation cushion construction: pour foundation cushion concrete in the cleaned foundation trench, and carry out subsequent construction after initial setting.
[0040] In this step, by pouring the foundation cushion layer 3 , a solid base layer can be provided to support and fix the installation of the retaining wall unit 2 . Construction after initial setting helps to ensure the stability and strength of the foundation cushion layer 3 .
[0041] S3, installation of retaining plate unit: align the outer edge of the retaining plate 21 with the outer edge of the base cushion layer 3 and place it.
[0042] In this step, the alignment operation ensures a tight fit between the retaining plate 21 and the base cushion 3, ensuring that the retaining plate 21 remains stable when subjected to force.
[0043] S4, installation of horizontal tie bars: horizontal tie bars 24 are installed through the horizontal reserved holes 23, and the tie bars 24 are anchored into the surrounding soil to improve the tie efficiency.
[0044] In this step, the installation of the horizontal tie bars 24 strengthens the connection between the retaining plate 21 and the soil around the foundation, and increases the tensile strength of the entire formwork system through the anchoring effect.
[0045] S5, column construction: pour concrete in the first column groove 22, and the concrete flows through the gap between the horizontal reserved hole 23 and the horizontal tie bar 24, filling the pores to enhance the tie strength and ensure the molding quality of the column 1.
[0046] In this step, the connection between the column 1 and the retaining plate 21 is ensured to be firm through casting, and the sufficient flow and filling of concrete enhance the tightness of the overall structure.
[0047] S6, edge column construction: pour concrete in the second column groove 22, and the concrete flows through the gap between the horizontal reserved holes 23 and the horizontal tie bars 24 to ensure the stability of the four corners of the formwork system.
[0048] In this step, since the edge columns 4 are located at the corners of the structure, the design of the second column grooves 22 ensures the reinforcement effect at the corners, avoids the risk of instability caused by stress concentration, and ensures the firmness of the overall structure.
[0049] Furthermore, during the construction of the column 1 and the edge column 4, a vibration tool is used to vibrate and compact the concrete when pouring the concrete. This operation can ensure that the concrete is evenly distributed inside the column 1 and the edge column 4 through the use of the vibration tool, and eliminate bubbles and voids that may be generated during the concrete pouring process, thereby improving the density and strength of the concrete. The vibration compaction process can also ensure that the concrete forms a strong bond with the horizontal tie bars 24 and the retaining plate 21, further enhancing the stability and durability of the entire formwork system.
[0050] In summary, the present invention discloses an assembled deep foundation pit foundation formwork system and an installation method thereof. Through modular design, the formwork system includes columns 1, retaining plate units 2, foundation cushion layers 3 and edge columns 4, which can be flexibly adjusted according to the actual conditions of foundation thickness, length and width, ensuring applicability and efficient construction. The retaining plate 21 of the retaining plate unit 2 adopts an autoclaved aerated concrete plate, which has a strong supporting capacity and can effectively support the slope of the foundation pit to prevent soil collapse. Through the design of the upright groove 22 and the horizontal reserved hole 23, the column 1 and the edge column 4 are firmly connected to the retaining plate unit 2, thereby increasing the safety of construction. The installation method of the present invention includes multiple steps. First, the foundation is ensured to be flat by cleaning the foundation groove, and then the foundation cushion layer 3 is constructed. The retaining plate unit 2 is installed immediately thereafter to ensure its close combination with the foundation cushion layer 3, and then the horizontal tie bar 24 is installed through the horizontal reserved hole 23 to improve the tie effect. The column 1 and the edge column 4 are formed by pouring concrete in the first column groove 22 and the second column groove 22, and a vibrating tool is used to vibrate and compact the concrete during the pouring process to ensure the density of the concrete and the final molding quality. The present invention not only standardizes the foundation construction process and reduces the construction risk through reasonable structural design and efficient construction methods, but also significantly improves the construction efficiency through batch operations, ensures the quality and overall stability of the foundation molding, and is suitable for various large-scale construction projects.
[0051] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of those skilled in the art without departing from the spirit of the present invention.
Claims
1. An assembled deep foundation pit formwork system, characterized in that: The formwork system comprises columns (1), retaining plate units (2), foundation cushion layers (3) and edge columns (4); the columns (1) are made of concrete; the retaining plate units (2) comprise retaining plates (21), upright bar grooves (22), horizontal reserved holes (23) and horizontal tie bars (24); the retaining plates (21) are made of autoclaved aerated concrete plates, and the overall vertical cross-section is a right-angled trapezoid, with the hypotenuse facing the soil and the right-angled sides facing the foundation; the upright bar grooves (22) are provided at the edges of both sides of the retaining plate (21), and the cross-section is a rectangle in the shape of a long strip. The horizontal reserved hole (23) is arranged in the retaining plate (21), has a circular cross-section, and extends in the horizontal direction of the retaining plate (21); the horizontal tie bar (24) is made of hot-rolled ribbed steel bars, and has a diameter smaller than that of the horizontal reserved hole (23) to facilitate installation and concrete pouring; the base cushion layer (3) is made of concrete, and its outer edge is flush with the outer lower edge of the retaining plate (21); the edge columns (4) are made of concrete and are arranged at the four corners of the formwork system to constrain the formwork system and enhance overall stability.
2. The assembled deep foundation formwork system according to claim 1 is characterized in that: The upright pole groove (22) comprises a first upright pole groove at a non-corner position and a second upright pole groove at a corner position, the upright column (1) is formed by pouring concrete in the first upright pole groove at a non-corner position, and the edge upright column (4) is formed by pouring concrete in the second upright pole groove at a corner position.
3. The assembled deep foundation formwork system according to claim 2 is characterized in that: The columns (1) and edge columns (4) are both made of concrete with a large slump and a small aggregate particle size.
4. The assembled deep foundation formwork system according to claim 3 is characterized in that: The diameter of the horizontal reserved hole (23) is 16 mm, and the diameter of the horizontal tie bar (24) is 14 mm.
5. The assembled deep foundation formwork system according to claim 4 is characterized in that: The size range of the foundation cushion layer (3) is 100 mm outside the foundation edge, and its thickness is 100 mm.
6. The assembled deep foundation formwork system according to any one of claims 2 to 5, characterized in that: The length of the horizontal tie bars (24) exceeds the range of the retaining plate (21) and is anchored into the surrounding soil to improve the tie effect.
7. The assembled deep foundation formwork system according to claim 6 is characterized in that: The upright post groove (22) runs through the edge of the retaining plate (21) to provide a flow channel for pouring concrete, thereby ensuring the connection strength between the upright post (1) and the edge upright post (4) and the retaining plate unit (2).
8. The assembled deep foundation formwork system according to claim 7 is characterized in that: The retaining plates (21) of the retaining plate unit (2) are arranged to form a rectangle, and the retaining plates (21) are arranged at staggered heights at the horizontal reserved holes (23) on the four sides of the rectangle.
9. A method for installing the assembled deep foundation formwork system according to any one of claims 3 to 8, characterized in that: The installation method comprises the following steps: S1, cleaning the foundation trench: using a combination of mechanical excavation and manual cleaning to ensure that the soil around the foundation trench is not disturbed and the ground is flat; S2, foundation cushion (3) construction: pouring foundation cushion concrete in the cleaned foundation trench, and carrying out subsequent construction after initial setting; S3, installation of the retaining plate unit (2): aligning the outer edge of the retaining plate (21) with the outer edge of the foundation cushion layer (3); S4, installation of horizontal tie bars (24): installing horizontal tie bars (24) through horizontal reserved holes (23), and anchoring the tie bars into the surrounding soil to improve the tie efficiency; S5, construction of the column (1): pouring concrete in the first column groove, the concrete flowing through the gap between the horizontal reserved hole (23) and the horizontal tie bar (24), filling the pores to enhance the tie strength, and ensuring the molding quality of the column (1); S6, edge column (4) construction, pouring concrete in the second column groove, the concrete flows through the gap between the horizontal reserved hole (23) and the horizontal tie bar (24), ensuring the stability of the four corners of the formwork system.
10. The installation method according to claim 9, characterized in that: During the construction of the upright columns (1) and the edge upright columns (4), a vibrating tool is used to vibrate and compact the concrete when pouring the concrete.
Citation Information
Cited By
Reinforced concrete prefabricated part for repairing edge of foundation pit
CN120556493A